This document is a Bid Addendum for the Clatsop County Circuit Court Security Improvements project located in Astoria, Oregon. The addendum modifies the original project manual and drawings dated June 28th, 2023, primarily by adding a new Specification Section 22 00 50 - Basic Plumbing Materials and Methods, and deleting Sections 09 65 66 - Resilient Athletic Flooring and 09 66 13 - Terrazzo Flooring. Contract document holders must acknowledge receipt of this addendum on the Bid Form, as failure to do so may result in disqualification.

The overall Clatsop County Courthouse Security Improvements project involves remodeling the courthouse, including the basement entry, installing holding cells, upgrading the reception desk at the District Attorney's Office, elevator modernization, and replacing historic windows. The project is located in Astoria, Oregon and is being overseen by Clatsop County.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Addendum

ADDENDUM No. 01 -

Project Name Clatsop County Circuit Court Security Improvements Project Number 2101028 Project Address 749 Commercial St

Astoria, OR 97130

Company Name SERA Design and Architecture, Inc Address 600 SW 10th Ave, Suite 500

Portland, OR 97205

Addendum # 01

Date of Issuance 07 July 2023

To: All Contract Document Holders

This Addendum forms a part of the Contract Documents and modifies the original Project Manual and Drawings, dated June 28th, 2023 as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject bidder to disqualification.

This Addendum consists of nine (9) addendum pages and one (1) attachment:

ATTACHMENTS

1. Specification Section 22 00 50 – Basic Plumbing Materials and Methods

PROJECT MANUAL

Division 01 – GENERAL REQUIREMENTS

00 01 10 - Table of Contents

1. Delete: Section 09 65 66 – Resilient Athletic Flooring.

2. Delete: Section 09 66 13 – Terrazzo Flooring

DIVISION 22 – PLUMBING

Section 22 00 50 – Basic Plumbing Materials and Methods

1. Add: Entire Section. This was omitted in original bid set and is adopted into the contract documents with this addendum.

END OF ADDENDUM NO. 1