CGC HUDSON Tank Cleaning SOW.pdf

PDF 443 KB Posted

Attached to
USCGC HUDSON TANK, POTABLE WATER CLEANING AND INSPECTION
Solicitation number
52050PR260000307
Issued by

About this file

This is a Specification for Dockside Repairs for the USCGC HUDSON (WLIC 801) for Fiscal Year 2026, developed by Erik C Elasik (Rev-0, 15 October 2025). The specification contains fourteen work items detailing comprehensive maintenance and repair requirements for the vessel's tank systems and piping infrastructure.

The work items encompass cleaning and inspection of six potable water tanks (ranging from 1,779 to 3,551 gallons capacity), three ballast tanks (2,506 to 7,102 gallons capacity), two accessible voids (942 gallons each), three fuel and waste tanks (115 to 1,690 gallons capacity), one sewage collection tank (450 gallons capacity), and grey water and sewage piping systems. Key contractor requirements include: tank content removal and proper disposal per Federal, state, and local regulations; interior cleaning to remove sediment, sludge, and biological growth without damaging coatings; visual inspection and completion of Tank and Void Assessment Forms; plug accountability logging for tank vents; tank closure in the presence of Coast Guard inspectors using new gasket materials (ANSI/NSF 61 for potable water tanks, ASTM D1330 for ballast and void tanks, AMS-C-6183 for fuel tanks); renewal of fasteners (100% of nuts and washers for most tanks); post-repair operational testing; and tank disinfection per AWWA C652 standards for potable water systems. Ballast tank work includes 50 ultrasonic thickness measurements and 100 pit-depth measurements. Piping cleaning requires hydrojet cleaning at minimum 2500 psig pressure, borescope inspection, chemical cleaning if necessary (with 96-hour advance plan submittal to Contracting Officer Representative), and leak testing. All work must comply with applicable Coast Guard standards, SFLC specifications, and environmental regulations, with Coast Guard personnel operating all shipboard machinery. Contractors must furnish all protective measures and handle system interferences such as fluid contents, piping, RO system components, pumps, and deck grating.

View the file

Other files

File Type Posted
Synopsis Solicitation.pdf PDF
WAGE DETERMINATIONS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC HUDSON (WLIC 801)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2026

Developed By: Erik C Elasik

(Rev-0, 15 October 2025)

USCGC HUDSON (WLIC-160A) DOCKSIDE AVAILABILITY FY2026

15 (Rev-0)

12314_ESD_0423_FLT

REC_12314_FLT160’ WLIC ‘A’ Class (ALL) (0611)

WORK ITEM 1: Tanks, Potable Water, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

TABLE 1 - TANKS

TYPE OF TANK LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION

(GALLONS)

Potable Water 2-34-1-WW 3,306 100

Potable Water 2-34-2-WW 3,306 100

Potable Water 2-44-1-WW 1,779 50

Potable Water 2-44-2-WW 1,779 50

Potable Water 2-49-1-WW 3,551 100

Potable Water 2-49-2-WW 3,551 100

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 160 WLIC 103-002, Rev A, Booklet of General Plans

COAST GUARD PUBLICATIONS

16 (Rev-0)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water

System Components - Health Effects American National Standards Institute/American Water Works Association (ANSI/AWWA)

C652, 2011, Disinfection of Water-Storage Facilities

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:

• Fluid contents

• Piping

• RO system components

• Deck grating.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.

• TLI

3.3 Plug log. The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.

17 (Rev-0)

3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

3.4 Tank content removal. The Contractor must remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. The Contractor must notify the Dockmaster prior to filling or draining the potable water tank(s), when this item is being executed in a drydock availability. The Contractor must refer to Coast Guard drawings 160 WLIC 103-002 for guidance.

3.5 Tank cleaning. The Contractor must remove tank cover(s); clean tank interior surfaces free of all foreign materials, such as sediment, sludge and bacterial growth. Remove all persistent residues, taking care not to damage any tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.

3.6 Inspection. The Contractor must visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Complete the “Tank and Void Assessment Form” (found in the Work Item titled “General Requirements”) and submit via CFR. Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:

• Tank structural condition.

• Inaccessible areas, if any.

• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.

• Tank level indicator (TLI) and/or float switch condition (if applicable).

• Sounding tube and striker plate condition.

• Suction and discharge piping condition.

• Fastener material and condition.

3.7 Tank closing. The Contractor must notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to ANSI/NSF 61. Renew all stud cotton grommets (as applicable) upon reinstallation of manhole cover(s).

3.7.1 The Contractor must renew 100% of nuts and washers.

3.8 Tank disinfecting. After all other work involving the potable water system and tank closing have been completed, the Contractor must disinfect and treat the affected potable water tank(s) and associated disturbed piping and components, as necessary, to meet or exceed the requirements of AWWA C652.

After tank disinfecting, remove and dispose of all treated water in accordance with all Federal, state and local regulations. Ensure that no one enters the tanks once disinfection is completed. Submit CFR providing confirmation that disinfection of tank(s) and associated potable water system disturbed piping

18 (Rev-0) and components has been completed and certifying that all sampling and testing is negative for coliform organisms.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.9 Operational test, post repairs. After completion of work and in the presence of the Coast Guard Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition. Submit a CFR.

• TLI

4. NOTES

This section is not applicable to this work item.

19 (Rev-0)

12316_0723_FLT

REC_12316_FLT_160’ WLIC ‘A’ Class (ALL) (0813)

WORK ITEM 2: Tanks, Ballast, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following

TABLE 1 - TANKS

TYPE OF STRUCTURE LOCATION CAPACITY - 95%

LOW SUCTION

(GALLONS)

Ballast Tank 2-17-1-W, Fr 17-27 7,102 ________70________

Ballast Tank 2-17-2-W, Fr 17-27 7,102 _________70________

Ballast Tank 2-139-2-W, Fr 139-145 2,506 _________50

2. REFERENCES

General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

OTHER REFERENCES

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

20 (Rev-0)

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.

• TLI’s for tanks listed in paragraph 1.1

3.3 Plug log. The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.

3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.3.2 The plug log must be available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

3.3 Content removal. The Contractor must remove access cover(s); remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. Plug all inlet and outlet piping in the tank to prevent contaminants from entering the tank. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings. Maintain a plug accountability log outside the tank(s) to prevent any of the installed temporary plugs from being lost inside the tank or forgotten inside at tank closure.

3.4 Cleaning. The Contractor must clean the designated structure’s (see paragraph 1.1 (Intent)) interior surfaces free of all foreign materials, such as sediment, sludge and fungal growth. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the compartment during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations. The Contractor must refer to Coast Guard drawings 160 WLIC 103-002 for guidance.

21 (Rev-0)

3.5 Inspection. The Contractor must visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Complete the “Tank and Void Assessment Form” (found in the Work Item titled “General Requirements”) and submit via CFR. Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:

• Structural condition.

• Inaccessible areas, if any.

• Condition of coating, including measurements taken, percentage, location, and type of coating failure.

• Tank level indicator (TLI) and/or float switch condition.

• Sounding tube and striker plate condition.

• Suction and discharge piping condition.

• Fastener material (stainless steel) and condition.

• Anodes (as applicable).

3.6 Closing. The Contractor must ensure that the compartment(s) remain open for at least 24 hours after completion of any KO-authorized tank repairs and preservation. Notify the COR at least 24 hours prior to closing the compartment(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330 and new cotton grommets on each stud (as applicable).

3.6.1 The Contractor must renew 100% of nylon insert/nylock nuts and washers.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.7 Operational test, post repairs. After completion of work and in the presence of the Coast Guard Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition. Submit a CFR.

• TLIs

3.8 Ultrasonic thickness (UT) measurement. The Contractor must take a total of 50 UT measurements of tank plating, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C. Use Coast Guard Drawing ________________________ as guidance. Submit a CFR.

3.8.1 In addition to the UT measurements, take a total of ___100__ pit-depth measurements, using a suitable pit depth gauge

22 (Rev-0)

12316_ESD_0723_FLT

REC_12316_FLT160’ WLIC ‘A’ Class (ALL) (0813)

WORK ITEM 3: Voids, Accessible, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following void(s):

TABLE 1 - VOIDS

TYPE OF STRUCTURE LOCATION CAPACITY - 95%

LOW SUCTION

(GALLONS)

Void 2-72-1-V, Fr 71½-74½ 942 50

Void 2-72-2-V, Fr 71½-74½ 942 50

2. REFERENCES

General Requirements

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

23 (Rev-0)

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.

3.3 Cleaning and inspection requirements. The Contractor must refer to Coast Guard drawings 160 WLIC 103-002 for guidance. to accomplish the following tasks:

3.3.1 Content removal. The Contractor must remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations.

3.3.2 Cleaning. The Contractor must remove access cover(s). Clean the designated structure’s interior surfaces free of all foreign materials, such as sediment, sludge and fungal growth. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the compartment during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.

3.3.3 Inspection. The Contractor must visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Complete the “Tank and Void Assessment Form” (found in the Work Item titled “General Requirements”) and submit via CFR. Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:

• Structural condition.

• Inaccessible areas, if any.

• Condition of coating, including measurements taken, percentage, location, and type of coating failure.

• Tank level indicator (TLI) and/or float switch condition.

• Sounding tube and striker plate condition.

24 (Rev-0)

• Suction and discharge piping condition.

• Fastener material and condition.

3.4 Closing. The Contractor must ensure that the compartment(s) remain open for approximately 24 hours after completion of the tasks specified above. Notify the COR at least 24 hours prior to closing the compartment(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector.

After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330 and cotton grommets on the studs (as applicable). The Contractor must renew up to 10% of missing or damaged nuts and washers.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test, post repairs. After completion of work and in the presence of the Coast Guard inspector, the Contractor must thoroughly test and demonstrate the TLI’s for tanks listed in paragraph 1.1 (Intent), to be in satisfactory operating condition. Submit a CFR.

25 (Rev-0)

12317_ESD_0723_FLT

REC_12310_FLT_160’ WLIC ‘A’ Class (ALL) (0121)

WORK ITEM 4: Tanks, Dirty Oil and Waste, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

TABLE 1 – TANKS

TYPE OF TANK LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION

(GALLONS)

Oily Waste 2-113-1-F 115 20

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

3. REQUIREMENTS

3.1 General.

Diesel Fuel Tank 2-75-1-F 1014 20 Diesel Fuel Tank 2-79-1-F 1690 20

26 (Rev-0)

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 The Contractor must remove up to a total of 100 gallons of waste oil and oily water, to facilitate gas-freeing. Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.3 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard Personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.

• TLI’s for tank(s) listed in paragraph 1.1 (Intent)

3.4 Plug log. The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.

3.4.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.4.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

NOTE

Vessel may come in with less tank fluid contents than specified above.

3.5 Cleaning requirements. The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.

3.6 Tank content and waste disposal. The Contractor must dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.7 Inspection. The Contractor must visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and

27 (Rev-0) gasket seating surfaces. Complete the “Tank and Void Assessment Form” (found in the Work Item titled “General Requirements”) and submit via CFR. Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:

• Tank structural condition.

• Inaccessible areas.

• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.

• Tank level indicator (TLI) and/or float switch condition.

• Sounding tube and striker plate condition.

• Suction and discharge piping condition.

• Fastener material and condition (correct fastener material is stainless steel).

3.8 Tank closing. The Contractor must ensure that the tank(s) remain open for at least 24 hours after completion of all authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector.

After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.9 Operational test, post repairs. After completion of work and in the presence of the Coast Guard Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition. Submit a CFR.

• TLI’s for tank listed in paragraph 1.1 (Intent)

4.1 The Coast Guard Inspector will visually inspect the tank interior immediately prior to closing.

48 (Rev-0)

59302_ESD_0723_FLT

REC_59301_FLT_160’ WLIC ‘A’ Class (ALL) (1209)

WORK ITEM 12: Sewage Holding Tanks, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following

TABLE 1 – TANKS

TYPE OF TANK LOCATION CAPACITY - 95%

(Gallons)

LOW SUCTION (Gallons)

Sewage Collection Tank 2-94-0-E 450 40

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 160 WLIC 103-002, Rev A, Booklet of General Plans

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

49 (Rev-0)

3.1.1 CIR.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).

3.1.3.1 Plug all inlet and outlet piping in the tank(s) to prevent contaminants from entering. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings.

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:

• Piping.

• Pump(s).

3.2 Plug log. The Contractor must keep a written record of all plugs put in any tank vents. A separate list must be kept for each tank being entered.

3.2.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.2.2 The plug log must be available to the Coast Guard Inspector when the inspector is performing his close-out inspection on each tank.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.3 Operational test - initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.4 Service disruption. When sewage collection service is disrupted due to contractor repairs, the Contractor must refer to SFLC Standard Spec 0000 par 3.2.11 to provide required temporary facilities.

3.5 Cleaning and inspection requirements. The Contractor must accomplish the following for the tank(s) listed in paragraph 1.1 (Intent), referring to Coast Guard Drawing 160 WLIC 103-002 for guidance:

3.5.1 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations

3.5.2 Cleaning requirements. Remove manhole cover(s). Clean all tank structure’s interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths.

Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all

50 (Rev-0)

Federal, state, and local regulations. Clean all tank vent lines. Remove and clean the eductors and level switches inside of the tank(s). Reinstall the eductors and level switches upon completion of tank cleaning.

Use new gaskets and o-rings to install/reinstall all removed/disturbed components.

3.5.3 Inspection. Visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.

Submit the “Tank and Void Assessment Form” via CFR (see paragraph 4.2 of the Work Item titled “General Requirements”). Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:

• Tank structural condition.

• Inaccessible areas.

• Condition of tank coating, including measurements, percentage, location, and type of coating failure (not applicable for stainless steel tanks).

• Tank level indicator (TLI), vacuum and/or float switch condition.

• Suction and discharge piping and vent line condition.

• Fastener material (stainless steel) and condition.

• Zinc anode condition (remaining percentage).

3.5.4 Control panel assembly. Open and vacuum clean the control panel assembly. Inspect the control panel assembly for any indications of overheating or loose wiring or connections. Submit a CFR

3.6 Closing. The Contractor must notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330.

3.6.1 The Contractor must renew 100% of nylon insert/nylock nuts and washers.

3.6.1 Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing fasteners. Existing undamaged fasteners may be reused. For purpose of bid, assume 10% of existing fasteners will require renewal. Renew all nylon insert nuts.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.7 Operational test, post repairs. After completion of work, the Contractor must accomplish the following in the presence of the Coast Guard Inspector, and submit a CFR:

3.7.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.

3.7.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.

3.7.3 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tank(s) to the limit of the ship’s installed pumps.

51 (Rev-0)

52 (Rev-0)

59320_ESD_0323_FLT

REC_59320_FLT_160 WLIC 'A' Class (ALL)(0323)

WORK ITEM 13: Grey Water Piping, Clean and Flush

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the grey water piping system.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawing 160 WLIC 4808-1, Rev F, Pollution & Drainage Sys

General Requirements

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

53 (Rev-0)

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:

• Grey water pumps

3.2 Contamination prevention. The Contractor must take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.

3.3 Personnel qualification. The Contractor must ensure that personnel accomplishing this work are qualified and experienced in operating the pressurized water system and handling the chemicals. For each operator/cleaning technician, submit documentation of applicable experience and training obtained within the last twelve months along with the Cleaning Plan (see paragraph 3.5.6.2).

