CCENV19005 - LOCOMOTIVE RFI
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2019.01.29_RFI_-CCENV19005_Locomotives_KBM_rev-1_02028019.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CCENV19005 - LOCOMOTIVES
WASHINGTON
METROPOLITAN AREA
TRANSIT AUTHORITY
(WMATA)
REQUEST FOR INFORMATION (RFI)
CCENV19005 - LOCOMOTIVE
DUE DATE: March 01, 2019 AT 2:00 P.M. EST
DISCLAIMER:
This is not a solicitation. This is not a Request for Quote (RFQ), Invitation for Bid (IFB), Request for Proposal (RFP), or an announcement of a solicitation and does not assume Washington Metropolitan Area Transit Authority (WMATA) will award a contract or proceed with any of the above solicitations. The information requested herein is for information purposes and does not constitute a commitment, implied or otherwise, that a procurement action will be issued or awarded.
SYNOPSIS: REQUEST FOR INFORMATION (RFI)
Vendor’s response to this RFI is not an offer. This Request for Information does not commit WMATA to any incurred costs in preparation of any submissions to this notice, or to contract for services and it is issued for WMATA Market Research purposes only. No cost(s) associated with your response shall be charged to WMATA for any reason. This document shall not be construed as a request or authorization to perform work at WMATA’s expense. Any work performed by a vendor will be at the vendor’s own discretion and expense. This RFI does not represent a commitment to purchase nor does it obligate WMATA in any manner. Submission of a response constitutes an acknowledgement that the vendor has read and agrees to be bound by such terms.
WMATA may submit a formal Request for Proposal (RFP) for the services described in this document. There is no guarantee that WMATA will publish an RFP. If published, the RFP will be sent to vendors that demonstrate adequate capabilities in response to this RFI. The information contained in this RFI is provided based upon the information gathered and/or known now. There are no guarantees as to the accuracy of this information.
Participation in this RFI is voluntary and WMATA will not pay for the preparation of any information submitted by a respondent or for WMATA’s use of that information.
This RFI is issued to conduct market research and information gathering for the manufacture and delivery of six (6) locomotives to be utilized throughout the WMATA Rail System for the Washington Metropolitan Area Transit Authority (WMATA) and to solicit information that will enable WMATA to determine industry participation in response to the release of a possible future solicitation and as a means of technical discovery and information gathering. This RFI is for planning purposes only and should not be construed as a solicitation nor should it be construed as an obligation on the part of the WMATA to make any purchases. WMATA may utilize the results of this RFI in revising a specification that will allow for development of a competitive solicitation
(RFP) for the subject services/products/equipment. Any future contract that may be awarded must comply with WMATA’s procurement requirements.
Based on the information provided by the respondents to this RFI, a determination will be made regarding any actual contracting through a procurement process at WMATA’s discretion.
Submission of Responses
Ensure that all requests for information in this document are answered as concisely as possible. Any deviations from requirements, or requirements that cannot be satisfied by the vendor, must be clearly identified. Points to follow during the generation of responses to this RFI include the following:
1. Interested offerors shall provide a capability statement of their experience in successfully providing similar solutions to other transit agencies or railroads.
2. Responses must include a statement indicating that the vendor understands the requirements of the RFI. The original response must be signed under the corporate seal by an authorized officer. The original and all copies, including all supplementary literature, must be forwarded to the WMATA point of contact identified in this section of the RFI instructions.
3. Any information of a confidential or proprietary nature contained in a vendor response should be clearly marked ‘PROPRIETARY’ or ‘CONFIDENTIAL’ next to the item or at the top of each respective page.
4. If an answer is best presented as an attachment, the required document may be provided as an attachment.
Please forward the above information along with your company’s name, address, point of contact, telephone number, and e-mail address no later than March 1, 2019 to the Primary Contact Person:
Robert Jones, Procurement, Washington Metropolitan Area Transit Authority. For questions please email rjones5@wmata.com or call 301-955-5492.
All responses, once delivered, becomes the property of WMATA.
Information submitted will be reviewed by WMATA’s Office of Vehicle Program Services staff, Department of Transit Infrastructure and Engineering Services. WMATA may meet with individual offerors to discuss and review the information provided. If WMATA decides to proceed with procurement of the services or products offered, a formal solicitation will be issued.
Below are our current Scope of Work and Technical Specifications. Please review and provide comments.
AGENCY OVERVIEW
The Washington Metropolitan Area Transit Authority (WMATA or Metro) is the transit provider for the National Capital Region, providing safe, clean, and reliable service to both residents and visitors. Our customers include more than a third of the federal government workforce and millions of tourists who visit the Nation’s Capital every year. Metro operates the second largest heavy rail transit system, sixth largest bus network, and fifth largest para-transit service in the United States.
PROJECT OVERVIEW
WMATA is looking for potential suppliers who are willing to provide six locomotives that will be used to transport track maintenance cars. The primary traction power will be provided by a diesel engine and AC traction motors with each of the four axles powered.
INTRODUCTION:
The Washington Metropolitan Area Transit Authority (WMATA) is seeking feedback from suppliers, vendors, and manufacturers to determine if a commercially available product can meet our needs or if a component design and specifications may be provided for six locomotives.
Background
WMATA is seeking information on locomotives for use in transporting track maintenance cars.
The locomotives must be capable of negotiating all of WMATA’s rail system including tracks, tunnels, and structures while pulling consists of up to 200 tons for a single locomotive and up to 500 tons with three locomotives in distributed power, multiple-unit configurations.
