About this file
This document is a Request for Proposal (RFP) issued by the Charter Township of Canton, Michigan, for floor coating installation at Fire Station No. 3, located at 520 N Denton. The project involves removing the existing epoxy coating and installing a new floor coating system during the summer months, with work to be performed while keeping the fire station operational. The mandatory site visit is scheduled for June 3rd, 2025 at 12 noon, and proposals are due by 3:00 p.m. on June 12th, 2025, to be submitted online through the bidnetdirect.com/MITN Purchasing Group web portal.
The project requires a detailed proposal including individual costs per color, demonstrated experience with floor coatings at a minimum of three fire stations, and a comprehensive warranty description. Contractors will be evaluated on a 100-point scale, with points allocated for cost proposal (30 points), proven experience and methods (40 points), references (20 points), and proposal quality (10 points). The specified floor coating system is the Sikafloor PurCem Self-Leveling Broadcast System, a medium-duty, three-component polyurethane-based coating with specific performance requirements. Contractors must provide proof of pre-qualification, have at least five years of experience, and comply with extensive technical specifications, including surface preparation, application conditions, and environmental requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Charter Township of Canton
Request For Proposal for
FLOOR COATING INSTALLATION – FIRE STATION # 3
Contact: Tom Gaffka E-mail: tom.gaffka@cantonmi.gov
Telephone: (734) 394-5314
Date Issued: 5/29/2025
Due Date & Time: 3:00 p.m., Thursday, June 12, 2025 mailto:tom.gaffka@cantonmi.gov
The deadline established for the receipt of your sealed proposal is 6/12/2025 at 3:00 p.m. The proposal is to be submitted online on the bidnetdirect.com / MITN Purchasing Group web portal.
SECTION # 1 GENERAL REQUIREMENTS & INSTRUCTIONS
1. SUBMISSION OF OFFERS: All offers should be submitted online in the bidnetdirect.com / MITN Purchasing Group web portal. Any submittal received in the Clerk’s Office will not be considered. No offer may be modified after acceptance. No offer may be withdrawn after opening for a period of sixty days unless otherwise specified. The proposal must include all costs.
2. EXECUTION OF OFFER: Offer shall contain a manual signature in the space(s) provided of a representative authorized to legally bind the offeror to the provisions therein.
3. EXECUTION OF ACCEPTANCE: Canton Township legally recognizes acceptance of formal offer when a written contract is signed by both parties. Offerer is not to assume that the Canton Board of Trustees resolution approving the bid or proposal is a binding contract.
4. OPENING & RECORDING: Opening shall be public in the Clerk’s Office immediately following the advertised deadline date and time for receipt of submittals.
5. INTEGRITY: Canton Township does not discriminate on the basis of race, color, national origin, sex, religion, age or disability in employment or the provision of services.
6. TABULATION: Bid results will be posted on the MITN website at https://www.bidnetdirect.com/mitn/solicitations/open-bids/page1
7. BOARD AWARDS: As the best interest of Canton may require, Canton reserves the right to make award(s) by an individual item, group of items, all or none, or a combination thereof; on a geographical basis and/or on a countrywide basis with one or more supplier(s) or provider(s); to reject any and all offers or waive any irregularity or technicality in offers received. Offerors are cautioned to make no assumptions. Any or all awards made as a result of this invitation shall conform to applicable ordinances and policies of Canton Township. Bid awards will be posted on the Township’s website at www.cantonmi.gov
8. BRAND NAME OR EQUAL: If items requested by this invitation have been identified in the specifications by a brand name “OR EQUAL” description, such identification is intended to be descriptive and not restrictive and is to indicate the quality and characteristics of products that will be acceptable. Offers proposing “equal” products will be considered for award if such products are clearly identified in the offer and are determined by Canton to meet fully the salient characteristic requirements listed in the specifications.
https://www.bidnetdirect.com/mitn/solicitations/open-bids/page1 http://www.cantonmi./
9. PRICING: Unless otherwise specified prices offered shall remain firm for a period of at least sixty (60) days; all pricing of goods shall include FOB Canton Township, all packing, handling, shipping charges and delivery to any point(s) within Canton to a secure area or inside delivery.
