This is a Combined Synopsis/Solicitation for sod delivery and installation services at the Louisiana National Cemetery in Zachary, LA. The Department of Veterans Affairs (VA) National Cemetery Administration intends to award a Firm Fixed Price contract to a Service-Disabled Veteran-Owned Small Business (SDVOSB) for sod supply and installation, with a NAICS code of 561730 and a small business size standard of $9.5 million.

The solicitation covers five contract line items (CLINs) for sod delivery and installation from June 2025 to March 2030, with each CLIN covering a one-year period. The contractor will provide Tif419 bermudagrass sod, with quantities ranging from 10,000 to 12,000 square feet per year. Sod must be freshly cut, weed-free, and machine-cut to specific standards. Delivery and installation will occur within three business days of order, with work performed during normal business hours. The solicitation is a Request for Quote (RFQ) with a submission deadline of June 10, 2025 at 11:00 a.m. EST, and evaluation will be based on technical approach, past performance, and price.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMBINED SYNOPSIS/ SOLICITATION

Sod Supply and Installation Service at Louisiana National Cemetery

i. This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.

ii. Solicitation 36C78625Q50291 is issued as a Request for Quote.

iii. This solicitation document incorporates provisions and clauses of those in effect through Federal Acquisition Circular 2025-03 effective 03 January 2025.

iv. This is a Service-Disable Veteran-Owned Small Business (SDVOSB) set-aside. The associated North American Industrial Classification System (NAICS) code for this procurement is 561730 with a small business size standard of 9.5 million dollars.

v. National Cemetery Administration (NCA), Contracting Services, intents to award a

Firm Fixed Price Contract for Tree Maintenance for Baton Rouge National Cemetery with optional CLINs that can be exercised any time before the 9/30/2025.

vi. Place of performance:

Louisiana National Cemetery 303 West Mount Pleasant Road Zachary, LA 70791

vii. SOLICITATION QUESTIONS:

All solicitation questions must be submitted through email to the Contracting Officer:

david.hester@va.gov. Vendor questions must be received by 10 pm EST on Jun 3, 2025, and will be answered via solicitation amendment no later than June 6, 2025.

Questions submitted after the Q&A due date will not be answered.

viii. The following clauses and provisions are applicable to this combined synopsis/solicitation: 52.212-1, Instructions to Offerors; 52.212-3 Offeror Representations and Certifications—Commercial Items; 52.212-4 Contract Terms and Conditions—Commercial Items; 52-212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Items.

a. The FAR may be obtained at: Home | Acquisition.GOV

ix. The Government intends to evaluate offers and award without discussion but reserves the right to conduct discussions. Therefore, the offeror’s initial offer should contain the offeror’s best terms from a price and technical standpoint. However, the Government reserves the right to conduct discussions if later determined by the Contracting Officer to be necessary. Offers that fail to furnish required representations or information or reject the terms and conditions of the solicitation may be excluded from consideration.

https://www.acquisition.gov/

COMBINED SYNOPSIS/ SOLICITATION

Sod Supply and Installation Service at Louisiana National Cemetery

The right to make multiple or no award is reserved in the event it is advantageous to the Government to do so.

x. Submission Due: 6/10/2025 at 11:00 a.m. EST

xi. Point of Contacts:

a. David Hester, david.hester@va.gov

xii. It is the responsibility of the offeror to review the posting for any changes or amendments that may occur concerning this RFQ. It is the responsibility of the offeror to ensure all proposals and/or questions are submitted in a timely manner by specified due date.

xiii. Mandatory Registrations. To be eligible for award, registration with the System for Award Management (SAM). If this requirement is a SDVOSB set aside, the Offeror shall have an active and current registration in VetCert, at the time of submission and will maintain its status throughout the performance of the contract.

xiv. Notice to Offeror. The Government reserves the right to cancel this RFQ, either before or after suspense date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs. The contractor shall not request, nor will the Government make, payments for any preliminary measurement, quotes, bids, site visit, time or proposal cost incurred.

mailto:david.hester@va.gov https://sam.gov/content/home https://sam.gov/content/home https://veterans.certify.sba.gov/