The locomotive must have the ability to operate throughout the entire WMATA system which includes above and below-ground yard tracks, below-ground tunnels with tight clearances and 3rd rail power, above-ground dedicated right of way with 3rd rail power, and aerial structures.
Scope of Work
The following sections describe the functional and technical considerations that WMATA seeks in new locomotives. They are presented as high-level business needs and as questions or statements for soliciting information.
The Technical Specification (attached) establishes and controls both the specific and general design parameters for the procurement of locomotives.
The locomotives will be a self-propelled, diesel-electric powered rail vehicle with an enclosed cab and all equipment necessary to pull work cars. The locomotives will have AC propulsion with individually driven axles. They must be capable of multiple unit (MU) operation with up to three locomotives distributed anywhere in a work car consist. The locomotives will be designed to have a useful life of 30 years. The locomotives must achieve high reliability, have high tractive effort and the ability to operate without restriction underground.
The scope includes the delivery of as-built drawings, an as-built specification, user manuals, maintenance manuals, any special tools, test equipment, spare parts, and training for WMATA operations and maintenance personnel.
Technical Specifications
Due to its size and detail, the technical specification for the vehicle, associated equipment, and deliverables is attached to this Scope of Work as Attachment “A” with related drawings and additional addendums described herein. All requirements in the Technical Specification must be met. Any alternate designs, deviations, or exemptions must be requested by the vendor in writing to WMATA for review and approval.
Alternative Propulsion Options:
For this RFI, WMATA is also evaluating locomotive propulsion options as alternatives to diesel-only based propulsion systems. WMATA intends to evaluate the availability of zero-emissions technology and whether that technology is appropriate for serious consideration during the upcoming locomotive procurement process.
To support this evaluation, it is requested that the Contractor provides information to WMATA regarding the different zero-emissions propulsion systems available for the base platform that the Contractor recommended for the operations described in the Technical Specification.
Addendum A to the Technical Specification, Inquiry – Alternative Propulsion Options for the Locomotive, is provided within this RFI package for the Contractor’s evaluation and comments. Please review the noted addendum and provide the information requested therein as part of this RFI inquiry.
Automatic Train Control (ATC):
In addition to available alternative propulsion options, WMATA is also seeking feedback from Contractors regarding an automatic train control (ATC) system for the locomotive described in the Technical Specification. For this portion of the RFI, WMATA intends to evaluate the availability of ATC system technology and whether that technology is feasible for the rolling stock being purchased during the upcoming locomotive procurement process.
Addendum B to the Technical Specification, Inquiry – Automatic Train Control (ATC) System for the Locomotive, is provided within this RFI package for the Contractor’s evaluation and comments regarding available ATC systems and any issues associated with placing such a system on the locomotive of interest. Please review the noted addendum and provide the information requested as part of this RFI inquiry.
Questions for Potential Contractors WMATA requests that potential contractors provide responses to the following questions in addition to commenting on the provided scope of work:
1. What impact does WMATA’s small tunnel clearance have on the locomotive design configuration offered by the Contractor?
2. What is the expected maximum personnel capacity in the locomotive cab?
3. What is the expected noise decibel level from the locomotive (exterior, Interior @ full power?)?
4. Can an FRA compliant event recorder be integrated? Which signals beyond the FRA requirement can be recorded?
5. Can a three-locomotive consist achieve the desired tractive effort illustrated on the Locomotive Speed Curve found in the Technical Specification? Limitations for the required performance target?
6. WMATA prefers the driveline described in Section 10 as a minimum. What is the impact in case of a truck or locomotive level failure?
7. What are the expected maintenance intervals of the major components?
8. What is the expected service availability for the locomotives on a monthly/yearly basis and how many service days are required annually?
9. What impact does WMATA’s small tunnel clearance have on the locomotive cooling design configuration?
10. Can you provide fully integrated locomotive level maintenance manuals (not just collection of supplier manuals)? Estimate the cost of providing this as a percentage of the equipment cost.
11. What is the diagnostic interface for maintenance personnel?
12. What are the capabilities for diagnostics, troubleshooting, etc.?
13. Does the locomotive provide any predictive maintenance indications/information?
14. How long after contract award could a final design be completed?
15. How long after contract award can production start?
16. What is the total production time for the three-locomotive MU set described in the 12-piece work train described in the Technical Specification?
17. Delivery method after production is complete?
18. Based on the information provided in this RFI package, would your firm respond to a RFP (if published) for all listed services? If the answer to question is ‘yes’, please provide the name, title, address, telephone, and e-mail for the primary contact for receiving an RFP.
APPENDIX A: Template for RFI Responses
Please use the template below to provide comments, questions, or additional information relevant to sections within the Technical Specification. Please identify the Technical Specification Section in the left-hand column below, e.g.C.3.3. Please feel free to provide additional comments that be will be helpful to WMATA.
Technical Specification Section
Comments, Questions, or Additional information
Rights and Obligations of WMATA
WMATA reserves all rights (which rights shall be exercisable by WMATA in its sole discretion) available to it under applicable law, including without limitation, the following, with or without cause and with or without notice:
The right to cancel, withdraw, postpone or extend the RFI in whole or in part at any time, without incurring any obligations or liabilities;
The right to issue a new RFI;
The right to reject any submittals and responses received at any time;
The right to modify all dates set or projected in this RFI;
The right to terminate evaluations of responses received at any time;
The right to suspend and terminate this RFI at any time;
The right to waive or permit corrections to data submitted with any response to this RFI;
The right to issue addenda, supplements, and modifications to this RFI;
The right to permit the submittal of addenda and supplements to data previously provided with any response to this RFI;
The right to hold meetings, conduct discussions and draft correspondence with one or more of the Respondents responding to this RFI to seek an improved understanding of the responses to the RFI.
