CG 45740 Insulation Spec.pdf

PDF 236 KB Posted

Attached to
INSULATION RENEWAL ON 45’ RESPONSE BOAT - MEDIUM Federal contract opportunity
Solicitation number
52050PR240000338
Issued by
Department of Homeland Security US Coast Guard

About this file

This document is a Request for Proposal (RFP) for a fixed-price contract to renew the interior hull insulation on a 45-foot Response Boat - Medium (RB-M) for the U.S. Coast Guard. The contractor will be required to remove the existing insulation, inspect the substrate, and install new insulation in the engine room, machinery space, and auxiliary space of the vessel. Specific installation materials are specified, including Pyrotek sound attenuation barrier and Owens Corning insulation. The work is to be performed at the USCG Base Miami Beach Industrial Production Facility, with an estimated period of performance in mid to late July 2024. The RFP is a small business set-aside, with proposals due by 3 p.m. on July 8, 2024. Award will be made to the responsible offeror whose proposal provides the best value to the government, considering cost and past performance. A pre-proposal site visit is scheduled for July 1, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to INSULATION RENEWAL ON 45’ RESPONSE BOAT - MEDIUM, newest first.
File Type Posted
Insulation Details 45-RB-M-635-002 Rev C.pdf PDF
Statement of Work_RB-M Insulation Renewal.pdf PDF
Synopsis Solicitation 45740 Insulation Renewal.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG 45740 (RB-M-45) DOCKSIDE AVAILABILITY FY2025

125 (Rev-2)

63500_AKP_0423_45RBM

WORK ITEM 26: Interior Hull Insulation, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the interior hull insulation selected in Table 1.

TABLE 1- HULL INSULATION LOCATION

SELECT DESCRIPTION LOCATION APPROXIMATE SQFT

TO BE REPLACED

Pilothouse XX Entire Insulation Area Machinery Space 270 Square Feet Auxiliary Space

Survivor Cabin

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 45 RB-M 635-002, Rev C, Insulation Details

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

126 (Rev-2)

3.1.2 Tech Rep.

None.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

• Sheathing

• Bulkhead insulation

• Piping

• Electrical wiring

CAUTION

The insulation currently installed in the 45 RB-M engine room and engine room ventilation supply ducts are made up of two layers of fiberglass with a thin layer of lead sheathing in the middle. Lead is a recognized health hazard.

Lead may adversely affect the peripheral and central nervous systems, as well as the red blood cells, kidneys, reproductive and endocrine systems.

3.2 Removal. The Contractor must remove the interior insulation and associated fastening hardware selected in Table 1. Refer to Coast Guard Drawing 45 RB-M 635-002 and SFLC Std Spec 0000 for guidance.

3.2.1 Disposal. The Contractor must dispose of all removed materials, in accordance with all applicable Federal, state, and local regulations.

3.3 Substrate inspection - visual inspection. Upon removal of existing insulation, the Contractor must visually inspect the exposed surfaces for corrosion, pitting and any other visible defects. Submit a CFR.

3.4 Installation. The Contractor must install the new insulation in accordance with Coast Guard Drawing 45 RB-M 635-002 and SFLC Std Spec 0000.

NOTE

Lead sheet is no longer authorized for installation.

3.4.1 Engine Room Specific Insulation. The Contractor must renew the engine room insulation as follows:

3.4.1.2 The Contractor must provide all installation material and fasteners:

• Sound attenuation barrier: Pyrotek "Quadzero", P/N 17763007

• Hullboard: Owens Corning 2-inch Foil -Faced "Insul-Quick" insulation.

3.4.1.3 The Contractor must replace up to 20 percent of the welded studs and caps.

3.4.1.3.1 The Contractor must weld all insulation mounting studs.

127 (Rev-2)

3.4.1.4 The Contractor must install the insulation as follows starting at the bulkhead/hull in the following sequence.

• Quadzero

• Insulation Speed Washer

• 2-inch Insul-Quick Hullboard

• Insulation Speed Washer

• Trim Pin (as required)

• Insulation Cap

• Tape all boundaries.

4. NOTES

This section is not applicable to this work item.

Blank Page