This document is a schedule for the CFM Special Equipment Consolidation, a PACT ACT procurement under the General Services Administration's multiple award schedule framework. The schedule outlines a consolidated acquisition process for special equipment across all modalities, with an estimated timeline spanning from June through September 2026.

Key milestones include requirements submission to the NAC (Network Acquisition Center) by 6/30/2026, publication of a pre-solicitation notice on 7/10/2026, and posting of requirements and Request for Offers (RFO) on 7/18/2026. Vendors have until 7/24/2026 to submit equipment questions using a QA template provided in the Schedule of Line Items Excel File, with NAC publishing responses via amendment by 7/31/2026. Vendors must submit their offers to NAC by 8/14/2026. Customers will receive vendor offers via shared drive on 8/26/2026 and must submit technical evaluations using best value selection criteria by 9/4/2026. The NAC will assign Contracting Officer workload on 9/11/2026, with execution of delivery order awards scheduled for 9/25/2026. The document explicitly notes that all dates are estimates and subject to change.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CFM SPECIAL EQUIPMENT CONSOLIDATION SCHEDULE

Dates *PACT ACT Special

Consolidation* Milestone – All Modalities

6/30/2026 Requirements due to the NAC in FORCE

7/10/2026 Publish Pre-Solicitation Notice

7/18/2026 Post Requirements and Request for Offers (RFO)

7/24/2026

Vendors to submit Equipment Questions to NAC USE QA Template found in Schedule of Line Items Excel File

(second tab)

7/31/2026 NAC Published Responses to Vendor Questions via Amendment

8/14/2026 Vendors to Submit Offers to NAC

8/26/2026 Customers Receive Vendor Offers via the Shared Drive

9/4/2026

Customers Submit Technical Evaluations (Best Value

Selections)

9/11/2026 NAC Assigns CO Workload

9/25/2026 Execution of Delivery Order Awards

*Dates are estimates and are subject to change*