The information and responses received in response to this RFI may be shared with others.
CONFIDENTIALITY & RFI OWNERSHIP
All responses to the RFI will become the property of WMATA and will not be returned.
WMATA shall not be liable for or suffer any consequential damages for any identified proprietary information. Properly identified proprietary information will be safeguarded in accordance with WMATA regulations. The purpose of this announcement is solely to gather information from the market place and any responses received will not be considered an offer by the responding party and cannot be returned.
No requests for solicitation packages will be granted, as no solicitation has been prepared.
This page is intentionally blank.
Attachment A:
Locomotive
WMATA
Vehicle Program Services (CENV)
Car Track Equipment Maintenance (CTEM) Technical Specification - Sections 1-16, Version 0.2
Sections 17-20, Version 0.1 February 1, 2019
Technical Specifications – Locomotive 3
Table of Contents
Section Title
1 SCOPE OF SPECIFICATION
2 SYSTEM DESIGN
3 LOCOMOTIVE CONSTRUCTION AND ASSEMBLY
4 TRUCKS AND SUSPENSION
5 COUPLER EQUIPMENT
6 CAB AND CAB CONTROLS
7 CONSIST MANAGEMENT CONTROLS
8 MONITORING AND DIAGNOSTIC SYSTEM
9 AUXILIARY ELECTRICAL EQUIPMENT
10 PROPULSION
11 AIR BRAKE SYSTEM
12 HEATING, VENTILATION, AND AIR CONDITIONING
13 COMMUNICATIONS
14 LIGHTING SYSTEM
15 WORKMANSHIP, PROCESSES AND MATERIALS
16 SOFTWARE SYSTEMS
17 COMPLIANCE PROGRAM
18 SYSTEM ASSURANCE
19 CONTRACT MANAGEMENT
20 IN-SERVICE SUPPORT
Scope of Specification – 1
Technical Specification – Locomotive – V-0.2 1
Locomotive Technical Specification
Scope of Specification
1 – Scope of Specification
2 V-0.2 – Locomotive – Technical Specification
Technical Specification – Locomotive – V-0.2 3
Scope of Specification - 1 Table of Contents
Section/Sub-section Title Page
1 SCOPE OF SPECIFICATION
1.1 GENERAL
1.2 PROJECT SCOPE
1.3 DELIVERY TO WMATA FACILITIES
1.4 SECURITY
1.5 DEFINITIONS AND ABBREVIATIONS
1.6 DELIVERABLES
4 V-0.2 – Locomotive – Technical Specification
Technical Specification – Locomotive – V-0.2 5
1 SCOPE OF SPECIFICATION
1.1 GENERAL
1) This Technical Specification establishes and controls both the specific and general design parameters for the procurement of Locomotives used primarily for track maintenance on WMATA’s track system.
2) The intent of this specification is to provide basic and specific guidelines and requirements for a competent, experienced Contractor to design, manufacture, test, furnish, and deliver the vehicle described herein. Also, the Contractor must provide adequate documentation and training for WMATA to maintain the equipment. WMATA encourages Contractors to propose service proven designs that meet, exceed, or provide a similar and comparable feature to the requirements of this specification.
3) This Specification is generally complete and comprehensive but is not intended to describe all work details to be performed and therefore must be supplemented by the Contractor's experience in building heavy rail locomotives, on its examination of the WMATA system, and on its detailed design, manufacturing and testing capabilities.
4) The specific and general design parameters outlined within this specification shall be met unless deviations thereof are specifically noted or approved by
WMATA.
5) The term “Locomotive” will be used in this document to identify the vehicle.
It is not intended to limit the Contractor to a particular type of vehicle configuration.
1.2 PROJECT SCOPE
1.2.1 General
1) The Contractor shall design, manufacture, test, furnish, and deliver the dedicated rail Locomotive with all accessories and appurtenances as described by this specification and approved by WMATA.
2) The Contractor shall be responsible for the design and integration of all vehicle systems such that all specified requirements are achieved without conflict or error within or between systems. The Contractor shall ensure that all designers, suppliers, and subcontractors are informed of all specified requirements and that engineering management tools are utilized to ensure
6 V-0.2 – Locomotive – Technical Specification that coordination and communication occurs between the designers of inter-related systems.
3) Name brands, specific equipment, or specific materials may be referenced in this specification. Such equipment has been shown to be successful in previous applications, where correctly applied and integrated with other equipment; however, such references shall not be interpreted as pre-approval of any Contractor designs or applications. The Contractor is responsible for the selection, application, and integration of equipment and materials as necessary to comply with the specified requirements.
4) All equipment provided under this Contract shall be new. Rebuilt or refurbished equipment is prohibited. New equipment damaged during execution of this Contract may be restored to new condition only where approved by WMATA on a case-by-case basis, and all restorations shall be performed by the original equipment manufacturer.
5) Should conflicts exist or an item or feature is deemed by the Contractor not to be adequately described or explained in the Technical Specification, the Contractor shall apply to WMATA for further written explanation, as may be necessary, and shall conform to the written explanation provided by WMATA. The Contractor shall be responsible for ensuring the suitability of the systems, devices, apparatus, components and parts for the service intended.
1.2.2 Key Requirements
1) The Locomotive shall have the ability to operate on the entire WMATA system which includes above and below-ground yard tracks, below-ground tunnels with 3rd rail power, above-ground dedicated right of way with 3rd rail power, and aerial structures.