Document Number: 36C78625Q50291 PROCESSED Page 3 of 51

Table of Contents

Section Description Page Number

1 Continuation Sheet 1 Statement of Work 1 Evaluation Factors 2 Contract Clauses

52.252-2 Clauses Incorporated by Reference (Feb 1998) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.237-3 Continuity of Services (Jan 1991) 52.212-4 Contract Terms and Conditions-Commercial Products and Commercial Services (Nov 2023) 52.212-5 (DEV) Contract Terms and Conditions Required To Implement Statutes or Executive Orders- Commercial Products and Commercial Services (JAN 2025) (DEVIATION FEB 2025) 52.216-22 Indefinite Quantity (Oct 1995) 52.217-8 Option to Extend Services (Nov 1999) 52.217-9 Option to Extend the Term of the Contract (Mar 2000) 52.232-19 Availability of Funds for the Next Fiscal Year (Apr 1984)

852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY

2020)

852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR VERIFIED SERVICE-DISABLED

VETERAN-OWNED SMALL BUSINESSES (NOV 2022)

852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)

852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)

3 Documents, Exhibits, or Attachments 4 Solicitation Provisions

52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) 52.204-7 System for Award Management (Nov 2024) 52.212-1 Instructions to Offerors-Commercial Products and Commercial Services (Sep 2023) 52.212-2 Evaluation-Commercial Products and Commercial Services (Nov 2021) 52.212-3 Offeror Representations and Certifications-Commercial Products and Commercial Services (May 2024)

852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

EOD Wage Determination 2015-5177

Document Number: 36C78625Q50291 PROCESSED Page 4 of 51

Section 1 - Continuation Sheet

Number Supplies or Services Max. Qty Unit Unit Price Total (Inc. disc., tax, and fees)

0001 See Description Below

PSC: S208

LANDSCAPING/

GROUNDSKEEPING

SERVICES

10,000.000000 S3

Description: SOD DELIVERY AND INSTALLATION

Period of Performance: 06/30/2025 - 03/31/2026

Reference Line: F367004-25-2000006 - 0001

Pricing Options: Base 0001

Number Supplies or Services Max. Qty Unit Unit Price Total (Inc. disc., tax, and fees)

0002 See Description Below

PSC: S208

LANDSCAPING/

GROUNDSKEEPING

SERVICES

12,000.000000 S3

Description: SOD DELIVERY AND INSTALLATION

Period of Performance: 04/01/2026 - 03/31/2027

Reference Line: F367004-25-2000006 - 1001

Pricing Options: 0001

Number Supplies or Services Max. Qty Unit Unit Price Total (Inc. disc., tax, and fees)

0003 See Description Below

PSC: S208

LANDSCAPING/

GROUNDSKEEPING

SERVICES

12,000.000000 S3

Description: SOD DELIVERY AND INSTALLATION

Period of Performance: 04/01/2027 - 03/31/2028

Reference Line: F367004-25-2000006 - 2001

Pricing Options: 0001

Document Number: 36C78625Q50291 PROCESSED Page 5 of 51

Number Supplies or Services Max. Qty Unit Unit Price Total (Inc. disc., tax, and fees)

0004 See Description Below

PSC: S208

LANDSCAPING/

GROUNDSKEEPING

SERVICES

12,000.000000 S3

Description: SOD DELIVERY AND INSTALLATION

Period of Performance: 04/01/2028 - 03/31/2029

Reference Line: F367004-25-2000006 - 3001

Pricing Options: 0001

Number Supplies or Services Max. Qty Unit Unit Price Total (Inc. disc., tax, and fees)

0005 See Description Below

PSC: S208

LANDSCAPING/

GROUNDSKEEPING

SERVICES

12,000.000000 S3

Description: SOD DELIVERY AND INSTALLATION

Period of Performance: 04/01/2029 - 03/31/2030

Reference Line: F367004-25-2000006 - 4001

Pricing Options: 0001

Document Number: 36C78625Q50291 PROCESSED Page 6 of 51

SCOPE OF WORK

National Cemetery Administration

Louisiana National Cemetery

Sod Delivery and Installation

A. GENERAL INFORMATION

The Department of Veteran Affairs, National Cemetery Administration intends to award an IDIQ contract for the procurement of tree maintenance services at Louisiana National Cemetery and hereafter referred to as “Cemetery”. The Contractor shall provide all necessary expertise, supervision, labor, equipment, and supplies to accomplish the delivery and placement of Tif419 bermudagrass at the Cemetery.

