CDRLs.pdf

PDF 1 MB Posted

Attached to
Depot-level overhaul of LM2500+ gas generator
Solicitation number
N64498-21-Q-5020
Issued by

About this file

This Contract Data Requirements List (CDRL) outlines six data items required from an LM2500+ gas generator overhaul contract. The contract calls for depot-level overhaul services of one US Navy LM2500+ gas generator in accordance with GE technical manual GEK 109982. Required data items include an incoming inspection summary report, disassembly inspection report, overhaul repair report, requests for waivers or deviations from specifications, quality management system documentation, and a counterfeit prevention plan. Submittals are due within five to sixty days of receipt or completion of work. The Naval Surface Warfare Center Philadelphia Division will evaluate responses to award a single firm-fixed-price contract for a one-year period of performance to a GE Level IV certified repair depot on a limited competition basis.

View the file

Other files

File Type Posted
N6449821Q5020.pdf PDF
GFP Attachment LM2500 GGA Repair.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423-1, FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

TBD A QCIC

LM2500+ Gas Generator TBD TBD

A001 Incoming Inspection Summary Report N/A

DI-QCIC-80376A SOW Para. C.2.7 NSWCPD C/423

LT

N/A C*

ASREQ

See Blk 16

See Blk 16

ASREQ

NSWCPD C/423 0 1 0

COR 0 1 0

PCO 0 1 0

0 3 0

Block 9: Distribution Statement C. Distribution authorized to U.S. Government Agencies and their contractors for administrative and operational use, 3 April 2020.Other requests for this document shall be referred to Commander, Naval Surface Warfare Center, Philadelphia Division, 5001 South Broad Street, Building 4, Philadelphia, PA 19112.

Blocks 10,11,12,13: 1.Within five (5) working days after receipt of the US Navy LM2500 SST GG, the contractor shall contact NAVSSES Code 423, to provide the serial number of the GG, and physical condition of the shipping container. 2. If the shipping container is unable to hold the nitrogen charge when the container is received, or at any other time when the gas generator is stored in the shipping container, the contractor shall notify NAVSSES Code 423 within two (2) working days. 3. Within five (5) calendar days of container opening and receipt inspection of the US Navy LM2500 SST GG, the repair activity shall contact NAVSSES Code 423 to report all parts/components that are missing, damaged or cannibalized.

Block 14: Submit via electronic mail in a digital format that can be read by Microsoft Office 2010 applications (or earlier) or Adobe PDF applications.

QUINONES.MARTIN.1228918403

Digitally signed by

QUINONES.MARTIN.1228918403

Date: 2020.09.29 08:50:10 -04'00'

09/29/20 DESHMUKH.DESIREE.1241

432439

Digitally signed by

DESHMUKH.DESIREE.1241432439

Date: 2020.10.01 07:51:25 -04'00'

10/1/2020

Adobe Professional 8.0

(1 Data Item)

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

TBD A QCIC

LM2500+ Gas Generator TBD TBD

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

DD FORM 1423-1 (BACK), FEB 2001

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

TBD A QCIC

LM2500+ Gas Generator (GG) TBD TBD

A002 Incoming Inspection Summary Report Disassembly Inspection Report (DIR)

DI-QCIC-80376A SOW Para. C.2.9 NSWCPD C/423

LT

N/A C

ASREQ

See Blk 16

See Blk 16

ASREQ

NSWCPD C/423 0 1 0

COR 0 1 0

PCO 0 1 0

0 3 0

Block 4: The contractor shall compile the DIR containing the below data elements in the contractor’s format. At a minimum, the DIR shall contain the following data elements :

1. All incoming inspection results with tear-down inspection records.

2. All inspection data and damage reports.

3. GG serial number and selected component serial and part numbers.

4. Illustration and pictures of damage found.

5. Borescope inspection report(s) (if performed by the repair activity).

6. List of all technical directives, mandatory upgrades and service bulletins pending.

7. All authorized deviations from US Navy LM2500+ depot level technical manuals.

8. Metallurgical evaluation and laboratory reports.

9. All parts, components missing.

10. Condition (Serviceable / Not Serviceable) or Applicability (GG)

11. Replace / Rework

12. Findings Summary (FOD, MFG design, etc)

13. Conditions found (dimensions vs. spec)

14. Assembly nomenclature / part number

15. Accessories and gearboxes

16. Assembly model

17. Inspection and discrepancies found

18. Assembly manufacturer

19. Part number

20. Removal date

21. Serial number

22. Removal location (installed location)

23. CONCLUSIONS: Removal reason, Summary, Engineering comments

Block 9: Distribution Statement C. Distribution authorized to U.S. Government Agencies and their contractors for administrative and operational use, 3 April 2020.Other requests for this document shall be referred to Commander, Naval Surface Warfare Center, Philadelphia Division, 5001 South Broad Street, Building 4, Philadelphia, PA 19112.

