Chapel Pews Refinish - SOW.pdf
PDF 95 KB Posted
- Attached to
- Luke AFB Base Chapel Pew Refinishing Federal contract opportunity
- Solicitation number
- FA488725Q0035
About this file
This Statement of Work details a project for sanding and varnishing 30 chapel pews, consisting of 27 large pews measuring 16 ft 8 inches and 3 small pews measuring 9 ft 8.5 inches. The scope of work requires the contractor to provide labor, materials, and equipment to prepare the pews, including protecting the chapel floor, thoroughly cleaning pew surfaces, sanding to achieve a smooth finish, applying matching varnish with uniform coats, and cleaning up the work area upon project completion. The contractor must coordinate work with the Superintendent to minimize disruption to worship services, with the work necessitated by varnish wear from excessive cleaning and COVID prevention chemicals.
The document includes provisions for a warranty that the work will be performed professionally using quality materials, with finished pews expected to be free from defects for a reasonable period. Any changes to the scope of work, materials, or schedule must be submitted in writing and approved by both parties, with the understanding that approved change orders may impact the project schedule and budget. The primary objective is to restore the wooden pews to a high-quality, uniform finish while maintaining the chapel's operational requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WD 2015-5469 Rev 28 Dated 8 July 2025.pdf | ||
| Solicitation Amendment FA488725Q00350001.pdf | ||
| Solicitation - FA488725Q0035.pdf | ||
| Pictures.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work: Sanding & Varnishing 30 Chapel Pews
1. Project Title: Sanding and Varnishing of 30 Chapel Pews
- 27 Large pews measure 16ft 8 inches
- 3 small pew measure 9 ft 8.5 inches
2. Project Description:
This project involves spot sanding and applying a fresh varnish finish to 30 existing chapel pews. The pews are constructed of wooden material. The varnish has worn out due to excessive cleaning and cleaning chemicals used for COVID prevention measures. The work will have to be properly coordinated with the Superintendent to minimize worship services disruptions.
3. Scope of Work:
The Contractor shall provide all labor, materials, and equipment necessary to complete the following tasks:
3.1. Preparation:
• Protect the chapel’s floor and surrounding areas from dust and debris.
• Thoroughly clean all pew surfaces to remove dust, dirt, and debris.
3.2. Sanding:
• Sand all necessary pew surfaces to achieve a smooth and consistent surface.
• Pay particular attention to removing any existing imperfections in the current finish.
3.3. Varnishing:
• Apply matching varnish to all pew surfaces, ensuring a uniform and consistent finish.
• Allow adequate drying time between each coat of varnish as per manufacturer instructions.
3.4. Clean Up:
• Clean all work areas and remove all debris from the chapel facility upon completion of the project.
4. Warranty:
The Contractor warrants that all work will be performed in a professional and workmanlike manner, using quality materials. The Contractor further warrants that the finished pews will be free from defects in materials and workmanship for a reasonable period.
5. Change Orders:
Any changes to the scope of work, materials, or schedule must be submitted in writing and approved by both parties. Approved change orders may affect the project schedule and budget.