1. Location:

These services will be performed at the following location:

Louisiana National Cemetery

303 West Mount Pleasant Road

2. Order Procedures

The grass sod shall be delivered and installed within three (3) business days of order from the

COR. The COR will be responsible for requesting delivery of the material from the vendor. All requests will be made via email and follow up phone call to verify request with the vendor (the contracting office will be copied on all emails). The request will be placed in time for the vendor to meet the delivery timeframe outlined above.

Note: The email will contain a minimum of vendor name, contract number, cemetery name, address, and phone number of POC. Request the delivery of [specify CLIN and pallets] and estimated delivery date.

3. Work Hours

All work shall be performed during the normal working hours (8:00 a.m. to 4:00 p.m.), Monday through Friday. No work will be allowed to be performed on weekends and official government

Holidays, without advance written consent of the COR. All work shall be scheduled and coordinated with the COR.

4. Submittals

The contractor shall submit the following documents or information in accordance with the table

A.1 to the COR.

For the sod, the sod provider’s specification sheet shall be submitted prior to each delivery. The information shall contain the company name, company address, and sod type (Tif 419

Bermudagrass).

A delivery ticket shall be provided with each delivery.

Table A.1. Louisiana National Cemetery submittals for sod delivery and installation.

Submittal Frequency Submittal Schedule

Sod provider and information sheet Initial and as revised Prior to beginning work

Sod delivery tickets and certification As needed Upon delivery

Document Number: 36C78625Q50291 PROCESSED Page 7 of 51

B. SOD DELIVERY AND INSTALLATION

1. CLIN 001 Sod Installation and Delivery – per COR instructions

Grass sod shall be ordered, delivered, and installed within the cemetery as directed by the COR.

Orders will occur approximately once a month during the active growing season. Installation may be on first interment, second interment, or other non-burial sites as directed by the COR. Burial sections may include full casket crypt, full casket traditional, or cremation sections; and gravesites may be scattered throughout the cemetery.

The amount of grass sod to be delivered may vary depending on the interment rate but will be approximately 1,350 square feet (3 pallets) per order as directed by the COR. For each placed order, the US Government guarantees a minimum order of 900 square feet (2 pallets). The maximum amount of sod ordered under each task order shall not exceed 2,250 square feet (5 pallets).

C. SOD SPECIFICATIONS

1. Tif 419 Bermudagrass

Grass sod shall be certified Tif 419 bermudagrass. If the Contractor is unable to source Tif 419 bermudagrass, certified TifTuf bermudagrass may be substituted with COR approval.

2. Sod Quality

The sod will be delivered freshly cut, weed, disease, and insect free, and of healthy appearance with uniform color, leaf texture, and shoot density. Grass sod shall be relatively free of thatch, less than

0.5 inch (uncompressed). Grass sod shall be machine cut at a uniform soil thickness of 0.60 inch, plus or minus .25 inch, at the time of cutting. Measurement for thickness shall exclude top growth and any thatch. Irregular sized pads, broken pads, and torn or uneven ends will not be acceptable.

Standard sized sections of grass sod shall be strong enough that it can be picked up and handled without damage. Grass sod shall not be harvested or transplanted when its moisture content

(excessively dry or wet) may adversely affect its survival.

D. SOD INSTALLATION

1. Location

Grass sod shall be installed per COR’s instructions at locations within the cemetery specified in writing by COR.

2. Timeline

Grass sod shall be harvested, delivered, and installed within a 24-hour period, unless a suitable preservation method is approved prior to delivery.

3. Installation Specifications

Grass sod shall be installed to match existing grade of turf (cemetery responsible for correct soil preparation and finish grade). All joints shall be butted tightly. Lateral joints shall be staggered to promote more uniform growth and strength. Care shall be exercised to ensure that sod pieces are not stretched or overlapped. Installed grass sod shall be properly rolled with sod roller to correct firmness.

