CDRLs EH5C0112EH.docx

DOCX document 26 KB Posted

Attached to
BOAST RFOP - Mount, Telescope - NSN: 1240-01-277-0473
Solicitation number
PANDTA-25-P-0000_007619
Issued by

About this file

This is a Contract Data Requirements List (DD Form 1423) for the Mount, Telescope (NSN: 1240-01-277-0473) procurement under contract number EH5C0112EH. The document specifies four data deliverables that the contractor must submit throughout the contract lifecycle.

The required deliverables include: (1) Engineering Change Proposals (ECP) submitted as-required using DD Form 1692 per SAE-EIA-649-1 standards; (2) Requests for Variance (RFV) submitted as-required using DD Form 1694 per SAE-EIA-649-1 standards; (3) Notices of Revision (NOR) submitted as-required using DD Form 1695 per SAE-EIA-649-1 standards; and (4) a Test Procedure for Heavy Phosphate Coating (pre-production) due 60 days after contract award, requiring government approval prior to production initiation. Additionally, a First Article Test Report (FATR) is required as-needed with actual inspection and test results, measurements, and certifications keyed to drawing and specification requirements. The contractor must provide at least 15 calendar days advance written notice before the scheduled First Article Test, and the government will provide feedback within 30 calendar days of FATR receipt. All submissions must be in government-compatible software formats (Microsoft Office or PDF) and routed electronically to the Procuring Contracting Officer (daniel.j.gibson43.civ@army.mil), Contract Specialist (colin.t.creagh.civ@army.mil), and relevant engineering points of contact at the U.S. Army DEVCOM Ammunition Center.

View the file

Other files

File Type Posted
Mount Telescope BOAST RFOP.xlsx XLSX spreadsheet
Mount Telescope BOAST RFOP.xlsx XLSX spreadsheet
Mount Telescope BOAST RFOP.xlsx XLSX spreadsheet
Mount Telescope BOAST RFOP.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423, FEB 2024

CONTRACT DATA REQUIREMENT LIST, PREVIOUS EDITION MAY BE USED Form Approval OMB No. 0704-0188 The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 1000

B. EXHIBIT:

C. CATEGORY:

TDP _X_ TM ____ OTHER ____

D. SYSTEM/ITEM: Mount, Telescope, NSN: 1240-01-277-0473

E. CONTRACT/PR NO.: EH5C0112EH

F. CONTRACTOR: TBD

1. DATA ITEM NO: A001

2. TITLE: ENGINEERING CHANGE PROPOSAL (ECP)

3. SUBTITLE: N/A

4. AUTHORITY: DI-SESS-80639E

5. CONTRACT REFERENCE: SECTION C

6. REQUIRING OFFICE:

7. DD250 REQ: LT

8. APP CODE: N/A

9. DIST. STATEMENT REQ: SEE ITEM 16

10. FREQUENCY: ASREQ

11. AS OF DATE: N/A

12. DATE OF FIRST SUBMISSION: ASREQ

13. DATE OF SUBS. SUBMISSION: ASREQ

14. DISTRIBUTION: SEE ITEM 16

A. ADDRESSEE: PCO, CS, ACO, ENG

B. COPIES:

DRAFT:

FINAL:

REG REPRO: 0

15. TOTAL COPIES: SEE ITEM 16

16. REMARKS: DATA MUST BE IN GOVERNMENT COMPATIBLE SOFTWARE (i.e., MICROSOFT OFFICE OR PORTABLE DOCUMENT FORMAT (pdf)). *UNLESS OTHERWISE SPECIFIED THE DISTRIBUTION STATEMENT ASSIGNED TO THE ECP SHALL BE THE MOST RESTRICTIVE DISTRIBUTION STATEMENT OF THE AFFECTED ITEMS IDENTIFIED IN THE ECP. **SUBMIT ELECTRONICALLY TO THE PROCURING CONTRACTING OFFICER AT daniel.j.gibson43.civ@army.mil AND CONTRACT SPECIALIST AT colin.t.creagh.civ@army.mil; COPY FURNISH TO THE ADMINISTRATIVE CONTRACTING OFFICE AT (ACO TBD) AND ENGINEERING POC AT usarmy.pica.devcom-ac.mbx.ecp-document@army.mil. DOCUMENTATION SHALL BE IN ACCORDANCE WITH PARAGRAPH 3.3.1 OF SAE-EIA-649-1 (CURRENT REVISION) USING DD FORM 1692 (CURRENT REVISION) LOCATED AT http://www.dtic.mil/whs/directives/infomgt/forms/.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

1. DATA ITEM NO: A002

2. TITLE: REQUEST FOR VARIANCE (RFV)

3. SUBTITLE: N/A

4. AUTHORITY: DI-SESS-80640E

5. CONTRACT REFERENCE: SECTION C

6. REQUIRING OFFICE:

7. DD250 REQ: LT

8. APP CODE: N/A

9. DIST. STATEMENT REQ: SEE ITEM 16

10. FREQUENCY: ASREQ

11. AS OF DATE: N/A

12. DATE OF FIRST SUBMISSION: ASREQ

13. DATE OF SUBS. SUBMISSION: ASREQ

14. DISTRIBUTION: SEE ITEM 16

A. ADDRESSEE: PCO, CS, ACO, ENG

B. COPIES:

DRAFT:

FINAL:

REG REPRO: 0

15. TOTAL COPIES: SEE ITEM 16

16. REMARKS: DATA MUST BE IN GOVERNMENT COMPATIBLE SOFTWARE (i.e., MICROSOFT OFFICE OR PORTABLE DOCUMENT FORMAT (pdf)). *UNLESS OTHERWISE SPECIFIED THE DISTRIBUTION STATEMENT ASSIGNED TO THE RFV SHALL BE THE MOST RESTRICTIVE DISTRIBUTION STATEMENT OF THE AFFECTED ITEMS IDENTIFIED IN THE RFV. **SUBMIT ELECTRONICALLY TO THE PROCURING CONTRACTING OFFICER AT daniel.j.gibson43.civ@army.mil AND CONTRACT SPECIALIST AT colin.t.creagh.civ@army.mil; COPY FURNISH TO THE ADMINISTRATIVE CONTRACTING OFFICE AT (ACO TBD) AND ENGINEERING POC AT usarmy.pica.devcom-ac.mbx.ecp-document@army.mil. DOCUMENTATION SHALL BE IN ACCORDANCE WITH PARAGRAPH 3.3.2 OF SAE-EIA-649-1 (CURRENT REVISION) USING DD FORM 1694 (CURRENT REVISION) LOCATED AT http://www.dtic.mil/whs/directives/infomgt/forms/.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

1. DATA ITEM NO: A003

2. TITLE: NOTICE OF REVISION (NOR)

3. SUBTITLE: N/A

4. AUTHORITY: DI-SESS-80642E

5. CONTRACT REFERENCE: SECTION C

6. REQUIRING OFFICE:

7. DD250 REQ: LT

8. APP CODE: N/A

9. DIST. STATEMENT REQ: SEE ITEM 16

10. FREQUENCY: ASREQ

11. AS OF DATE: N/A

12. DATE OF FIRST SUBMISSION: ASREQ

13. DATE OF SUBS. SUBMISSION: ASREQ

14. DISTRIBUTION: SEE ITEM 16

A. ADDRESSEE: PCO, CS, ACO, ENG

B. COPIES:

DRAFT:

FINAL:

REG REPRO: 0

15. TOTAL COPIES: SEE ITEM 16

16. REMARKS: DATA MUST BE IN GOVERNMENT COMPATIBLE SOFTWARE (i.e., MICROSOFT OFFICE OR PORTABLE DOCUMENT FORMAT (pdf)). *UNLESS OTHERWISE SPECIFIED THE DISTRIBUTION STATEMENT ASSIGNED TO THE NOR SHALL BE THE MOST RESTRICTIVE DISTRIBUTION STATEMENT OF THE AFFECTED ITEMS IDENTIFIED IN THE NOR. **SUBMIT ELECTRONICALLY TO THE PROCURING CONTRACTING OFFICER AT daniel.j.gibson43.civ@army.mil AND CONTRACT SPECIALIST AT colin.t.creagh.civ@army.mil ; COPY FURNISH TO THE ADMINISTRATIVE CONTRACTING OFFICE AT (ACO TBD) AND ENGINEERING POC AT usarmy.pica.devcom-ac.mbx.ecp-document@army.mil. DOCUMENTATION SHALL BE IN ACCORDANCE WITH PARAGRAPH 3.3.4 OF SAE-EIA-649-1 (CURRENT REVISION) USING DD FORM 1695 (CURRENT REVISION) LOCATED AT http://www.dtic.mil/whs/directives/infomgt/forms/.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

