Change Order Notice~14.docx

DOCX document 13 KB Posted

Attached to
CHANGE ORDER - Spoon River State Forest Management Harvest
Solicitation number
19-422DNR-RESCO-B-7386
Issued by
Illinois

About this file

This document is a Change Order Notice from the Illinois Department of Natural Resources, regarding a contract with Ben Bruggeman DBA B&R Logging for the Spoon River State Forest Management Harvest. The agency is issuing a change order to extend the contract end date by 12 months, from June 30, 2019 to June 30, 2020, to allow time to complete the project. The original procurement method was a small purchase, and the change is being made due to unforeseeable poor weather conditions during the last season that prevented the cutting from being completed. The costs for the contract remain the same.

The related State and Local Contract Opportunity is also for the CHANGE ORDER - Spoon River State Forest Management Harvest, with the state being Illinois. This is a timber management harvest project where the vendor pays the Illinois Department of Natural Resources for the designated trees removed.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Change Order Notice Agency: Illinois Department of Natural Resources Title of Procurement: Spoon River State Forest Management Harvest BidBuy Reference Number: 19-422DNR-RESCO-B7386

The Illinois Department of Natural Resources requires a change order to a contract with Ben Bruggeman DBA B&R Logging to extend the contract end date 12 months to allow time to complete the project. The Agency requires this change order as defined in 30 ILCS 500/1-15.12 and 720 ILCS 5/33E.

Contract will be extended from June 30, 2019 – June 30, 2020. Costs remain the same.

The original procurement method was a small purchase.

The circumstances were unforeseeable at the time the contract was executed and changes are germane to the original contract.

Poor weather conditions this last season did not allow for cutting. This is a timber management harvest where the Vendor pays IDNR for designated trees removed.