2) The Locomotive must be capable of hauling work cars to and from work sites on the WMATA system as described in Section 2 of this specification.
3) The Locomotive shall be equipped with compressed air and electrical trainlines to power peripheral equipment such as lighting, and related apparatus in the work cars being hauled.
4) The Locomotive shall be equipped with lighting as described in Section 14 of this specification.
5) The Locomotive shall be capable of mechanically coupling to the existing work vehicles. Refer to Section 5 for coupling requirements.
Technical Specification – Locomotive – V-0.2 7
6) Equipment with limited rail transit service experience will be given consideration by WMATA only if accompanied by timely presentations containing sufficient information for WMATA to weigh the merits of the design.
7) This specification is oriented towards the performance of the vehicle and the standards, by which it is constructed, rather than the specific components, control schemes, and features of the vehicle. It is intended to allow a variety of designs.
8) The Authority reserves the right to contact past and present clients of the Contractor as part of WMATA's research process related to their internal technical review of the Contractor's proposal.
1.3 DELIVERY TO WMATA FACILITIES
1) The Contractor will be responsible for shipping the Locomotives to WMATA.
2) Delivery of the equipment to WMATA’s Greenbelt Rail Yard shall take place xxx days after Notice to Proceed (NTP), at the following address:
WMATA, 5801 Sunnyside Ave., College Park, MD 20740
1.4 SECURITY
1) The Contractor design will provide means for the Locomotive to be secured when crew members are not present. Any area that permits operation of any devices other than lighting must be secured.
2) WMATA must approve the method used to secure the areas. At minimum, a positive key-activated locking device shall be used.
1.5 DEFINITIONS AND ABBREVIATIONS
1.5.1 Definitions
The following terms used in the Contract shall, except where, by the context, it is clear that another meaning is intended, be construed as follows:
ACCEPTANCE: The formal written acceptance by the Authority that all work, or a specific portion thereof, under the Contract has been satisfactorily completed.
8 V-0.2 – Locomotive – Technical Specification
ACCEPTANCE, CONDITIONAL: Not fully accepted, but with a defined set of conditions identified for achieving acceptance.
ACTIVE CAB: The cab in which the control key is switched on, providing control of the train consist, normally the cab at the front of the train.
ADHESION, PERCENT: During rolling contact, the maximum value of the ratio between the longitudinal tangential force and the normal force at the wheel-rail interface.
ALIGNMENT, HORIZONTAL: The horizontal location of a track as described by curves and tangents.
ANCHORAGE: The attachment of the coupler, draft gear, and drawbar to the car underframe.
APPROVED: Approved by the Authority, unless otherwise stated. Approval in no way relieves the Contractor of meeting all requirements of the Specifications. Approval may be qualified as pertaining to a particular stage of the procurement.
APPROVED EQUAL OR EQUIVALENT: An item, material, or method offered as a substitute for that designated herein, for which approval in writing has been obtained from the Authority. The burden of proof that a substitute is, in fact, equal shall rest with the Contractor.
AUTHORITY: The Washington Metropolitan Area Transit Authority.
AUTOMATIC TRAIN CONTROL: The system for automatically controlling train movement, enforcing train safety, and directing train operations.
AUXILIARY EQUIPMENT: Any mechanism or structure, other than the vehicle body, traction motor, or propulsion equipment gearing that performs a function at some time during the operation of the transit vehicle: e.g., heating and cooling subsystem, pumps, vehicle door mechanism, air compressor or hydraulic power unit, transit vehicle lighting, etc.
AVAILABILITY: The percentage of the annual duty time that the Locomotive is ready for operation.
BASELINE DESIGN: The design of the car or any of its components, apparatus, systems, sub-systems, or materials which has received both design review approval and first article approval by WMATA.
BODY ROLL: The angle in degrees, from the normal to the top-of-rail height plane to the body centerline as the vehicle sways from side to side during normal running at any speed on level tangent track.
Technical Specification – Locomotive – V-0.2 9
BRAKING, DYNAMIC: Electrical braking in which the power generated by the traction motors, when driven as generators, is being dissipated by resistor banks or auxiliary loads on the vehicle and is providing retardation effort.
BRAKING EFFORT: Retarding force developed by the propulsion subsystem, braking subsystem, or a combination of both subsystems.
BRAKING, EMERGENCY: An irretrievable braking effort to fully stop a vehicle at a higher retardation rate than is obtained with a full-service brake application.
BRAKING, FULL SERVICE: The normal maximum braking effort employed to stop a vehicle in the absence of an emergency stop signal.
BUFF LOAD: A horizontal compressive load applied to the Locomotive, usually along the Locomotive centerline at the couplers or anti-climbers.
COAST: The mode of operation of transit vehicle or consist in which propulsion (positive traction) and braking are inactive.
COMPONENT: Any individual assembly, plug-in module, or element that is designed to perform a particular function relating to the operation of a system such as a traction motor, gear box, or friction brake control unit. For the purpose of reliability testing, a component or subsystem shall be considered as a component of a system which may require costly repairs or which, if inoperative, will render the vehicle unusable.
CONCEPT DRAWINGS/PLANS: An initial set of drawings showing the general vehicle layout and arrangement provided by WMATA with the Specification.
CONSIST: The quantity and specific identity of vehicles that make up a train.
CONSOLE: The control panel located in the cab directly in front of the Operator's seat.
CONTRACT: The written agreements executed by the Authority and the Contractor, covering the performance of the work and furnishing of labor, materials, equipment, and tools, including work incidental to the procurement.
