CH-53K_CNI PERFORMANCE SPECIFICATION_DRAFT_11-25-24.docx
DOCX document 745 KB Posted
- Attached to
- CH-53K Communication, Navigation, and Instrumentation Part Task Trainer (CNI PTT) Sources Sought Notice
- Solicitation number
- N6134025R0022
About this file
This is a Performance Specification document for a CH-53K Communication, Navigation and Instrumentation (CNI) maintenance trainer (Device 11B112) for the United States Marine Corps, to be located at the Center for Naval Aviation Technical Training Marine Unit facilities at MCAS New River, Jacksonville, North Carolina.
The specification defines requirements for a full-size maintenance task trainer that replicates the CH-53K nose, cockpit, and forward cabin section to Station 282, including instrument panels, consoles, avionics bays, flight controls, displays and other systems. The trainer must support maintenance training tasks including system functional testing, fault isolation, troubleshooting, and component replacement across 49 different aircraft systems ranging from flight controls to communications equipment. Key requirements include an instructor operator station for fault insertion/control, high-fidelity physical components matching the actual aircraft, replicated wiring and interfaces, and the ability to simulate normal operations and fault conditions according to aircraft technical manuals. The trainer must operate in an unclassified mode and meet various environmental, safety, cybersecurity and maintainability requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CH-53K CNI PTT - Sources Sought Notice (2024-11-26).docx | DOCX document | |
| CH-53K_CNI STATEMENT OF WORK_DRAFT_11-22-24.docx | DOCX document | |
| CH-53K CNI PTT - Sources Sought Notice (2024-11-26).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| CUI | PRF 230007B |
| 22 Nov 2024 |
PRF 230007B
22 November 2024
SUPERSEDING
| PRF 230007A |
| CAGE 89297 |
| 14 March 2024 |
PERFORMANCE SPECIFICATION
FOR
UNITED STATES MARINE CORPS
CH-53K Communication, Navigation and Instrumentation (CNI) Maintenance Trainer
NAVAL AIR WARFARE CENTER
TRAINING SYSTEMS DIVISION
12211 SCIENCE DRIVE
ORLANDO, FL 32826
APPROVED BY: _________________________________ DATE:
Jenny Barriger (PMA-205, Level II IPTL) H-53 Training Systems of designee
APPROVED BY: _________________________________ DATE:
Lynn Rau (APME designee) APEO (E) or designee
APPROVED BY: _________________________________ DATE:
Chad Guillet (PSM designee) APEO (L) or designee
APPROVED BY: _________________________________ DATE:
Ryan Schmidt (APMT&E designee)
Distribution Statement D: Distribution authorized to Department of Defense and U.S. DoD contractors only; Controlled Technical Information (CTI); 8 November 2019. Other requests for this document must be referred to Program Executive Officer Air (PEO(A)), PMA-261, 47123 Buse Rd., Building 2272 RM 155, Patuxent River, MD 20670.
Controlled by: Department of Navy Controlled by: NAWCTSD CUI Category: CTI Distribution/Dissemination Control: FEDCON
CUI
POC: Cattien.T.Nguyen.civ@us.navy.mil
CUI
REVISIONS
| Revision |
| Affected Paragraph(s) |
| Changes |
| Initial Release |
| All |
| PRF 230007 baseline for CNI Device 11B112 |
A
| 2.2.1 |
| Removed MIL-DTD-461G and MIL-STD-464D |
| 2.2.2 |
| Removed 47 CFR 15 and 47 CFR 15.109 |
| 2.3 |
| Removed BS EN 55035:2017+A11:2020, IEC 61000-4-2:2008, and UNE EN 55032:2016/A1:2021 |
| 3.1.1.a, b |
| Changed station 242 to station 282. |
| 3.3.1.a |
| Changed "provide for operational modes ranging from Unclassified up to and including SECRET NOFORN classification", to "provide for unclassified operational modes", |
| 3.4.1.1 |
| Deleted electromagnetic compatibility requirements |
| 3.4.1.1.1 |
| Deleted intra system EMC requirements |
| 3.4.1.2 |
| Deleted electromagnetic interference requirements |
| 3.4.1.3 |
| Changed electrostatic discharge requirements to “The trainer shall assure that all electrical and electronic system devices are not damaged by EST during handling, testing, maintenance, and operation. |
| 3.4.2 |
| Changed from “…requirements for both direct and indirect effects of lightning as defined in IAW MIL-STD-464D” to “…requirements for indirect effects of lightning” |
| 3.4.3 |
| Removed MIL-STD-464D reference; added minimum bonding resistance requirement; added bonding of trainer removable panels requirement. |
| 3.4.3.1.a |
| Changed from “…from the facility earth ground to the first equipment closure, from the first equipment enclosure to subsequent equipment enclosure(s) and equipment enclosure to system structure…effect of all faying…” to “…from the equipment enclosure to system structure…effect of the faying…” |
| 3.4.3.1.c |
| Changed from “…or less across…the equipment and equipment enclosure(s), such…” to “…or less resistance across…the equipment, such…” |
| 3.8.1 |
| Fixed the numbering to start with a. Previously started with f |
| 3.8.2.c |
| Deleted MIL-STD-461G |
| 3.8.2.d |
| Deleted MIL-STD-464D |
| 4.3.4.1.1 |
| Deleted EMC verification |
| 4.3.4.1.1.1 |
| Deleted intra-system EMC verification requirements |
| 4.3.4.1.2 |
| Deleted EMI verification requirements. |
| 4.3.4.1.3.a |
| Deleted “as defined inANSI/ESDA/JEDEC JS-001-207 (Human Body Model (HBM) EST)” |
| 4.3.4.1.3.b |
| Deleted “by applying MIL-STD-461G: CS118, Personnel Borne Electrostatic Discharge procedure: |
| 4.3.4.2 |
| Updated lightning verification language |
| 4.3.4.3 |
| Updated bonding verification language |
Revision A Changes Accepted
Michael Miller USMC APMSE
| B |
| 2.2.2 |
| Deleted reference to DFARS 252.227-7014. |
| 3.b |
| Removed “…available 30 days prior to CDR…”. |
| 3.c |
| Replaced “…available 30 days prior to Critical Design Review (CDR)” with “…with IETM lockdown to occur NLT 30 days prior to PDR and provided to seller”. |
