Champion Mill Stabilization Project (Revised)_Part1.pdf

PDF 875 KB Posted

Attached to
PKAA FY 2018 Champion Mill Stabilization Project (Revised)
Solicitation number
IFB1 PKAA 2017000297 3
Issued by
Kit Carson County, Denver City, Colorado

About this file

Champion Mill Stabilization Project (Revised) – Bid Document Summary

This is a sealed bid solicitation issued by the State of Colorado, Division of Reclamation, Mining and Safety for the Champion Mill Stabilization Project (Bid Number 2017-0297). The project involves critical stabilization of the deteriorating Champion Mill, located in Lake County approximately 14 miles southwest of Leadville at an elevation of 11,700 feet in the San Isabel National Forest. Work includes replacing compromised rafters, purlins, and roof decking; reroofing the structure with galvanized corrugated metal panels; replumbing and stabilizing portions of the structure with steel cables; repairing or replacing support posts; and bracing a stone masonry wall. The bid schedule includes 13 line items covering mobilization/demobilization, a Project Safety, Health & Environmental Action Plan (SHEAP), stabilization of the upper shed, support trusses and posts, the north wall of the lower shed, masonry wall bracing, rafter and purlin repairs (550 linear feet), roof decking removal and replacement (5,550 square feet), metal roofing replacement (6,660 square feet), and additional optional items for helicopter services (up to 5 hours), three-person work crews, and additional construction materials ($25,000 fixed). A mandatory pre-bid meeting was held on June 29, 2017 at 10:00 a.m. at Colorado Mountain College in Leadville. Sealed bids were due by July 12, 2017 at 4:00 p.m., with bid opening scheduled for July 13, 2017 at 10:00 a.m. The project is scheduled for construction between September 1 and October 20, 2017, with a 50-calendar-day completion deadline from the Notice to Proceed, including 10 days of mobilization. Award will be made to the lowest responsive and responsible bidder meeting all pre-qualification and responsiveness requirements.

Bidders must provide a bid bond equal to 5 percent of the total bid price and include a List of Equipment Offered with their submission. Pre-qualification requirements mandate submission of documentation showing at least two previous successful construction projects involving stabilization or preservation of historic structures, with verifiable client contact information. For bids exceeding $50,000, performance and payment bonds equal to 100 percent of the original contract price are required, along with commercial general liability insurance of $1,000,000 each occurrence and automobile liability insurance of $1,000,000 combined single limit. If the bid amount is between $50,000 and $149,999.99, 10 percent retainage will be withheld until project completion; if $150,000 or over, 5 percent retainage applies. Liquidated damages of $400 per day apply for completion delays beyond the 50-calendar-day deadline. The project is funded by Colorado Severance Tax. Payment will be made within 45 days of receipt of correct invoices, with interest accruing at 1 percent per month beginning on the 46th day for delinquent amounts. Contractors must comply with Colorado labor requirements (80 percent of laborers must be Colorado residents) and provide evidence of compliance with all federal and state safety regulations, environmental standards, and historical preservation requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO BID

Project Name: Champion Mill Stabilization Project (Revised) Bid Number: 2017 - 0297 Fund: PCAABIM60 Pre-Bid Meeting Date: June 29, 2017 Time: 10:00 A.M.

Bid Submittal Date: July 12, 2017 Time: 4:00 P.M.

Bid Opening Date: July 13, 2017___________Time: 10:00 A.M.____

To: Purchasing Agent Division of Reclamation, Mining and Safety Total Bid $ 1313 Sherman St., Rm. 215 Receipt of Addenda Nos.

Denver, Colorado 80203 is Hereby Acknowledged

1. BID: The undersigned bidder proposes to furnish all the labor and materials and to perform all the work required for the complete and prompt execution of everything described or shown in or reasonably implied from the Bidding Documents, including the Drawings and Specifications, for the base bid above indicated, and according to the attached Bid Schedule.

2. EXAMINATION OF DOCUMENTS AND SITE: The bidder has carefully examined the Bidding Documents, including the Drawings and Specifications, and has examined the site of the work, so as to make certain of the conditions at the site and to gain a clear understanding of the work to be done.

3. PARTIES INTERESTED IN BID: The bidder hereby certifies that the only persons or parties interested in this Bid are those named herein, and that no other bidder or prospective bidder has given any information concerning this Bid.

4. BID GUARANTY: This Bid is accompanied by the required Bid Guaranty. You are authorized to hold said Bid Guaranty for a period of not more than thirty (30) days after the opening of the Bids for the work above indicated, unless the undersigned bidder is awarded the Contract, within said period, in which event the Director, Division of Reclamation, Mining and Safety may retain said Bid Guaranty, until the undersigned bidder has executed the required Agreement and furnished the required Performance Bond, Labor and Material Payment Bond, Insurance Policy, Certificates of Insurance and any other documents required by the Special Conditions.

5. TIME OF COMPLETION: The bidder agrees to complete the entire project within __50 calendar days from the Notice to

Proceed, subject to Article 33 TIME OF COMPLETION and Article 39 LIQUIDATED DAMAGES, of The General Conditions of the Contract. If awarded this work, the bidder agrees to begin work within ten (10) days from the date of the Notice to proceed and agrees to prosecute the work with due diligence to completion.

6. EXECUTION OF DOCUMENTS: The bidder understands that if this Bid is accepted, he must execute the required Agreement and furnish the required Performance Bond, Labor and Material Payment Bond, Insurance Policy and Certificates of Insurance and any other documents required by the Special Conditions within ten (10) days from the date of the Notice of Award.

7. LATE BIDS: Unless there are extraordinary circumstances for which the Purchasing Director may approve a bid received after the time and date due it will be rejected per R-24-103-202a-07(a), Colorado Procurement Code and Rules.

8. The right is reserved to waive informalities and to reject any Bid.

(TYPE/PRINT NAME UNDER ALL SIGNATURES) Dated this day of , 20__

THE BIDDER

Signature

Name and Title (Typed or Printed)

Company Name

Address

Phone #

Signatures: If the Bid is being submitted by a Corporation, the Bid should be signed by an officer, i.e., President or Vice President.

If the Bid is being submitted by an individual or a partnership, the Bid shall so indicate and be properly signed.

Champion Mill Stabilization Project (Revised) Bid Schedule 2017 - 0297

ITEM DESCRIPTION QTY UNIT UNIT PRICE AMOUNT

1.0 Mobilization/Demobilization 1

Lump Sum N/A $

2.0 Project Safety, Health & Environmental Action Plan (SHEAP) 1

Lump Sum N/A $

3.0 Stabilize Upper Shed 1

Lump Sum N/A $

4.0 Stabilize Support Trusses & Posts 1

Lump Sum N/A $

5.0 Stabilize North Wall of Lower Shed 1

Lump Sum N/A $

6.0 Brace Masonry Wall 1

Lump Sum N/A $

7.0 Repair/Replace Rafters & Purlins 550

Linear Feet $ /LF $

8.0 Remove & Replace Roof Decking 5,550

Square

Feet $ /ft2 $

9.0 Replace Metal Roofing 6,660

Square

Feet $ /ft2 $

ADDITIONAL BID ITEMS – THESE BID ITEMS ARE NOT GUARANTEED

10.0 Helicopter Services 5 Hour $ /hr $

11.0 Provide Three Person Work Crew 8 Hour $ /hr $

12.0 Provide Add’l Construction Materials N/A N/A N/A $ 25,000.00

13.0 Previous Job Experience SUBMIT WITH BID N/A

TOTAL $

DO NOT AMEND ANY PART OF THIS BID SCHEDULE

ALL PAGES OF THIS BID SCHEDULE MUST BE RETURNED

ALL LINES ITEMS MUST BE COMPLETED

Page 1 of 1 Pages

State Form SBP-6.14 Rev. 9/2006

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAMS

BID BOND

Institution/Agency:

Project No./Name:

KNOW ALL MEN BY THESE PRESENTS:

WHEREAS, hereinafter called the “PRINCIPAL”, is submitting a PROPOSAL for the above described project, to the STATE OF COLORADO, hereinafter called the “OBLIGEE”.

WHEREAS, the Advertisement for Bids has required as a condition of receiving the Proposals that the Principal submit with the PROPOSAL GUARANTY in an amount not less than five per cent (5%) of the Proposal, which sum it is specifically agreed is to be forfeited as Liquidated Damages in the event that the Principal defaults in his obligation as hereinafter specified, and, in pursuance of which Requirement, this Bid is made, executed and delivered.

NOW THEREFORE, the Principal and a corporation of the State of , duly authorized to transact business in Colorado, as Surety, are held and firmly bound unto the Obligee, in the sum of five per cent (5%) of the Principal’s total bid price, lawful money of the United States for the payment of which sum, well and truly to be made to the Obligee, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

FURTHER THAT, a condition of the obligation that the Principal shall maintain his Proposal in full force and effect for thirty (30) days after the opening of the proposals for the project, or, if the Principal’s Proposal is accepted, the Principal shall, within the prescribed time, execute the required Agreement, furnish the required Performance Bond, Labor and Material Payment Bond, Insurance Policy, and Certificates of Insurance, then this obligation shall be null and void, otherwise it shall remain in full force and effect, and subject to forfeiture upon demand as Liquidated Damages.

IN WITNESS WHEREOF said Principal and Surety have executed this Bond, this day of , A.D., 20 .

(Corporate Seal) THE PRINCIPAL

Company Name

ATTEST

Address (including city, state and zip) Secretary Phone number:

Name (Print) Signature

Name (Print) and Title

SIGNATURES If the “Principal” is doing business as a Corporation, the Bid Bond shall be signed by an officer, i.e., President or Vice President. The signature of the officer shall be attested to by the Secretary and properly sealed.

If the “Principal” is an individual or a partnership, the Bid Bond shall so indicate and be properly signed.

(Corporate Seal) THE SURETY

By __________________________________________ Secretary Attorney-in-Fact

THIS BOND MUST BE ACCOMPANIED BY POWER OF ATTORNEY, EFFECTIVELY DATED.

FAILURE TO PROVIDE A PROPERLY EXECUTED BID BOND WITH A PROPERLY EXECUTED POWER OF

ATTORNEY WILL RESULT IN THE BIDDER’S PROPOSAL BEING DEEMED NON-RESPONSIVE.

As of 8/16/2012

LIST OF EQUIPMENT OFFERED

Under the headings below, list all equipment which you offer to perform the work described in the Bid. Please see “List of Equipment Offered” in the Special Conditions.

ITEM

MAKE

MODEL NUMBER

SERIAL NUMBER

YEAR

MANUFACTURED

THIS PAGE MUST BE RETURNED WITH YOUR BID

OR THE BID MAY BE CONSIDERED NON-RESPONSIVE

PAGE 1 OF 1 PAGE

SPECIAL CONDITIONS

Champion Mill Stabilization Project (Revised)

2017 - 0297

PROJECT LOCATION

The project is located in Lake County approximately fourteen (14) miles southwest of Leadville at the headwaters of Halfmoon Creek in the San Isabel National Forest. The Champion Mill sits in the shadow of Mount Champion at an elevation of 11,700 feet. Please see the attached map.

WORK SUMMARY

The project work will involve critical stabilization of the deteriorating Champion Mill by replacing compromised rafters, purlins and roof decking as necessary and reroofing the structure with galvanized corrugated metal. A portion of the structure will be replumbed and stabilized with steel cables and several support posts will be repaired or replaced. And a stone masonry wall will require bracing to prevent further failure.

PRE-BID MEETING AND SITE SHOWING

A mandatory pre-bid meeting and site showing will be held at Colorado Mountain College (CMC) in Leadville, Colorado on Thursday, June 29, 2017 at 10:00 a.m. Colorado Mountain College is located at 901 South Highway 24 (campus is up on the hill). Please see attached map. We will meet at the gazebo and proceed from there.

NOTE: Due to the inaccessibility of the Champion Mill this time of year, the pre-bid meeting will not be held at the project site. Instead the pre-bid will be conducted offsite at CMC where the project details and logistics will be presented and any potential questions answered.

The purpose of the Pre-Bid meeting is to afford potential bidders the opportunity to inspect the proposed work and access conditions. Attending the entire Pre-Bid meeting is mandatory. Bidders are advised to be prompt. A sign-in sheet will be available at the Pre-Bid meeting for firms to register their attendance. It is the bidder's responsibility to make certain their attendance is recorded on the sign-in sheet. Each individual may represent him/herself or a single company for the purpose of bidding. Signing the Pre-Bid Meeting attendance list to represent more than one person or company is not permitted. Failure to sign-in and sign out, as directed by the Project Manager, will be cause for rejection of a bid.

Please review Meeting Requirements PRIOR to the meeting. All interested bidders MUST attend. Bidding documents must be obtained prior to the pre-bid meeting. Any Documents that cannot be loaded to the VSS System are the ONLY documents that will be distributed at the Pre-Bid Meeting. A copy of the structural assessment report will be provided at the Pre- Bid.

Bidders are cautioned that, notwithstanding any remarks or clarifications given at this meeting and site showing, all terms and conditions of the contract documents remain unchanged unless they are changed by written amendment issued by the OWNER. If the answers to questions, or any amendment to the contract documents create ambiguities, it is the responsibility of the bidder to seek clarification prior to submitting a bid.

** PRE-QUALIFICATION REQUIREMENTS **

At the time of bidding, CONTRACTOR is required to provide OWNER with a list of at least two (2) successful construction projects documenting CONTRACTOR’s experience in stabilization or preservation of historic structures. Projects provided should be similar in nature and include the previous client’s contact information.

Please see Bid Item 13.0 on the Bid Schedule. There will not be any payment for submittal of this information. This information MUST be submitted with the bid. Bids received from contractors who fail to provide verifiable pre-qualification project experience will be considered non-responsive, and therefore the bid will be rejected.

BID SUBMITTAL

The Deadline for all bids to be submitted is no later than 4:00 p.m. on Wednesday, July 12, 2017.

All bids need to be submitted as SEALED BIDS in single copy for the work described herein. Bids will be received until the date and time specified above at the Colorado Division of Reclamation, Mining and Safety, 1313 Sherman Street, Suite 215, Denver, Colorado 80203. Electronic bids are NOT being accepted by the Vendor Self Service system at this time.

A responsive bid must include the following, properly completed:

• Bid Form

• Bid Schedule

• Bid Bond

• List of Equipment (including helicopter requirement for Bid Item 10.0)

• Previous Job Experience

This is a sealed bid. Telegraphic or electronic (FAX, Western Union, Telex, etc.) bids will NOT be accepted directly by the Division of Reclamation, Mining and Safety in response to this bid.

Bid Form. Bids shall be submitted on the bid form furnished. Bids must be manually signed in ink.

All bid items must be priced or the bid will be disqualified. In case of error in the extension of price, the unit price shall govern. If a Bid Schedule is included it must also be returned with the bid. The quantities listed on which unit prices are requested are estimates only. The prices indicated on the Bid Schedule and included in the Contract Documents shall include the cost of all labor and materials, equipment and services, and all other expenses necessary for the completion of the work.

Alternate bids will not be accepted. Bids must be signed as follows:

If the Bidder is a corporation: The bid must be signed by an officer (President or Vice President), and the title indicated.

If the Bidder is a proprietorship: The Owner must sign the bid and print or type his name, the business name.

If the Bidder is a partnership: The majority or general partner must sign the bid. The same person must sign the contract, if awarded. Also include the company name.

Bid Bond. A bid bond is required for all jobs over $50,000.00. A bid guarantee in an amount not less than five percent (5%) of the total bid price must be submitted in the form of a firm commitment, such as a bid bond, bank money order, certified check or cashier's check. Checks or money orders should be made payable to the Treasurer, State of Colorado. If a bid bond is submitted, the State form shall be used. An irrevocable letter of credit is not acceptable as a bid guarantee. Bid guarantees, other than bid bonds, will be returned (a) to unsuccessful bidders as soon as practicable after the opening of bids, and (b) to the successful bidder upon execution of such further contractual documents and bonds (including any necessary coinsurance or reinsurance agreements) as may be required by the bid as accepted.

Failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids may be cause for rejection of the bid.

If the successful bidder, upon acceptance of his bid by the OWNER, fails to execute such further contractual documents, and give such bond(s) (including any necessary coinsurance or reinsurance agreements) as may be required within ten (10) days after receipt of the Notice of Award, the contract may be terminated for default. In such event the CONTRACTOR shall be liable for any cost of procuring the work which exceeds the amount of his bid, and the bid guarantee shall be available toward offsetting such difference.

BID OPENING DATE

The bid opening date for this project is Thursday, July 13, 2017 at 10:00 am.

All bid openings are open to the public and bidders are welcome to attend and record the bid results.

A written tabulation of the Bid results will be available to those bidders who submit an email address or a clearly-visible, self-addressed, stamped envelope with their bid. Please allow two weeks for receipt of Bid results. Telephone requests cannot be honored because of time constraints.

Performance and Payment Bonds – ARE REQUIRED for bids over $50,000.00.