CONTRACT DATA REQUIREMENTS LIST (CDRL): A matrix listing data (such as drawings, catalogs, reports, notices, and samples), services, and equipment that the Contract specifies must be provided by the Contractor. The matrix also indicates when and how often submittals and resubmittals are required.
CONTRACT SPECIFICATIONS BOOK: A document issued by the Authority that includes the Request for Proposals, Proposal Forms, General Provisions, Terms and Conditions, Technical Specification, and other forms and exhibits.
10 V-0.2 – Locomotive – Technical Specification
CONTRACTOR: The person or persons, firm, partnership, corporation, or any combination thereof, which, as an independent Contractor, has entered into a Contract with the Authority.
COUPLER: A device for mechanically coupling vehicles together.
DAYS: Unless otherwise designated, the word "days" means calendar days.
DEADMAN FEATURE: A device that causes a brake application in the event that inattention or disability of a train operator is detected.
DEFECT: Malfunction or failure in the manufacture or design of any component or subsystem that causes a vehicle to cease operating or operate in a degraded mode.
DELIVERABLE(S): All materials and equipment furnished by the Contractor to WMATA under the terms of this contract including but not limited to drawings, documents, samples, data, special tools or test equipment.
DESIGN LIFE: The period of time for which the vehicle is intended to be safely and reliably usable for its original purpose.
DRAFT GEAR: The energy-absorbing mechanism that attaches the coupler to the anchorage.
DRAFT LOAD: A tensile load applied to the Locomotive through the couplers; the opposite of Buff Load.
DUTY CYCLE: The period or percentage of time associated with the activated state of operation, occurring during normal cyclic operations, in relation to the elapsed time of a full cycle.
DYNAMIC OUTLINE: The largest dimensional cross-sectional area generated by a moving Locomotive under worst-case conditions.
ENDURANCE LIMIT: The maximum stress in a material that can be completely reversed an infinite number of times without causing fracture.
ENGINEER: For this procurement, the "Engineer" shall be embodied in the Authority's Technical Project Manager or by his designee.
FACTOR OF SAFETY: The ratio of the design load to the load that would cause failure of a structure.
FAIL-SAFE: Equipment configurations that are implemented in hardware where each component has a known set of predictable failure modes that may be individually
Technical Specification – Locomotive – V-0.2 11 analyzed for their effect on equipment performance and function. Any failure or set of failures resulting from a single causative event must cause the equipment to revert to a safe state that is self-annunciating.
FAILURE: Any malfunction that requires unscheduled equipment maintenance action, repair, or replacement.
FAILURE RATE: The frequency of failure, typically expressed as failures per million miles.
FATIGUE: Failure of a structure by progressive fracture under large number of repetitions of stress considerably less than the yield stress.
FIRST ARTICLE: The first one of any production components of the vehicle that is produced. The specification requires that nothing be manufactured prior to approval, so the First Article shall have been made to approved drawings.
FIRST ARTICLE INSPECTION (FAI): An extraordinary inspection of a First Article which accomplishes two purposes. First, it permits the Engineer to see, in three dimensions, what could be seen only on two dimensional drawings up to that point. If the First Article Inspection is of a component that the Contractor is purchasing, rather than making itself, the First Article Inspection discloses details that were not visible beforehand. The First Article Inspection is usually the first point at which maintainability of the component can be evaluated, inasmuch as it is the first point at which relationships between elements can be appreciated. The Engineer may approve the design that is revealed at the First Article Inspection or may require changes in order that the component can meet the requirements of the Contract. Second, it is used to establish the quality level of workmanship that will be maintained for the balance of the components. The level is established jointly by the Engineer and the Inspector.
FLEET: All vehicles furnished under the terms of this Contract.
FULLY LOADED: Same as Maximum Gross Weight.
FTA: The Federal Transit Administration of the United States Department of Transportation.
FURNISHING: Providing, manufacturing, fabricating, and completely assembling all material, plant, power, tools, pattern, supplies, appliances, vehicles and conveyances necessary or required for the completion of the work.
GAUGE, TRACK: The distance between the inside face of rails, usually measured
0.625 inch below the top of the heads of running rails and at a right angle thereto.
12 V-0.2 – Locomotive – Technical Specification
GENERAL TERMS: Whenever the words "acceptable," "approved," " submitted," "designated," "established," "permitted," "required," "satisfactory," or "unsuitable" "unacceptable," "unsatisfactory," are used they shall be understood to imply "by the Authority" or "to the Authority" unless the context clearly indicates a different meaning.
Whenever the verbs "submit", "designate", "notify", "bear", "use", "furnish", "install", "comply", and other like verbs are used, without being preceded by a subject, it shall be understood that the subject is responsibility of the Contractor unless the context clearly indicates a different meaning.
INDICATED: As described in the Specifications, as-built drawings or as required by the other Contract documents.
INTERFACE: The point at which one system component or subsystem comes into physical or functional contact with another.
INTERLOCK: An arrangement in which the operation of one function or mechanism automatically causes (or prevents) the operation of another.
IRRETRIEVABLE: In braking, a condition imposed in which a brake cannot be released until zero-speed is attained.
JERK: The rate of change of acceleration or deceleration, normally measured in miles per hour per second per second.
JUMPER: A short piece of wire or cable with appropriate terminations on each end to permit connection to terminals within a terminal board or to an adjacent terminal strip.
LATENT DEFECT: A defect not reasonably found through inspection or initial operation (see defect).
LOW VOLTAGE SYSTEM: The voltage used for auxiliary systems on the vehicle.
