CDBG_PRO_Housing_Milestone_Workbook_Final.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
CDBG PRO Housing: Addressing Zoning, Permitting, & Building Code Barriers to Affordable Housing
Solicitation number
GR_4261_PROHOUSING
Issued by
Dane County, Wisconsin

About this file

This is a CDBG PRO Housing Milestone Workbook instruction document for Dane County Department of Human Services, Wisconsin, which serves as a planning and policy implementation tool for municipalities addressing zoning, permitting, and building code barriers to affordable housing. The workbook requires applicants to complete required milestone tables for either Category A or Category B activities, with milestone categories including Project Setup & Readiness (10%), Studies & Technical Analysis (30%), Public & Stakeholder Process (20%), Formal Action & Adoption (25%), and Implementation & Execution (15%). Category A projects operate on a 36-month implementation timeline requiring completion of at least 60% of total milestones within 24 months and 100% within 36 months of the RFP application submission deadline of April 24, 2026. Category B projects operate on a 24-month implementation timeline requiring completion of at least 60% of total milestones within 18 months and 100% within 24 months. The proposal response deadline was April 24, 2026 at 11:59 p.m., submitted electronically through the Dane County eProcurement Portal, with awards estimated for Summer/Fall 2026. Contract effectiveness begins upon execution with pricing structured as reimbursement-based payments contingent upon achievement of specified milestones and completion of County-approved deliverables.

The workbook mandates certification by the municipality's highest-ranking official (City Mayor, Village President, or Town Chairperson) affirming that milestone information is accurate and that the project will meet specified completion thresholds. Applicants must enter project-specific milestone details including descriptions and target completion dates in designated input cells and utilize dropdown menus to indicate Y/N responses regarding milestone completion within required timeframes. Direct project delivery costs are allowable, including municipal staff time for planning and project coordination, professional services, legal services, community engagement activities, environmental reviews, and impact fees, while administrative costs cannot be billed to the contract. The procurement is exclusively restricted to municipalities within Dane County, though multiple municipalities may collaborate if communication channels and memoranda of understanding are clearly documented. No specific funding amounts are provided in the workbook; however, the broader HUD PRO Housing program provides national awards ranging from $1,000,000 to $7,000,000, with Dane County municipal allocation amounts to be determined.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

CDBG PRO Housing Milestone Workbook
Use this workbook to complete the required milestone table for either Category A or Category B activities.
Workbook Structure
This workbook includes three sheets: Instructions, Category A, and Category B.
How to Use
Complete only the category sheet that matches your application. Keep milestone categories and percentage weights unchanged.
Input Fields
Enter milestone descriptions, target completion dates, and required documentation. Use the Y/N dropdowns in the completion columns.
Category A Thresholds
Applicants must complete at least 60% of total milestones within 24 months and 100% within 36 months of the RFP application submission deadline.
Category B Thresholds
Applicants must complete at least 60% of total milestones within 18 months and 100% within 24 months of the RFP application submission deadline.
Certification
Each category sheet includes a certification block for the authorized representative to sign and date.

Category A

Required Milestone Table (Category A)
Complete all milestones in alignment with the Category A implementation-ready requirements described in the RFP.
Milestone CategoryMilestone Description% of Total MilestonesTarget Completion Date
(If already completed, add date of completion)Completed Within 24 Months
(Y/N)Completed Within 36 Months

(Y/N)

Project Setup & Readiness10%
Studies & Technical Analysis30%
Public & Stakeholder Process20%
Formal Action & Adoption25%
Implementation & Execution15%
Enter project-specific milestone details in blue input cells. Use the dropdowns to indicate whether each milestone will be completed within the required timeframe.
Implementation-ready Certification
By signing below, the applicant certifies that the information provided is true and accurate and that the project will complete at least 60% of the total milestones within 24 months and 100% of the total milestones within 36 months of the RFP application submission deadline.

Certification must be signed by the municipality’s highest-ranking official (e.g., City Mayor, Village President, or Town Chairperson).

Authorized Representative Name Title Date

Signature Date Signed

Category B

Required Milestone Table (Category B)
Complete all milestones in alignment with the Category B implementation-ready requirements described in the RFP.
Milestone CategoryMilestone Description% of Total MilestonesTarget Completion Date
(If already completed, add date of completion)Completed Within 18 Months
(Y/N)Completed Within 24 Months

(Y/N)

Project Setup & Readiness10%
Studies & Technical Analysis30%
Public & Stakeholder Process20%
Formal Action & Adoption25%
Implementation & Execution15%
Enter project-specific milestone details in blue input cells. Use the dropdowns to indicate whether each milestone will be completed within the required timeframe.
Implementation-ready Certification
By signing below, the applicant certifies that the information provided is true and accurate and that the project will complete at least 60% of the total milestones within 18 months and 100% of the total milestones within 24 months of the RFP application submission deadline.

Certification must be signed by the municipality’s highest-ranking official (e.g., City Mayor, Village President, or Town Chairperson).

Authorized Representative Name Title Date

Signature Date Signed