10. PAYMENT TERMS: Canton Township will remit full payment on all undisputed invoices within thirty (30) days from receipt by the appropriate person(s) of the invoice or receipt of all products or services ordered.
11. INCURRED EXPENSE: This invitation does not commit Canton to make an award nor shall Canton be responsible for any cost or expense which may be incurred by any respondent in preparing and submitting a reply, or any cost or expense incurred by any respondent prior to the execution of a purchase order or contract agreement.
12. QUESTIONS/ ADDENDA: Any questions concerning the conditions or specifications shall be directed to the designated contact person. Addenda items will be posted on the township website, on the Purchasing Division page under Requests for Bids, Proposals and Qualifications. It is the bidder’s responsibility to check and verify that addenda have been issued. Failure to acknowledge addenda may result in the offer not being considered.
13. CLARIFICATION/CORRECTION OF ENTRY: Canton reserves the right to allow for the clarification of questionable entries and the correction of OBVIOUS MISTAKES.
14. INSURANCE: The successful bidder is required to furnish evidence of the following insurance requirements in accordance with Canton’s Risk Management Policy O:02.
Work may not commence until the Certificates of Insurance have been received. The coverage requirements are as follows:
Workers’ Compensation Insurance: The Contractor shall procure and maintain during the life of this contract, Workers’ Compensation Insurance, including Employers’ Liability Coverage, in accordance with all applicable statutes of the State of Michigan.
Commercial General Liability Insurance: The Contractor shall procure and maintain during the life of this contract, Commercial General Liability Insurance on an “Occurrence Basis” with limits of liability not less than $ 1,000,000 per occurrence and aggregate combined single limit, Personal Injury, Bodily Injury, and Property Damage. Coverage shall include the following extensions:(A) Contractual Liability; (B) Products and Completed Operations; (C) Independent Contractors Coverage; (D) Broad Form General Liability Extensions or equivalent.
Motor Vehicle Liability: The Contractor, or its subcontractors, shall procure and maintain during the life of this contract Motor Vehicle Liability Insurance, including Michigan No-Fault Coverage, with limits of liability not less than $ 1,000,000 per occurrence combined single limit, Bodily Injury, and Property Damage. Coverage shall include all owned vehicles, all non-owned vehicles, and all hired vehicles.
Additional Insured: Commercial General Liability Insurance as described above, shall include an endorsement stating that the following shall be Additional Insured: The Charter Township of Canton, all elected and appointed officials, all employees and volunteers, all boards, commissions, and/or authorities and board members, including employees and volunteers thereof.
Cancellation Notice: The Insurance coverage described above, shall include an endorsement stating the following: “It is understood and agreed that Thirty (30) days Advance Written Notice of Cancellation, Non-Renewal, Reduction, and/or Material Change shall be sent to: Jeanette Aiello, 1150 Canton Center S., Canton MI, 48188.
Indemnification: To the fullest extent permitted by law, the (name of contractor) agrees to defend, pay on behalf of, indemnify, and hold harmless the Charter Township of Canton, its elected and appointed officials, employees and volunteers, and others working on behalf of the Charter Township of Canton against any and all claims, demands, suits, or loss, including all costs connected therewith, and for any damages which may be asserted, claimed, or recovered against or from the Charter Township of by reason of personal injury, including bodily injury or death and/or property damage, including loss of use thereof, which arises out of or is in any way connected or associated with this agreement.