| 3.1.1.e |
| Changed from “…available 30 days prior to CDR…” to “…available 30 days prior to PDR…”. |
| 3.1.1.h then throughout the document |
| Changed from “…A1-CH53K-IETM-MMO-000 available 30 days prior to CDR…” to “…A1-CH53K-IETM-MMO-000 available 30 days prior to PDR…” |
| 3.1.3.36.c |
| Deleted from statement “contain the components, subcomponents and hardware to” |
| 3.1.3.42.e |
| Deleted “TGB/IGB Chip Detector System. Added “Tail Pylon Fold System”. |
| 3.1.4 |
| Modified section language to clarify the number Operational Hours (standard workday) and the number of Continuous Powered Hours (continuous operability) that will satisfy the Operational Availability and Reliability requirement for the trainer. |
| 3.3.1 |
| Removed “b. include device architecture designed for quick and easy transition between classified and unclassified operational modes, and” |
| 3.3.2 |
| Removed “with a Classified overlay”. |
| 3.5.5.3.c |
| Added language “software interface” to the sentence. |
| 3.6.3 |
| Language clarification to include harness and cable containment means that will not cause cable insulation damage. |
| 3.7.3.3.5 |
| Accessibility language was modified to clarify means to access internal components and parts, complete required testing and perform routine servicing and maintenance. |
| 3.7.6.g |
| Reworded statement to clarify requirement to relocate the training device without the need of special support equipment. |
| 3.7.6.h |
| Deleted reference to back-up generator. |
| 3.8.2.b |
| Language change MIL-HDBK-454C can be used as guidance. |
| 3.8.2.e |
| Deleted reference manual. |
| 3.8.8.1.a |
| Clarification added to the required warning label on electrical & electronic units enclosure that contain more than one source of electrical power. |
| 4.2.c |
| Incremental Configuration Audit – Deleted! |
| 4.2.d |
| Change from Final Physical Configuration Audit to Drawing Configuration Audit. |
| CUI | PRF 230007B |
| 22 Nov 2024 |
iii
CUI
Table of Contents
| Section | Title | Page |
| 1. | SCOPE | 1 |
| 1.1 | System Identification | 1 |
| 1.2 | System Overview | 1 |
| 1.3 | Document Overview | 1 |
| 2. | APPLICABLE DOCUMENTS | 1 |
| 2.1 | General | 1 |
| 2.2 | Government Documents | 1 |
| 2.2.1 | Specifications, Standards, and Handbooks | 1 |
| 2.2.2 | Other Government Documents, Drawings, and Publications | 2 |
| 2.3 | Non-Government Publications | 3 |
| 2.4 | Order of Precedence | 4 |
| 3. | REQUIREMENTS | 4 |
| 3.1 | Subsystem Functional Requirements | 4 |
| 3.1.1 | Training Tasks and Objectives | 4 |
| 3.1.1.1 | Trainer Tasks and Objectives Precedence | 5 |
| 3.1.3 | Training System or Subsystem Functional Requirements | 5 |
| 3.1.3.1 | Integrated Vehicle Health Management System (IVHMS) Integrated Built-In-Test (IBIT) | 6 |
| 3.1.3.2 | Environmental Control System (ECS) IBIT | 7 |
| 3.1.3.3 | Flight Control System (FCS) IBIT | 8 |
| 3.1.3.4 | Communication (Comm) 1 AN/ARC-210(V) System IBIT | 8 |
| 3.1.3.5 | Comm 2 AN/ARC-210(V) System IBIT | 9 |
| 3.1.3.6 | Multifunctional Information Distribution System (MIDS) IBIT | 10 |
| 3.1.3.7 | Satellite Communications (SATCOM) System IBIT | 11 |
| 3.1.3.8 | Inter-Communication System (ICS) IBIT | 11 |
| 3.1.3.9 | Alternating Current (AC) Power System IBIT | 12 |
| 3.1.3.10 | Direct Current (DC) Power System IBIT | 13 |
| 3.1.3.11 | Fire Detection System IBIT | 14 |
| 3.1.3.12 | Fire Extinguishing System IBIT | 14 |
| 3.1.3.13 | Pressure Refueling and Defueling System IBIT | 15 |
| 3.1.3.14 | Fuel Dump System IBIT | 16 |
| 3.1.3.15 | Fuel Quantity Gauging System IBIT | 16 |
| 3.1.3.16 | First Stage Hydraulic System IBIT | 17 |
| 3.1.3.17 | Standby Instrument System (SIS) IBIT | 18 |
| 3.1.3.18 | Avionics Management System (AMS) IBIT | 18 |
| 3.1.3.19 | Master Warning System IBIT | 19 |
| 3.1.3.20 | Landing Gear Control System IBIT | 20 |
| 3.1.3.21 | Instrument Panel Lighting System IBIT | 21 |
| 3.1.3.22 | Controllable Searchlight System IBIT | 22 |
| 3.1.3.23 | Emergency Egress Lighting System (EELS) IBIT | 22 |
| 3.1.3.24 | No. 1 Air Data System (ADS) IBIT | 23 |
| 3.1.3.25 | No. 2 ADS IBIT | 24 |
| 3.1.3.26 | No. 3 ADS IBIT | 25 |
| 3.1.3.27 | No. 1 Radar Altimeter System IBIT | 25 |
| 3.1.3.28 | No. 2 Radar Altimeter System IBIT | 26 |
| 3.1.3.29 | Very High Frequency (VHF) Omnidirectional, Instrument Landing System (ILS) and Marker Beacon System IBIT | 27 |
| 3.1.3.30 | No. 1 Embedded Global Positioning and Inertial Navigation System IBIT | 28 |
| 3.1.3.31 | No. 2 Embedded Global Positioning and Inertial Navigation System IBIT | 29 |
| 3.1.3.32 | Interface Blanker Unit (IBU) System IBIT | 29 |
| 3.1.3.33 | No. 1 Utility Management System (UMS) IBIT | 30 |
| 3.1.3.34 | No. 2 UMS IBIT | 31 |
| 3.1.3.35 | Auxiliary Power Unit (APU) System IBIT | 31 |
| 3.1.3.36 | Overhead Door and Cargo Ramp System IBIT | 32 |
| 3.1.3.37 | Main Rotor Blade (MRB) Fold System IBIT | 33 |
| 3.1.3.38 | Rotor Brake System (RBS) IBIT | 34 |
| 3.1.3.39 | Main Gearbox (MGB) Chip Detector System IBIT | 35 |
| 3.1.3.40 | Nose Gearbox (NGB) Chip Detector System IBIT | 35 |
| 3.1.3.41 | Tail Gearbox (TGB) and Intermediate Gearbox (IGB) Chip Detector System IBIT | 36 |
| 3.1.3.42 | Tail Pylon Fold System IBIT | 37 |
| 3.1.3.43 | Engine System IBIT | 38 |
| 3.1.3.44 | Forward Looking Infrared (FLIR) System IBIT | 38 |
| 3.1.3.45 | Identification Friend or Foe (IFF) System IBIT | 39 |
| 3.1.3.46 | Countermeasures Dispenser System IBIT | 40 |
| 3.1.3.47 | Radar Signal Detecting Set AN/APR-39C(V)2 System IBIT | 40 |
| 3.1.3.48 | Directional Infrared Countermeasures (DIRCM) AN/AAQ-24(V) System IBIT | 41 |
| 3.1.3.49 | Laser Detecting Set AN/AVR-2B(V) System IBIT | 42 |