LOWEST LEVEL REPLACEABLE UNIT: The lowest component or assemblage of components to which a malfunction can be isolated, and which normally can be replaced in its field application or in the workshop.
MAINTAINABILITY: Shall mean a characteristic of design and installation, expressed as the probability that an item shall be restored to a specified condition within a given period of time when maintenance is performed in accordance with prescribed procedures and resources.
MAINTENANCE, SCHEDULED: Inspection and repair or replacement of components at intervals measured by time or usage.
Technical Specification – Locomotive – V-0.2 13
MAXIMUM GROSS WEIGHT: The maximum operating weight of the vehicle (including services such as fuel, coolant and sand) plus allowable load.
MEAN TIME BETWEEN FAILURES (MTBF): The mean time (in hours, days, years as appropriate) between Component Failures.
MIL-STD.: Military Standard
NOISE LEVEL: As defined by the latest version of ANSI/ASA S1.4 Part 3. The weighted sound pressure level measured by the use of a metering characteristic and weighting A, B, or C as specified in ANSI/ASA S1.4 Part 3. The unit of noise level is the decibel (dB), and the reference pressure is 20 µPa.
NOTICE: A written announcement.
NOTICE TO PROCEED (NTP): A document that apprises the Contractor that this Contract has been approved by WMATA.
OFFEROR: Any individual, firm, partnership, corporation or joint venture submitting a Proposal on the Form for Proposal provided, for the work contemplated, acting directly or through a duly authorized representative.
OWNER: WMATA
OVERHAUL: Disassembly into component parts or subassemblies; replacement of worn and defective parts (with new or reconditioned parts as approved by the Authority);
and reassembly into complete functional assemblies, in accordance with the OEM recommended instructions/procedures.
PERFORMANCE: The measure of output or results obtained by a component, system, person, team, and so forth, as specified.
PORTABLE TEST EQUIPMENT (PTE): Shall mean laptop computers or any portable test equipment that can Interface with onboard Systems such as the engine or Locomotive control Systems, or other controllers for monitoring, troubleshooting, and programming of such Systems.
PRE-SHIPMENT INSPECTION: Source Inspection of product, parts, components subsystems and/or systems conducted immediately prior to releasing items for shipment to Contractor or other destination.
PROCUREMENT (WORK): The furnishing of all equipment, items, materials, parts, systems, data, design, services, incidentals, labor and management and performance of the contractual requirements defined in the Contract Documents, including changes
14 V-0.2 – Locomotive – Technical Specification thereto, in order to produce and deliver the specified vehicles, Spare Parts, software goods, and services.
PROOF (Used as a Suffix): Apparatus is designated as splashproof, dustproof, etc., when so constructed, protected, or treated that its successful operation is not interfered with when subjected to the specified material or condition.
PROPOSAL: The Offer in response to the Authority's Request for Proposal, including the Contract Documents with Specifications, to be submitted in the prescribed manner, properly signed and certified using the forms provided by the Authority as required and all data to be supplied by the Offeror to be in conformance with said Documents.
QUALIFICATION TEST: Tests conducted to demonstrate compliance with Specification design requirements at operating and environmental extremes. These tests shall be performed on the first Locomotive only and at the Contractor's plant unless other arrangements are approved by the Authority.
QUALITY ASSURANCE: The planned and systematic pattern of all actions necessary to provide adequate confidence that the end items will perform in accordance with original manufacturer's specifications and in accordance with the requirements set forth in these contract documents in actual operations.
QUALITY CONTROL: The discipline that ensures the manufacture of a product in accordance with specification requirements.
READY-TO-RUN: Shall mean the Locomotive, ready for operation, with all the fluids filled, with all ancillary equipment, and with a crew of three (3) people.
REDUNDANCY: The existence within a system or subsystem of more than one means of accomplishing a given function.
RELIABILITY: The probability of performing a specified function without failure and within design parameters, for the period of operation intended, under actual operating conditions.
REPAIR: To restore a failed component or system to an operational state.
REQUIREMENTS: The criteria that must be met in designing the vehicle.
REWORK: To reprocess a component or system to as-designed conditioned.
SAFE: The condition in which personnel are secure from threat or danger, harm, or loss arising from improper design, manufacture, assembly, malfunction, or failure of the car or any of its components or systems.
Technical Specification – Locomotive – V-0.2 15
SECTION: Section refers to the indicated Section of the Contract Documents and Specifications plus all subsections thereof (unless the context indicates otherwise).
SERVICE, AS IN-SERVICE USE, SERVICE BRAKING, REVENUE SERVICE: The operation of the vehicles under normal conditions.
SERVICE LIFE: The actual time during which a vehicle serves its intended purpose.
The end of service life occurs when degradation of the structural integrity of the vehicle, or technical obsolescence of its electrical and mechanical systems, requires that it be removed from service.
SERVICE PROVEN: A demonstrated history, subject to Authority agreement, of satisfactory performance in rapid transit rail service, with a high level of availability under a duty cycle and environmental conditions similar to those encountered in the Authority's operations.
SHIPMENT: The physical process of transporting a vehicle and associated components, or other required physical deliverable item, from the point of manufacture or assembly to the next manufacturing or assembly facility or to WMATA property.
SPECIFICATIONS: The directions, provisions, and requirements contained or referred to herein, together with all written agreements made, or to be made, that pertain to the manner of performing the Work, or the quantities of Work and materials, to be provided under the Contract.
SPECIFICATIONS, TECHNICAL: The specifications, provisions, and requirements that detail the work and the materials, products (including the methods of manufacture, construction, assembly, and testing), and other requirements relative thereto.
