Central_Plant_-_Climate_Control_System_Upgrade.pdf

PDF 354 KB Posted

Attached to
Central Plant - Climate Control System Upgrade
Solicitation number
4723
Issued by
Sacramento County, San Francisco City, California

About this file

Central Plant Climate Control System Upgrade

This is a scope of work document for a capital improvement project issued by a California county government. The project encompasses the furnishing of all necessary labor, materials, equipment, and incidental work required to complete a climate control system upgrade at a central plant facility. The work must be performed in strict conformance with detailed specifications, applicable permits from regulatory agencies, and all pertinent regulations. The document notes that quantities of work and materials are provided as approximations for bid comparison purposes only, with actual quantities subject to variation at the county's discretion. The file does not specify response dates, due dates, site visit requirements, bidders' conferences, award dates, or contract term information.

The document does not provide specific pricing terms, pricing structures, or cost details. No set-asides are explicitly identified or selected. The file contains no information regarding incumbent contractors, current environmental conditions, funding requirements, funding sources, or project budget amounts. Additional contract details necessary for bidding preparation, such as bonding requirements, insurance provisions, payment terms, and project timeline, are not included in this portion of the documentation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTICE TO CONTRACTORS

CENTRAL PLANT - CLIMATE CONTROL SYSTEM UPGRADE

County of Sacramento

9660 Ecology Lane

Sacramento, CA 95827

RELEASE DATE: November 24, 2026

DEADLINE FOR QUESTIONS: December 16, 2026

RESPONSE DEADLINE: January 7, 2027, 2:00 pm

RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:

https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/%7bproject.government.code%7d

NOTICE TO CONTRACTORS

Central Plant - Climate Control System Upgrade

1. Introduction

2. Notice to Contractors

3. Pricing Proposal

4. Vendor Submissions

Attachments:

A - Contract_4723_-_Bid_Set_Plans_20260930

B - Contract 4723 - Bid Set Special Provisions

C - Contract 4723 Pre Bid Agenda 20261124

Notice to Contractors #4723 Title: Central Plant - Climate Control System Upgrade

1. Introduction

1.1. Summary

The Project includes, without limitation, furnishing all necessary labor, materials, equipment and other incidental and appurtenant Work necessary to satisfactorily complete the Project, as more specifically described in specifications. This Work will be performed in strict conformance with the specifications, permits from regulatory agencies with jurisdiction, and applicable regulations. The quantity of Work to be performed and materials to be furnished are approximations only, being given as a basis for the comparison of Bids. Actual quantities of Work to be performed may vary at the discretion of the County.

1.2. Background

The work to be performed under this contract includes the replacement of the existing climate control system serving the central chilled and hot water plant at 700 H street. This project provides a replacement controls system to service the existing equipment. New Johnson Controls field devices and units are required to pair with the existing County downtown building management network. The scope includes a new electrical panel to service line voltage hydronic valves. Refer to the bid plans and special provisions for more details.

The contractor is required to accommodate the use of the chillers during all seasons, and the system will need to be placed in hand while the controls work is under construction.

1.3. Contact Information

Any inquiries or requests regarding this solicitation must be submitted via OpenGov. Contact with unauthorized County personnel during the selection process may result in disqualification.

Terry Keys

Sr Contract Services Officer

Email: keyst@saccounty.gov

Phone: (916) 876-6367

Department:

DGS: CAPSD - Construction

Department Head:

Joshua Green

Department Director

1.4. Timeline

Release Project Date November 24, 2026 mailto:keyst@saccounty.gov tel:(916)876-6367

Pre-Bid Meeting (Mandatory) December 10, 2026, 9:00am

Agenda

700 H street - see agenda attached. RSVP required

24 hours prior via OpenGov

Question Submission Deadline December 16, 2026, 10:00am

Bid Submission Deadline January 7, 2027, 2:00pm

Bid Opening January 7, 2027, 2:01pm via OpenGov https://government-project.s3.amazonaws.com/281319/c3cddb19-169f-4bc6-8b19-4cb29bc0b727_Contract_4723_Pre_Bid_Agenda_20261124.pdf

2. Notice to Contractors

2.1. ADVERTISEMENT SUMMARY

Notice is hereby given that the Board of Supervisors of the County of Sacramento will receive sealed bids for the following project:

BID DATE: Thursday, January 7, 2027

SUBMIT BIDS TO: COUNTY OF SACRAMENTO. SUBMIT ELECTRONIC RESPONSES VIA THE SACRAMENTO

COUNTY ELECTRONIC BIDDING PORTAL (SACCOUNTYEBIDS). BIDDERS MUST ELECTRONICALLY SUBMIT

THEIR BID ONLINE NO LATER THAN 2:00 PM ON THE DAY OF THE BID. BID OPENING(S) WILL

AUTOMATICALLY OCCUR ONLINE AT 2:01 PM AT THE FOLLOWING LINK: SACCOUNTYEBIDS.

Responses delivered by hand, fax, telephone, e-mail, or any postal carrier will not be accepted. If bidder uploads a file to SacCountyEbids, it is the bidder's responsibility to ensure the file is not corrupt or damaged. If County is unable to open an attachment because it is damaged, corrupt, infected, etc., it may disqualify bidder’s submission. See this training guide for assistance in entering your online response.

FOR: Central Plant - Climate Control System Upgrade

CONTRACT NUMBER: 4723

ESTIMATED CONSTRUCTION COST: 775,000.00

CONTRACTOR LICENSE REQUIRED: The prime contractor shall be required to hold a General Building

Contractor License, Class B. In addition, the prime contractor or their hired subcontractors shall hold the following licenses: • Low Voltage Systems Contractor, C-7 (this work may alternately be completed by a

C-10 licensed contractor) • Electrical Contractor, C-10 • Warm-Air Heating, Ventilating and Air-

Conditioning Contractor, Class C-20

PRE-BID QUESTIONS DUE VIA Q&A: Date: Wednesday, December 16, 2026 No later than: 10:00 am

PROJECT DESCRIPTION: The work to be performed under this contract includes the furnishing of all labor, materials, equipment, and other incidental work for: Replacement of the existing climate controls system, for 700 H Street central plant.

BASIS FOR AWARD: The basis for award shall be base bid only, with no additive or deductive items, or no consideration of additive or deductive items.

CONTRACT INFORMATION: Contract Documents are contained herein and include: Notice to

Contractors, the Sacramento County Standard Construction Specifications, the Special Provisions, the

Bid Proposal form and any attachments, exhibits, drawings, addenda, and/or documents provided by the Project Manager that pertain to this project.

• Contract Documents are available at: SacCountyEbids

• The Standard Construction Specifications, which are incorporated by reference in the Contract

Documents, may be downloaded at: https://saccountyspecs.saccounty.gov/Pages/default.aspx.

https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/saccounty http://help.procurenow.com/en/articles/5815468-opengov-procurement-vendor-training https://secure.procurenow.com/portal/saccounty https://saccountyspecs.saccounty.gov/Pages/default.aspx

2.2. MANDATORY PRE-BID MEETING

A mandatory pre-bid meeting will be held on Thursday, December 10, 2026, at 9:00 am, 700 H street -see agenda attached. RSVP required 24 hours prior via OpenGov. The project engineers will be present to provide a project summary and to answer questions.

Attendance of the Pre-Bid Conference is MANDATORY for this project. The mandatory pre-bid conference and walk-through will be held for the purpose of reviewing questions regarding the project.

A representative of the prime Contractor must be in attendance and sign the log. A representative of the

County will be present to review the project with the bidders, allow bidders to walk the site and to answer questions. Bids received from bidders who do not attend this meeting will be deemed non-responsive.

2.3. BID GUARANTEES

Each bid must be submitted on the bid forms provided in the Contract Documents; however, if none are provided, the surety may issue on its own paper. Each bid must also be accompanied by security in the form of a bid bond issued by a corporate surety, a certified check or cashier's check payable to the

Treasurer of Sacramento County, or cash for an amount not less than ten percent (10%) of the aggregate sum of the bid.

2.4. BONDS

The successful bidder shall be required to execute a material and labor Payment Bond and Performance

Bond, issued by a corporate surety, acceptable to the County of Sacramento, each for not less than one hundred percent (100%) of the contract price.

