This is a Contract Data Requirements List (CDRL) for a First Article Inspection Test Report related to a B-2 Cylinder Assembly contract. The document outlines specific requirements for a first article test report for a new manufacture of 23 cylinder assemblies (NSN 1680-01-350-2780) with a contract number FD20302401363. The report must be submitted 120 days after contract award and must provide objective evidence that all engineering, design, and specification requirements are correctly understood, verified, and recorded. The inspection report should include certifications for hardware/materials, dimensional check worksheets, calibration certifications, process job travelers, and testing results as specified in the drawing requirements. The delivery will be to the Air Force Materiel Command (AFLCMC/LZPED) at Tinker Air Force Base, with the government providing approval/disapproval within 30 days of receipt.

View the file

Other files

File Type Posted
Transportation Data.pdf PDF
CAV_AF_REPORTING_REQUIREMENTS.pdf PDF
Item_Description_Redacted.pdf PDF
DID 80809B Test Inspection Report.pdf PDF
FA8118-25-R-0058.pdf PDF
AFMC_260_First_Article_Redacted.pdf PDF
Packaging Requirements.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188).

Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER X

D. SYSTEM / ITEM

B-2 / Cylinder Assembly

E. CONTRACT / PR NO.

FD20302401363

F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

Test/Inspection Report

3. SUBTITLE

First Article Inspection Test Report

4. AUTHORITY

DI-NDTI-80809B/T

(Data Acquisition Document No.) 5. CONTRACT REFERENCE

N/A

6. REQUIRING OFFICE

AFLCMC/LZPED

7. DD 250 REQ

NO

8. APP CODE

N/A

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

1 XTIME

11. AS OF DATE

Test Day

12. DATE OF FIRST

SUBMISSION

SEE BLOCK 16

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

a. ADDRESSEE

Draft Final

ReproReg

b. COPIES

14. DISTRIBUTION

16. REMARKS

Zilar, Dale NNAME: 29 JUL 2024DATE:

NSN: 1680013502780FW

PN: DAA3297P242-121

Nomen: Cylinder Assembly Application: B-2

BLOCK 7: ALL INSPECTION AND ACCEPTANCE SHALL BE AT DESTINATION UTILIZING WAWF. A

COMBINATION OF AN INVOICE AND RECEIVING REPORT SHALL BE SUBMITTED THROUGH WAWF IN

ORDER TO RECEIVE PAYMENT FOR DATA REPORTS.

BLOCK 8: GOVERNMENT WRITTEN NOTICE OF APPROVAL/DISAPPROVAL IS DUE 30 DAYS AFTER

RECEIPT OF CONTRACTOR'S REPORT.

BLOCK 9: Distribution Statement A: Approved for public release; distribution is unlimited.

BLOCK 12: 120 DAYS AFTER CONTRACT AWARD.

SEE ATTACHED DD FORM 1664, DATA ITEM DESCRIPTION.

BLOCK 14: Deliveries shall be submitted on ISO-10149 compliant CD-ROM in Adobe Acrobat Portable Document Format.

Contractor format acceptable unless otherwise defined by applicable Data Item Description (DID).

A. THE PURPOSE OF THE FIRST ARTICLE INSPECTION IS TO GIVE OBJECTIVE EVIDENCE THAT ALL

ENGINEERING, DESIGN AND SPECIFICATION REQUIREMENTS ARE CORRECTLY UNDERSTOOD,

ACCOUNTED FOR, VERIFIED AND RECORDED.

B. SHOW COMPLETION OF INSPECTION AND RESULTS OF INSPECTION PERFORMED TO

DEMONSTRATE THAT THE FIRST ARTICLE UNIT(S) CONFORM TO THE APPLICABLE CONTRACT

TECHNICAL REQUIREMENTS.

C. REPORT SHALL DELINEATE THE SPECIFIC RESULTS OBTAINED, THE WITNESSES, AND ANY

OTHER PERTINENT OBSERVATIONS.

D. INSPECTION RESULTS SHALL BE THE APPLICABLE VARIABLE & ATTRIBUTE DATA IN THE FORM

OF RECORDINGS, INSTRUMENT READINGS AND RELATED DATA.

E. AS APPLICABLE, THE FIRST ARTICLE INSPECTION TEST REPORT SHOULD IDENTIFY ANY

DEVIATIONS OR LIMITATIONS IN THE FIRST ARTICLE UNIT(S) INVOLVED.

DELETE PARAS: 10.2.4(a), 10.2.5, 10.2.6.2, 10.2.6.3, 10.2.6.4.2(b-d), 10.2.6.5, 10.2.6.6, 10.2.7.2 & 10.2.8

AS 9102 FORMAT OR EQUIVALENT IS ACCEPTABLE.

423 SCMS/GUEA

3001 Staff Drive Tinker Air Force Base, Oklahoma 73145

0 1 0

AFLCMC/LZPED

ATTN: FA Monitor DoDAAC

FA8111

3001 Staff Drive, Suite

1AB85A

Tinker AFB, OK 73145-3041

0 1 0

0 2 015. TOTAL

Page 1 of 2DD FORM 1423-1, FEB 2001 Version 1Generated by PRPS using Jasper Reports on 25 Mar 2025

PREVIOUS EDITION MAY BE USED.

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188(1 Data Item)

REMARK APPLICABLE TO HAZARDOUS ITEMS ONLY: THE TESTS REQUIRED ARE AS

SPECIFIED IN CHAPTER 9 OF THE UNITED NATIONS TRANSPORT OF DANGEROUS GOODS (ORANGE

BOOK) RECOMMENDATIONS.

COORDINATORS:

G. PREPARED BY

Zilar, Dale N

424 SCMS / GUBAB

405-736-7976

H. DATE

29 JUL 2024

I. APPROVED BY

//ELECTRONICALLY SIGNED//

Stephens, Andrew B

423 SCMS / GUEA 405-582-5400 / 852-5400

J. DATE

29-JUL-24

Page 2 of 2DD FORM 1423-1, FEB 2001 Version 1Generated by PRPS using Jasper Reports on 25 Mar 2025