SUBCONTRACTOR: An individual, partnership, firm, or corporation that undertakes integrally on the Project the partial or total design, manufacture, or performance of one or more items of work under the terms of the Contract. As used herein, the terms "subcontractor," "supplier," and "sub-supplier" are synonymous.
SUBSYSTEM: A subsystem comprises functional elements interconnected within a system to perform a specific function, such as door operations, communications, and lighting.
SUPERELEVATION: On a curve, the vertical distance that the outer rail is above the inner rail, measured in inches.
SUPPLIER: The persons, firm, or corporations who furnish materials/services to the Contractor. Supplier furnished materials/services shall comply with all the contract requirements. Note: During the course of this contract, WMATA may interchangeably
16 V-0.2 – Locomotive – Technical Specification use the word subcontractor, supplier, sub-supplier or vendor as synonyms, all the aforementioned being under contract to the Contractor.
SYSTEM: Any group of functionally-interrelated equipment that performs in concert to produce a desired function relating to the performance of the vehicle. The components of a system are dependent on the function of the apparatus as it performs on the vehicle and may be furnished by one or more suppliers.
TIGHT (USED AS A SUFFIX): Apparatus is designated as watertight, dust-tight, etc., when so constructed that the enclosing case will exclude the specified material.
TIME, DEAD: The time from the occurrence of a step change of the control signal to the beginning of change of the controlled variable.
TIME, REACTION: Time from the initiation of a step change of the control signal to the first attainment of the new steady-state value of the controlled variable, within the designed accuracy.
TRACTIVE EFFORT: Propelling or braking force developed by the propulsion system.
TRAIN: A configuration of at least two (2) railcars to be used in service.
TRAINLINE: The means of sending a signal to all railcars in a consist via a continuous electrical circuit connected through appropriate coupling devices.
TRAM: A condition of ideal truck geometry in which the axles are perfectly parallel and the wheels longitudinally in perfect alignment. The centers of the journal bearings represent the corners of a perfect rectangle. Tram is checked by measuring the diagonal and longitudinal distances between reference points on the axle bearing housing.
ULTIMATE TENSILE STRENGTH: The maximum tensile stress that a material can sustain under uni-axial tension, calculated on the basis of the load at rupture and the original unstrained dimensions.
UNDERFRAME: The main structure that supports the cab, engine compartment, and all associated equipment below the main structure.
VEHICLE: Same as Locomotive
VITAL: A function or a unit which is critical to overall system safety.
VITAL FUNCTION: A function in a safety-critical system that is required to be implemented in a fail-safe manner.
Technical Specification – Locomotive – V-0.2 17
WEIGHTS, ACTUAL: The measured weights of finished vehicles ready to run.
WHEEL SLIDE: The condition is which the equivalent linear velocity of the wheel is less than the linear velocity of the transit vehicle.
WHEEL SPIN: The condition in which the equivalent linear velocity of the wheel is greater than the linear velocity of the transit vehicle.
WORK: The furnishing of all the products, materials, equipment, services and the performance of the contractual requirements in the Contract documents, including changes thereto.
WORK CAR(S): Any WMATA non-revenue heavy rail vehicle used in service.
WORK SITE: Any location on the WMATA system where Maintenance of Way activities are being done.
WORK WEEK: Monday through Friday
YIELD STRESS: The stress at which a material exhibits a specified deformation or set.
ZERO-SPEED: Vehicle velocity of less than 0.5 mph for more than 1 second.
1.5.2 Abbreviations
The following is a list of abbreviations used in the Specification. The list is not intended to be all-inclusive.
A Ampere AAR Association of American Railroads AC Alternating Current AFSS Automatic Fire Suppression System ANSI American National Standards Institute APS Auxiliary Power Supply APTA American Public Transit Association AREA American Railway Engineering Association AREMA American Railway Engineering and Maintenance-of-Way Association ASHRAE American Society of Heating, Refrigeration and Air Conditioning Engineers ASIC Application Specific Integrated Circuit ASME American Society of Mechanical Engineers
18 V-0.2 – Locomotive – Technical Specification
ASTM American Society for Testing and Materials ATP Automatic Train Protection AWG American Wire Gauge AWS American Welding Society Btu British Thermal Unit ºC Degrees Centigrade C Capacitance ºCDB Degrees Centigrade Dry Bulb ºCWB Degrees Centigrade Wet Bulb CAD Computer Aided Design CCTV Closed Circuit Television CDR Critical Design Review CDRL Contract Data Requirements List cfm Cubic Feet Per Minute CFR Code of Federal Regulations COTS Commercial Off-The-Shelf CO Carbon Monoxide CRC Cyclic Redundancy Check CRF Critical Radiant Flux dB Decibel dBA Decibel, A Scale Reading DB Dry Bulb DC Direct Current DVR Digital Video Recorder ECU Electronic Control Unit EMI Electromagnetic Interference EMC Electromagnetic Compatibility EN European Norms – standards developed and adopted by either the
European Committee for Standardization (CEN) or by the European Committee for Electro-technical Standardization (CENELEC)
EPA U.S. Environmental Protection Agency F Degrees Fahrenheit F DB Degrees Fahrenheit Dry Bulb F WB Degrees Fahrenheit Wet Bulb FCC Federal Communications Commission FE Finite Element FEA Finite Element Analysis FEM Finite Element Model FMECA Failure Mode and Effects Critical Analysis fpm Feet Per Minute
Technical Specification – Locomotive – V-0.2 19
FRA Federal Railroad Administration FRP Fiberglass Reinforced Plastic ft Foot FTA Fault Tree Analysis FTA Federal Transit Administration ft-lbs Foot-Pounds g Force of gravity GFCI Ground Fault Current Interrupter HCL Hydrogen Chloride HCN Hydrogen Cyanide HF Hydrogen Fluoride HP Horsepower hr Hour HSLA High Strength Low Alloy HVAC Heating, Ventilation, and Air Cooling Hz Hertz I/O Input/Output ICEA Insulated Cable Engineers Association ID Identification IEC International Electrotechnical Committee IEEE Institute of Electrical and Electronics Engineers IGBT Insulated Gate Bi-Polar Transistor ISO International Standards Organization kg Kilogram km Kilometer kHz Kilohertz kN Kilo Newton kPa Kilopascal km/h Kilometers per hour kW Kilowatt l Liter lbs Pounds lbf Pounds force LED Light Emitting Diode LLRU Lowest Level Replaceable Unit LRU Line Replacement Unit LVPS Low Voltage dc Power Supply m Meters mA Milliampere
20 V-0.2 – Locomotive – Technical Specification mm Millimeter MDBF Mean Distance Between Failures MDS Monitoring and Diagnostic System MDU Monitoring and Diagnostic Unit MHz Megahertz MIL Military Specification Min Minute µPa Micropascal mph Miles Per Hour mphps Miles Per Hour Per Second mphpsps Miles Per Hour Per Second Per Second ms Millisecond MSDS Material Safety Data Sheets MTBF Mean Time Between Failures MTTR Mean Time To Repair MU Multiple-Unit μA Micro Ampere N Newton NBS National Bureau of Standards NDT Non-Destructive Testing NEC National Electrical Code NEMA National Electrical Manufacturers' Association NFL No Field Lubrication NFPA National Fire Protection Association NIST National Institute of Standards and Technology NO2 Nitrogen Dioxide NOA Notice of Award NOx Oxides of Nitrogen NTP Notice to Proceed OD Outside Diameter OEM Original Equipment Manufacturer OHA Operating Hazard Analysis OSHA Occupational Safety and Health Administration PA Public Address PCB Polychlorinated Biphenyl PDR Preliminary Design Review PHA Preliminary Hazard Analysis PLC Programmable Logic Controller ppm Parts Per Million
Technical Specification – Locomotive – V-0.2 21 psi Pounds Per Square Inch psig Pounds Per Square Inch, Gauge PTE Portable Test Equipment PTU Portable Test Unit PVC Polyvinyl Chloride PDR Preliminary Design Review QA Quality Assurance QC Quality Control RF Radio Frequency RAM Random Access Memory RFI Radio Frequency Interference rms Root Mean Square rpm Revolutions Per Minute ROM Read-Only Memory R-407C Refrigerant 407C s, sec Second SAE Society of Automotive Engineers SCFM Standard Cubic Feet Per Minute SFD System Functional Description SHL System Hazard List SO2 Sulfur Dioxide SRS Software Requirements Specification SSHL Subsystem Hazard List SSPP System Safety Program Plan S&I Service and Inspection Facility S/N Signal to Noise Ratio TBD To Be Determined TE Tractive Effort TIR Total Indicated Runout T/L Trainline TOD Train Operator's Display TOR Top-of-Rail TTCS Train Trouble Control System US, U.S. United States UL Underwriters Laboratories Inc.
USB Universal Serial Bus V Volt VAC Volts, Alternating Current VDC Volts, Direct Current
22 V-0.2 – Locomotive – Technical Specification
W Watt WAN Wide Area Network WB Wet Bulb WPS Weld Procedure Specifications WMATA Washington Metropolitan Area Transit Authority
1.6 DELIVERABLES
The following Contract Deliverables are defined in this section:
CDRL Reference Deliverable Timing None
System Design – 2
Technical Specifications – Locomotive – V-0.2 1
System Design
2 – System Design
2 V-0.2 – Locomotive – Technical Specifications
Technical Specifications – Locomotive – V-0.2 3
System Design - 2
Section/Sub-section Title Page
2 SYSTEM DESIGN
2.1 DESIGN BASIS AND PARAMETERS
2.2 LOCOMOTIVE DIMENSIONS
2.3 LOCOMOTIVE LOADING AND WEIGHT
2.4 OPERATING ENVIRONMENT
2.5 OPERATING AND BRAKING PERFORMANCE
2.6 ELECTRO-MAGNETIC COMPATIBILITY AND INTERFERENCE
2.7 NOISE, SHOCK, AND VIBRATION
2.8 WARNING DEVICES
2.9 COMPLIANCE PROGRAM GENERAL DESCRIPTION
2.10 TEST PROGRAM
2.11 TEST PLANS, PROCEDURES, AND REPORTS
2.12 SYSTEM DESIGN TEST PHASES
2.13 TEST DETAILS
2.14 CLEARANCE TEST
2.15 CURVE TESTS
2.16 WHEEL LOAD TEST
2.17 NOISE TESTS
2.18 EMI TEST
2.19 DELIVERABLES
4 V-0.2 – Locomotive – Technical Specifications
Technical Specifications – Locomotive – V-0.2 5
2 SYSTEM DESIGN
This section establishes the functions, performance, and general design criteria for a work locomotive, herein referenced as the “Locomotive”. Included in the section are requirements for configuration, capacity, dimensions, performance, operating environment or environmental parameters, weight and other requirements that impact system design. Detailed system requirements are further defined in the sections explicitly covering those systems.
2.1 DESIGN BASIS AND PARAMETERS
2.1.1 General Design Requirements
1) All Contractor's…