Change Order Notice V.25.1 Fusion~1.pdf
PDF 1 MB Posted
- Attached to
- CHANGE ORDER NOTICE-Pharmacy System Amendment
- Solicitation number
- 26-444DHS-MIS44-B-52213
- Issued by
- Illinois
About this file
This is a Change Order Notice documenting an amendment to a pharmacy system contract in Illinois. The amendment adds the Fusion 360 software component to the existing contract in response to new Federal requirements. The change order extends the initial contract term and introduces the Fusion software system as a required addition to the pharmacy services being provided.
The financial impact of this change order is an increase of $197,600.00 to the contract value. This amendment reflects mandatory compliance with updated Federal requirements that necessitated the incorporation of the Fusion 360 software platform into the existing pharmacy system contract. No other details regarding pricing structure, payment terms, incumbent contractor information, or contract timeline modifications are specified in the change order notice.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Change Order Notice V.25.1 Fusion_UPDATED.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| CurrentPage: |
| PageCount: |
| DropDownList1: DHS - Human Services |
| ProcurementTitle: 24-OCAPS Pharmacy System RFP |
| BBREFNO.: 26-444DHS-MIS44-B-52213 |
| thedetails: Due to new Federal requirements, the agency is amending contract 4100222212 (P-85550) to add the Fusion 360 software component, increasing initial term by $197,600.00. |
| CheckBox1: 1 |
| CheckBox2: 1 |
File details come from the government source that posted it. Updated .