This document is a Fiscal Year 2024-2025 budget-approved fee update for the Commission on Equal Opportunities, adopted by Mayor Justin Elicker in New Haven, Connecticut. The document outlines a comprehensive schedule of oversight penalties, fines, and sanctions for various compliance violations related to construction contracts, focusing on areas such as pre-award conferences, wage reporting, daily reporting, and participation goals for minority, female, and resident workforce engagement.

The penalties are structured to incentivize contractor compliance across multiple dimensions, with financial assessments ranging from $750 to $4,000 per violation. Specific penalties include charges for not meeting pre-award conferences ($3,000-$4,000), late or missing payroll reports ($1,000 per week), incomplete daily reporting ($750 per violation), and failures to meet participation goals for minority, female, and resident workers ($2,000 or 1% of contract amount per week). These penalties can be applied to subcontractors, hiring contractors, and general contractors across all tiers, with the intent of ensuring rigorous adherence to contractual and regulatory requirements for workforce diversity and reporting standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Permits, License User Fee Update

FY 2024-2025 BOA Approved Budget

Ordinance No or C.G.S

FY 2024-25 MAYOR

PROPOSED & BOA

APPROVED

Not meeting for a pre-award conference - $3,000 or 2% of construction contract amount per violation, whichever is more, charged against the

(sub)contractor. 17-201 (15) $3,000.00

Three or more subcontractors hired for the same project not meeting for a pre-award conference - when third subcontractor violation occurs, charge

$4,000 per violation per subcontractor for each occurrence against each hiring contractor (all tiers) including the general contractor. 17-201 (15) $4,000.00

Late Certified or Living Wage Weekly Payroll Reports - $1,000 per week for every week that each report is overdue, or 1% of construction contract amount per week for every week that each report is overdue, whichever is more, charged to the employees' company. 17-201 (15) $1,000.00

Certified or Living Wage Weekly Payroll Reports Past Due for 8 Weeks -

$1,000 per week for the 9th and every subsequent week that each report is overdue, or 1% of construction contract amount per week for 9th and every subsequent week that each report is overdue, whichever is more, per subcontractor, for each occurrence, charged to each hiring contractor

(all tiers) up to and including the general contractor. 17-201 (15) $1,000.00

Missing, Unfilled, or Incorrectly Filled-In Daily Reports (employee attendance, hours, demographics, trades worked) - $750 per violation assessed against the subcontractor. 17-201 (15) $750.00

Sixth Site Visit at the Same Project In Which There Are Missing, Unfilled, or Incorrectly Filled-In Daily Reports (employee attendance, hours, demographics, trades worked) by the Same Contractor - $750 per violation for the sixth and subsequent violation assessed against the each hiring contractor (all tiers) up to and including the general contractor. 17-201 (15) $750.00

Violation of "Maximum Effort" to Reach Minority Participation Goal -

$2,000 or 1% of the respective construction contract amount, whichever is more, for each week of violation, up to the entire project work period, charged separately against the (sub)contractor and all tiers of hiring contractor up to and including the general contractor. 17-201 (15) $2,000.00

Violation of "Maximum Effort" to Reach Female Participation Goal -

$2,000 or 1% of the respective construction contract amount, whichever is more, for each week of violation, up to the entire project work period, charged separately against the (sub)contractor and all tiers of hiring contractor up to and including the general contractor. 17-201 (15) $2,000.00

Violation of "Maximum Effort" to Reach Resident Participation Goal (when applicable) - $2,000 or 1% of the respective construction contract amount, whichever is more, for each week of violation, up to the entire project work period, charged separately against the (sub)contractor and all tiers of hiring contractor up to and including the general contractor. 17-201 (15) $2,000.00

COMMISSION ON EQUAL OPPORTUNITIES

Oversight Penalties, fines and sanctions for Compliance Violations

ADOPTED BY: MAYOR JUSTIN ELICKER