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.5 Piping hydrojet cleaning. The Contractor must perform the following work:

3.5.1 .

3.5.2 Prior to commencing work, coordinate with the Coast Guard Inspector. Determine required down times for affected piping system. Determine the feasibility/need for the piping system to be split to minimize system down time.

3.5.3 With the aid of ship’s force, split the plumbing drain system fore and aft by closing isolation valves in the drainage system. Work on only one section of the plumbing drain system at a time to allow use of toilet and shower facilities in the other section of the system by the ship’s duty section.

3.5.4 Using the referenced Coast Guard drawings as guidance, hydro blast the internal surfaces of all of the plumbing drain piping. Hydro blast pressure must be at least 2500 psig at the discharge nozzle in all piping to ensure removal of all salts and scale from piping internal surfaces.

NOTE

Ship’s force will provide an assistant to the Contractor to show the Contractor the location of clean-out connections within the plumbing drain system.

3.5.4.1 Open each of the clean out connections as required to clean and hydro blast all of the internal piping within the system. Catch any fluid that drains from the clean out connections when it is opened and clean up any spills using bleach to disinfect the spill after cleaning.

3.5.4.2 It may be necessary for the Contractor to install additional clean-out connections to access all portions of the plumbing drain system. If additional clean-out connections are needed, a separate specification item in this specification package must be authorized to install additional clean-out connections.

54 (Rev-0)

3.5.4.3 Empty and clean all connected grease traps, and dispose of waste in accordance with all Federal laws and regulations.

3.5.4.4 Hydro blast cleaning water may be collected in the ship’s sewage system and disposed of via the ship’s sewage shore tie connections.

3.5.5 Clean until all of the following conditions are met:

• All visible calcium carbonate deposits, solid deposits, grease and build-up are removed from pipe walls.

• Discharge water from the piping being cleaned is free of all visible scale and deposits.

3.5.5.1 Inspect the piping interior using a borescope in the presence of the COR, to verify that all solid deposits visible to the unmagnified eye have been removed. Continue the cleaning process until all visible solid deposits are removed from the pipe walls.

3.5.6 In the event that hydroblasting alone does not clean piping to required conditions, Contractor must use chemical cleaning methods.

3.5.6.1 Ensure that chemical cleaners do not damage the environment, heat exchanger or the vessel.

3.5.6.2 Submit the written plan for chemical cleaning to the COR for approval 96 hours before work is to commence. The procedure must include products to be used, safety precautions, disposal requirements, sequence of events, etc. Submit a MSDS to the COR for all chemicals proposed for use. Changes to the chemical cleaning plan as written, need to be approved by the COR (and Facilities).

3.5.6.3 Chemical cleaning waste water disposal. Dispose of all cleaning fluids and debris in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item. Do not drain any fluids (including fresh water) into any space, bilge, or exterior location.

• Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.

• Flush twice the volume of the system cleaned with water to include 3 repeated pH tests between 6 and 8. The flushing water shall be collected and disposed by the Contractor.

3.6 Pumps and valves. The Contractor must replace system tank valve(s) with temporary spool piece(s).

Visually inspect system pumps and valve(s); and submit a CFR. Upon completion of work, reinstall the removed tank valve(s) with new gaskets.

3.7 Gasket renewal. The Contractor must reinstall all removed valves and fittings with new gasket material conforming to applicable referenced drawings.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.8 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

55 (Rev-0)

3.8.1 Leak test. After all system components are reinstalled, the Contractor must test all disturbed piping for leaks, as follows, and submit a CFR:

• Plug all system openings (except the highest) and fill system with water to the point of overflow. Ensure that the water level does not go down (without adding any water) for sufficient time to inspect the entire system (no less than 15 minutes).

• Closely monitor the system for leaks. Repair all leaks detected.

• Repeat test and inspection until no leaks are detected.