The contractor shall furnish a labor and material payment bond for 100 percent of the original contract price and a performance bond for 100 percent of the original amount of the contract. The bonds are required by State Law, Title 24-105,202,203, C.R.S., as amended. The bonds shall be submitted using the State forms. A certified or cashier’s check or bank money order may be accepted in lieu of the bonds. If a surety other than a bond is used, the State will hold fifty percent (50%) of the surety until the final settlement date and fifty percent (50%) for six (6) months after the final settlement date.

RETAINAGE

If the bid amount is between $50,000.00 and $149,999.00, 10 percent retainage will be withheld until the project has been satisfactorily completed and advertised. If the bid amount is $150,000.00 or over, 5% retainage will be withheld until the project has been satisfactorily completed and advertised.

List of Equipment Offered. The List of Equipment Offered form must be returned with each bid.

All equipment to be used on the project must be listed. The CONTRACTOR must own, have a current lease for the equipment intended to be used to perform the work, or must furnish a statement of arrangements to rent, or otherwise procure, adequate equipment to perform the work. Inclusion of a piece of equipment on the List of Equipment Offered represents a commitment to devote that piece of equipment to the project work for the entire duration of the project. If several contractors propose to join together to perform the work under this contract, equipment owned or controlled by each should be listed and the owner identified. A contract will not be awarded to a bidder who in the opinion of the OWNER (a) does not have adequate equipment, or (b) does not have firm and satisfactory arrangements to obtain adequate equipment to perform the work described in the Invitation and Bid.

If the List of Equipment Offered is not submitted with the bid, the bid may be considered non-responsive. Include helicopter requirement for Bid Item 10.0.

BID AWARD

Award will be made with reasonable promptness, by written notice to the low responsive and responsible bidder whose bid meets the requirements and criteria set forth in the Invitation for bid.

These criteria will include, but not be limited to the lowest GRAND TOTAL PRICE, corrected if necessary for errors in price extension and/or addition, on the Bidder's equipment if a List of Equipment Offered is required with the bid, and capability to meet the performance time requirements. The GRAND TOTAL PRICE will be used for comparing bids only.

To be considered responsive and responsible, bidders may not have a Below Standard "(1)", OVERALL (Final) performance rating in the Colorado Contract Management System (CMS), for any construction project completed for Colorado in the last five years, per C.R.S. 24-105- 1(2)

Additive Alternates. The lowest responsible bid, taking into account the Colorado resident bidder preference, Article 14 of the General Conditions, will be determined by and the contract will be awarded on the base bid plus all additive alternates, to the extent that the addition of alternates results in a sum total within available funds to finance the contract. Additive alternates will be used in determining the lowest responsible bidder, adding in the numerical order listed. An equal number of alternates shall be added to the base bid of each bidder within funds available to finance the contract for the purposes of determining the lowest responsible bidder. If this bid exceeds such amount, the right is reserved to reject all bids.

GENERAL BID SPECIFICATIONS

The Colorado Inactive Mine Reclamation Program General Bid Specifications 2009, which include General Conditions, Standard Work Specifications, and Standard Drawings and Figures are intended to complement these Special Conditions. The Special Conditions combined with the General Bid Specifications 2009 form the complete Invitation and Bid document. Please refer to the Standard Work Specifications for all applicable types of work required in the Special Conditions. The General Conditions apply to all work covered in the Special Conditions. Copies of the General Bid Specifications are available at the Pre-Bid Meeting or from the Division of Reclamation, Mining and Safety (CDRMS), 1313 Sherman Street, Room 215, Denver, Colorado 80203 (303) 866-3567.

PROJECT DATES

The project is scheduled for construction between September 1, 2017 and October 20, 2017. This includes ten (10) days mobilization time. These dates are tentative and may change.

TIME OF COMPLETION

The time of completion allowed for the project is fifty (50) calendar days after receipt of the Notice to Proceed. This includes ten (10) days mobilization time.

LIQUIDATED DAMAGES

The liquidated damages for this project will be $400.00 per day. Please see General Conditions, Article 39.

NOTICE OF AWARD AND EXECUTION OF DOCUMENTS

A Notice of Award will be sent to the apparent low bidder with reasonable promptness. The contract signing date and time will be set for fourteen (14) days after the bid is awarded. The Division of Reclamation, Mining and Safety must receive the following:

(a) Executed Agreement;

(b) Fully-executed Performance and Payment Bonds, accompanied by appropriate Power of Attorney, if required;

(c) Certificates of Insurance showing proof of required coverage and Additional

Insured Endorsement;

(d) Project schedule;

(e) AML Contractor Ownership and Control Form;

(f) Minority (MBE)/women (WBE) Business Participation form;

(g) Three-Way Agreement for Reclamation Activities, if required by the Special

Conditions;

(h) A list of all subcontractors to be used on the project, the work tasks and dollar value to be subcontracted to each, and

(I) Completed W-9 forms, if required (for contractors new to the State).

(j) Project Schedule

Please consult Articles 2-7 of the General Conditions.

If the above documents are not submitted properly by the contract signing date, the Division of Reclamation, Mining and Safety may elect to award the contract to the next lowest bidder. Bidders are advised to keep close contact with CDRMS during this period.

THREE-WAY AGREEMENT

A three way "Agreement for Reclamation Activities" is not required for this job. Please see Article 4 of the General Conditions for the applicable insurance requirements.

CONDITIONS AFFECTING THE WORK

In addition to examining the drawings and specifications, completion schedule, and other instructions, bidders shall visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, including average climatic conditions and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work.

PROJECT FUNDING

This project is funded by Severance Tax collected by the State of Colorado.