Pursuant to Public Contract Code, section 22300, the Contractor may, at its own expense, substitute securities for any money being withheld by the County to ensure performance under this contract. The

Contractor must notify the County of its intent to pursue this option prior to the issuance/execution of a contract.

2.5. LICENSE REQUIREMENTS

Award of this contract requires a valid California contractor's license with the classification identified above.

Public Contract Code, section 4104(a)(1), requires that any person making a bid must submit the name, location of the place of business, and the subcontractor’s license number on the bid form.

No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].

No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5.

2.6. LABOR COMPLIANCE PROGRAM

The County of Sacramento received final approval from the Director of California Department of

Industrial Relations as a Labor Compliance Program effective March 15, 1994. All questions regarding this Labor Compliance Program and prevailing wage requirements should be directed to the Labor

Compliance Section at: 916-875-2711. In accordance with Section 1771.5 of the California Labor Code, the payment of the general prevailing rate of per diem wages or the general prevailing rate of per diem wages for holiday and overtime is not required for any public works project of $25,000 or less when the project is for construction work, or for any public works project of $15,000 or less when the project is for alteration, demolition, repair, or maintenance work.

This is a Alteration project in accordance with Labor Code section 1771.5.

Pursuant to California Labor Code, section 1720 and following, and section 1770 and following, the successful bidder shall pay not less than the prevailing rate of per diem wages as determined by the

Director of the California Department of Industrial Relations. Copies of the prevailing wage determinations are on file at the office of the County of Sacramento Labor Compliance Program, 9800

Goethe Road, Suite D, Sacramento, CA 95827, and are also available at http://www.dir.ca.gov/DLSR/PWD.

2.7. ADVANCED CLEAN FLEETS REGULATION

Vehicles with a gross vehicle weight rating greater than 8,500 lbs. and light-duty package delivery vehicles operated in California may be subject to the California Air Resources Board

(CARB) Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, see CARB Advanced

Clean Fleets and Advanced Clean Fleets Regulation & Advisories | California Air Resources

Board.

The apparent low bidder shall provide copies of valid Certificates of Reported Compliance as described in California Code of Regulations, title 13, ("13 CCR") section 2449(n) for the bidder’s fleet, and fleets of any listed subcontractors, of vehicles subject to 13 CCR section 2449 which may be use in performance of this project.

If the apparent low bidder’s fleet, or any subcontractor’s fleet, is exempt or is not subject to the regulation bidder shall clearly indicate the applicable exemption in the bidder’s response. For more information, see CARB Advanced Clean Fleets Regulation Exemptions and Extensions

Overview | California Air Resources Board.

Certificates of Reported Compliance and/or exemptions must be submitted by the apparent low bidder by 4:00PM on Monday following Bid Opening and must be received by the County prior to contract award.

https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets/advanced-clean-fleets-regulation-advisories https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets/advanced-clean-fleets-regulation-advisories https://ww2.arb.ca.gov/resources/fact-sheets/advanced-clean-fleets-regulation-exemptions-and-extensions-overview https://ww2.arb.ca.gov/resources/fact-sheets/advanced-clean-fleets-regulation-exemptions-and-extensions-overview

2.8. QUESTIONS

Direct pre-bid questions to the Project Manager via the Q&A tab in the portal. ALL PRE-BID QUESTIONS

MUST BE SUBMITTED IN WRITING VIA THE Q&A TAB NO LATER THAN Wednesday, December 16, 2026

BY 10:00 am. Questions received after that time will not be answered. Responses will be by addenda to the bid documents.

The Board reserves the right to reject any or all bids, to waive any informality in any bid, and to determine which bid, in their judgment, is the lowest responsive bid of a responsible Bidder.

By order of the Board of Supervisors of the County of Sacramento, Sacramento County, California, dated: November 17, 2026.

Clerk of the Board

3. Pricing Proposal

PRICING TABLE

Line Item Description Quantity Unit of

Measure Unit Cost Total

10 Bid Proposal - Lump Sum 1 LS

TOTAL

4. Vendor Submissions

4.1. What form of Bid Guarantee will Contractor be submitting?* Bid security must be a bidder bond, a certified check or cashier’s check payable to the Treasurer of the

County of Sacramento, or cash. Bids secured by personal checks or personal guarantees will be rejected.

☐ Scanned copy of Fully Executed Bid Bond

☐ E-bid Bond (Use Surety 2000)

☐ Cashier's or Certified Check

☐ Cash

*Response required

4.2. Bid Guarantee

Upload a scanned copy of your fully executed bid bond here if Contractor is submitting a scanned bid bond.

4.3. E-Bid Bond

Please enter your Bid Bond information from Surety2000 below If Contractor is submitting an E-Bid

Bond

4.4. Non-collusion Declaration*

The undersigned declares:

I am an authorized representative with binding authority for my company, the party making the foregoing bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on the date this bid is submitted.

☐ Please confirm

*Response required

4.5. Designation of Subcontractors - Unit Price Contracts*

Please download the below documents, complete, and upload.

• DESIGNATION_OF_SUBCONTRACTO...

*Response required

4.6. Bid Item Percentage Listing on Designation of Subcontractor form* Bidder shall certify that the bidder entered the PERCENTAGE OF BID ITEM SUBCONTRACTED in Column

(C) of the Designation of Subcontractor form NOT the percentage of total bid.

☐ Please confirm

*Response required

4.7. Additional Submittals Required With Bid*

Attach all additional submittals specified in the Special Provisions as required at the time of bid.

Reference specification 23 09 23, part 1.5 Quality Assurance and list of projects

*Response required

4.8. Type of Business*

☐ C Corporation

☐ S Corporation

☐ Limited Liability C Corporation

☐ Partnership

☐ Limited Liability Partnership

☐ Sole Proprietor/Individual

☐ Other

*Response required

4.9. Type your Legal Company Name Here*

State your Company's Name Here. This will be verified against the California Secretary of State's

Website.

*Response required

4.10. CA Secretary of State Entity Number*

Provide your Entity Number from the CA Secretary of State.

If your business is not registered in CA, provide the Entity Number from your registered state and identify the state.

*Response required

4.11. Contractors State License Board (CSLB) Number*

Please enter your License Number here. This will be verified against the state database https://government-project.s3.us-west-2.amazonaws.com/14260/4c72069d-701a-4f52-9d88-093a99683f23_DESIGNATION_OF_SUBCONTRACTORS.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4LZWFLGK5%2F20261124%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20261124T212943Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEM3%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJIMEYCIQDutuETj6FxtdWdrl%2BniSBezGow0WWW%2F8sCXYEiodK87AIhAJ0A4H8GRsb1Z6Qm%2FUl3TYhUt83Ckmug0l6E0%2BiSDNFvKpUFCJX%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEQAhoMODkyMzY0Njg3NjcyIgwd2JvC05%2Bfuq9C860q6QRNefOs81qVqLa5pZsquPvHx6DccavPjc%2Bv1LC71CbX23natD5K9IYYoWAZ94d0JgH%2BvbSRYjhs%2B2DE%2FhNFEt8BwVUcyCrDFGtj0%2FwKpIH1XjgzuQM7V%2B0AE%2B3ePT7QGRn8kx72ywujHqHZUTJ%2BmR%2F2uHkjmnOSMw4Qm9VawpmHZ0psb%2BDfSJCelIv%2FJUOVNJYrDE0HZFGBa1dhQgW9x8vk8YZWHvmV1NRpNRWAZo8TybYAQ%2BP2HO9PrQt070cb%2BowjdBlEElkRWeKZJmYZCsb5c2%2BOoUZ4JSLCg71YyqGPtnZ7BFFrCY5JaXelkkdEZWsgL%2BnQbwaL2TgnSL%2FpNykjdypYldmy%2BgWhUprPuzd8gD9G8FerzndQZ%2F9RKeCbmQCps7mGtNYF%2BDTMrFWM1Ed7DItROa5zlSUpLJ9zzB59jmGdKZaCXgen1LuA9DvstznE%2BzwGKQ3gV%2BdXnb7i9G6%2Fm11suQPQ%2F7SbiYjTYd4Bybjci4sYyHCD70auww0V4uSD6UWevyV99j04BTyKfGa2NCCS%2FoEejyldB17cvZpGse4rMeL26MMCpxRyRDyZc2jFwZ4j0TiYXKJjXSa2K3S04kjX2jPKuop%2F%2B6%2B2Wg%2BL%2BR5UzV1PWHIe6oacpxaUoE6quFoqwcisfyz1L%2BctN8pfw5CxQEmphKDhZWtuHpq7HQttp1w0ILjDMBj8kjGym%2BktmPFe%2BYQtWSNIUI%2FmUk%2FXPygwexvSEddczDXwl84kUKIFbmeaFvePSdIIil6rRIy5tAE%2FwT0%2B2%2FLpFRtmeGKH5j29kacMg5GJg5kaDi3%2Bnc9Cxi0seG5sQjCy4pfYBjqYAcudU8K3DwDi93BkusqTShUa%2ByIxk5t1lJcRk%2FS9mtcnSj3E4gPh4ldwCg1HDsPkGkSxqCtMHoBYfOyZLpEIbYXgexC5ECudgjCz75ukQheIInlRwvtazX3DuccA%2Fp363FlgDeddoQ70%2B7K3wubE0UZ%2F7vXW7NjflbETESwKEQnE%2Bp%2Bs64EH2RySLUMJvhwYlItHgblLOfsu&X-Amz-Signature=26a569f3a2cf282a40d541d718fa0aad8eafc74cc15580a5afa85679032b91ba&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22DESIGNATION_OF_SUBCONTRACTORS.docx%22&x-id=GetObject

