This document is a Request for Information (RFI) Response to Vendor Questions for the Cohesive Cloud Environment (C3E) project by the Secretary of the Air Force Office, Competitive Activities (SAF/OC). The RFI addresses nine vendor questions about the upcoming cloud environment contract, revealing key details about the procurement strategy. The project involves developing and sustaining cloud baselines across NIPR and JWICS networks, with current work partially completed by AWS Professional Services (ProServ). The government is considering multiple acquisition approaches, including potentially using ProServ to develop the JWICS baseline or incorporating that development into the overall C3E effort.

The RFI indicates this will be a single-award contract requiring contractors with TS/SCI eligible personnel to work in government facilities. The scope encompasses enterprise-class, multi-cloud application hosting, development, collaboration, cybersecurity, and mission data solutions. Critical requirements include supporting information at classification levels from U, S/SAR, to TS/SCI/SAR. The acquisition team is still determining specific details, such as the number of tenants or applications to be hosted, and is conducting a review of mission requirements. The contract will focus on enabling swift deployment of secure operational mission capabilities and supporting rapid threat detection and response.

View the file

Other files for this federal contract opportunity

Other files attached to C3E Request for Information, newest first.
File Type Posted
SOO_C3E_Draft_Final.pdf PDF
C3E RFI_26Mar25.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cohesive Cloud Environment (C3E)

Secretary of the Air Force Office, Competitive Activities (SAF/OC)

Concepts Development Management (CDM)

RFI Response to Vendor Questions

16 April 2025

Question CTR Question Govt Response

Is there an incumbent currently performing the same or similar work currently? If so, can a contract number be provided?

C3E is a new requirement; no incumbent or previous contract number exists. LOE 1 is a NIPR baseline developed by ProServ, an AWS entity. That effort has closed out and is now in need of sustainment (LOE 2). The acquisition strategy is considering (1) using ProServ to develop the JWICS baseline (LOE 3) or (2) not using ProServ and including LOE 3 in the overall requirements of the C3E effort (i.e. the awarded vendor for C3E will develop the JWICS baseline).

The RFI references "ProServ" having delivered a C3E NIPR baseline among other things --> Is "ProServ" a current vendor or a solution?

Reference Question 1

In light of the recent Memo on CSO / OT .. has the discussion about using SAF/CDMs CSO (FA7146-21-S-C-0001) been had as of yet or is still TBD?

Still TBD, the acquisition team is considering all options for the acquisition strategy.

Does the government have an estimate of how many tenants or applications it may host on NIPR and JWICS?

Not at this time. A review of mission requirements is being conducted.

When the government refers to “ProServ”, does this refer to AWS Professional Services?

Yes. Reference Question 1

The language of LOE 1 and LOE 3 is unclear. Will the government clarify which services described in LOE 1 currently exist, which services ProServ is expected to deliver, and which services the awardee is expected to deliver?

LOE 1 is a NIPR baseline built by ProServ and currently exists. The awardee is expected to sustain that baseline in LOE 2. As part of LOE 2, the awardee will also be responsible for any additional development to the NIPR baseline while in sustainment. LOE 3 does not exist yet. It is similar to the NIPR baseline in LOE 1, but on JWICS.

The intent is to use LOE 1 as the framework to build LOE 3. The acquisition strategy is still considering if ProServ will develop LOE 3 or if the awardee will also be responsible for the development of

LOE 3.

Question 6 reads: “The current acquisition strategy is to utilize the developer of LOE 1 for the development of LOE 3. Are there any compelling reasons for adding the development of a JWICS baseline (LOE 3) to this requirement (i.e. not just sustainment of LOE 2 and LOE 4, but also include development of LOE 3)?” Is the government asking if this should be a single or multiple award?

No. This will be a single award. The Government is trying to determine if a vendor responsible for sustainment (LOE 2 and LOE 4) could also potentially develop (LOE 3). The Government did not want to assume one vendor could do both sustainment and development and used Question 6 in the RFI to gather market research to better understand vendor capabilities.

Paragraph 2.0 says that C3E needs to include information at the "U, S/SAR, TS/SCI/SAR classification level." Will respondents require a SAP cleared facility and/or SAP eligible personnel to perform some of the work?

No, vendors do not need a SAP cleared facility or SAP cleared personnel. Contracted work is expected in Government facilities.

Contractors will need TS/SCI eligible personnel.

Is this to manage an existing AWS environment? Or are you looking for a new cloud environment?

Reference Question 1