A. CONTRACT LINE ITEM NO.: 9000

B. EXHIBIT: A

C. CATEGORY:

TDP _X__ TM ____ OTHER ___

D. SYSTEM/ITEM: Mount, Telescope, NSN: 1240-01-277-0473

E. CONTRACT/PR NO.: EH5C0112EH

F. CONTRACTOR: TBD

G. PREPARED BY: FCDD-ACE-SP

H: DATE: 2/3/25

I: APPROVED BY: Steven Carpenter

J: DATE: 2/3/25

1. DATA ITEM NO.: A004

2. TITLE OF DATA ITEM: TEST PROCEDURE – HEAVY PHOSPHATE COATING

3. SUBTITLE: PRE-PRODUCTION PROCEDURE

4. AUTHORITY: DI-NDTI-80603A

5. CONTRACT REFERENCE: RFOP–A004

6. REQUIRING OFFICE: RDAR-MEE-W(R)

7. DD250 REQ: Not Required

8. APP CODE: A

9. DIST. STATEMENT: D

10. FREQUENCY: ONE/R

11. AS OF DATE: Date of Contract award

12. DATE OF FIRST SUB: 60DAC

13. DATE OF SUBS: N/A

14. DISTRIBUTION:

A. ADDRESSEE: [Government Procuring Contract Officer (PCO)], [Contract Specialist (CS)], and mark.a.godlewski.civ@army.mil

B. COPIES:

DRAFT:

FINAL:

15. TOTAL:

16. REMARKS:

BLOCK 8 CONT. - PRIOR TO PRODUCTION, APPROVAL THRU THE CONTRACTING OFFICER IS REQUIRED W/IN 60 DAYS AFTER CONTRACT AWARD. CONTRACTING OFFICER WILL ROUTE INTERNALLY TO THE APPROVING OFFICE (RDAR-MEE-W(R)). CONTRACTING OFFICER SHALL PROVIDE PROCEDURE REVIEW RESPONSE BACK TO CONTRACTOR. COATED PANELS PER PARA 3.2.2 SHALL INCLUDE THREE WITH PHOSPHATE ONLY, THREE WITH PHOSPHATE AND PRIMER, AND THREE WITH PHOSPHATE, PRIMER AND TOP COAT.

The contract number must be cited on all phosphate coating procedures submitted for review and approval. Procedures shall include product name and manufacturer of all chemicals/materials to be used. All processes, equipment, controls along with testing and test frequencies used for phosphating including application of supplemental finishes shall be described in detail.

A. CONTRACT LINE ITEM NO.: 9000

B. EXHIBIT: A

C. CATEGORY:

TDP _X__ TM ____ OTHER ___

D. SYSTEM/ITEM: Mount, Telescope, NSN: 1240-01-277-0473

E. CONTRACT/PR NO.: EH5C0112EH

F. CONTRACTOR: TBD

G. PREPARED BY: FCDD-ACE-SP

H: DATE: 2/3/25

I: APPROVED BY: Steven Carpenter

J: DATE: 2/3/25

1. DATA ITEM NO.: A005

2. TITLE OF DATA ITEM: FIRST ARTICLE TEST REPORT (FATR)

3. SUBTITLE: TEST/INSPECTION REPORT

4. AUTHORITY: DI-NDTI-80809B

5. CONTRACT REFERENCE: RFOP-0001AB

6. REQUIRING OFFICE: RDAR-EIQ-P

7. DD250 REQ: Not required

8. APP CODE: A*

9. DIST. STATEMENT: D

10. FREQUENCY: ASREQ

11. AS OF DATE: SEE BLOCK 16

12. DATE OF FIRST SUB: SEE BLOCK 16

13. DATE OF SUBS: SEE BLOCK 16

14. DISTRIBUTION:

A. ADDRESSEE: Engineering, usarmy.pica.devcom-ac.mbx.qesa-qew-aie@army.mil, Quality Assurance, usarmy.ria.devcom-ac.mbx.rdar-qep@army.mil

B. COPIES:

DRAFT:

FINAL:

15. TOTAL:

16. REMARKS: REQUIRED BY THE AUTHORITY IN BOX 4, PARA 10.2 AND ITS SUBPARAGRAPHS. CONTRACTOR FORMAT IS ACCEPTABLE.

The FATR shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and QAP requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. Evidence of the QAR's verification will be provided. THE CONTRACTOR SHALL PROVIDE TO THE PROCURING CONTRACTING OFFICER, QAR, AND RDAR-EIQ-P AT LEAST 15 CALENDAR DAYS ADVANCE NOTICE (IN WRITING) OF THE SCHEDULED DATE, TIME AND LOCATION OF START OF FAT, SO THAT THE GOVERNMENT MAY WITNESS THE TESTS. THE GOVERNMENT WILL REVIEW THE FATR AND PROVIDE FEEDBACK TO THE CONTRACTOR WITHIN 30 CALENDAR DAYS OF RECEIPT OF FATR.

BLOCK 13: SUBSEQUENT SUBMISSION ONLY IF INITIAL FAT FAIL

03 FEBRUARY 2025

File details come from the government source that posted it. Updated .