4.12. Contractors State License Board (CSLB) License Expiration Date * Enter your CSLB license expiration date:

4.13. Contractors State License Board (CSLB) License Classifications* Enter your current CSLB license classifications:

*Response required

4.14. California Department of Industrial Relations Registration* Please enter your Public Works Contractor Registration Number. This will be verified against the state database.

*Response required

4.15. Provide the full contact name, title, and e-mail of the signatory for your firm. Provide contact information for the contract manager for your firm in order to distribute Contract Documents, including other recipients requiring a copy, if awarded.**

Signatory: name, title, email

Contract manager/admin: name, phone, email

*Response required

4.16. PaymentWorks Contact*

Please provide the name and e-mail for a finance point-of-contact for your firm that will receive an invitation to complete the vendor registration process on the County's PaymentWorks portal.

To clarify, if you are set-up with other agencies using PaymentWorks, that information is not available to the County, so you must complete this process for the County.

*Response required

4.17. Bidder certifies they understand the post-bid submittals specified and required on this project and will comply with the timeline for submission. *

☐ Please confirm

*Response required

4.18. I hereby certify under penalty of perjury that the above statements are true.*

☐ Please confirm

1. Introduction
1.1. Summary
1.2. Background
1.3. Contact Information
1.4. Timeline
2. Notice to Contractors
2.1. ADVERTISEMENT SUMMARY
2.2. MANDATORY PRE-BID MEETING
2.3. BID GUARANTEES
2.4. BONDS
2.5. LICENSE REQUIREMENTS
2.6. LABOR COMPLIANCE PROGRAM
2.7. ADVANCED CLEAN FLEETS REGULATION
2.8. QUESTIONS
3. Pricing Proposal
4. Vendor Submissions
4.1. What form of Bid Guarantee will Contractor be submitting?*
4.2. Bid Guarantee
4.3. E-Bid Bond
4.4. Non-collusion Declaration*
4.5. Designation of Subcontractors - Unit Price Contracts*
4.6. Bid Item Percentage Listing on Designation of Subcontractor form*
4.7. Additional Submittals Required With Bid*
4.8. Type of Business*
4.9. Type your Legal Company Name Here*
4.10. CA Secretary of State Entity Number*
4.11. Contractors State License Board (CSLB) Number*
4.12. Contractors State License Board (CSLB) License Expiration Date *
4.13. Contractors State License Board (CSLB) License Classifications*
4.14. California Department of Industrial Relations Registration*
4.15. Provide the full contact name, title, and e-mail of the signatory for your firm. Provide contact information for the contract manager for your firm in order to distribute Contract Documents, including other recipients requiring a copy, if awarde...
4.16. PaymentWorks Contact*
4.17. Bidder certifies they understand the post-bid submittals specified and required on this project and will comply with the timeline for submission. *
4.18. I hereby certify under penalty of perjury that the above statements are true.*