| 3.1.4 | Testing Operational Availability and Reliability | 43 |
| 3.2 | Environmental, Safety, and Operational Health (ESOH) Requirements | 43 |
| 3.2.1 | Structural Safety | 43 |
| 3.2.2 | Emergency Equipment Power Disconnect | 43 |
| 3.2.3 | Temperature Sensing Alarms | 43 |
| 3.3 | Security and Privacy Requirements | 43 |
| 3.3.1 | Classification | 43 |
| 3.3.2 | Cybersecurity | 44 |
| 3.3.2.1 | Processing of National Security Information | 44 |
| 3.3.2.2 | Cybersecurity Requirements for Operating Systems (OSs) and Software | 44 |
| 3.3.2.3 | Cybersecurity Configuration Criteria | 44 |
| 3.3.2.4 | Hardware and Account Management | 45 |
| 3.3.2.5 | Cybersecurity and Software Management System | 45 |
| 3.3.2.6 | Virus Protection | 45 |
| 3.3.2.7 | Boundary Defense Mechanisms and Network Devices | 46 |
| 3.3.2.8 | Audit Logging | 46 |
| 3.3.2.9 | Image Management System | 47 |
| 3.3.2.10 | Encryption | 47 |
| 3.4 | System Environment Requirements | 47 |
| 3.4.1 | Electromagnetic Environmental Effects (E3) | 47 |
| 3.4.1.1 | DELETED | 47 |
| 3.4.1.1.1 | DELETED | 47 |
| 3.4.1.2 | DELETED | 47 |
| 3.4.1.3 | Electrostatic Discharge (ESD) | 47 |
| 3.4.2 | Lightning | 47 |
| 3.4.3 | Bonding | 47 |
| 3.4.3.1 | DC Bonding Levels | 48 |
| 3.5 | Computer Resource Requirements | 48 |
| 3.5.1 | Computational Systems | 48 |
| 3.5.1.1 | Scalable Architecture | 48 |
| 3.5.1.1.1 | Standard Hardware Interfaces | 48 |
| 3.5.1.1.2 | Open Hardware Architecture | 48 |
| 3.5.2 | Computational Hardware Components and Peripherals | 48 |
| 3.5.2.1 | Internal Computer Networks | 48 |
| 3.5.3 | Computational Subsystems | 48 |
| 3.5.3.1 | Centralized Keyboard Video Monitor (KVM) Position | 48 |
| 3.5.3.2 | Host Computational System (HCS) | 49 |
| 3.5.3.3 | Instructor Operator Station | 49 |
| 3.5.3.4 | Software Support Environment (SSE) | 49 |
| 3.5.3.5 | SSE Interface Requirements | 49 |
| 3.5.3.5.1 | Software Configuration Management | 49 |
| 3.5.3.5.2 | DVCS clients | 50 |
| 3.5.4 | Peripherals | 50 |
| 3.5.4.1 | Drive Trays | 50 |
| 3.5.4.2 | Displays | 50 |
| 3.5.5 | Open Software Architecture | 50 |
| 3.5.5.1 | Commercial and Non-Developmental Item Software | 50 |
| 3.5.5.2 | Noncommercial Software | 50 |
| 3.5.5.3 | Software Stability and Reliability | 50 |
| 3.5.5.4 | Diagnostic Software | 51 |
| 3.5.6 | DORT Program | 51 |
| 3.5.7 | Spare Computational Resource Requirements | 51 |
| 3.5.7.1 | Physically Separated Networks | 51 |
| 3.5.7.1.1 | Network Spare | 51 |
| 3.5.7.2 | I/O Interface | 52 |
| 3.5.7.2.1 | I/O Subsystem Spare Capacity | 52 |
| 3.6 | Design and Construction Constraints | 52 |
| 3.6.1 | Cleaning | 52 |
| 3.6.2 | Threaded Fasteners | 52 |
| 3.6.3 | Wiring | 52 |
| 3.6.3.1 | Shielding | 52 |
| 3.6.4 | Metals | 52 |
| 3.6.5 | Wood Products | 52 |
| 3.6.6 | Radioactive Material | 53 |
| 3.6.7 | Processes | 53 |
| 3.6.7.1 | Painting, and Preparation for Painting | 53 |
| 3.6.7.2 | Nonskid Surfaces | 53 |
| 3.6.7.3 | Corrosion Prevention | 53 |
| 3.6.8 | Flammable Materials | 53 |
| 3.6.9 | Fungus-inert Materials | 53 |
| 3.6.10 | Hazardous Materials | 53 |
| 3.6.10.1 | Use of Hazardous Materials | 53 |
| 3.6.10.2 | Marking of Hazardous Materials | 54 |
| 3.6.10.3 | Precautions | 54 |
| 3.7 | Logistics-related Requirements | 54 |
| 3.7.1 | Environmental Conditions | 54 |
| 3.7.2 | Materials and Processes | 54 |
| 3.7.2.1 | Parts | 54 |
| 3.7.2.1.1 | Custom Designed Microelectronic Devices | 54 |
| 3.7.2.1.2 | Power Supplies | 54 |
| 3.7.2.2 | Materials | 54 |
| 3.7.3 | Maintenance | 55 |
| 3.7.3.1 | Maintenance Concept | 55 |
| 3.7.3.1.1 | Maintenance Clearance | 55 |
| 3.7.3.1.2 | On-Equipment, Organizational Maintenance | 55 |
| 3.7.3.1.3 | Off-Equipment, Intermediate Level Maintenance | 55 |
| 3.7.3.1.4 | Depot Level Maintenance | 56 |
| 3.7.3.2 | Service-life Items | 56 |
| 3.7.3.3 | Qualitative Maintainability Requirements | 56 |
| 3.7.3.3.1 | Special Tools | 56 |
| 3.7.3.3.2 | Lamps | 56 |
| 3.7.3.3.3 | Blown Fuse Indicator Lights | 56 |
| 3.7.3.3.4 | Utility Receptacles | 56 |
| 3.7.3.3.5 | Accessibility | 57 |
| 3.7.3.3.6 | Cable Slack | 57 |
| 3.7.3.3.7 | Parts | 57 |
| 3.7.3.3.7.1 | Interchangeability | 57 |
| 3.7.3.3.8 | Assemblies | 57 |
| 3.7.3.3.9 | Covers, Panels, and Doors | 58 |
| 3.7.3.3.10 | Handles | 58 |
| 3.7.3.3.11 | Modular Assemblies | 58 |
| 3.7.3.4 | Circuit Cards | 58 |
| 3.7.3.4.1 | Circuit Card Connectors | 59 |
| 3.7.3.4.2 | Circuit Card Connectors, Power and Ground | 59 |
| 3.7.3.4.3 | Wiring Board Extender Cards | 59 |
| 3.7.4 | Reliability | 59 |
| 3.7.5 | Maintainability | 59 |
| 3.7.6 | Facilities, Facility Interfaces, and Facility Equipment | 59 |
| 3.7.6.1 | Training Device Maintenance Access | 59 |
| 3.7.6.2 | Safety | 60 |
| 3.7.6.3 | Cables | 60 |
| 3.7.6.4 | Equipment Cooling | 60 |
| 3.7.6.5 | Life Safety | 60 |
| 3.7.6.6 | Fire Protection | 60 |
| 3.7.6.7 | Protective Devices | 60 |
| 3.7.6.7.1 | Voltage Transients | 60 |
| 3.7.6.7.2 | Phase Rotation | 60 |
| 3.7.6.7.3 | Frequency Transients | 60 |
| 3.7.6.7.4 | Power Interruption | 61 |
| 3.7.6.8 | Training Device Power Requirements | 61 |
| 3.7.6.8.1 | Power Distribution | 61 |
| 3.7.6.8.2 | Phase Balance | 61 |
| 3.7.6.8.3 | Operational Electrical Interlock | 61 |
| 3.7.6.9 | Uninterruptible Power Supply (UPS) System | 61 |
| 3.7.6.9.1 | UPS Standard | 61 |
| 3.7.6.9.2 | Backup Power | 61 |
| 3.7.6.9.3 | Compatibility | 61 |
| 3.7.6.9.4 | Damage Prevention | 61 |
| 3.7.6.9.5 | Surge Suppression | 61 |
| 3.7.6.9.6 | Notification | 62 |
| 3.7.6.9.7 | Output | 62 |
| 3.7.6.9.8 | Distortion | 62 |
| 3.7.6.9.9 | Backup Power | 62 |
| 3.7.6.9.10 | Integration | 62 |
| 3.7.6.9.11 | Automation | 62 |
| 3.7.6.9.12 | Protection | 62 |