AMERICANS WITH DISABILITIES ACT

All programs, services and activities of the Department of Natural Resources, Division of Reclamation, Mining and Safety and the Colorado Mined Land Reclamation Board are operated in compliance with the Americans with Disabilities Act. Questions, complaints and requests for additional information may be directed to ADA Coordinator, Department of Natural Resources, 1313 Sherman Street, Room 415, Denver, CO 80203.

CORA DISCLOSURE

To the extent not prohibited by federal law, this Contract and the performance measure and standards under CRS 24-103.5-101, if any, are subject to public release through the Colorado Open Records Act, CRS 24-72-101, et. seq.

STATEWIDE CONTRACT MANAGEMENT SYSTEM

By entering into this Contract, Contractor agrees to be governed, and to abide, by the provisions of CRS §24-102-205, §24-102-206, §24-103-601, §24-103.5-101 and §24-105-102 concerning the monitoring of vendor performance on state contracts and inclusion of contract performance information in a statewide contract management system.

Contractor’s performance shall be evaluated in accordance with the terms and conditions of this Contract, State law, including CRS §24-103.5-101, and State Fiscal Rules, Policies and Guidance.

Evaluation of Contractor’s performance shall be part of the normal contract administration process and Contractor’s performance will be systematically recorded in the statewide Contract Management System. Areas of review shall include, but shall not be limited to quality, cost and timeliness.

Collection of information relevant to the performance of Contractor’s obligations under this Contract shall be determined by the specific requirements of such obligations and shall include factors tailored to match the requirements of the Statement of Project of this Contract. Such performance information shall be entered into the statewide Contract Management System at intervals established in the Statement of Project and a final review and rating shall be rendered within 30 days of the end of the Contract term. Contractor shall be notified following each performance and shall address or correct any identified problem in a timely manner and maintain work progress.

Should the final performance evaluation determine that Contractor demonstrated a gross failure to meet the performance measures established under the Statement of Project, the Executive Director of the Colorado Department of Personnel and Administration (Executive Director), upon request by the Department of Natural Resources, and showing of good cause, may debar Contractor and prohibit Contractor from bidding on future contracts. Contractor may contest the final evaluation and result by: (i) filing rebuttal statements, which may result in either removal or correction of the evaluation (CRS §24-105-102(6)), or (ii) under CRS §24-105-102(6), exercising the debarment protest and appeal rights provided in CRS §§24-109-106, 107, 201 or 202, which may result in the reversal of the debarment and reinstatement of Contractor, by the Executive Director, upon showing of good cause.

INDEMNIFICATION

Contractor shall indemnify, save and hold harmless the State, its employees and agents, against any and all claims, damages, liability and court awards including costs, expenses and attorney fees and related costs, incurred as a result of any act or omission by Contractor or its employees, agents, subcontractors, or assignees pursuant to the terms of this contract.

PROJECT WORK DESCRIPTION

The project work will involve stabilization of the deteriorating Champion Mill by replacing compromised rafters, purlins and roof decking as necessary and reroofing the structure with galvanized corrugated metal. A portion of the structure will be replumbed and stabilized with steel cables and several support posts will be repaired or replaced. And a stone masonry wall will require bracing to prevent further failure.

A structural assessment was completed on the Champion Mill in 2016 to identify the repairs required to stabilize the structure. This project will focus on the “Critical Repairs” recommended in the report.

All repairs will be undertaken in collaboration with a consulting structural engineer with experience in historic building preservation. Wherever the specifications or assessment report disagree with the structural engineer on treatment recommendations, the advice provided by the structural engineer will be adhered to. A copy of the structural assessment report will be provided at the pre-bid meeting.

Please see the attached drawings and photos for additional structural details.

Item 1.0: Mobilization/Demobilization This item includes all costs necessary and incidental to move equipment and supplies onto the project area, perform minimal road improvements, if required, move equipment within the project area during prosecution of the project, and any other requirements necessary for the successful completion of this project per Section 1.0 of the General Bid Specifications 2009. The CONTRACTOR shall also operate and maintain such temporary works and equipment throughout the period of construction. This item also includes all labor, equipment, and costs associated with demobilization and clean-up of the project site following the completion of the project. Applicable temporary works, such as sanitation facilities, shall fully comply with all rules and regulations.

Measurement and payment No measurement for payment shall be made for mobilization and demobilization. Payment of two-thirds of the lump sum price bid for Item 1.0 of the Bid Schedule shall be made with the first monthly progress payment after completion of the work described above for mobilization. Payment of one-third of the lump sum price bid for this task will be made with the progress payment following completion of all work. In the event the price bid for mobilization and demobilization items is greater than 15 percent (15%) of the total contract price, original invoices supporting the mobilization costs will be required before payment is approved.

Remobilization, if required, will be paid in accordance with the General Bid Specifications Section 1.4.4.

Item 2.0: Project Safety, Health, and Environmental Action Plan (SHEAP) The job will involve working around inactive mine features and hazards, and it is the responsibility of the CONTRACTOR to be aware of all OSHA regulations which apply to this contract. This task includes all the contractor’s expenses for employee time, labor, materials, and safety equipment and safety training necessary for preparing and executing a job safety plan. The Successful Bidder will be required to prepare the Project Safety Plan (SHEAP) and submit it for review and approval to the DRMS. The CONTRACTOR is required to develop and implement a Project Safety Plan in conjunction with project implementation. PROJECT MANAGER must receive the Project Safety Plan within five (5) working days of Notice to Proceed date.

The Project Safety Plan must be submitted to:

Craig Bissonnette PO Box 1619 Leadville, CO 80461

FAX (303) 832-8106

craig.bissonnette@state.co.us

At a minimum, the plan MUST provide specific, detailed responses to the following list of safety concerns that are likely to present themselves during the course of Project completion. When developing the Project Safety Plan, please list specific types of equipment to be provided by CONTRACTOR, including subcontractor(s), in order to address the safety concern, or specifically state the actions to be taken by CONTRACTOR, including crew and subcontractor(s) order to address the safety concern.

It is expected that the Project Safety Plan will be comprehensive and sufficiently detailed so that every member of the work crew, including sub-contractors, on site understands their responsibilities and the responsibilities of CONTRACTOR to ensure a safe and injury free work place. The Project Safety Plan must be provided to the work crew members in the language in which they are most readily able to comprehend.

Upon receipt of the SHEAP, the OWNER will either accept the plan, or request that more detail be provided.

The CONTRACTOR and their employees or sub-contractors are expected to follow the SHEAP during performance of every component of the Project. If the PROJECT MANAGER determines that the SHEAP is not being followed, either in whole or in part, the Project may be immediately suspended, without stopping the job clock, until such time as the SHEAP is implemented.

Measurement and Payment There will be no measurement for payment. Payment for this task shall be for the lump sum bid price under Item 2.0 of the Bid Schedule. This lump sum bid will cover all costs for developing and implementing the SHEAP, including writing and revising the plan as required, provisions and maintenance of safety equipment and personnel, conduct of daily safety meetings, employee training, and all other items necessary and incidental to fulfilling the requirements of this task and of the SHEAP. Payment of two-thirds of the lump sum price bid for Item 2.0 shall be made with the first monthly progress payment. Payment of one-third of the lump sum price bid will be made with the progress payment following completion of all work. Payment will only be made upon approval from the PROJECT MANAGER.

Item 3.0: Stabilize Upper Shed The upper stages of the structure, starting at the south top plates (south end of the upper shed), exhibit severe wracking toward the west. The leaning becomes more severe through the structure as the wall runs north. A plumb line dropped from a height of thirty feet (30’) to the floor of Deck 2 fell four feet four inches (4’-4”) from the base of the wall indicating an average lean of 8.22° from the vertical. A measurement taken within the ore bin demonstrated a deviation of three feet eight inches (3’-8”) over fifteen feet (15’); a lean of 13.74° from plumb.

CONTRACTOR shall stabilize and replumb the upper stage of the shed structure. Brace interior walls with three-eighths inch (3/8”) or greater, galvanized steel cables. Where cables attach to the structure, install timber or steel bearing plates to spread the load over a greater surface area to avoid point loading.

Install six inch by six inch (6” x 6”) or two inch by ten inch (2” x 10”) glulam (glue laminated timber) struts at a forty-five degree (45°) angle to wall and floor. Cost of fasteners must be included in the bid price for this task.

Measurement and Payment No measurement for payment shall be made for this task. Payment will be lump sum under Item 3.0 of the Bid Schedule, and will be made upon completion of the specified tasks and approval by the PROJECT MANAGER. The price bid shall include all materials, labor, equipment and any other items necessary and incidental to complete the tasks as described.

Item 4.0: Stabilize Support Trusses and Posts Trusses supporting the rooms projecting to the north, east and west from the upper shed have failed in multiple places as a result of the wracking in the main structure.

CONTRACTOR shall stabilize the load critical structural trusses supporting the north, east and west projecting rooms with timber posts, glulams or steel C-channel depending on location, deterioration and access. The method of reinforcement in the various locations will be determined onsite. Any timbers replaced will be of the same size and type and will be joined in the same manner originally employed.

Reinforce split post in middle stage of upper shed using six inch (6”) steel C-channel and one-half (1/2) inch bolts. The steel C-channel will span the compromised section of the post and extend above and below the split a minimum of eighteen inches (18”) and will be bolted every twelve inches (12”). Cost of fasteners must be included in the bid price for this task.

Measurement and Payment No measurement for payment shall be made for this task. Payment will be lump sum under Item 4.0 of the Bid Schedule, and will be made upon completion of the specified tasks and approval by the

Item 5.0: Stabilize North Wall of Lower Shed The weight of retained earth and debris is causing the masonry wall in the lower shed to bow inward and as a result, the sill plate and wall system sitting on the wall are consequently being thrust inward also.

CONTRACTOR shall replumb and stabilize the north wall of the lower shed by installing six inch by six inch (6” x 6”) wooden posts, braces and kickers to transfer the load vertically into the ground to reduce the pressure on the masonry wall below. Removal of rocks, timber and debris will be required to complete this task. Material removed will be placed neatly to the side in an area designated by the PROJECT MANAGER. Cost of fasteners must be included in the bid price for this task.

Measurement and Payment No measurement for payment shall be made for this task. Payment will be lump sum under Item 5.0 of the Bid Schedule, and will be made upon completion of the specified tasks and approval by the

Item 6.0: Brace Masonry Wall The stone masonry wall in the lower shed is bowing inward due to pressure from the retained earth.

The unbraced section of wall is fourteen feet (14’) in height and spans roughly fifteen feet six inches (15’-6”). The wall leans into the room from the top at a maximum of about 13.54° from the vertical.

CONTRACTOR shall stabilize the retaining wall by covering it with two (2) layers of three-quarter inch (3/4”) plywood and installing eight inch by eight inch (8” x 8”) vertical posts and kickers at forty-five degrees (45°). Four (4) brace sets will be constructed approximately every four feet (4’). A ground anchor will be constructed to secure each kicker in place. Cost of fasteners must be included in the bid price for this task.

Once the retaining wall has been braced, CONTRACTOR will slope the ground surface on the outside of the structure to ensure positive drainage to the west and away from the wall.

Measurement and Payment No measurement for payment shall be made for this task. Payment will be lump sum under Item 6.0 of the Bid Schedule, and will be made upon completion of the specified tasks and approval by the

Item 7.0: Repair or Replace Rafters and Purlins While the overall roof support structure is relatively sound, some repairs to the rafters and purlins are required.

