This is a Contract Data Requirements List (CDRL) Form DD 1423-1 specifying a single data item requirement for contract FD20302600492. The required deliverable is a First Article Qualification Report (Data Item A001) for the T56/CONE, EXHAUST system/item, submitted under the authority of Data Acquisition Document DI-NDTI-80809B. The contractor must deliver one complete unassembled item for parts with multiple sub-assembly components as the first article submission.

The first article submission deadline is 180 days after contract award date. Draft copies must be electronically delivered via email in PDF format to three government recipients: Joshua Russell (Engineer) at 407 SCMS/GUEA, Chetaun Smith (Program Manager) at 407 SCMS/GULC, and Jimmy Hicks (PCO) at DLA/ABW. Physical first articles must be delivered to DDOO-SOP/FIRST ARTICLES at DODAAC FY2303, marked for attention to DDOO-SOP with instructions not to post as non-accountable or place in supply. The government has 45 calendar days to approve the submission. The cognizant engineering organization responsible for approval is AFLCMC/LPS DN, with Gregory Olson as the approving engineer. The requiring office is 407 SCMS GUEA. The CDRL was prepared by Tiffany L. Wright on 19 DEC 2025 and approved by Anthony D. Walswick on 18-DEC-25.

View the file

Other files

File Type Posted
DID_DI_NDTI_80809B_Test_Report.pdf PDF
Form_260_FA_Rev_002.pdf PDF
SPRTA126Q0263_SOL.pdf PDF
Form_1653_Initial.pdf PDF
Form_158_Initial.pdf PDF
IUID_Checklist.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188).

Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER X

D. SYSTEM / ITEM

T56/CONE,EXHAUST

E. CONTRACT / PR NO.

FD20302600492

F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

First Article Qualification Report

3. SUBTITLE

N/A

4. AUTHORITY

DI-NDTI-80809B

(Data Acquisition Document No.) 5. CONTRACT REFERENCE

N/A

6. REQUIRING OFFICE

407 SCMS GUEA

7. DD 250 REQ

LT

8. APP CODE

A

9. DIST STATEMENT

REQUIRED

C

10. FREQUENCY

1 XTIME

11. AS OF DATE

N/A

12. DATE OF FIRST

SUBMISSION

See block 16

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

a. ADDRESSEE

Draft Final

ReproReg

b. COPIES

14. DISTRIBUTION

16. REMARKS

Morris, Michael LNAME: 03 NOV 2025DATE:

NOTE: Changes to office symbols and/or e-mail addresses, when necessary, shall be made by letter through the Government CO/ACO without further revision to this CDRL.

Block 12: First article shall include one complete unassembled item for parts with multiple sub-assembly components.

BLOCK 9F(3): DELIVER GOVERNMENT FIRST ARTICLES TO

DDOO-SOP/FIRST ARTICLES

DODAAC:FY2303

MARK FOR: FIRST ARTICLES

Attn: DDOO-SOP

DO NOT POST, NON-ACCOUNTBALE, DO NOT PUT IN SUPPLY

DODAAC: FY2303

BLK 13: 13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING

(Name, Organization, Phone) Gregory Olson

AFLCMC / LP S D N

405-496-9279

BLK 14: BLANK

Crowley, Amanda LNAME: 10 FEB 2023DATE:

NOTE: Changes to office symbols and/or e-mail addresses, when necessary, shall be made by letter through the Government CO/ACO without further revision to this CDRL.

Block 8: The Government has 45 calendar days to approve.

Block 12: 180 Days ARO Contract Award Date

BLK 14: Electronic delivery of Draft copies via e-mail to the following Distribution Addresses shall be delivered in PDF format.

407 SCMS/GUEA

Joshua Russell, Engineer (1 each) joshua.russell@us.af.mil

407 SCMS/GULC

Chetaun Smith, Program Manager (1 each) chetaun.smith@us.af.mil

DLA/ABW

Jimmy Hicks, PCO (1 each) jimmy.hicks@us.af.mil

15. TOTAL

Page 1 of 2DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 07 Jan 2026

PREVIOUS EDITION MAY BE USED.

1615132604C Typewritten Text

1615132604C Typewritten Text See Block 16

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

COORDINATORS:

G. PREPARED BY

Wright, Tiffany L

421 SCMS / GUMFA

405-734-4967

H. DATE

19 DEC 2025

I. APPROVED BY

//ELECTRONICALLY SIGNED//

Walswick, Anthony D

421 SCMS / GUMFB 405-582-9547 / 852-9547

J. DATE

18-DEC-25

Page 2 of 2DD FORM 1423-1, FEB 2001 Version 2Generated by PRPS using Jasper Reports on 07 Jan 2026