Blocks 10, 11, 12, 13: Within forty five (45) working days after induction of the US Navy LM2500+ GG, the contractor shall provide a DIR to NSWCPD Code 423 to report all parts/components that have failed inspection.

Block 14: Submit via electronic mail in a digital format that can be read by Microsoft Office 2010 applications (or earlier) or Adobe PDF applications.

QUINONES.MARTIN.1228918403

Digitally signed by

QUINONES.MARTIN.1228918403

Date: 2020.09.29 08:52:05 -04'00'

09/29/20 DESHMUKH.DESIREE.1241

432439

Digitally signed by

DESHMUKH.DESIREE.1241432439

Date: 2020.10.01 07:51:56 -04'00'

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

TBD A QCIC

LM2500+ Gas Generator (GG) TBD TBD

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

TBD A ILSS

LM2500+ Gas Generator (GG) TBD TBD

A003 Overhaul Repair Report LM2500+ Asset GGA-5001 Repair Report

DI-ILSS-80755 SOW Para. C.2.9 NSWCPD C/423

LT

N/A C

ASREQ

See Blk 16

See Blk 16

ASREQ

NSWCPD C/423 0 1 0

PCO 0 1 0

COR 0 1 0

0 3 0

Block 4: This report at a minimum shall contain:

1. Table of contents.

2. All incoming inspection results with teardown inspection records.

3. All inspection data and damage reports.

4. Total overhaul work scope.

5. A photographic disassembly and condition report of the gas generator at induction and all sub-assemblies during teardown and inspection. Include photographs of components when required to show damage or unusual occurrences in the appropriate sub-assembly condition report.

6. The condition reports shall be segregated by gas generator sub-assembly as follows:

a. Compressor Front Frame

b. Compressor Rotor

c. Compressor Stator

d. Compressor Rear Frame

e. Combustor

f. Stage 1 HPT Nozzle

g. Stage 2 HPT Nozzle

h. HPT Rotor

i. Turbine Mid Frame

j. Inlet Gearbox

k. Transfer and Accessory Gearbox

l. Accessories and Components

7. A list of all parts replaced and/or upgraded (e.g. part numbers, serial numbers and work performed).

8. Metallurgical evaluations and laboratory reports.

9. Compressor blade lengths, segregated by stage, in table format.

10. Compressor vane lengths, segregated by stage, in table format.

11. HPT blade clearances after tip grinding.

12. Assembly records, a detailed step-by-step record of the GG assembly.

13. Test records from all testing performed (including accessories). Test data shall include the slave exhaust nozzle part number (or equivalent) and cold exit area measurements for the slave exhaust nozzle used during gas generator acceptance testing.

14. Accessory inspection and overhaul reports.

15. Borescope inspection report (for the borescope that is performed by the contractor).

16. List of all technical directives, and industrial service bulletins incorporated.

17. All authorized deviations from US Navy LM2500+ depot level technical manuals.

18. Final invoice including cost profile by sub-assembly.

19. Method of shipment and location shipped to.

QUINONES.MARTIN.1228918403

Digitally signed by

QUINONES.MARTIN.1228918403

Date: 2020.09.29 08:54:08 -04'00'

09/29/20 DESHMUKH.DESIREE.1241

432439

Digitally signed by

DESHMUKH.DESIREE.1241432439

Date: 2020.10.01 07:52:34 -04'00'

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

TBD A ILSS

LM2500+ Gas Generator (GG) TBD TBD

Block 9: Distribution Statement C. Distribution authorized to U.S. Government Agencies and their contractors for administrative and operational use, 3 April 2020.Other requests for this document shall be referred to Commander, Naval Surface Warfare Center, Philadelphia Division, 5001 South Broad Street, Building 4, Philadelphia, PA 19112.

Blocks 10, 11, 12, 13: The contractor shall compile a gas generator repair report in the contractor’s format. This report shall be submitted to NSWCPD Code 423 within sixty (60) days after completion all engine repairs.

Block 14: Submit via electronic mail in a digital format that can be read by Microsoft Office 2010 applications (or earlier) or Adobe PDF applications.

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

TBD A SESS

LM2500+ Gas Generator (GG) TBD TBD

A004 Request for Waivers (RFW) Request for Waiver or Deviation

DI-SESS-81732 SOW Para. C.2.6 NSWCPD C/423

DD

A C*

ASREQ

See Blk 16

See Blk 16

ASREQ

NSWCPD C/423 1 1 0

PCO 0 1 0

COR 0 1 0

1 3 0

BLOCK 4: THIS DATA ITEM SHALL BE SUBMITTED FOR ALL ANTICIPATED

UNREPAIRABLE AND OR OUT OF TOLERANCE CONDITIONS. FORMAT AND

CONTENT SHALL BE IN ACCORDANCE WITH MIL-STD-973, APPENDIX “E”,

SHORT FORM IN LIEU OF DI-CMAN-80640C.

THE CONTRACTOR SHALL UTILIZE DD FORM 1694 FOR SUBMISSION OF ALL

REQUESTS.

DEPARTURES (WAIVERS AND DEVIATIONS) SHALL BE SUBMITTED FOR

PRE-EXISTING CONDITIONS AND DEPARTURES FROM SPECIFICATION

GENERATED OR FOUND AFTER THE COMMENCEMENT OF WORK.

BLOCK 8: APPROVAL WILL BE BASED UPON IMPACT OF DEPARTURES ON

ITEM FORM, FIT OR FUNCTION. GOVERNMENT REQUIRES 15 DAYS (TOTAL)

REVIEW TIME. ALL DEPARTURES SHALL BE FORWARDED TO NSWCPD CODE

423 FOR REVIEW AND COMMENT. CODE 423 WILL FORWARD DEPARTURES

WITH COMMENTS ON DD FORM 1998 DIRECTLY TO NSWCPD CODE 424 WITH

A COPY OF THE DEPARTURE TRANSMITTAL TO THE CONTRACT OFFICER FOR

REVIEW AND DISPOSITION.

Block 9: Distribution Statement C. Distribution authorized to U.S. Government Agencies and their contractors for administrative and operational use, 3 April 2020.Other requests for this document shall be referred to Commander, Naval Surface Warfare Center, Philadelphia Division, 5001 South Broad Street, Building 4, Philadelphia, PA 19112.

BLOCKS 10, 11, 12, 13: SUBMISSION REQUIRED WHENEVER A DEPARTURE

FROM SPECIFICATION HAS OCCURRED OR IS ANTICIPATED. A COPY OF THE

DISPOSITIONED DEPARTURE SHALL BE PROVIDED WITH POST REPAIR

INSPECTION REPORT OF THE ITEM.

CONTRACTOR SHALL NOT ESTIMATE DEPARTURE PREPARATION PRICE ON

DD FORM 1423-1, BLOCKS 17 AND 18. SUPPORTING DATA, SUCH AS

DRAWINGS, SKETCHES, PHOTOGRAPHS, CALCULATION, FINANCIAL

ANALYSIS OR OTHER ATTACHMENTS THAT WILL CLARIFY OR JUSTIFY THE

REQUESTS FOR DEPARTURE SHALL BE INCLUDED.

QUINONES.MARTIN.1228918403

Digitally signed by

QUINONES.MARTIN.1228918403

Date: 2020.09.29 08:55:59 -04'00'

09/29/20 DESHMUKH.DESIREE.1241

432439

Digitally signed by

DESHMUKH.DESIREE.1241432439

Date: 2020.10.01 07:53:08 -04'00'

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

TBD A SESS

LM2500+ Gas Generator (GG) TBD TBD

BLOCK 14: IN ADDITION TO HARD COPY FORMAT, THE CONTRACTOR SHALL PROVIDE A COPY OF THE DEPARTURE IN ADOBE

ACROBAT, VERSION 7.0 OR LATER.