Document Number: 36C78625Q50291 PROCESSED Page 8 of 51

4. Inspection

Once grass sod is installed, contractor shall notify COR for inspection and acceptance of work, prior to submitting invoice(s). Contractor is responsible for replacing any grass sod delivered and installed that does not meet the requirements stated in this scope of work within two (2) weeks after planting.

E. CONTRACTOR EQUIPMENT, PERSONNEL, AND CONTRACTOR RESPONSIBILITIES

1. Damage

Contractor shall not damage any property within the cemetery grounds. Any damage incurred by contractor shall be repaired or replaced at contractor expense with no additional charge to the government. This damage includes, but not is not limited to, rutting of grounds caused by contractor equipment, headstone and marker damage, and any other damage to cemetery property and grounds caused by contractor.

2. Heavy Equipment

Contractor shall not use any heavy equipment (i.e. back hoes, forklifts, dump trucks, etc.) within burial sections. Contractor will be allowed to use light duty motorized utility carts for the transport of grass sod and tools, as needed, and at contractor expense.

3. Site Cleanup

Contractor shall clean up and/or pick up any trash, debris, dirt, mud, tire marks or any other related items upon completion of work in that area on any given workday.

4. Storage

Contractor shall not store any materials, tools, or equipment overnight on the cemetery grounds.

5. Contractor Foreman / Work Leader

Contractor shall provide an English-speaking Foreman or Work Leader for this contract.

F. CEMETERY RESPONSIBILITIES

1. Damage

The cemetery is responsible for grass sod damaged by cemetery personnel, third parties, storms, flood, frost, freeze, animals on cemetery grounds, or related.

2. Maintenance

The cemetery is responsible for the required maintenance (including watering) of the grass sod once it is delivered, correctly installed, and accepted.

End of Scope of Work

Document Number: 36C78625Q50291 PROCESSED Page 9 of 51

Source Selection Plan / Evaluation Factors

Louisiana National Cemetery – Sod

I. BACKGROUND

A. Purpose. The purpose of this Source Selection Plan is to set forth the process by which the NCA

Contracting Office will evaluate offers received in response to solicitation for Sod Installation and Delivery at Louisiana National Cemetery.

B. Source selection approach. This plan covers the approach for soliciting and evaluating offers, provides the source selection organizational structure, and designates persons who will perform the evaluation.

II. BASIS OF AWARD: This procurement is being conducted pursuant to FAR Part 13 procedures.

The Government intends to award a contract resulting from this solicitation to the responsible offeror who offers the lowest price, whose quoted price is found to be reasonable, and whose quote is found to be technically acceptable when considering the non-price evaluation factors described below. Offerors who fail to meet any technical acceptability evaluation factors below will not be eligible to receive contract award.

III. EVALUTION FACTORS

1) Factor 1: Technical Approach and Understanding of the Work: Proposal shall be evaluated in accordance with the criteria contained in the Statement of Work and on how well the technical approach meets the Government requirements. The proposal shall be more than restating the SOW.

Technical approach will be evaluated for the following:

a) Contractor-provided statements and/or literature that clearly explains their experience, approach and/or abilities to perform the tasks described in the Statement of Work (SOW).

b) Sod specification sheet for proposed Tif 419 bermudgrass to be provided.

c) Example of delivery ticket for sod delivery orders.

2) Factor 2: Past Performances: Past performance shall be evaluated based on the Contractor’s technical qualifications on projects within the last 5 years that are comparable in size, complexity, and scope. Past Performance information shall be obtained by the following methods.

a) The Contracting Officer’s knowledge of previous experience with the supply or service being acquired.

b) Contractor’s past performance descriptions of a minimum of 3 recent (within the last 5 years) projects of similar size and scope

c) The Contractor Performance Assessment Reporting System (CPARS) at https://www.cpars.gov

d) Any other reasonable basis.

3) Factor 3: Price: Proposed price will be evaluated for LPTA and accuracy in the provided CLIN structure.

Document Number: 36C78625Q50291 PROCESSED Page 10 of 51

Section 2 - Contract Clauses

52.252-2 Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/ these address(es):

www.acquisition.gov/browse/index/far (FAR) www.va.gov/oal/library/vaar/index.asp (VAAR) [Insert one or more Internet addresses]

(End of clause) Clause Title Fill-ins

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

52.204-13 System for Award Management Maintenance (Oct 2018)

52.237-3 Continuity of Services (Jan 1991)

52.212-4 Contract Terms and Conditions-Commercial Products and Commercial Services (Nov 2023)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights--

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

Document Number: 36C78625Q50291 PROCESSED Page 11 of 51

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include--

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer--System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer--Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.--

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall--

Document Number: 36C78625Q50291 PROCESSED Page 12 of 51

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the--

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109 , which is applicable to the period in which the amount becomes due, as provided in (i)(6)

(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if--

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on--

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

Document Number: 36C78625Q50291 PROCESSED Page 13 of 51

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) [Reserved]

(u) Unauthorized Obligations

Document Number: 36C78625Q50291 PROCESSED Page 14 of 51

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of clause)

52.212-5 (DEV) Contract Terms and Conditions Required To Implement Statutes or Executive Orders-Commercial Products and Commercial Services (JAN 2025) (DEVIATION FEB 2025)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).

(6) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(7) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004)(Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Jun 2020), with Alternate I (Nov 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).

__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C. 3509).

Document Number: 36C78625Q50291 PROCESSED Page 15 of 51

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

X (4) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) (41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community--see FAR 3.900(a).

X (5) 52.204-10, Reporting Executive Compensation and 3-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) (31 U.S.C. 6101 note).

__ (6) [Reserved].

__ (7) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (8) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

X (9) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of Division R of Pub. L. 117-328).

__ (10) 52.204-28, Federal Acquisition Supply Chain Security Act Orders-Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts. (Dec 2023) (Pub. L. 115-390, title II).

__ (11)(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition. (Dec 2023) (Pub. L. 115-390, title II).

__ (ii) Alternate I (Dec 2023) of 52.204-30.

__ (12) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025) (31 U.S.C. 6101 note).

__ (13) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) (41 U.S.C. 2313).

__ (14) [Reserved].

__ (15) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Oct 2022) (15 U.S.C. 657a).

__ (16) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

__ (17) [Reserved]

__ (18)(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-6.

__ (19)(i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-7.

__ (20) 52.219-8, Utilization of Small Business Concerns (Jan 2025) (15 U.S.C. 637(d)(2) and (3)).

__ (21)(i) 52.219-9, Small Business Subcontracting Plan (Jan 2025) (15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (Nov 2016) of 52.219-9.

__ (iii) Alternate II (Nov 2016) of 52.219-9.

__ (iv) Alternate III (Jun 2020) of 52.219-9.

__ (v) Alternate IV (Jan 2025) of 52.219-9.

X (22)(i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

Document Number: 36C78625Q50291 PROCESSED Page 16 of 51

__ (ii) Alternate I (Mar 2020) of 52.219-13.

__ (23) 52.219-14, Limitations on Subcontracting (Oct 2022) (15 U.S.C. 657s).

__ (24) 52.219-16, Liquidated Damages-Subcontracting Plan (Sep 2021) (15 U.S.C. 637(d)(4)(F)(i)).

X (25) 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (Feb 2024) (15 U.S.C. 657f).

X (26)(i) 52.219-28, Postaward Small Business Program Rerepresentation (Jan 2025) (15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (Mar 2020) of 52.219-28.

__ (27) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Oct 2022) (15 U.S.C. 637(m)).

__ (28) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Oct 2022) (15 U.S.C. 637(m)).

__ (29) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar 2020) (15 U.S.C. 644(r)).

__ (30) 52.219-33, Nonmanufacturer Rule (Sep 2021) (15 U.S.C. 637(a)(17)).

X (31) 52.222-3, Convict Labor (Jun 2003) (E.O. 11755).

__ (32) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (Jan 2025) (E.O. 13126).

__ (33) [Reserved].

__ (34) [Reserved].

__ (35)(i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).

__ (ii) Alternate I (Jul 2014) of 52.222-35.

__ (36)(i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C. 793).

__ (ii) Alternate I (Jul 2014) of 52.222-36.

__ (37) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C. 4212).

__ (38) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

X (39)(i) 52.222-50, Combating Trafficking in Persons (Nov 2021) (22 U.S.C. chapter 78 and E.O. 13627).

__ (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

__ (40) 52.222-54, Employment Eligibility Verification (Jan 2025) (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)

__ (41)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) (42 U.S.C. 6962(c) (3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (42) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (May 2024) (42 U.S.C.

7671, et seq.).

Document Number: 36C78625Q50291 PROCESSED Page 17 of 51

__ (43) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (May 2024) (42 U.S.C. 7671, et seq.).

__ (44) 52.223-20, Aerosols (May 2024) (42 U.S.C. 7671, et seq.).

__ (45) 52.223-21, Foams (May 2024) (42 U.S.C. 7671, et seq.).

__ (46) 52.223-23, Sustainable Products and Services (May 2024) (DEVIATION FEB 2025) (7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l).

__ (47)(i) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552a).

__ (ii) Alternate I (Jan 2017) of 52.224-3.

__ (48)(i) 52.225-1, Buy American--Supplies (Oct 2022) (41 U.S.C. chapter 83).

__ (ii) Alternate I (Oct 2022) of 52.225-1.

__ (49)(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (Nov 2023) (19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C. chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.

__ (ii) Alternate I [Reserved].

__ (iii) Alternate II (Jan 2025) of 52.225-3.

__ (iv) Alternate III (Feb 2024) of 52.225-3.

__ (v) Alternate IV (Oct 2022) of 52.225-3.

__ (50) 52.225-5, Trade Agreements (Nov 2023) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

X (51) 52.225-13, Restrictions on Certain Foreign Purchases (Feb 2021) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

__ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

__ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).

__ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).

__ (55) 52.226-8, Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) (E.O. 13513).

__ (56) 52.229-12, Tax on Certain Foreign Procurements (Feb 2021).

__ (57) 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services (Nov 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

__ (58) 52.232-30, Installment Payments for Commercial Products and Commercial Services (Nov 2021) (41 U.S.C. 4505, 10 U.S.C.

3805).

X (59) 52.232-33, Payment by Electronic Funds Transfer--System for Award Management (Oct 2018) (31 U.S.C. 3332).

__ (60) 52.232-34, Payment by Electronic Funds Transfer--Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).

__ (61) 52.232-36, Payment by 3 Party (May 2014) (31 U.S.C. 3332).

__ (62) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).

Document Number: 36C78625Q50291 PROCESSED Page 18 of 51

__ (63) 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024) (Sections 1821-1826, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).

__ (64) 52.242-5, Payments to Small Business Subcontractors (Jan 2017)(15 U.S.C. 637(d)(13)).

__ (65)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2021) (46 U.S.C. 55305 and 10 U.S.C.

2631).

__ (ii) Alternate I (Apr 2003) of 52.247-64.

__ (iii) Alternate II (Nov 2021) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

__ (1) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter 67).

__ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) (Aug 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards--Price Adjustment (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (May 2014) (41 U.S.C. chapter 67).

__ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-- Requirements (May 2014) (41 U.S.C. chapter 67).

__ (7) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan 2022).

X (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2022) (E.O. 13706).

X (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020) (42 U.S.C. 1792).

__ (10) 52.247-69, Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to Prevent Human Trafficking (Jan 2025) (49 U.S.C. 40118(g)).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, as defined in FAR 2.101, on the date of award of this contract and does not contain the clause at 52.215-2, Audit and Records--Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor's directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

Document Number: 36C78625Q50291 PROCESSED Page 19 of 51

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e)(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c), and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1) in a subcontract for commercial products or commercial services. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause--

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C. 3509).

(ii) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) (41 U.S.C. 4712).

(iii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(iv) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(v) 52.204–25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(vi) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of Division R of Pub. L. 117-328).

(vii)(A) 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition. (Dec 2023) (Pub. L. 115-390, title II).

(B) Alternate I (Dec 2023) of 52.204-30.

(viii) 52.219-8, Utilization of Small Business Concerns (Jan 2025) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds the applicable threshold specified in FAR 19.702(a) on the date of subcontract award, the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(ix) [Reserved].

(x) [Reserved].

(xi) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).

(xii) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C. 793).

(xiii) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C. 4212)

(xiv) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(xv) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter 67).

(xvi) (A) 52.222-50, Combating Trafficking in Persons (Nov 2021) (22 U.S.C.

This is the start of the file's text. The full file is on GovTribe.