| 3.7.6.9.13 | Interface | 62 |
| 3.7.6.9.14 | Configurability | 62 |
| 3.7.6.9.15 | Reporting | 62 |
| 3.7.6.9.16 | Self-test | 62 |
| 3.7.6.9.17 | Test Results | 63 |
| 3.7.6.9.18 | Event Log | 63 |
| 3.7.6.9.19 | User Viewable | 63 |
| 3.7.6.9.20 | Historical Data Reporting | 63 |
| 3.7.6.9.21 | Operating Limits | 63 |
| 3.7.6.9.22 | Run Time | 63 |
| 3.7.6.9.23 | Battery Replacement | 63 |
| 3.7.6.9.24 | Capacity | 63 |
| 3.8 | Product Marking | 63 |
| 3.8.1 | Training Device Nameplate | 63 |
| 3.8.2 | Marking of Units, Assemblies, Subassemblies, and Parts | 64 |
| 3.8.2.1 | Units Marking | 65 |
| 3.8.2.2 | Plug-in Assemblies Marking | 65 |
| 3.8.2.3 | Fuse Holders Marking | 65 |
| 3.8.2.4 | Controls and Indicating Device Marking | 66 |
| 3.8.2.5 | Sockets Marking | 66 |
| 3.8.2.6 | Printed Wiring Boards Marking | 66 |
| 3.8.2.7 | Terminals, Terminal Blocks, and Strips Marking | 66 |
| 3.8.2.8 | ESD Marking | 67 |
| 3.8.2.8.1 | ESD Sensitive Assemblies Marking | 67 |
| 3.8.2.8.2 | ESD Sensitive Equipment Marking | 67 |
| 3.8.2.8.3 | External Equipment Terminals Marking | 68 |
| 3.8.2.9 | Fluid and Gaseous Lines Marking | 68 |
| 3.8.3 | Reference Designators Marking | 68 |
| 3.8.4 | Cable and Wire Markings | 69 |
| 3.8.5 | Cable Marking Method | 69 |
| 3.8.5.1 | Cable Marking Information | 69 |
| 3.8.5.1.1 | “W” and “P” Cable Designations | 69 |
| 3.8.5.1.2 | To-from Designators | 70 |
| 3.8.5.1.3 | Assembly/Part Number Marking | 71 |
| 3.8.6 | Commercial Items, and Non-Developmental Items Marking | 71 |
| 3.8.6.1 | Commercial Items, and Non-Developmental Items Identification, Nameplates, and Labels | 71 |
| 3.8.7 | Warning Marking for Simulated and Modified Equipment | 71 |
| 3.8.7.1 | Training Device-use-only Identification Marking | 71 |
| 3.8.8 | Safety Markings | 71 |
| 3.8.8.1 | Equipment Energized from Multiple Power Sources Marking | 72 |
| 4. | VERIFICATION | 72 |
| 4.1 | Verification Methods | 72 |
| 4.2 | Verifications Events | 73 |
| 4.3 | Inspections and Verifications | 73 |
| 4.3.1 | Training System or Subsystem Functional Verification | 73 |
| 4.3.1.1 | Training Task and Objectives Verification | 73 |
| 4.3.1.2 | IOS Verification | 73 |
| 4.3.1.3 | Subsystem Function Verification | 74 |
| 4.3.1.4 | Testing Operational Availability and Reliability Verification | 74 |
| 4.3.1.4.1 | Assessment duration | 74 |
| 4.3.1.4.2 | Failure Criteria | 74 |
| 4.3.1.4.3 | Testing Operational Availability and Reliability Verification Conditions | 74 |
| 4.3.1.4.3.1 | Environmental Conditions during Testing Operational Availability and Reliability Verification | 74 |
| 4.3.2 | Environmental, Safety, and Operational Health (ESOH) Verification | 74 |
| 4.3.2.1 | Emergency Equipment Power Disconnect Verification | 74 |
| 4.3.2.2 | Temperature Sensing Alarm Verification | 75 |
| 4.3.3 | Security and Privacy Verification | 75 |
| 4.3.3.1 | Classification Verification | 75 |
| 4.3.3.2 | Cybersecurity Verification | 75 |
| 4.3.4 | System Environment Verification | 75 |
| 4.3.4.1 | E3 Verification | 75 |
| 4.3.4.1.1 | DELETED | 75 |
| 4.3.4.1.1.1 | DELETED | 75 |
| 4.3.4.1.2 | DELETED | 75 |
| 4.3.4.1.3 | ESD Verification | 75 |
| 4.3.4.2 | Lightning Verification | 75 |
| 4.3.4.3 | Bonding Verification | 76 |
| 4.3.5 | Ancillary Items Verification | 76 |
| 4.3.5.1 | Structural Verification | 76 |
| 4.3.5.2 | Electrical Verification | 76 |
| 4.3.5.2.1 | Grounding and Grounding Systems Verification | 76 |
| 4.3.5.3 | Thermal Survey | 76 |
| 4.3.6 | Computer Resource Verification | 76 |
| 4.3.6.1 | DORT Verification | 76 |
| 4.3.6.2 | Spare Resource Measurement Verifications | 76 |
| 4.3.6.2.1 | Spare CPU Capacity Verification | 77 |
| 4.3.6.2.2 | Spare Memory Verification | 77 |
| 4.3.6.2.3 | Spare Storage Verification | 77 |
| 4.3.6.2.4 | Network Spare Verification | 77 |
| 4.3.6.2.5 | I/O Interface Variation | 78 |
| 4.3.7 | Nonfunctional Verification | 78 |
| 5. | PACKAGING | 78 |
| 5.1 | Packaging | 78 |
| 6. | NOTES | 78 |
| 6.1 | Definitions | 78 |
| 6.1.1 | Contractor Logistics Support Concept | 78 |
| 6.1.2 | Control Drawing | 79 |
| 6.1.3 | Cybersecurity-Enabled OSs | 79 |
| 6.1.4 | Depot Level Maintenance | 79 |
| 6.1.5 | Design Basis Aircraft | 79 |
| 6.1.6 | Failure Definitions and Criteria | 79 |
| 6.1.6.1 | Chargeable Failures | 79 |
| 6.1.6.2 | Non-chargeable Failures | 80 |
| 6.1.6.3 | Non-relevant Failures | 80 |
| 6.1.6.4 | Relevant Failures | 80 |
| 6.1.7 | High Fidelity | 81 |
| 6.1.8 | Interchangeable Item | 81 |
| 6.1.9 | Intermediate Level Maintenance | 81 |
| 6.1.10 | Operational Hours | 81 |
| 6.1.11 | Scheduled Maintenance | 81 |
| 6.1.12 | Service-life Item | 82 |
| 6.1.13 | Unscheduled On-Site Maintenance | 82 |
| 6.1.14 | User Interface | 82 |
| 6.1.15 | Verification Methods | 82 |
| 6.1.15.1 | Analysis | 82 |
| 6.1.15.2 | Demonstration | 82 |
| 6.1.15.3 | Examination | 82 |
| 6.1.15.4 | Test | 82 |
| 6.1.16 | Worst-Case Scenario(s) | 82 |
| 6.2 | Acronyms and Abbreviations | 83 |
| 6.3 | Changes from Previous Issue | 85 |
| CUI | PRF 230007B | |
| 22 Nov 2024 |
| CUI | PRF 230007B |
| 22 Nov 2024 |
Table of Contents
Section Title Page xiv
CUI
xiii
CUI
Tables
| Table No. | Title | Page |
| TABLE I IVHMS failed components | 7 | |
| TABLE II ECS failed components | 8 | |
| TABLE III FCS failed components | 9 | |
| TABLE IV Comm 1 AN/ARC-210(V) System failed components | 9 | |
| TABLE V Comm 2 AN/ARC-210(V) System failed components | 10 | |
| TABLE VI MIDS failed components | 11 | |
| TABLE VII SATCOM System failed components | 12 | |
| TABLE VIII ICS failed components | 12 | |
| TABLE IX AC Power System failed components | 13 | |
| TABLE X DC Power System failed components | 14 | |
| TABLE XI Fire Detection System failed components | 15 | |
| TABLE XII Fire Extinguishing System failed components | 15 | |
| TABLE XIII Pressure Refueling and Defueling System failed components | 16 | |
| TABLE XIV Fuel Dump System failed components | 17 | |
| TABLE XV Fuel Quantity Gauging System failed components | 17 | |
| TABLE XVI First Stage Hydraulic System failed components | 18 | |
| TABLE XVII SIS failed components | 19 | |
| TABLE XVIII AMS failed components | 19 | |
| TABLE XIX Master Warning System failed components | 20 | |
| TABLE XX Landing Gear Control System failed components | 21 | |
| TABLE XXI Instrument Panel Lighting System failed components | 22 | |
| TABLE XXII Controllable Searchlight System failed components | 23 | |
| TABLE XXIII EELS failed components | 23 | |
| TABLE XXIV No. 1 ADS failed components | 24 | |
| TABLE XXV No. 2 ADS failed components | 25 | |
| TABLE XXVI No. 3 ADS failed components | 26 | |
| TABLE XXVII No. 1 Radar Altimeter System failed components | 26 | |
| TABLE XXVIII No. 2 Radar Altimeter System failed components | 27 | |
| TABLE XXIX VHF Omnidirectional, ILS and Marker Beacon System failed components | 28 | |
| TABLE XXX No. 1 Embedded Global Positioning and Inertial Navigation System failed components | 29 | |
| TABLE XXXI No. 2 Embedded Global Positioning and Inertial Navigation System failed components | 30 | |
| TABLE XXXII IBU System failed components | 30 | |
| TABLE XXXIII No. 1 UMS failed components | 31 | |
| TABLE XXXIV No. 2 UMS failed components | 32 | |
| TABLE XXXV APU System failed components | 33 | |
| TABLE XXXVI Overhead Door and Cargo Ramp System failed components | 34 | |
| TABLE XXXVII MRB Fold System failed components | 34 | |
| TABLE XXXVIII RBS failed components | 35 | |
| TABLE XXXIX MGB Chip Detector System failed components | 36 | |
| TABLE XL NGB Chip Detector System failed components | 37 | |
| TABLE XLI TGB/IGB Chip Detector System failed components | 37 | |
| TABLE XLII Tail Pylon Fold System failed components | 38 | |
| TABLE XLIII Engine System failed components | 39 | |
| TABLE XLIV FLIR System failed components | 40 | |
| TABLE XLV IFF System failed components | 40 | |
| TABLE XLVI Countermeasures Dispenser System failed components | 41 | |
| TABLE XLVII Radar Signal Detecting Set AN/APR-39C(V)2 System failed components | 42 | |
| TABLE XLVIII DIRCM AN/AAQ-24(V) System failed components | 43 | |
| TABLE XLIX Laser Detecting Set AN/AVR-2B(V) System failed components | 44 | |
| TABLE L Government facilities interfaces | 61 | |
| CUI | PRF 230007B | |
| 22 Nov 2024 |
Table of Contents
Figures
| Figure. No. | Title | Page |
| FIGURE 1. | Sample Training Device Nameplate | 64 |
| FIGURE 2. | Unit Identification Plate | 65 |
| FIGURE 3. | Electrostatic Discharge Symbols | 67 |
| FIGURE 4. | Electrostatic Discharge Caution Label | 68 |
| FIGURE 5. | Example of Cable Markings | 70 |
| FIGURE 6. | Trainer Use Only Identification | 71 |
| FIGURE 7. | Multiple Power Source Label | 72 |
| CUI | PRF 230007B |
| 22 Nov 2024 |
Performance Specification for CH-53K CNI Training Device
SCOPE
This specification establishes the functional, performance, and verification requirements for a new United States Marine Corps (USMC) CH-53K Communication, Navigation and Instrumentation (CNI) maintenance trainer that will be at the Center for Naval Aviation Technical Training Marine Unit (CNATT MARU) facilities building AS235 located at Marine Corps Air Station (MCAS) New River, Jacksonville, North Carolina.
System Identification The CH-53K CNI is designated as Device 11B112. The CNI will be used as a full-size training device to aid in the development of maintenance skills and support first-level maintenance training of the CH-53K cockpit and avionics areas to maintenance personnel as described herein, see section 3.1 and subsequent paragraphs.
System Overview The primary use of the CNI training device will be to train cockpit and avionics system familiarization, component identification, the performance of function tests and all variations of Built-In Tests, fault isolation and remove and installs of selected Weapons Repairable/Replaceable Assemblies or Line Replaceable Assemblies.
Document Overview For purposes of this specification, the terms CNI, device, trainer, training system, and training device are equivalent. The terms “shall”, “will”, and “objective” are used with specific intent throughout this document. All requirements are threshold requirements except those specified as objective. The threshold requirements represent the minimum acceptable value necessary to satisfy the training need. The use of “shall” denotes a threshold. Requirements defined using “shall” are considered to be binding and require formal verification. Requirements defined using “will” express intent, are not binding, and therefore do not require formal verification. The term “objective” expresses capabilities beyond the threshold requirement. Objectives present an opportunity to exceed the threshold requirement if a cost effective implementation is achievable.
APPLICABLE DOCUMENTS
General The documents listed in this section are cited in sections 3, 4, and 5 of this specification. This section does not include documents cited in other sections of this specification or recommended for additional information or as examples. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet the specified requirements of documents cited in sections 3, 4, and 5 of this specification, whether or not they are listed.
Government Documents Specifications, Standards, and Handbooks The following specifications, standards, and handbooks of the exact revision listed below form a part of this specification to the extent specified herein.
Department of Defense Standards
| MIL-STD-130N |
| - |
| Identification and Marking of U.S. Military Property. |
(Copies of these documents are available online at https://quicksearch.dla.mil or from the Standardization Document Order Desk, 700 Robbins Avenue, Building 4D, Philadelphia, PA 19111-5094)
Department of Defense Handbooks
| MIL-HDBK-454C |
| - |
| General Guidelines For Electronic Equipment |
(Copies of these documents are available online at https://quicksearch.dla.mil or from the Standardization Document Order Desk, 700 Robbins Avenue, Building 4D, Philadelphia, PA 19111-5094)
Other Government Documents, Drawings, and Publications The following Government documents, drawings, and publications of the exact revision level shown form a part of this document to the extent specified herein.
Code of Federal Regulations
| 21 CFR 1040 |
| - |
| Performance Standards for Light-Emitting Products |
| 29 CFR 1910 |
| - |
| Occupational Safety and Health Standards |
(Copies of this document are downloadable from http://www.ecfr.gov)
DOD Security/Cybersecurity Documents
| CNSSI 1253 |
| - |
| Committee on National Security Systems Instruction - Security Categorization and Control Selection for National Security Systems, dated 27 March 2014 |
| DoDI 8500.01 |
| - |
| Cybersecurity, Incorporating Change1, effective 07 October 2019 |
| DoDI 8510.01 |
| - |
| Risk Management Framework for DoD Systems Risk Management Framework Incorporating Change 1, effective 24 19 May July 202216 |
| NIST SP 800-53 Revision 5 |
| - |
| Security and Privacy Controls for Information Systems and Organizations, dated September 2020 (Updates as of December10, 2020) |
| NIST SP 800-131A Revision 2 |
| - |
| Transitioning the Use of Cryptographic Algorithms and Key Lengths, dated March 2019 |
| NIST SP 800-147B |
| - |
| BIOS Protection Guidelines for Servers, dated August 2014 |
| ISO/IEC 11889-1:2015 |
| - |
| Information Technology – Trusted Platform Module Library – Part 1: Architecture, Second Edition, dated 15 December 2015 (Corrected 01 April 2016) |
ISO/IEC 11889-2:2015
Information Technology – Trusted Platform Module Library – Part 2: Structures, Second Edition, dated 15 December 2015
ISO/IEC 11889-3:2015
Information Technology – Trusted Platform Module Library – Part 3: Commands, Second Edition, dated 15 December 2015
| ISO/IEC 11889-4:2015 |
| - |
| Information Technology – Trusted Platform Module Library – Part 4: Commands, Second Edition, dated 15 December 2015 |
| FIPS 140-3 |
| - |
| Security Requirements for Cryptographic Modules, dated 22 March 2019 |
| DoDI 8551.01 |
| - |
| Ports, Protocols, and Services Management (PPSM), Incorporating Change 1, effective 27 July 2017) |
(Copies of the above documents are downloadable from https://www.esd.whs.mil/directives/issuances/, https://csrc.nist.gov/publications, https://www.dcsa.mil/portals/91/documents/ctp/nao/CNSSI_No1253.pdf, https://standards.iso.org/ittf/PubliclyAvailableStandards/index.html)
DoD Unified Facilities Criteria (UFC)
| UFC 3-600-1 |
| - |
| Fire Protection Engineering for Facilities, with Change 6 |
(Copies of the above documents are downloadable from https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc)
Naval Air Systems Command (NAVAIR) Documents
| A1-CH53K-IETM-MMO-000 |
| - |
| Organizational Maintenance Navy Model CH-53K. |
| NAVAIR 01-1A-505-1 |
| - |
| Volume 1 Aircraft Electric and Electronic Wiring |
(Copies of the above documents will be delivered as Government-furnished information)
Office of the Law Revision Counsel United States Code
| Title 17 USC § 401 |
| - |
| Notice of copyright: Visually perceptible copies |
(Copies of this document are downloadable from http://uscode.house.gov/)
United States (US) Army Corp of Engineers – Engineer Manuals
| EM-385-1-1 |
| - |
| Safety and Health Requirements |
(Copies of these documents are downloadable from https://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/)
Non-Government Publications American National Standards Institute (ANSI)/National Electrical Manufacturers Association (NEMA)
| ANSI/NEMA Z535.1-2022 |
| - |
| Safety Colors |
| ANSI/NEMA Z535.2-2011 (R2017) |
| - |
| Environmental and Facility Safety Signs |
| ANSI/NEMA Z535.3-2022 |
| - |
| Criteria for Safety Symbols |
| ANSI/NEMA Z535.4-2011 (R2017) |
| - |
| Product Safety Signs and Labels |
| ANSI/NEMA Z535.5-2022 |
| - |
| Safety Tags and Barricade Tapes (for Temporary Hazards) |
(Copies of these documents are available from www.ansi.org)
American Society of Mechanical Engineers (ASME)
| ASME Y14.44 2008 (R2014) |
| - |
| Reference Designations for Electrical and Electronics Parts and Equipment |
(Copies of this document are available from http://www.asme.org)
JEDEC Solid State Technology Association
| JESD471 (R2009) |
| - |
| Symbol and Label for Electrostatic Sensitive Devices |
| JS-001-2017 |
| - |
| Joint JEDEC/ESDA Standard for Electrostatic Discharge Sensitivity Test – Human Body Model (HBM) – Component Level |
(Copies of this document are available from http://www.jedec.org)
National Fire Protection Association (NFPA)
| NFPA 70 |
| - |
| National Electrical Code, 2023 Edition |
| NFPA 72 |
| - |
| National Fire Alarm and Signaling Code, 2022 Edition |
| NFPA 90A |
| - |
| Standard for the Installation of Air-Conditioning and Ventilating Systems |
| NFPA 101 |
| - |
| Life Safety Code, 2021 Edition |
| NFPA 110 |
| - |
| Standard for Emergency and Standby Power Systems, 2022 Edition |
| NFPA 704 |
| - |
| Standard System for the Identification of the Hazards of Materials for Emergency Response, 2022 Edition |
| NFPA 2001 |
| - |
| Standard on Clean Agent Fire Extinguishing Systems, 2022 Edition |
(Copies of the above documents are downloadable from http://www.nfpa.org and are available from are available from NFPA 1 Batterymarch Park Quincy, Massachusetts USA 02169-7471)
Order of Precedence Unless otherwise noted herein or in the contract, in the event of a conflict between the text of this specification and the references cited herein, the text of this specification takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.
REQUIREMENTS
The CNI device functional and performance characteristics shall be in accordance with (IAW) the following subordinate paragraphs, based on procedures/tasks identified in the latest version of CH-53K Interactive Electronic Technical Manual (IETM) (A1-CH53K-IETM-MMO-000), and aligned to the latest aircraft Bureau Number (BUNO) # XXXXXX with IETM lockdown to occur NLT 30 days prior to PDR and provided to seller.
Subsystem Functional Requirements Training Tasks and Objectives The trainer shall
1. be a stand-alone, full-size, high fidelity (see 6.1.7) maintenance task trainer replicating the CH-53K nose, cockpit, and forward cabin section to Station 282 on the System Demonstration Test Article (SDTA) 6 airframe (provided as GFE located at NAS Patuxent River, MD) including but not limited to the overhead and instrument panels, consoles, avionics bays and shelves, flight controls, Multifunctional Displays (MFDs) and Control Display Units (CDUs);
only include CH-53K cockpit through forward Station 282;
have the components necessary to accomplish the maintenance procedures listed in 3.1.3;
have embedded simulated or stimulated functionality, with a separate instructor operator station (IOS) for fault insertion/isolation/correction;
represent the latest version CH-53K aircraft BUNO represented by CH-53K design basis aircraft (DBA) (see 6.1.5) available 30 days prior to PDR;
be comprised of components, panels and avionics replicating the form and fit as the CH-53K DBA (see 6.1.5);
present the trainees with realistic operational checkout, troubleshooting situations, and component replacement tasks; and function IAW latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, demonstrating the operation, testing, fault identification and isolation, adjustment, diagnostics, and replacement of the aircraft systems and components.
Trainer Tasks and Objectives Precedence The training system shall not require wire repair except as explicitly stated in the tables within subsections of 3.1.3. The tables within the subsections of 3.1.3 correspond with A1-CH53K-IETM-MMO-000 available 30 days prior to PDR.
1.1.1 IOS Subsystem
The IOS shall
1. identify the designated training scenario with reference to applicable maintenance task in the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, including Fault Code, Fault Condition, and failed component if applicable;
have controls to monitor and display system status;
have instructor controls to initiate, and stop training events;
assign functional test and insert fault training scenarios;
manually insert and reset system fault conditions; and monitor and fault trainer system circuit breakers;
b. have controls to turn on and off electrical power to support tasks in the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
c. perform Diagnostic analysis of the trainer (Daily Operational Readiness Test (DORT)); and have controls to insert up to three, unrelated tasks (not cascading faults), simultaneously.
Training System or Subsystem Functional Requirements The CNI shall
1. replicate system functional testing with no failure IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
replicate system functional testing with failures IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have the failures defined as a single combination of Fault Code and Fault Condition per training exercise as defined per the tables within subsections of 3.1.3;
have fault isolation and troubleshooting defined as the same;
have the failures display the associated failure indicators for that combination of Fault Code and Fault Condition on the CNI MFD;
replicate system troubleshooting and failure identification IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, with the following fidelity:
1. high fidelity (see 6.1.7) physical interface connectors;
high fidelity (see 6.1.7) physical components;
replicate component location, obstructions and accessibility IAW CH-53K DBA (see 6.1.5);
replicate component interfaces and attachments with training device IAW CH-53K DBA (see 6.1.5);
replicate component attachments to the training device IAW CH-53K DBA (see 6.1.5);
replicate wiring harnesses, routing, and interfacing IAW CH-53K DBA (see 6.1.5); and replicate continuity or voltage reading for specified fault IAW CH-53K DBA (see 6.1.5);
receive the inserted fault from the IOS IAW the tables within subsections of 3.1.3;
have the fidelity and functionality required to repair the fault by replacement of failed high fidelity (see 6.1.7) replica or actual component;
receive the command from the IOS, and to clear the inserted fault manually; and have sounds and aural cues associated to normal operation and faults within the latest version A1-CH53K-IETM-MMO-000 tasks available 30 days prior to PDR identified in this specification (e.g. inter-communication system (ICS), radios, Auxiliary Power Unit (APU), engine start, audio master caution warnings, etc.), to support training outcome IAW latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR.
Integrated Vehicle Health Management System (IVHMS) Integrated Built-In-Test (IBIT) The CNI shall
1. replicate the CH-53K IVHMS IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have an IVHMS comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the IVHMS Function Test with no failure indication IAW the latest version available A1-CH53K-IETM-MMO-000, 30 days prior to PDR, procedure 19-10-00-01A-340A-A, excluding steps 5-6;
have IOS controls to insert and remove Fault Codes and Fault Conditions (if applicable) listed in TABLE I for IVHMS functional IBIT test;
perform IVHMS IBIT with the indicated Fault Codes and Fault Conditions (if applicable) listed in TABLE I IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 19-10-00-01A-340A-A;
perform fault isolation procedures per the Fault Codes and Fault Conditions (if applicable) listed in TABLE I IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 19-10-00-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE I; and execute the IVHMS Function Test with no failure indications after the failed component has been repaired.
TABLE I IVHMS failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| No. 1 Data Concentrator Unit Junction Box |
| 19-10-00-03 |
| 17F7C90D |
| 31-40-03-04A-920A-A |
| Maintenance Data Transfer Unit |
| 19-10-00-20 |
| 03D67647 |
| 19-10-03-01A-920A-A |
| No. 2 Integrated Vehicle Health Management Unit |
| 19-10-00-97 |
| D43609ED |
| 19-10-02-01A-920A-A |
| No. 2 Data Concentrator Unit Junction Box |
| 19-10-00-99 |
| 04D25581 |
| 31-40-04-04A-920A-A |
| #1 Cabin Relay Panel Relay K102 |
| 19-10-00-111 |
| N/A |
| 24-90-01-01C-663B-A |
Environmental Control System (ECS) IBIT The CNI shall
1. replicate the CH-53K ECS IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have an ECS comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the ECS Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000, available 30 days prior to PDR, procedure 21-90-00-01A-340A-A, excluding steps 6-10;
have IOS controls to insert and remove the Fault Codes and Fault Conditions listed in TABLE II for ECS functional IBIT test;
perform ECS functional IBIT Function Test with the indicated Fault Codes and Fault Conditions listed in TABLE II IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 21-90-00-01A-340A-A;
perform fault isolation procedures per the Fault Codes and Fault Conditions listed in TABLE II IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 21-90-00-01A-421A-A, excluding Fault Codes 21-90-00-31, 21-90-00-32 and 21-90-00-37;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE II, excluding Fault Codes 21-90-00-31, 21-90-00-32 and 21-90-00-37; and execute the ECS Function Test with no failure indications after the failed component has been repaired.
TABLE II ECS failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| ECS Control Panel |
| 21-90-00-02 |
| 9D9C79B5 |
| 31-10-05-03A-920A-A |
| Circuit Breaker Cabin Divert (CB1D16) |
| 21-90-00-04 |
| 859B7387 |
| 24-91-03-01C-663B-A |
| ECS Control Panel |
| 21-90-00-20 |
| 311B8E2E |
| 31-10-05-03A-920A-A |
| No. 2 Engine Bleed Shut Off Valve |
| 21-90-00-31 |
| 562DB87C |
| (Repair capability not required) |
| No. 3 Engine Pneumatic Molded Harness. |
| 21-90-00-32 |
| A1083DE4 |
| (Repair capability not required) |
| Secondary Power System Electronic Control Unit |
| 21-90-00-35 |
| 13BB4D2E |
| 49-31-01-01A-920A-A |
| Bleed Supply Pressure Sensor |
| 21-90-00-37 |
| F7C38096 |
| (Repair capability not required) |
Flight Control System (FCS) IBIT
1. replicate the CH-53K FCS IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have a FCS comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the FCS Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 22-10-00-01A-340A-A, excluding steps 4.6.5 -16;
have IOS controls to insert and remove Fault Codes and Fault Conditions listed in TABLE III for FCS functional IBIT test;
perform FCS functional IBIT Function Test with the indicated Fault Codes and Fault Conditions listed in TABLE III IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 22-10-00-01A-340A-A, excluding steps 4.6.5 through 4.6.8;
fault isolation procedures per the Fault Codes and Fault Conditions listed in TABLE III IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 22-10-00-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE III; and execute the FCS Function Test with no failure indications after the failed component has been repaired.
