Addendum_1_Carpet_Installation_061915-2.docx

DOCX document 14 KB Posted

Attached to
Carpet Installation
Solicitation number
Carpet_Installation_061915-2
Issued by

About this file

Addendum 1 Carpet Installation 061915-2 - addresses comments and questions during the pre-bid meetings

View the file

Other files

File Type Posted
JC_Vendor_Packet_2015.pdf PDF
RFQ_-_Carpet_Services_2015.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #1

Carpet Installation 061915-2
Inland Empire Job Corps Center
3173 Kerry St
San Bernardino CA 92407

Date: July 2, 2015

This Addendum forms a part of the Contract Documents and is issued for the purpose of changing the scope of work of this project and/or provides additional essential information. Acknowledge receipt of Addendum in the space provided on the Bid Form.

Clarifications from Pre Bid meeting:

Item 1:

Task #3 Leadership Development Office Building F- Remove carpet on wall below closets, but do not install carpet tiles in its place. The center may have tile setting trade work on that area.

Item 2:

Task #2 Programs Area Building – In small copier room carpet should be flush with glass entrance door (building A).

Item 3:

Task #1 Room G-9 Classroom/Library – In library area walls do not get cove base due to the book cases. The book cases will not be removed.

Item 4:

Task #4 Maintenance/Transportation Operations Area Building I – top of stairs and in the two small offices carpet will be removed and ACT eliminated. Floor will be plywood. Contractor to install quarter inch (¼ “) csx grade plywood over existing and install carpet tiles. Furniture in mini conference area will be removed however, two large desks cannot be moved. Center staff will coordinate with carpet installers to move desk from one side of room to the other as carpet removal and installation takes place.

Item 5:

Spare carpet tiles: selected Contractor shall provide one box (no less than 10 tiles) of spares per location (provided to Facilities Manager at time of contract sign off).

Item 6:

Selected Contractor shall complete the construction completion notices that will be presented to successful bidder.

The rest of the Request for Quotation remains unchanged.