Change Order Notice V.25.1_B54241.pdf
PDF 1 MB Posted
- Attached to
- Change Order Notice_2305 Buwick Change Order #1
- Solicitation number
- 27-422DNR-MINES-B-54241
- Issued by
- Illinois
About this file
This is a Change Order Notice issued by the Chief Procurement Office for General Services regarding Contract #P-94823 with the Illinois Department of Natural Resources (DNR) for abandoned mined lands remediation services. The project involves construction services for the remediation of two dams associated with Old Man Lake, located northeast of Cuba, Illinois. The Abandoned Mined Lands Reclamation Division received federal funding from the U.S. Department of the Interior, Office of Surface Mining to eliminate mine-related public health and safety hazards at this site, which has been approved for AML remediation. The change order modifies the original contract specifications to enhance construction feasibility and operational efficiency at the primary lake outlet structure.
The change order increases the contract scope and cost by revising the specifications for Structure No. 1. The originally specified precast concrete structure will be replaced with a larger precast box structure, and the inlet pipe will be changed from a concrete pipe to a longer ductile iron pipe. This modification is considered germane to the original contract as signed and addresses construction and operational needs identified after contract execution. Per procurement regulations, this change order, which increases contract costs by more than $25,000, was posted on the Bulletin/BidBuy for the required 14-day review period prior to implementation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| CurrentPage: |
| PageCount: |
| DropDownList1: DNR - Natural Resources |
| ProcurementTitle: AML 2305 Buwick Dam |
| BBREFNO.: 26-422DNR-MINES-P-94823 |
| thedetails: DNR is making a change to #P-94823. |
Construction services. DNR has procured the services of a contractor to complete remediation of two dams associated with Old Man Lake. This lake is located northeast of Cuba, IL.
The Abandoned Mined Lands Reclamation Division (AMLRD) receives federal dollars for the sole purpose of eliminating mine related public health and safety hazards. The U.S. Department of the Interior, Office of Surface Mining has approved this site for AML remediation. Procuring the noted services will insure remediation can be completed in accordance with the engineering design, specifications, and other project related documents.
This change order makes the following revisions to the contract. Structure No. 1 associated with the primary lake outlet will be modified to better accommodate construction and operation. Specifically, the originally specified precast concrete structure will be replaced with a larger precast box structure, and the inlet pipe to the structure will be changed from a concrete pipe to a longer ductile iron pipe.
| CheckBox1: 1 |
| CheckBox2: 1 |