56 (Rev-0)

59321_ESD_0323_FLT

REC_59320_FLT_160 WLIC 'A' Class (ALL)(0323)

WORK ITEM 14: Sewage Piping, Clean and Flush

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage piping system.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawing 160 WLIC 4808-1, Rev F, Pollution & Drainage Sys

General Requirements

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

57 (Rev-0)

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:

• Sewage pumps

• Toilets

3.2 Contamination prevention. The Contractor must take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.

3.3 Personnel qualification. The Contractor must ensure that personnel accomplishing this work are qualified and experienced in operating the pressurized water system and handling the chemicals. For each operator/cleaning technician, submit documentation of applicable experience and training obtained within the last twelve months along with the Cleaning Plan.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Operational test - initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.5 Cleaning plan. Submit the written plan for chemical cleaning to the COR for approval 96 hours before work is to commence. The procedure must include products to be used, safety precautions, disposal requirements, sequence of events, etc. Submit a MSDS to the COR for all chemicals proposed for use.

Changes to the chemical cleaning plan as written, need to be approved by the COR (and Facilities).

CAUTION

Although the Coast Guard prefers pressurized water as the cleaning fluid, the Contractor may propose chemical cleaning as an alternative, providing that the proposed chemical cleaning agent is environmentally safe, suitable for use in marine sewage piping application, and pre-approved by the COR.

The chemicals used in the cleaning (including cleaning chemicals, neutralizing compounds, and defoaming chemicals) must not cause any significant detrimental effects to the sewage piping system or any other system components Due to the fact that system piping has historically been difficult to clean by pressure washing only, chemical cleaning is usually required to successfully complete the cleaning process.

3.5.1 Procedure requirements. The Contractor must ensure that the procedure includes the following:

• Methods of cleaning.

• All safety precautions required during cleaning operations.

• List of qualified personnel who will operate machinery or handle chemicals (see paragraph

3.3 (Personnel qualification) herein).

• Locations in the sewage piping where cleaning will take place, and any additional fittings necessary.

58 (Rev-0)

• Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.

3.5.2 Plan submittal. The Contractor must submit the written plan to the COR for approval at least 48 hours prior to commencing cleaning operations. Changes to the chemical cleaning plan as written, need to be approved by the COR (and local Facilities).

3.6 Clean and flush. The Contractor must clean and flush approximately100 linear feet of sewage system piping, shown on Coast Guard Drawing 160B WLIC 4808-1..

3.6.1 Pumps and valves. Replace system tank valve(s) with temporary spool piece(s) before cleaning.

Visually inspect system pumps and valve(s); and submit a CFR. Upon completion of work, reinstall the removed tank valve(s) with new gaskets.

3.6.2 Cleaning. Continue cleaning until all of the following conditions are met:

• All visible calcium carbonate deposits, solid deposits and build-up are removed from pipe walls.

• Discharge water from the piping being cleaned is free of all visible scale and deposits.

3.6.3 Inspect the piping interior using a borescope in the presence of the COR, to verify that all solid deposits visible to the unmagnified eye have been removed. Continue the cleaning process until all visible solid deposits are removed from the pipe walls.

3.6.4 Flush twice the volume of the system cleaned with water to include 3 repeated pH tests between 6 and 8. The flushing water shall be collected and disposed by the Contractor.

3.7 Waste disposal. The Contractor must dispose of all cleaning fluids and debris in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item. Do not drain any fluids (including fresh water) into any space, bilge, or exterior location.

3.8 Gasket renewal. The Contractor must reinstall all removed valves and fittings with new gasket material conforming to ASTM D1330.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.9 Operational test – post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

3.9.1 Leak test. After all system components are reinstalled, the Contractor must test all disturbed piping for leaks, as follows, and submit a CFR:

• Plug all system openings (except the highest) and fill system with water to the point of overflow. Ensure that the water level does not go down (without adding any water) for sufficient time to inspect the entire system (no less than 15 minutes).

• Closely monitor the system for leaks. Repair all leaks detected.

59 (Rev-0)

• Repeat test and inspection until no leaks are detected.

Blank Page
Blank Page
Blank Page