Compromised rafters will be repaired or replaced as needed or directed by the PROJECT MANAGER. Approximately five percent (5%), or fifty (50) linear feet of rafters, have been identified as needing repair or replacement. Rafter timbers measure eight inches by eight inches (8” x 8”).

Compromised purlins will be repaired or replaced as needed or directed by the PROJECT MANAGER. Approximately fifteen percent (15%), or five hundred (500) linear feet of purlins, have been identified as needing repair or replacement. Purlins measure eight inches by three inches (8” x 3”).

Timber dimensions are nominal. Any timbers replaced will be of the same size and type and will be joined in the same manner originally employed. Cost of fasteners must be included in the bid price for this task.

Measurement and Payment Payment for this task will be made at the unit price established in Item 7.0 of the Bid Schedule.

Repairs will be measured to the nearest linear foot and paid at the unit price bid on the Bid Schedule under Item 7.0. The price bid shall include all costs for labor, materials, equipment, fasteners and all other items necessary and incidental to complete the tasks as described. Payment will be made upon completion of the described task and approval by the PROJECT MANAGER.

Item 8.0: Remove and Replace Roof Decking Large sections of metal roofing is missing and as a result the underlying roof decking has deteriorated due to exposure.

Compromised roof decking will be removed and replaced as needed or directed by the PROJECT MANAGER. Approximately eighty percent (80%), or five thousand, five hundred and fifty (5,550) square feet of roof decking has been identified as needing replacement. Roof decking measures one inch by six inches (1” x 6”). Timber dimensions are nominal. Cost of fasteners must be included in the bid price for this task.

Measurement and Payment Payment for this task will be made at the unit price established in Item 8.0 of the Bid Schedule.

Repairs will be measured to the nearest square foot and paid at the unit price bid on the Bid Schedule under Item 8.0. The price bid shall include all costs for labor, materials, equipment, fasteners and

Item 9.0: Replace Metal Roofing Missing or deteriorated metal roofing will be replaced as needed or directed by the PROJECT MANAGER. Approximately ninety percent (90%), or six thousand, six hundred and sixty (6,660) square feet of metal roofing has been identified as needing replacement. Metal roofing shall be twenty-six (26) gauge, twenty-four (24) inch coverage galvanized corrugated steel panels. The roofing will be attached using one and one-half (1-1/2) inch metal-to-wood roofing screws.

Additionally, all existing metal roofing that is retained will be refastened with the same one and one-half (1-1/2) inch metal-to-wood roofing screws. Approximately seven hundred and fifty (750) square feet of existing metal roofing will need to be secured. Cost of fasteners must be included in the bid price for this task.

Measurement and Payment Payment for this task will be made at the unit price established in Item 9.0 of the Bid Schedule.

Repairs will be measured to the nearest square foot and paid at the unit price bid on the Bid Schedule under Item 9.0. The price bid shall include all costs for labor, materials, equipment, fasteners and

ADDITIONAL BID ITEMS

There are included on the Bid Schedule, several additional bid items. These bid items are not guaranteed, and will be used only in the event that conditions change on site, and only after approved by the PROJECT MANAGER. The additional bid items for this project include:

Item 10.0: Helicopter Services The access road leading to the Champion Mill is rugged and crosses the creek at several locations requiring high-clearance, four-wheel drive capability. Due to the difficult nature of the access road, it is anticipated that helicopter services will be needed to facilitate the transport of some materials and equipment to the project site. This Item is not guaranteed.

CONTRACTOR shall arrange for helicopter services capable of lifting loads to the project site at 12,000’ in elevation. Up to five (5) hours of helicopter time may be required for this project.

The number of hours indicated above is estimated. It is difficult to determine in advance the actual number of hours that may be necessary. Payment will not be provided for delays or downtime caused as a result of improper rigging, overweight loads or contractor negligence.

The List of Equipment Offered must specify the exact helicopter that will be used to accommodate this Bid Item. The PROJECT MANAGER will determine if the equipment offered is capable of performing the tasks required for this project. Failure to provide this information with the List of Equipment Offered may deem the bid non-responsive and cause for rejection.

One helicopter outfit that operates out of the Lake County Airport is RAVCO - Rota Aviation Company.

RAVCO can be contacted at 970-366-6600 or through their website: www.ravco.com. The information provided is one local resource. CONTRACTOR is not obligated to use these services.

Measurement and payment Payment for this task will be made at the unit prices established in Item 10.0 of the Bid Schedule.

The number of helicopter hours used under this specification will be counted to the nearest one half hour. Such payment shall include the cost of all materials, accessories, labor, maintenance, operating supplies, fuel, salaries of operators, ground crews and any other expenses incidental to the operation of the specified equipment to complete the tasks as described in Item 10.0.

http://www.ravco.com/

Item 11.0: Provide Three Person Work Crew If required, this Item provides for a three (3) person work crew for up to eight (8) hours to conduct miscellaneous tasks within the designated work area as directed by the PROJECT MANAGER. This Item is intended to be used if additional materials are required under Item 12.0 or for other tasks that may be needed. The CONTRACTOR’s hourly rate bid should include all employee costs, profit and use of onsite tools and equipment. Any required tasks will be determined and authorized by the PROJECT MANAGER. This Item is not guaranteed.

Measurement and Payment Payment for this task will be made at the unit price per hour bid under Item 11.0 of the Bid Schedule.

Hours will be measured to the nearest one-half (0.5) hour. The price bid for providing a work crew to perform miscellaneous tasks shall include all labor, tools, equipment, salaries and any other items necessary and incidental to complete the tasks described in Item 11.0. Payment shall be as this Item is completed and approved by the PROJECT MANAGER.

Item 12.0: Provide Additional Construction Materials If required, this Item provides funding in the event of unforeseen material needs. CONTRACTOR will be required to provide additional construction materials only as requested and authorized by the PROJECT MANAGER. Additional construction materials may include any materials deemed necessary to successfully complete the critical stabilization of the Champion Mill. CONTRACTOR will be required to purchase and supply to the project site any requested materials or an approved equivalent alternative. Cost of requested materials must be authorized by the PROJECT MANAGER prior to purchasing. This Item will not be used to purchase materials specified under any other Bid Item in these specifications. Installation of additional materials will be covered under Item 12.0. This Item will have a fixed-price of $25,000.00 established on the Bid Schedule. This Item is not guaranteed.

Measurement and Payment Payment for this Item will be made based on CONTRACTOR’s submission of itemized receipts for the requested items delivered to the project site. Payment will include documented receipt value of items requested plus and additional twenty percent (20%) of the documented receipt value. Such Payment will be considered full compensation for provision of the requested item and delivery to the project site.

PROJECT OBSERVATION

The PROJECT MANAGER will be at the project site periodically to monitor construction activities and ensure that each work item is completed and constructed to design specifications. The PROJECT MANAGER will be available during regular business hours (8:00 A.M. to 5:00 P.M.) on weekdays. Inspections will not be scheduled on weekend days or holidays without prior approval of the PROJECT MANAGER. It is the Contractor's responsibility to schedule inspections with the Project Manager so as not to delay the work. The following items must be observed and approved by the PROJECT MANAGER before proceeding with additional work:

• All stabilization treatments must be approved by the PROJECT MANAGER before starting work on any tasks.

Colorado Division of Reclamation, Mining and Safety SPECIFIC CONDITIONS

SHEAP

As of 06/08/09 Page 1

STANDARD WORK SPECIFICATIONS

SAFETY, HEALTH, & ENVIRONMENTAL ACTION PLAN RESPONSE ITEMS

The following is a summary list of items that must be addressed in writing by the CONTRACTOR. All items that are checked ( ) apply to the work to be performed and must be addressed in a written plan. Each employee is to read and sign the plan as part of the project orientation prior to starting work on the project.

A. SITE ACCESS

No person may enter the job site without first receiving hazard training from CONTRACTOR’S safety representative.

CONTRACTOR employees are required to travel to and from their work areas by designated routes.

All CONTRACTOR equipment is subject to a safety inspection before entering the job site.

B. PART 48 TRAINING REQUIREMENTS

Each CONTRACTOR employee shall receive orientation training, provided by the CONTRACTOR, comprised of all aspects of the contract's Safety, Health and Environmental Action Plan (SHEAP).

C. SUBSTANCE ABUSE SCREENING

Alcohol and drugs are not allowed on the job site.

D. PROACTIVE SAFETY

The CONTRACTOR shall designate one person to be the safety representative responsible for safety and health at the work site.

The CONTRACTOR shall conduct safety meetings at least weekly.

All safety meetings shall be documented and include the date, subject matter, trainer and all participants signatures.

Daily pre-job safety talks shall be given by the CONTRACTOR.

Any change in the daily work plan shall be communicated by the CONTRACTOR to all affected personnel.

The CONTRACTOR shall conduct daily work area inspections.

These inspections shall be documented in an approved book.

E. GENERAL SAFETY STANDARDS

Horseplay will not be tolerated.

Safety glasses, steel toe boots and hard hats are required to be worn at all times. This equipment must meet ANSI standards.

Safety glasses and a face shield or goggles are required when performing any work that generates or could generate flying debris or when this type of work is being performed.

As of 06/08/09 Page 2

Trenches and other excavations more than three feet deep must be properly shored or laid back to a 1:1 slope before personnel are allowed to enter.

Procedures for night work shall be established and adequate illumination shall be provided.

During drilling and underground work, a recently calibrated multi gas tester with audible alarm (measuring O2 , CO, H2S) shall be used at all times. A record shall be kept of tests.

An MSHA 40 hour underground mine safety training certificate, or a current Underground Miner training certificate, is required for each employee working underground.

Self-rescuers must be worn during underground work.

Rubber boots or waders shall be provided for each employee working in wet conditions.

Temperature sensors shall be provided at work locations.

Other safety requirements: Be aware of hazardous weather and lightening

F. ACCIDENT REPORTING

All accidents and injuries must be immediately reported to the Colorado Division of Reclamation, Mining and Safety project manager.

The CONTRACTOR shall investigate all such occurrences and develop an action plan to prevent their recurrence.

All investigations shall be documented.

G. FIRST AID

First aid kits meeting MSHA (CFR 75.1713-7 or 77.1707) requirements shall be maintained in a sanitary condition and placed at all work sites.

H. COMMUNICATIONS

All work areas shall have a method to communicate with other personnel at all time. Personnel will never be allowed to work alone without a secure means of communication and periodic checks by another party.

All communications will be positive in nature. A response is required.

Provide an equipment spotter equipped with a radio.

I. EQUIPMENT OPERATION

Seatbelts shall be used at all times.

Equipment always has the right-of-way.

Safe parking procedures (chock blocks, etc.) shall be used at all times.

All lights, horns, brakes, wipers, back-up alarms and other safety equipment shall be fully operational at all times.

Each piece of equipment shall have at least one portable fire extinguisher.

As of 06/08/09 Page 3

All mobile equipment, with the exception of pickup trucks with unrestricted rear view, will be equipped with back-up alarms.

Mobile equipment shall be equipped with roll-over-protection (ROPS) and/or falling object protection structures (FOPS) as required by MSHA regulations.

All machinery shall be secured to ensure zero mechanical potential prior to work being performed on the machinery.

Equipment shall be maintained in safe condition.

Provide a driller’s safety platform.

Inspect hydraulic and pneumatic lines and couplings daily.

Provide whip checks for all airline connections.

J. ELECTRICAL SAFETY

Overhead line clearances shall be checked…