TABLE III FCS failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| Copilot Cyclic Inceptor |
| 22-10-00-06 |
| 787BC254 |
| 67-10-02-01A-920A-A |
| Copilot Collective Inceptor |
| 22-10-00-18 |
| 1A6476BC |
| 67-10-04-01A-920A-A |
| No. 2 Flight Control Computer |
| 22-10-00-83 |
| 610CB591 |
| 22-10-02-01A-920A-A |
Communication (Comm) 1 AN/ARC-210(V) System IBIT
1. replicate the CH-53K Comm 1 AN/ARC-210(V) System IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have a Comm 1 AN/ARC-210(V) System comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the Comm 1 AN/ARC-210(V) System Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-10-01-01A-340A-A, excluding step 5;
have IOS controls to insert and remove the Fault Code and Fault Condition listed in TABLE IV for Comm 1 AN/ARC-210(V) System functional IBIT test;
perform Comm 1 AN/ARC-210(V) System functional IBIT Function Test with the indicated Fault Code and Fault Condition listed in TABLE IV IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-10-01-01A-340A-A;
perform fault isolation procedures per the Fault Code and Fault Condition listed in TABLE IV IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-10-01-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE IV; and execute the Comm 1 AN/ARC-210(V) System Function Test with no failure indications after the failed component has been repaired.
TABLE IV Comm 1 AN/ARC-210(V) System failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| No. 1 Data Concentrator Unit Junction Box |
| 23-10-01-01 |
| 8D81E556 |
| 31-40-03-04A-920A-A |
Comm 2 AN/ARC-210(V) System IBIT
1. replicate the CH-53K Comm 2 AN/ARC-210(V) System IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have a Comm 2 AN/ARC-210(V) System comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the Comm 2 AN/ARC-210(V) System Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-10-02-01A-340A-A, excluding step 5;
have IOS controls to insert and remove the Fault Code and Fault Condition listed in TABLE V for Comm 2 AN/ARC-210(V) System functional IBIT test;
perform Comm 2 AN/ARC-210(V) System functional IBIT Function Test with the indicated Fault Code and Fault Condition listed in TABLE V IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-10-02-01A-340A-A;
perform fault isolation procedures per the Fault Code and Fault Condition listed in TABLE V IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-10-02-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE V; and execute the Comm 2 AN/ARC-210(V) System Function Test with no failure indications after the failed component has been repaired.
TABLE V Comm 2 AN/ARC-210(V) System failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| No. 2 Data Concentrator Unit Junction Box |
| 23-10-02-01 |
| E4E3F58F |
| 31-40-04-04A-920A-A |
Multifunctional Information Distribution System (MIDS) IBIT
1. replicate the CH-53K MIDS IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have a MIDS comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the MIDS Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-11-00-01A-340A-A, excluding steps 6-7;
have IOS controls to insert and remove Fault Codes and Fault Conditions listed in TABLE VI for MIDS functional IBIT test;
perform MIDS functional IBIT Function Test with the indicated Fault Codes and Fault Conditions listed in TABLE VI IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-11-00-01A-340A-A;
perform fault isolation procedures per the Fault Codes and Fault Conditions listed in TABLE VI IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-11-00-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE VI; and execute the MIDS Function Test with no failure indications after the failed component has been repaired.
TABLE VI MIDS failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| Link 16 MIDS and TACAN Mount |
| 23-11-00-01 |
| 1669497E |
| 23-11-13-01A-920A-A |
| Circuit Breaker CB3D05 |
| 23-11-00-01 |
| 1669497E |
| 24-91-01-01C-663B-A |
| Link 16 Remote Power Supply |
| 23-11-00-02 |
| E795478B |
| 23-11-11-01A-920A-A |
| Circuit Breaker CB3D02 |
| 23-11-00-02 |
| E795478B |
| 24-91-01-01C-663B-A |
| No. 2 Data Concentrator Unit Junction Box |
| 23-11-00-03 |
| 7C1A306F |
| 31-40-04-04A-920A-A |
| Com 3 Lower Link 16 and TACAN Antenna |
| 23-11-00-06 |
| B196621F |
| 23-11-04-01A-920A-A |
| Com 3 Lower Link 16 and TACAN Antenna High Pass Filter |
| 23-11-00-06 |
| B196621F |
| 23-11-07-01A-920A-A |
| Link 16 MIDS and TACAN Receiver |
| 23-11-00-06 |
| B196621F |
| 23-11-12-01A-920A-A |
Satellite Communications (SATCOM) System IBIT
1. replicate the CH-53K SATCOM System IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have a SATCOM System comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the SATCOM System Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-15-00-01A-340A-A;
have IOS controls to insert and remove Fault Codes and Fault Conditions listed in TABLE VII for SATCOM System functional IBIT test;
perform SATCOM System functional IBIT Function Test with the indicated Fault Codes and Fault Conditions listed in TABLE VI IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-15-00-01A-340A-A;
have ability to perform fault isolation procedures per the Fault Codes and Fault Conditions listed in TABLE VI IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-15-00-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE VI; and execute the SATCOM System Function Test with no failure indications after the failed component has been repaired.
TABLE VII SATCOM System failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| Antenna Switching Unit |
| 23-15-00-01 |
| 0C576036 |
| 23-10-04-01A-920A-A |
| No. 1 Data Concentrator Unit Junction Box |
| 23-15-00-14 |
| E9ADC747 |
| 31-40-03-04A-920A-A |
Inter-Communication System (ICS) IBIT
1. replicate the CH-53K ICS IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have an ICS comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the ICS Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-50-00-01A-340A-A, excluding steps 5-11;
have IOS controls to insert and remove Fault Codes listed in TABLE VIII for ICS functional IBIT test;
perform ICS functional IBIT Function Test with the indicated Fault Codes listed in TABLE VIII IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-50-00-01A-340A-A;
perform fault isolation procedures per the Fault Codes listed in TABLE VIII IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 23-50-00-01A-421A-A;
remove and reinstall the failed components IAW the Repair IETM column listed in TABLE VIII; and execute the ICS Function Test with no failure indications after the failed component has been repaired.
TABLE VIII ICS failed components
| Failed Component |
| Fault Code |
| Fault Condition |
| Repair IETM |
| Pilot Inter-Communication Control Panel |
| 23-50-00-19 |
| N/A |
| 23-50-03-01A-920A-A |
| Pilot Cyclic |
| 23-50-00-19 |
| N/A |
| 67-10-01-03A-920A-A |
| Resistor R2003R |
| 23-50-00-25 |
| N/A |
| 91-20-00-21A-685A-A |
Alternating Current (AC) Power System IBIT
1. replicate the CH-53K AC Power System IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
have an AC Power System comprised of actual and/or simulated components, with the fidelity required to facilitate system component identification and perform function tests, fault isolation procedures, removal, repairs, and installations associated with the components IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR;
contain the components, subcomponents, and hardware to execute the AC Power System Function Test with no failure indication IAW the latest version A1-CH53K-IETM-MMO-000 available 30 days prior to PDR, procedure 24-20-00-01A-340A-A, excluding steps 6-7;
have IOS controls to insert and remove Fault Codes and Fault Conditions listed in TABLE IX for AC Power System functional IBIT test;
perform AC Power System functional IBIT Function Test with the indicated Fault Codes and Fault Conditions listed in TABLE IX IAW the latest version A1-CH53K-IETM-MMO-000 available 30…