15. PUBLIC ACT 517 OF 2012: In accordance with Public Act 517 of the Public Acts of 2012, any Iran linked business is not eligible to submit a bid on a request for proposal with a public entity in Michigan. An “Iran linked business” includes the following:
(1) A person engaging in investment activities in the energy sector of Iran, including a person that provides oil or liquefied natural gas tanker or products used to construct or maintain pipelines used to transport oil or liquefied gas for the energy section of Iran; and
(2) A financial institution that extends credit to another person, if that person will use the credit to engage in investment activities in the energy sector of Iran.
For purposes of this prohibition, “person” includes an individual, corporation, company, limited liability company, business association, partnership, society, trust, or any other non-governmental entity, organization or group. It also includes a governmental entity or instrumentality of a governmental entity, or any successor, subunit, parent company or subsidiary of, or company under common ownership or control with and of the foregoing.
REQUEST FOR PROPOSAL
Fire Station No. 3 Floor Coating Installation
520 N Denton, Canton, Michigan 48188
INTRODUCTION
The Township has chosen to issue this Request for Proposal (RFP) to seek a company(s) to provide floor coating installation at Canton Fire Station No. 3.
The original construction of the station was completed in 2005. Currently, the concrete surface of the fire truck bay area has an epoxy finish.
Refer to Attachment A - Fire Station 3 Floor Plan
SITE VISITS AND QUESTIONS
Any questions regarding the material contained in the RFP, please e-mail Tom Gaffka at Tom.Gaffka@Cantonmi.gov
Amendments will be issued for clarification on the Township website should the Township deem it necessary to do so.
SCOPE OF WORK
The fire station shall remain in service during the floor coating process. Areas will be taken out of service to provide contractors with space to work. The areas of work and timeframes will be negotiated with the selected contractor. For the purpose of responding to this RFP the contractor should anticipate that the work is done during the summer months and that the work can be performed with no more than 2 truck bays out of service at any one time. The non-bay areas shall be taken out of service with the least amount of disruption to the fire station operations.
Demolition shall include, but not limited to, the following:
• Areas of exposed concrete surface shall be cleaned of oils and debris.
• Areas of existing epoxy coated surface shall be completely cleared of all coating materials. The means and methods of removal shall be determined by the contractor. A description of the means and methods shall be provided in the contractor's proposal.
Refer to Attachment A: Site plans Highlighted work areas.
• All removed materials shall be removed from the site for proper disposal.
• Any manufacturer's recommendations for surface preparations shall be completed prior to coating installation. A description of the means and methods shall be provided in the contractor’s proposal.
Installation shall include, but not limited to, the following:
• The installation shall be done in accordance with/or equivalent to the specification provided in Attachment B. A description of the means and methods of installation shall be provided in the contractor's proposal. The selection process will be based on the contractor’s proven experience with the product at fire stations.
A warranty description shall be provided:
• The selection of the contractor shall include an evaluation of the proposed installation and product warrantees provided in response to this RFP.
Proposal Breakdown:
• The proposal should provide individual cost per color from diagram in Attachment A.
SCHEDULE:
Mandatory Site Visit will begin at the Fire station at 520 N Denton on June 3rd, 2025 at 12 noon.
Contractor to provide recommended construction schedule as part of proposal.
QUALIFICATIONS:
Experience Requirements:
It's very important that the Contractor's team performing the work on the Township property have a significant amount of experience working on similar projects. The Contractor must be able to provide proof of experience with successful coating installations at a minimum of 3 fire stations.
EVALUATION CRITERIA
All proposals shall be evaluated by a committee comprised of appropriate Canton Township personnel using a standard evaluation scoring as follows:
Criteria Maximum Score
Contractors' cost proposal and warrantee description: 30
Proposers' means and methods to perform work; proven Experience with floor coatings: 40
Proposers’ references (minimum of 3 fire stations): 20
Quality of Contractor ' s proposal and interview (if selected): 10 Total maximum score: 100
Fire Station No. 3
Floor Coating Installation Cost Sheet
520 N Denton rd, Canton, Michigan 48188
COMPANY NAME
ADDRESS
Total Amount Area 1 $ _____________________________
Total Amount Area 2 $______________________________
Total Amount $____________________________________
For Fire Station No. 3 Floor Coating Installation
520 N Denton rd, Canton, Michigan 48187
Attachment A
Fire Station No. 3 Floor Plan
SIKAFLOOR PURCEM SELF-LEVELING BROADCAST SYSTEM Section 03 99 25 Medium Duty Self-Leveling Polyurethane Screed Broadcast RESINOUS FLOORING and Sealed finish of 1/4 in. Page 1 of 8
FIRE STATION
Edition 01.06.2019
Part 1 General
1.1 SECTION INCLUDES
A. Labor, products, equipment and services necessary for resinous flooring Work in accordance with the Contract Drawings covering the following components:
.1 Primer: Substrate priming is normally not required under typical circumstances.
Substrate porosity/condition determines if primer/scratch coat is required.
.2 Self-Leveling Mortar: Sikafloor® 24NA PurCem.
.3 Grout Coat: Sikafloor® 264.
.4 Topcoat: Sikafloor 340.
1.2 RELATED SECTIONS
A. Section 03 30 00 - Cast-in-Place Concrete.
B. Section 03 01 00 - Concrete Rehabilitation.
C. Section 03 39 00 - Concrete Curing.
1.3 REFERENCES
A. ASTM C579, Standard Test Methods for Compressive Strength of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes.
B. ASTM D2240, Standard Test Method for Rubber Property—Durometer Hardness.
C. ASTM D2369, Standard Test Method for Volatile Content of Coatings.
D. ASTM D4060, Standard Test Method for Abrasion Resistance of Organic Coatings by the Taber Abraser.
E. ASTM D4541, Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers.
F. For additional standards please refer to Product Data Sheets
1.4 SUBMITTALS
A. Comply with Section 01 33 00 - Submittal Procedures.
B. Product Data: Submit manufacturer's product data, including physical properties and colors available.
C. Manufacturer’s Safety Data Sheet for each product being used.
D. Product Samples: Submit Architectural Standard samples representative of the final finish, as applied. The Standard shall be approved in writing by the Architect and shall be the final standard of acceptance of the finish.
E. Maintenance Instructions: Submit manufacturer's maintenance instructions.
and Sealed finish of 1/4 in. Page 2 of 8
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications:
.1 Acceptable Manufacturer: Sika Corporation, 201 Polito Drive, Lyndhurst, NJ 07071
.1 No request for substitution shall be considered that would change the generic type of system specified. Equivalent materials of other manufacturers may be substituted only on approval of the Architect or Engineer. Requests for substitution will be considered only if submitted 10 days prior to bid date. Requests shall include the respective manufacturer’s technical literature for each product giving the name, generic type, descriptive information, recommended dry film thickness (DFT), Material Safety Data Sheet (MSDS), and certified test reports showing results to equal performance criteria of products specified herein. Contact: Ray VanZytveld 616 666 5942
B. Applicator Qualifications:
.1 Pre-Qualification: Each bidder for this project shall be pre-qualified and approved in writing by the material manufacturer.
.2 Applicator Experience: Each bidder must have a minimum 5 years experience in the application of the type of system specified. Contractor shall submit a list of five projects of similar size, scope and complexity.
.3 Approved Installation Contractors: ProTech Concrete Coatings
P:586 201 5132.
E: info@protechconcretecoatings.com
C. Mock-Up:
.1 Construct one 100 sq.ft. (10 sq.m.) mock-up of each type and color of resinous flooring in location acceptable to Architect/Engineer to demonstrate quality of finished system, complying with manufacturer's instructions.
.2 Arrange for Architect/Engineer's review and acceptance, obtain written acceptance before proceeding with Work.
.3 Upon acceptance, mock-up shall serve as a minimum standard of quality for the balance of the work of this Section. Mock-up shall be left in place for the duration of the work.
D. Pre-application Meeting: Convene a pre-application meeting two (2) weeks before start of application of floor coating. Require attendance of parties directly affecting work of this section, including Contractor, Architect, applicator, and manufacturer's representative. Review surface preparation, priming, application, curing, protection, and coordination with other work.
1.6 DELIVERY, STORAGE AND HANDLING
A. Delivery:
.1 Deliver materials to site in manufacturer's original, unopened containers and packaging, with labels clearly identifying product name, manufacturer, batch or lot number, and date of manufacture.
and Sealed finish of 1/4 in. Page 3 of 8
.2 Material should be delivered to job site and checked for completeness and shipping damage prior to job start.
B. Storage:
.1 Store materials in accordance with manufacturer’s written instructions.
.2 Keep containers sealed until ready for use. Material should be stored in a dry, enclosed, protected area from the elements.
.3 Do not subject material to excessive heat or freezing.
.4 Shelf life: Established based on manufacturer’s written recommendation for each material being used.
C. Handling: Protect materials during handling and application to prevent damage or contamination.
D. Condition materials for use accordingly to manufacturer’s written instructions prior to application.
E. Record material lot number and quantity delivered to jobsite/storage.
1.7 SITE CONDITIONS
A. Do not install the Work of this Section outside of the following environmental ranges with Manufacturers’ written acceptance:
.1 Material Temperature: Precondition material for at least 24 hours between 65° to 75°F (18° to 24°C)
.2 Ambient Temperature: Minimum/Maximum 50˚/85˚F (10˚/30˚C)
.3 Substrate Temperature: Minimum/Maximum 50˚/85˚F (10˚/30˚C). Substrate temperature must be at least 5˚F (3˚C) above measured Dew Point.
.4 Mixing and Application attempted at Material, Ambient and/or Substrate Temperature conditions less than 65˚F (18˚C) will result in a decrease in product workability and slower cure rates.
.5 Relative Ambient Humidity: Minimum ambient humidity 30%, maximum ambient humidity 75% (during application and curing)
.6 Measure and confirm Substrate Moisture Content, Ambient Relative Humidity, Ambient and Surface Temperature and Dew Point.
B. Substrate moisture:
.1 Moisture content of concrete substrate must be ≤ 4% by mass as measured with a Tramex® CME/CMExpert type concrete moisture meter.
.2 Additionally, relative humidity tests may be conducted per ASTM F2170 and values must be ≤ 85%.
.3 If moisture content of concrete substrate is > 4% by mass as measured with Tramex® CME/CMExpert type and/or if relative humidity tests per ASTM F2170 exceed values > 85%, consider moisture mitigation systems or moisture tolerant primer.
C. Utilities, including electric, water, HVAC and permanent lighting to be supplied by General Contractor
D. Maintain constant ambient room temperature of plus or minus 15ºF (plus or minus 7ºC) with a minimum temperature of 50ºF (10ºC) and maximum temperature of 85ºF (30ºC).
Maintain constant ambient room temperature for 48 hours before, during and after installation, or until cured. Do not apply while ambient and temperatures are rising.
and Sealed finish of 1/4 in. Page 4 of 8
E. Erect suitable barriers and post legible signs at points of entry to prevent traffic and trades from entering the work area during application and cure period of the floor.
F. Protection of finished floor from damage by subsequent trades shall be the responsibility of the General Contractor.
G. Insure adequate ventilation and air flow.
1.8 WARRANTY
A. Manufacturer’s warranty covering the resinous flooring against defects in materials for one year from date of installation.
Part 2 Products
2.1 MANUFACTURER
A. Manufacturer shall be certified under ISO 9001: 2008 All liquid materials, including primers, resins, curing agents, finish coats, and sealants are manufactured and tested under an ISO 9001:2008 registered quality system.
B. Approved Manufacturer shall be Sika Corporation, