cap dev board lee county dixon correctional center 120-075-079-revised2-solicitation-plumbing.pdf
PDF 173 KB Posted
- Attached to
- Upgrade Water Treatment and Replace SCADA System
- Solicitation number
- 120-075-079-01
- Issued by
- Lasalle County, Illinois
About this file
This is a solicitation document issued by the Illinois Capital Development Board for a plumbing project at Dixon Correctional Center in Lee County. The project involves upgrading the water treatment system and replacing the SCADA (Supervisory Control and Data Acquisition) system at the facility located at 2600 N Brinton Ave, Dixon, Illinois. The solicitation is for a single-prime plumbing contractor and follows a sealed bid process. A non-mandatory but strongly encouraged prebid meeting is scheduled for June 10, 2026 at 10:30 a.m. at Dixon Correctional Center Control Building BC-122, with all contractors required to meet at the sallyport entrance off North Brinton Avenue for facility access. Sealed bids are due on August 18, 2026 at 11:00 a.m. Questions must be submitted by July 7, 2026. Plans are available from Stanley Consultants, 8501 Higgins Road, Suite 730, Chicago, Illinois 60631 for a $100 deposit.
The project is classified as Plumbing Remodeling and Rehabilitation with an estimated trade cost range of less than $7,000,000. A Project Labor Agreement applies to this project, and MBE/WBE subcontracting and supplier goals are required of all bidders. The project manager is Drew Stephenson, who can be contacted at (217) 720-0701 or drew.m.stephenson@illinois.gov for additional information. The original posting date was June 2, 2026, with the document being revised on July 17, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Illinois
CAPITAL DEVELOPMENT BOARD
120-075 Dixon Correctional Center - Lee County 120-075-079-01 | Upgrade Water Treatment and Replace SCADA System MBE/WBE Subcontracting and Supplier Goals Apply
ORIGINAL POSTING BID DATE: 6/2/2026
Prebid Meeting Date 6/10/2026 at 10:30 A.M.
Prebid Meeting Mandatory No Location Dixon Correctional Center, Control Building BC-122, 2600 N
Brinton Ave, Dixon, IL 61021. For access, all contractors must meet at the sallyport entrance off N Brinton Ave.
Plans Available From Stanley Consultants 8501 Higgins Road, Suite 730 Chicago, IL 60631
Plan Deposit 100.00 Project Manager Stephenson, Drew Phone Number (217) 720-0701 Email drew.m.stephenson@illinois.gov Special Instruction Single-Prime (Plumbing) Project Delivery Method. A Project Labor
Agreement (PLA) is applicable to this project. This is a non-mandatory prebid, but bidders are strongly encouraged to attend this meeting on Wednesday, June 10, 2026 at 10:30 A.M. at the Dixon Correctional Center, Control Building BC-122, 2600 N Brinton Ave, Dixon, IL 61021.
For access, all contractors must meet at the sallyport entrance off N Brinton Ave.
PLA Applicable Yes Delivery Method? Single Prime Bid URL Bidding Details
Bid Due Date Bid Due Time Trade Cost Range Bid Type Post Date 8/18/2026 11:00 AM Plumbing-
Remod & Rehab (82)
Less than $7,000,000
Revised 7/17/2026
File details come from the government source that posted it. Updated .