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

TBD A SESS

LM2500+ Gas Generator (GG) TBD TBD

A005 Quality Management System (QMS) N/A

DI-MGMT-82184 SOW Para. C.4.1 NSWCPD C/423

DD

A C*

ASREQ

See Blk 16

See Blk 16

ASREQ

NSWCPD C/423 1 1 0

PCO 0 1 0

COR 0 1 0

1 3 0

BLOCK 8: QUALITY MANAGEMENT SYSTEM (QMS) MANUAL IN ACCORDANCE

WITH ISO 9001:2015 SHALL BE SUBMITTED TO NSWCPD FOR APPORVAL NO

LATEER THAN 30 DAYS AFTER CONTRACT AWARD. CONTRACTOR MUST

SUBMIT FIRST, SECOND AND THIRD-TIER QMS DOCUMENTATION. APPROVAL

WILL BE BASED UPON IMPACT OF DEPARTURES ON ITEM FORM, FIT OR

FUNCTION. GOVERNMENT REQUIRES 15 DAYS (TOTAL) REVIEW TIME. ALL

DEPARTURES SHALL BE FORWARDED TO NSWCPD CODE 423 FOR REVIEW

AND COMMENT. CODE 423 WILL FORWARD DEPARTURES WITH COMMENTS

ON DD FORM 1998 DIRECTLY TO NSWCPD CODE 424 WITH A COPY OF THE

DEPARTURE TRANSMITTAL TO THE CONTRACT OFFICER FOR REVIEW AND

DISPOSITION.

Block 9: Distribution Statement C. Distribution authorized to U.S. Government Agencies and their contractors for administrative and operational use, 3 April 2020.Other requests for this document shall be referred to Commander, Naval Surface Warfare Center, Philadelphia Division, 5001 South Broad Street, Building 4, Philadelphia, PA 19112.

BLOCKS 10, 11, 12, 13: SUBMISSION REQUIRED WHENEVER A DEPARTURE

FROM SPECIFICATION HAS OCCURRED OR IS ANTICIPATED. A COPY OF THE

DISPOSITIONED DEPARTURE SHALL BE PROVIDED WITH POST REPAIR

INSPECTION REPORT OF THE ITEM.

CONTRACTOR SHALL NOT ESTIMATE DEPARTURE PREPARATION PRICE ON

DD FORM 1423-1, BLOCKS 17 AND 18. SUPPORTING DATA, SUCH AS

DRAWINGS, SKETCHES, PHOTOGRAPHS, CALCULATION, FINANCIAL

ANALYSIS OR OTHER ATTACHMENTS THAT WILL CLARIFY OR JUSTIFY THE

REQUESTS FOR DEPARTURE SHALL BE INCLUDED.

QUINONES.MARTIN.1228918403

Digitally signed by

QUINONES.MARTIN.1228918403

Date: 2020.09.29 08:58:42 -04'00'

09/29/20 DESHMUKH.DESIREE.1241

432439

Digitally signed by

DESHMUKH.DESIREE.1241432439

Date: 2020.10.01 07:53:57 -04'00'

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

TBD A SESS

LM2500+ Gas Generator (GG) TBD TBD

BLOCK 14: IN ADDITION TO HARD COPY FORMAT, THE CONTRACTOR SHALL PROVIDE A COPY OF THE DEPARTURE IN ADOBE

ACROBAT, VERSION 7.0 OR LATER.

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

TBD A MISC

LM2500+ Gas Generator TBD TBD

A006 Counterfeit Prevention Plan N/A

DI-MISC-81832 SOW Paragraph 10.0 NSWCPD C/424

LT

A D (BLK 16)

2 TIME/R (BLK 16)

N/A

SEE BLK 16

SEE BLK 16

PCO 0 1

Name and Code 0 1

COR 0 1

Other (as needed)

0 3 0

Block 4: Contractor’s format is acceptable. The contractor shall develop a Counterfeit Prevention Plan using SAE Aerospace Standards AS5553 and AS6174 as a guide.

Blocks 8 and 10: Allow 45 days for Government approval/disapproval. Resubmittals, if required, shall be submitted NLT 60 days after receipt of Government comments.

Block 9: Distribution Statement D. Distribution authorized to the U.S. Department of Defense and U.S. DoD contractors only. Critical Technology: (insert date). Other requests for this document shall be referred to Commander, Naval Surface Warfare Center, Philadelphia Division, 5001 South Broad Street, Building 4, Philadelphia, PA 19112.

Block 12: Initial submittal 90 days after contract award. Final submission shall be 90 days prior to Milestone C.

Block 13: Significant revisions shall be submitted 60 days after completion of revisions and submittals shall continue throughout the period of performance.

Block 14: Submit via electronic mail in a digital format compatible with Adobe Acrobat Document Format (PDF) and Microsoft Office 2000 and sent to the PCO (xxx@navy.mil) and COR, QUINONES.MARTIN.1228918403

Digitally signed by

QUINONES.MARTIN.1228918403

Date: 2021.02.08 14:50:21 -05'00'

02/08/21

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

TBD A MISC

LM2500+ Gas Generator TBD TBD

Intentionally left blank

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .