Cauley Creek Parking Lot Addition - Project Manual Summary
This is a Project Manual containing technical specifications for the City of Johns Creek, Georgia's construction of an overflow parking lot addition at Cauley Creek Park. The project, identified as City Project Bid #26-092 and CHA Project #084837, encompasses the development of 87 parking spaces and includes comprehensive site work including grading, subgrade preparation, graded aggregate base installation, asphalt paving, concrete improvements, and landscaping. The technical specifications document, prepared by CHA (Crestwood Heritage Associates), covers multiple divisions of work including earthwork, exterior improvements, and site restoration. Specifications are organized into detailed sections addressing geotextiles, site clearing, earth moving, rock removal, dewatering, erosion and sediment control, subbase courses, asphalt paving, cast-in-place concrete curbing, concrete sidewalks, pavement marking, and planting operations. All work must comply with the latest editions of State of Georgia Standard Specifications for Construction of Transportation Systems, AASHTO standards, and ASTM standards.
The specifications establish rigorous quality assurance requirements including independent testing laboratory verification of materials, field quality control testing for compaction and density, and comprehensive inspection protocols at multiple project phases. Contractors must provide proof rolling of subgrades, maintain specific compaction standards (minimum 95 percent of maximum density), and achieve specified tolerances for pavement thickness and surface smoothness. All exterior plants carry a one-year warranty period from substantial completion with concurrent maintenance requirements including watering, weeding, fertilizing, mulching, and pest control. Material specifications reference numerous approved manufacturers and establish performance standards for asphalt concrete meeting GDOT requirements, concrete achieving 4000-5000 psi compressive strength, and landscape materials complying with ANSI Z60.1 standards. The contractor assumes responsibility for erosion and sediment control throughout construction, environmental compliance with Georgia NPDES permits, and restoration of all disturbed areas to pre-construction conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cauley Creek Parking Lot Addition Civil Plans.pdf | ||
| 26_092 ITB CCP Overflow Parking Lot Bid Packe.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
CAULEY CREEK PARKING LOT ADDITION
CITY PROJECT BID # 26-092
FEBRUARY 22, 2026
CHA PROJECT #: 084837
Prepared for:
CITY OF JOHNS CREEK, GA
Prepared by:
CHA
3700 Crestwood Parkway, STE 700
Duluth, GA 30096
(770) 447-8999
TABLE OF CONTENTS PAGE 1 OF 1
CHA PROJECT NO. 084837
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\00 01 10 Table of Contents.docx SECTION 000110
CITY OF JOHNS CREEK, GA
CAULEY CREEK PARKING LOT ADDITION
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
Division 31 – Earthwork
310519.13 Geotextiles
311000 Site Clearing 312000 Earth Moving
312316.26 Rock Removal
312319 Dewatering 312500 Erosion and Sediment Control
Division 32 – Exterior Improvements 321116 Subbase Courses 321216 Asphalt Paving
321613.16 Cast-In-Place Concrete Curbing
321630 Concrete Sidewalks 321723 Pavement Marking 329000 Planting
GEOTEXTILES PAGE 1 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\310519.13 Geotextiles.docx SECTION 310519.13
SECTION 310519.13 – GEOTEXTILES
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the installation of separation/stabilization fabric as shown on the Drawings and as specified herein.
1.2 QUALITY ASSURANCE
A. The latest edition of the following standards, as referenced herein, shall be applicable.
1. American Society for Testing and Materials (ASTM).
1.3 DELIVERY, STORAGE, AND HANDLING
A. Delivery:
1. Deliver sufficient materials to the site to prevent interruption of the work.
2. All materials shall be inspected by Contractor upon delivery. Contractor shall notify Engineer of any damage. Products received at the site torn, with holes, deteriorated, or otherwise damaged will not be approved and shall be returned and replaced at no expense to the Owner.
B. Storage:
1. All material shall be stored in strict accordance with the manufacturer's recommendations and as approved by the Engineer.
2. Do not store products directly on ground. Ship and store geotextile with suitable wrapping for protection against moisture and ultraviolet exposure. Store geotextile in way that protects it from elements, if stored outdoors, elevate, and protect geotextile with waterproof cover.
C. Handling:
1. All material shall be handled in strict accordance with the manufacturer's recommendations and as approved by the Engineer.
PART 2 – PRODUCTS
2.1 WOVEN GEOTEXTILE
A. Stabilization Fabric: To be used beneath roadways and walks.
B. Composed of polymeric yarn interlaced to form a planar structure with uniform weave pattern.
C. Calendared or finished so yarns will retain their relative position with respect to each other.
D. Polymeric Yarn: Long-chain synthetic polymers (polyester or polypropylene) with stabilizer or inhibitors added to make filament resistant to deterioration due to heat and ultraviolet light exposure.
E. Sheet Edges: Selvaged or finished to prevent outer material from separating from sheet.
F. Unseamed Sheet Width: Minimum 12 feet.
GEOTEXTILES PAGE 2 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\310519.13 Geotextiles.docx SECTION 310519.13
G. Physical Properties: Conform to requirements noted below:
PROPERTY DESIGN VALUE TEST METHOD
Tensile Strength 315 pounds ASTM D4632
Elongation 12 percent ASTM D4632 Trapezoidal Tear 113 pounds ASTM D4533
CBR Puncture Strength 900 pounds ASTM D6241 A.O.S. 40 (US Sieve) ASTM D4751
Permittivity .05 sec-1 ASTM D4491
2.2 NONWOVEN GEOTEXTILE
A. Separation/Filtration Fabric: To be used in drainage ditches, haybale installation, culvert outfall installations, rip-rap outfall installations, and cover material separation
B. Pervious sheet of polyester, polypropylene, or polyethylene fabricated into stable network of fibers that retain their relative position with respect to each other. Nonwoven geotextile shall be composed of continuous or discontinuous (staple) fibers held together through needle-punching, spun-bonding, thermal-bonding, or resin-bonding.
C. Geotextile Edges; selvaged or otherwise finished to prevent outer material from pulling away from geotextile.
D. Unseamed Sheet Width: Minimum 12 feet.
E. Physical Properties: Conform to the requirements noted below:
PROPERTY DESIGN VALUE TEST METHOD
Tensile Strength 160 pounds ASTM D4632
Elongation 50 percent ASTM D4632 Trapezoidal Tear 60 pounds ASTM D4533
CBR Puncture Strength 400 pounds ASTM D6241 A.O.S. 70 (US Sieve) ASTM D4751
Permittivity 1.4 sec-1 ASTM D4491
PART 3 – EXECUTION
3.1 GENERAL
A. The Contractor shall be responsible for the installation, and seaming of geotextile fabric in accordance with the specifications and the manufacturer's recommendations, as approved by the Engineer.
3.2 SUBGRADE PREPARATION
A. Surfaces to be covered with geotextile fabric shall be smooth and free of rocks, sticks, roots, sharp objects, and all debris that may damage the fabric. The surface to be covered shall be firm and unyielding, with no sudden changes or breaks in grade. There shall be no standing water or excessive moisture on the surface when the fabric is placed.
B. The compacted subgrade shall be maintained in a smooth, uniform, and compacted condition during installation of the fabric.
GEOTEXTILES PAGE 3 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\310519.13 Geotextiles.docx SECTION 310519.13
3.3 GEOTEXTILE INSTALLATION
A. The fabric shall be cleaned of all debris or other materials that may negatively affect the fabric's performance.
B. Mechanical equipment shall not be permitted to operate directly on the fabric unless authorized to do so by the manufacturer and approved by the Engineer.
C. Geotextile Placement:
1. Fabric shall be placed as recommended by the manufacturer and approved by the Engineer on surfaces which have been prepared to conform with these Specifications and found acceptable for fabric installation.
2. The fabric shall be placed as smooth and wrinkle-free as possible.
3. When installing geotextile in trenches, swales, ditches, etc., overlap geotextile in the direction of flow.
4. All areas of fabric damaged during installation as determined by the Engineer shall be repaired or replaced by the Contractor as specified at no additional cost to the Owner. Should the fabric be damaged during any step of the installation, the damaged section shall be repaired by covering it with a piece of fabric which extends at least 24 inches in all directions beyond the damaged area. The fabric shall be secured by sewing or bonding as approved by the Engineer.
5. At time of installation, fabric will be rejected if it has defects, ribs, holes, flaws, deterioration, or damage incurred during manufacture, transportation, handling, or storage. Damaged materials shall be removed and replaced at no additional cost to the Owner.
6. Fabric shall be placed with long dimension down slope.
7. Fabric shall be protected at all times during construction from contamination by surface run-off and any fabric so contaminated shall be removed and replaced with uncontaminated fabric.
D. Seams and Overlaps of Geotextile:
1. All overlaps shall be a minimum of 18 inches (450 mm).
3.4 COVER MATERIALS OVER GEOTEXTILES
A. Granular materials shall be placed on geotextiles as shown on the Drawings. During back dumping and spreading, a minimum depth of 6 inches of granular material shall be maintained at all times between the fabric and wheels of trucks or spreading equipment. All equipment used in spreading or traveling on the cover layer for any reason shall exert low ground pressures and shall be approved by the manufacturer and Engineer. Dozer blades, etc., shall not make direct contact with the fabric;
however, if tears occur in the fabric during the spreading operation, the granular material shall be cleared from the fabric and the damaged area repaired as previously described.
B. The granular material shall be spread in the direction of fabric overlap. Large fabric wrinkles which may develop during the spreading operations shall be folded and flattened in the direction of the spreading. Occasionally, large folds may reduce the fabric overlap width. Special care shall be given to maintain proper overlap and fabric continuity.
C. All equipment spreading cover material or traveling on the cover layer shall avoid making sharp turns, quick stops, or quick starts.
D. Fabric shall be covered as soon as possible after placement to minimize exposure to sunlight. Fabric shall not be exposed for more than 5 days.
GEOTEXTILES PAGE 4 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\310519.13 Geotextiles.docx SECTION 310519.13
3.5 DISPOSAL OF SCRAP MATERIALS
A. On completion of installation, the Contractor shall legally dispose of all trash and scrap material off-site or in a location approved by the Owner and Engineer, remove equipment used in connection with the work herein, and shall leave the premises in a neat acceptable manner.
END OF SECTION
SITE CLEARING PAGE 1 OF 5
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\311000 Site Clearing.docx SECTION 311000
SECTION 311000 – SITE CLEARING
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Protecting existing trees, shrubs, groundcovers, plants, and grass to remain.
2. Removing existing trees, shrubs, groundcovers, plants, and grass.
3. Clearing and grubbing.
4. Stripping and stockpiling topsoil.
5. Removing above- and below-grade site improvements.
6. Disconnecting, capping or sealing, and abandoning site utilities in place and removing site utilities.
1.2 DEFINITIONS
A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches (50 mm) in diameter; and free of subsoil and weeds, roots, toxic materials, or other non-soil materials.
B. Tree Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction and defined by the drip line of individual trees or the perimeter drip line of groups of trees, unless otherwise indicated.
C. Grubbing: Removal of vegetation and other organic matter including stumps, buried logs, and roots.
1.3 MATERIAL OWNERSHIP
A. Except for excess stripped topsoil or other materials indicated to remain Owner's property, cleared materials shall become Contractor's property and shall be removed from Project site.
1.4 QUALITY ASSURANCE
A. Stake limits of clearing, grubbing, and stripping, prior to commencing of work.
B. Arborist Qualifications: Engage a qualified arborist who has successfully completed tree protection and trimming, to perform the following work:
1. Remove branches from trees that are to remain, if required.
2. Recommend procedures to compensate for loss of roots and perform initial pruning of branches and stimulation of root growth where removed to accommodate new construction.
3. Recommend procedures for excavation and grading work juxtaposed to established plants.
4. Perform tree repair work for damage incurred by new construction.
1.5 PROJECT CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
SITE CLEARING PAGE 2 OF 5
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\311000 Site Clearing.docx SECTION 311000
2. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction. Detour routes shall be identified by adequate signs in accordance with the
MUTCD.
B. Protect areas outside limits of disturbance from encroachment by construction personnel or equipment, regardless of property Ownership. Access shall be by specific, written permission or easement only.
C. Improvements on Adjoining Property: Authority for performing site clearing indicated on property adjoining Owner's property will be obtained by Owner before award of Contract.
1. Do not proceed with work on adjoining property until directed by Owner’s Representative.
D. Salvageable Improvements: Carefully remove items indicated to be salvaged and deliver to storage location defined on the plans or specified here in.
E. Utility Locator Service: Properly notify utility locator service for area where Project is located before site clearing in accordance with local protocol.
F. Do not commence site clearing operations until temporary erosion and sedimentation control measures are in place.
G. Contractor shall verify existing grades prior to performing work under this section. If existing grades are at variance with the drawings, notify the Owner and receive instructions prior to proceeding. No additional compensation will be considered resulting from grade variances once site clearing has commenced.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during construction.
B. Locate and clearly flag, fence and protect trees and vegetation to remain or to be relocated.
C. Remove branches from trees that are to remain, if required to clear new construction and only if specifically approved by Owner’s Representative.
1. Where directed by Engineer, extend pruning operation to restore natural shape of entire tree.
2. Cut branches and roots, if required, with sharp pruning instruments; do not break or chop.
D. Protect existing site improvements to remain from damage during construction.
1. Restore damaged improvements to their original condition, as acceptable to Owner.
3.2 TREE PROTECTION
A. Erect and maintain temporary fencing around tree drip line before starting site clearing. Remove fence when construction is complete.
1. Do not store construction materials, debris, or excavated material within fenced area.
2. Do not permit vehicles, equipment, or foot traffic within fenced area.
3. Maintain fenced area free of weeds and trash.
SITE CLEARING PAGE 3 OF 5
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\311000 Site Clearing.docx SECTION 311000
B. Do not machine excavate within tree drip line.
C. Where excavation for new construction is required within tree drip line, hand clear and excavate to minimize damage to root systems. Use narrow-tine spading forks, comb soil to expose roots, and cleanly cut roots as close to excavation as possible.
D. Do not allow exposed roots to dry out before permanent backfill is placed; provide temporary earth cover or pack with peat moss and wrap with burlap. Water and maintain in moist condition and temporarily support and protect from damage until permanently relocated and covered with earth.
1. Temporarily support and protect roots from damage until they are permanently redirected and covered with soil.
2. Coat cut faces of roots more than 1-1/2 inches (38 mm) in diameter with an emulsified asphalt or other approved coating formulated for use on damaged plant tissues.
3. Backfill with soil as soon as possible.
4. Where trenching for utilities is required within drip line, tunnel under or around roots by hand digging. Do not cut main lateral roots or tap roots; cut only smaller roots that interfere with installation of new work. Cut roots with sharp pruning instruments; do not break or chop.
E. Repair or replace trees and vegetation indicated to remain that are damaged by construction operations, in a manner approved by Engineer and acceptable to the Owner.
1. Employ an arborist, licensed in jurisdiction where Project is located, to submit details of proposed repairs and to repair damage to trees and shrubs.
2. Replace trees that cannot be repaired and restored to full-growth status, as determined by
Engineer and acceptable.
3.3 UTILITIES
A. Owner will arrange for disconnecting and sealing indicated utilities that serve existing structures before site clearing, when requested by Contractor.
1. Verify that utilities have been disconnected and capped before proceeding with site clearing.
B. Locate, identify, disconnect, and seal or cap off utilities indicated to be removed.
1. Arrange with utility companies to shut off indicated utilities.
2. Owner will arrange to shut off indicated utilities when requested by Contractor.
C. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Owner’s Representative and owner not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Owner’s Representative written permission.
D. Excavate for and remove underground utilities indicated to be removed.
3.4 MERCHANTABLE TIMBER
A. Saleable logs will remain property of Contractor.
B. Exercise care in cutting and felling to prevent damage to saleable logs. Cut, trim, and handle logs in such manner that will ensure best sale value.
C. Stockpile saleable logs in neat, orderly piles until removed from site.
SITE CLEARING PAGE 4 OF 5
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\311000 Site Clearing.docx SECTION 311000
3.5 CLEARING AND GRUBBING
A. Completely remove obstructions, trees, shrubs, stumps, roots, grass, and other vegetation to permit installation of new construction.
1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated.
2. Cut minor roots and branches of trees indicated to remain in a clean and careful manner where such roots and branches obstruct installation of new construction.
3. Use only hand methods for grubbing within tree protection zone.
4. Chip removed tree branches and any other material not utilized during construction to be removed at the end of job at no additional cost to owner
B. Fill depressions caused by clearing and grubbing operations in accordance with Section "Earth Moving" unless further excavation or earthwork is indicated.
1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches and compact each layer to a density equal to adjacent original ground.
3.6 TOPSOIL STRIPPING
A. Remove sod and grass before stripping topsoil.
B. Where trees are designated to remain, stop topsoil stripping and adequate distance from the trees to prevent damage to the main root system.
C. Strip topsoil to whatever depths are encountered in a manner to prevent intermingling with underlying subsoil or other waste materials.
1. Remove subsoil and non-soil materials from topsoil, including trash, debris, weeds, roots, and other waste materials.
D. Stockpile topsoil materials away from edge of excavations without intermixing with subsoil. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Limit height of topsoil stockpiles to 72 inches.
2. Do not stockpile topsoil within tree protection zones.
3. Dispose of excess topsoil as specified for waste material disposal.
3.7 SITE IMPROVEMENTS
A. Remove existing above- and below-grade improvements as indicated and as necessary to facilitate new construction.
B. Remove slabs, paving, curbs, gutters, and aggregate base as indicated.
1. Unless existing full-depth joints coincide with line of demolition, neatly saw-cut length of existing pavement to remain before removing existing pavement. Saw-cut faces vertically.
2. Paint cut ends of steel reinforcement in concrete to remain to prevent corrosion.
3.8 DISPOSAL
A. Burning of debris onsite is not permitted.
SITE CLEARING PAGE 5 OF 5
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\311000 Site Clearing.docx SECTION 311000
B. Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials including trash and debris, and legally dispose of them off Owner's property.
1. Separate recyclable materials produced during site clearing from other nonrecyclable materials.
Store or stockpile without intermixing with other materials and transport them to recycling facilities.
C. Dispose of all diseased Elmwood within 4 days after cutting by burning or by other methods approved by the Department of Environmental Conservation.
EARTH MOVING PAGE 1 OF 6
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312000 Earth Moving.docx SECTION 312000
SECTION 312000 – EARTH MOVING
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the preparation of the site, protection, excavation, embankment, drainage, dewatering, for site grading, as shown on the Drawings, and as herein specified.
B. The Contractor shall accept the site in the condition in which it exists at the time of the award of the Contract.
C. The Engineer shall determine the suitability of materials that are to be used in the work and should any materials encountered be unsatisfactory for the purpose intended, they shall be removed from the site at the Contractor's expense.
1.2 QUALITY ASSURANCE
A. Reference Standards:
1. The latest edition of the following standards, as referenced herein, shall be applicable.
a. State of Georgia Standard Specifications for Construction of Transportation systems, latest edition.
b. "Standard Specifications for Highway Materials and Methods of Sampling and Testing, American Association of State Highway and Transportation Officials (AASHTO)."
B. The Contractor shall comply with the requirements for soil erosion and sedimentation control, and other requirements of governmental authorities having jurisdiction, including the State of Georgia.
C. The Contractor shall provide and pay for all costs in connection with an approved independent testing facility to determine conformance of soils and aggregate with the specifications.
1.3 PROJECT REQUIREMENTS
A. Notify the Engineer of any unexpected subsurface condition.
B. Protection of Existing Utilities:
1. Locate existing underground utilities in areas of work. If utilities are to remain in place, provide adequate support and protection during earthwork operations, comply with OSHA requirements.
2. Coordinate interruption and/or termination of utilities with the utility companies and the Owner.
3. Provide a minimum of 48 hours’ notice to the Owner and receive written notice to proceed before interrupting any utility.
4. Demolish and completely remove from the site any existing underground utilities designated to be removed as shown on the Drawings or as specified in Section "Site Clearing."
5. Repair any damaged utilities as acceptable to the Engineer, at no additional cost to the Owner.
C. Protection of Persons and Property:
1. Barricade open excavations occurring as part of this work, and post with warning lights.
2. Operate warning lights as recommended by authorities having jurisdiction.
EARTH MOVING PAGE 2 OF 6
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312000 Earth Moving.docx SECTION 312000
3. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.
4. Perform excavation within drip-line of large trees to remain by hand and protect the root system from damage or dryout to the greatest extent possible. Maintain moist conditions for root system and cover exposed roots with burlap. Paint root cuts of 1-inch diameter and larger with emulsified asphalt tree paint.
PART 2 – PRODUCTS
2.1 PRECONSTRUCTION MATERIAL QUALIFICATION TESTING
A. A 100-pound minimum representative sample shall be obtained from each potential borrow source.
If different material gradations are known to exist in the pit, samples shall be obtained for each material. Each sample shall be mixed thoroughly and reduced to test specimen size, in accordance with AASHTO T87. The test shall be performed in the order shown. Failure to pass any test is grounds for disqualification and shall lead to cessation of the test program for that material.
1. Particle Size Analysis:
a. Method: ASTM D422.
b. Number of Tests: One (1) per potential source.
c. Acceptance Criteria: Gradation within specified limits.
2. Maximum Density Determination:
a. Method: ASTM D1557, Modified Proctor.
b. Number of Tests: One (1) per potential source.
3. Re-establish gradation and maximum density of fill material if source is changed during construction.
2.2 MATERIALS
A. Select Granular Material: Sound, durable, sand, gravel, stone or blends with these materials, free from organic, frozen, or other deleterious materials meeting the following gradation requirements:
SIEVE PERCENT PASSING
2" 100
1/4" 30 - 65 No. 40 5 - 40
No. 200 0 - 10
B. Selected Fill: Sound, durable, sand, gravel, stone, or blends of these materials, free from organic, frozen or other deleterious materials.
SIEVE PERCENT PASSING
4" 100
No. 40 0 - 70 No. 200 0 - 10
1. Fines passing No. 200 shall be non-plastic.
2. Particle size analysis shall show no gap grading.
EARTH MOVING PAGE 3 OF 6
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312000 Earth Moving.docx SECTION 312000
PART 3 – EXECUTION
3.1 PREPARATION
A. Establish required lines, levels, contours, and datum.
B. Maintain benchmarks and other elevation control points. Re-establish, if disturbed or destroyed, at no additional cost to the Owner.
C. Establish location and extent of utilities before commencement of grading operations.
3.2 EXCAVATION
A. Excavation shall consist, in general, of the excavation of whatever substance is encountered to the lines, grades, and sections shown on the Drawings including excavation as necessary for grading and other similar features.
B. All suitable materials removed in excavation shall be used in the construction of embankments, subgrade, shoulders, slopes, and at such other places as directed. The Engineer shall be the sole judge of what constitutes suitable material.
C. During construction, the grading operations shall be executed in such a manner that the excavation will be well drained at all times. All grading shall be finished on neat, regular lines conforming to the sections and contours shown on the Plans.
D. Removal of materials beyond the indicated subgrade elevations, without authorization by the Engineer, shall be classified as unauthorized excavation and shall be performed at no additional cost to the Owner.
E. Excavation shall be performed in proper sequence with all other associated operations.
F. Maintain the slopes of excavation in a safe condition until completion of the grading operation.
G. All excavation work shall be inspected and approved by the Engineer before proceeding with construction.
H. Any excess excavation shall be removed from the site to disposal areas at the Contractor's expense.
3.3 FILL
A. All site fill shall be “selected fill” unless otherwise shown on the Drawings or directed by the Engineer. “Select granular fill” shall be placed in lieu of selected fill where directed by the Engineer.
B. Before depositing fills, the surface of the ground shall be cleared of all refuse, brush, and large stones. Conform to Section "Site Clearing."
C. Prior to placing fill over undistributed material, scarify to a minimum depth of 6 inches.
D. Where fills are made on hillsides or slopes, the slope of the original ground upon which the fill is to be placed shall be plowed or scarified deeply or where the slope ratio of the original ground is steeper than 2 horizontal to 1 vertical, the bank shall be stepped or benched.
E. The original ground shall be proof rolled until the underlying soil is thoroughly compacted to the satisfaction of the Engineer before any filling is begun. A steel-wheel tandem roller weighing 8 to
EARTH MOVING PAGE 4 OF 6
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312000 Earth Moving.docx SECTION 312000
10 tons or equipment capable of obtaining the same effort shall be used to obtain a thoroughly compacted subgrade. Remove or recompact any soft or loose soils as determined by the Engineer prior to filling.
F. A thoroughly and satisfactorily subgrade is defined as having a minimum dry density of 95 percent of the maximum density of the material used. The subgrade material shall be compacted at a moisture content suitable for obtaining the required density.
G. Place backfill and fill materials in layers not more than 12 inches in loose depth unless shown otherwise on the Drawings. Lift height shall be governed by the ability of the compaction equipment to obtain the required compaction with 12 inches as a maximum lift height. Before compaction, moisten or aerate each layer as necessary to facilitate compaction to the required density. Do not place backfill or fill material on surfaces that are muddy, frozen, or contain frost, ice, ponded water, or extraneous debris.
H. When work is suspended during periods of freezing weather, measures shall be taken to prevent fill already in place from freezing. Upon resumption of work after any inclement weather, prepare the exposed surface by proof rolling to identify any zones of soft/loose soils. Soft/loose materials or frozen soils shall be removed and replaced by compacted granular fill.
I. Moisture Control:
1. Where fill or backfill must be moisture conditioned before compaction, uniformly apply water to the surface and to each layer of fill or backfill. Prevent ponding or other free water on surface subsequent to, or during, compaction operations.
2. Remove and replace, or scarify and air dry, soil that is too wet to permit compaction to specified density. Soil that has been removed because it is too wet to permit compaction may be stockpiled or spread and allowed to dry. Assist drying by discing, harrowing, or pulverizing until moisture content is reduced to a value which will permit compaction to the percentage of maximum density specified.
J. All fill shall be thoroughly and satisfactorily compacted to 95 percent of the maximum density of material used.
3.4 GRADING
A. The present and finished grade lines are shown on the Drawings. Grade over the entire area, as shown on the drawings, shall be to the finished subgrade levels. Upon completion of this work, all debris shall be cleaned out and removed from the premises.
B. All cutting, filling, backfilling and grading necessary shall be done to bring the area to the following grade or subgrade levels:
1. For roadway surface areas to the finished subgrade levels specified on the contract drawings.
2. For areas to be topsoiled and seeded to within 6 inches of the finished grade.
3. For other surface treatments as detailed on the Drawings.
C. Sufficient grading must be done during the progress of the work so that the entire site shall be well drained and free from water pockets.
D. Finish grading, including dressing swales, cleaning up excess footing excavation, dressing terraces, disposing of excess material and all other work necessary to prepare the site for topsoil and seeding shall be done after construction of structures and roadway surface areas is substantially complete.
EARTH MOVING PAGE 5 OF 6
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312000 Earth Moving.docx SECTION 312000
3.5 COMPACTION EQUIPMENT
A. Compaction equipment used for the Work is subject to approval by the Engineer. Any equipment not originally manufactured for compaction purposes and equipment which is not in proper working order will not be approved. Furnish manufacturer's specifications covering data not obvious from a visual inspection of the equipment and necessary to determine its classification and performance characteristics.
B. Vibratory Drum Compactors: A self-propelled compactor classified for use according to the developed compactive force rating (CFR) per linear inch of drum width (PLI). The actual operating frequency of the compactor will determine the PLI rating. Compute the CFR at the actual operating frequency for the compactor.
1. Furnish one vibratory reed tachometer for the exclusive use of the Engineer. Tachometers shall have a frequency range adequate to cover the operating frequencies of all vibratory compactors on the project with scale divisions of 50 vibrations per minute or less. The tachometer will be returned by the Owner’s Representative at the closeout of the project.
2. Approval of vibratory compactors usage is contingent upon proper operation of equipment at all times during compaction operations.
3. Compaction equipment other than vibratory drum compactors may be used subject to the approval of the Owner’s Representative. Submit specifications at least two (2) weeks prior to use of this equipment.
4. Do not use vibratory drum compactors after concrete is poured.
3.6 DRAINAGE AND DEWATERING
A. Prevent surface, subsurface or ground water from flowing into excavation and from flooding project area, as well as surrounding areas.
B. Do not allow water to accumulate in excavations. Remove water to prevent soil changes detrimental to the stability of subgrades.
C. Provide and maintain the pumps, well points, sumps, suction and discharge lines, and other dewatering components necessary to convey water away from excavations.
D. Provide and maintain temporary drainage ditches and other diversions outside excavation limits to convey rain water and water removed from excavations by dewatering, to collection or run-off areas.
E. Dewatering operations shall be as directed by the Engineer and performed in accordance with Section "Dewatering."
3.7 FIELD QUALITY CONTROL
A. Notify the Owner’s Representative at least one (1) working day in advance of all phases of filling and backfilling operations.
B. Compaction testing shall be performed to ascertain the compacted density of the fill and backfill materials in accordance with the following methods:
1. In-place relative density:
a. Method: AASHTO T310, Nuclear Method.
b. Number of Tests: One (1) per 8-inch vertical lift.
EARTH MOVING PAGE 6 OF 6
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312000 Earth Moving.docx SECTION 312000
1) Paved and Building Slab Areas: At subgrade and at each compacted fill and backfill layer, at least one (1) test for every 10,000 square feet or less of paved area of building slab, but in no case fewer than three (3) tests.
C. The Owner’s Representative may direct additional tests to establish gradation, maximum density, and in-place density as required by working conditions, at the Contractor's expense.
D. Acceptance Criteria: The sole criterion for acceptability of in-place fill shall be in situ dry density.
Minimum dry density for all fill or backfill shall be 95 percent of the maximum dry density, unless otherwise specified in the construction documents. If a test fails to qualify, the fill shall be further compacted and retested. Subsequent test failures shall be followed by removal and replacement of the material.
3.8 CLEAN UP
A. Provide and maintain protections or newly filled areas against damage. Upon completion or when directed, correct all damaged and deficient work by building up low spots and remove temporary protections, fencing, shoring and bracing.
B. Remove all surplus excavated material not required for filling and backfilling and legally dispose of same away from premises.
C. Leave the premises and work in clean, satisfactory condition, ready to receive subsequent operations.
ROCK REMOVAL PAGE 1 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312316.26 Rock Removal.docx SECTION 312316.26
SECTION 312316.26 – ROCK REMOVAL
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes drilling, blasting, excavation, removal and disposal of rock as necessary for the installation of the Work, and as indicated and specified herein.
1.2 REFERENCES
A. The latest edition of the following standards, as referenced herein, shall be applicable.
1. “Structure Response and Damage Produced by Ground Vibration from Surface Mine Blasting,”
U.S. Bureau of Mines Publication RI 8507.
1.3 DEFINITIONS
A. Rock: Limestone, sandstone, shale, granite, quartz, and formations of other varying mineral or aggregate composition in solid beds or masses in its original or stratified position that exceed 1 cubic yard and that cannot be excavated with one of the following:
1. A crawler tractor having a minimum draw bar pull rated at not less than 71,000 pounds (Cater-pillar D9N or equivalent) and occupying an original volume of at least 1 cubic yards or more.
2. A backhoe having a break out force rated at not less than 44,000 pounds (Caterpillar 235D or equivalent) and occupying an original volume of at least 1 cubic yards.
B. Rock Excavation: Removal of rock by means of drilling, blasting, or use of pneumatic tools or expansive chemical agents. Removal of materials which, in the opinion of the Engineer, can be loosened and excavated by mechanical means (ripping, etc.) including frozen materials, soft laminated shale or hardpan, pavements, curbs and similar materials shall be classified as earth excavation with the exception of rock face scaling. Do not proceed with the excavation of this material until the Owner’s Representative has classified the materials as common excavation or rock excavation and has taken cross sections as required. Failure on the part of the Contractor to uncover such material, notify the Owner's Representative, and allow ample time for classification and cross sectioning of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the Owner’s Representative for the areas of work in which such deposits occur.
C. Unauthorized Excavation: Removal of any material beyond horizontal and vertical limits indicated on the Drawings or as specified herein, without the prior approval of the Engineer.
D. Scaling: Scaling shall be considered the removal of loose and broken rock from the face of rock cuts by mechanical means. Scaling shall be included in Rock Excavation item as defined above.
E. Blasting Specialty Contractor: A subcontractor approved by the Engineer retained by the Contractor performing all work related to drilling and blasting for rock excavating.
F. Independent Specialty Condition Survey Contractor: A subcontractor approved by the Engineer retained by the Contractor to perform pre and post blast condition surveys of nearby structures.
G. Independent Specialty Condition Seismic Survey Contractor: A subcontractor approved by the Engineer retained by the Contractor to perform seismic vibration monitoring on-site and off-site at locations specified or designated by the Engineer.
ROCK REMOVAL PAGE 2 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312316.26 Rock Removal.docx SECTION 312316.26
H. Pre-splitting: A controlled blasting method in which a smooth excavation face is created by simultaneously blasting a single row of closely spaced holes along the excavation line prior to blasting the remainder of the holes in the blast pattern. Pre-splitting blast holes shall be a minimum of 3 inches diameter at a center-to-center spacing not exceeding 24 inches.
I. Line Drilling: A controlled blasting method in which a single row of closely spaced, unloaded holes are drilled along the neat excavation line to create a plane of weakness which the primary blast can break. Center-to-center spacing of line drilled holes shall be no more than twice the hole diameter.
1.4 REGULATORY REQUIREMENTS
A. The Blasting Specialty Contractor shall obtain all required permits, certificates, and licenses (city, state, local, etc.) prior to the commencement of any blasting operations.
B. Blasting safety procedures and operations shall comply with Title 29 Code of Federal Regulations Part 1910.109, and all other applicable state and local standards and regulations.
1.5 PROJECT/SITE CONDITIONS
A. Existing Conditions: Existing physical conditions as defined for design purposes are noted on the Drawings and are described in the Information Available to Bidders section of the Contract Documents.
1.6 SEQUENCING AND SCHEDULING
A. Work associated with blasting shall be performed in accordance with the following general sequence:
1. Complete and submit pre-blast survey.
2. Notify all appropriate authorities having jurisdiction of proposed activities.
3. Prepare site for blasting.
4. Notify affected utility owners, operators and nearby residents as required in Part 3 "Execution."
5. Complete test blast program simultaneously with seismic monitoring.
6. Complete production blasting work simultaneously with seismic monitoring.
7. Complete and submit post-blast survey.
1.7 MAINTENANCE
A. Any and all damage caused by the Blasting operations shall be repaired or replaced to the property Owner’s and Engineer’s satisfaction at the expense of the Blasting Specialty Contractor within 30 days of completion of the Post-Blast Survey.
PART 2 – PRODUCTS (NOT APPLICABLE)
PART 3 – EXECUTION
3.1 PREPARATION
A. All personnel working on-site shall be instructed as to the nature, times, duration, site safety, and warning signals concerning blasting operations.
B. Local residents within the Pre-Blast Survey area shall be notified at least 48 hours prior to initial blasting operations and provided with the name and phone number of one full-time, on-site contact
ROCK REMOVAL PAGE 3 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312316.26 Rock Removal.docx SECTION 312316.26 person designated by the Contractor for handling all complaints and inquiries. Residents shall be notified of blast schedule and changes on at least a weekly basis throughout the duration of blasting operations. Residents shall also be informed of warning signals identifying an upcoming blast and all-clear signals following completion of a blast as outlined in Site Safety Plan.
C. Explosives and blasting caps shall not be brought onto the site or used without appropriate permits, licenses, certificates, and/or prior written approval of authorities having jurisdiction. The Specialty Contractor is solely responsible for handling, storage, and use of explosive materials in accordance with regulatory and permit requirements.
3.2 ROCK REMOVAL
A. Remove rock as indicated by the Drawings and as necessary for the installation of the Work. Provide sufficient clearance, within the limits specified, for the proper execution of the Work.
B. Remove rock to lines and subgrade elevations indicated to permit installation of permanent construction without exceeding the following dimensions:
1. 24 inches outside of concrete forms other than at footings.
2. 12 inches outside of concrete forms at footings.
3. 6 inches outside of minimum required dimensions of concrete cast against grade.
4. Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments.
5. 6 inches beneath bottom of concrete slabs on grade.
6. 6 inches beneath pipe in trenches, and the greater of 24 inches wider than pipe or 42 inches wide.
C. Fill areas of over-excavated rock to the proposed subgrade elevations as required by Drawings with selected fill in accordance with Section “Trenching and Backfilling” or Section “Earth Moving” Over-excavation beneath foundations shall be filled with footing concrete (f'c = concrete compressive = 3000 psi minimum).
D. A test blast shall be performed and monitored prior to commencement of production blasting. Test blast records and seismic records shall be reported to the Engineer prior to continuation of blasting. If test blast indicates that the blasting plan requires modification, such changes shall be reported to the Engineer immediately. Reporting this information to the Engineer shall not relieve the Contractor(s) of complete responsibility for the successful performance of the method(s) used, nor shall the reporting constitute approval by the Engineer for the proposed plans.
E. The Seismic Specialty Contractor shall monitor the vibrations and sound levels caused by Blasting.
F. Seismic monitoring shall be performed for each blast, unless specified otherwise. Monitoring shall be performed at the nearest structure or at locations designated by the Engineer on each field day.
G. If the ground vibrations exceed specified tolerances the Blasting Specialty Contractor’s operations shall cease immediately and remain stopped until the Blasting Specialty Contractor has taken all necessary additional measures to protect adjacent property and personnel.
H. All finished rock faces as shown on the Plans shall be line drilled/presplit test sections shall be exposed at the outset of drilling and blasting for the evaluation of the rock faces by the Engineer. The Contractor shall to completely expose the rock face in the test section prior to production blasting operations.
ROCK REMOVAL PAGE 4 OF 4
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312316.26 Rock Removal.docx SECTION 312316.26
I. All rock slopes shall be thoroughly scaled to the satisfaction of the Engineer. Scaled rock slopes shall be stable and free from possible hazards of falling rocks or rock slides that endanger public or worker safety. If such conditions exist after proper scaling, remedial treatment shall be provided by the Contractor or Blasting Specialty Contractor at no additional expense to the Owner. In the event that natural conditions such as wedge instability are encountered, remedial treatment shall be provided as necessary to stabilize the rock slope. Such treatment may include, but is not necessarily limited to, rock bolting or grouting, shoring, or shotcreting. Large scale ripping shall not be permitted within 10 feet of any final rock slope prior to presplitting or line drilling.
J. The Blasting Specialty Contractor shall use steel or rubber blasting mats as may be necessary to control fly-rock.
3.3 EXCAVATION TOLERANCES
A. Blast hole drilling and overblast beyond the vertical limits indicated shall be less than 1.5 feet.
B. Rock removal limits shall include all materials defined as rock whether removal is accomplished by mechanical means (e.g., ripping) or by drilling and blasting.
3.4 VIBRATION AND SOUND TOLERANCES
A. Blast vibrations shall be maintained within safe limits as defined by the Peak Particle Velocity (inch per second) versus Blast Frequency (Hertz) as described in the United States Bureau of Mines Publication RI-8507, Appendix B ("Siskind Curve").
B. Sound levels shall not exceed 130 dB at the nearest structure.
C. Vibrations levels at new concrete structures shall be limited to the following levels:
AGE OF CONCRETE MAXIMUM ALLOWABLE
(DAYS) PPV
Less than 1/2 0.1 (in./sec.)
1/2 to 7 1.0 (in./sec.)
Greater than 7 2.0 (in./sec.)
DEWATERING PAGE 1 OF 3
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312319 Dewatering.docx SECTION 312319
SECTION 312319 – DEWATERING
PART 1 – GENERAL
1.1 SUMMARY
A. This section includes provisions for a dewatering system to continuously lower and control groundwater levels and hydrostatic pressures in order to maintain near-dry conditions for construction of the work as shown on the plans and specified herein.
1.2 JOB CONDITIONS
A. Site soil boring data and samples, soil laboratory testing, and any soil reports shall be made available to prospective bidders for study and review. Bidders must make their own interpretation of subsurface conditions that may affect methods or the cost of construction of the Work.
PART 2 – PRODUCTS
2.1 DEWATERING SYSTEM
A. Provide a dewatering system of adequate size and capacity to lower and maintain the groundwater at the specified level. The system shall include standby pumps and power source for continuous operation.
1. Dewatering system shall consist of wellpoints, deep wells, cut-off walls, riser pipes, swing joints, header lines, valves, pumps, discharge lines, and all other necessary fittings, accessories and equipment for a complete operating system. Provide hole punches, sand backfill, and clay plugs as required by soil conditions.
B. Observation Wellpoints: Provide groundwater reading wells or piezometers to monitor the groundwater level, as indicated on the approved Shop Drawings or as directed by the Engineer.
C. Sand: Clean concrete sand conforming to ASTM C33.
PART 3 – EXECUTION
3.1 PREPARATION
A. Install the observation well points at locations indicated on approved Shop Drawings or where directed by the Engineer. Install observation wellpoints in accordance with manufacturer's printed instructions and in accordance with approved Shop Drawings. Provide sand backfill around wellpoint. Test each observation wellpoint to verify that the installation is performing properly.
B. Protect observation well standpipes from damage by construction operations and maintain accessibility to them. Maintain reading wells until groundwater is allowed to return to its normal level.
3.2 INSTALLATION
A. Install the dewatering system in accordance with approved Shop Drawings and as required by site conditions. Locate elements of the system to allow a continuous dewatering operation without interfering with the installation of any permanent project Work.
DEWATERING PAGE 2 OF 3
V:\ProjectSpecs\084837.000\Final\OTB Submittal - Current\312319 Dewatering.docx SECTION 312319
3.3 OPERATION
A. Keep the system in continuous operation from the time excavation is started in the dewatering area (or before if required by site conditions to lower the groundwater to the elevations specified) until the time backfilling is completed at least 2 feet above the normal groundwater level.
1. Do not discontinue dewatering operations without specific approval from the Engineer.
2. Rates of groundwater withdrawal during dewatering operations, shall at all times be below the rate at which soil particles are removed from the existing soils.
B. In the event excavation proceeds subsequent to dewatering as specified above, and the groundwater level is found to be within two feet of the excavation, the dewatering Contractor shall immediately continue to dewater as specified herein, including, but not limited to, additional dewatering and monitoring facilities, at no additional cost to the Owner. The excavation shall not be allowed to proceed below groundwater.
3.4 FIELD CONTROL
A. Maintain a careful check to detect any settlement in existing adjacent Work. Notify the Engineer of any signs of settlement.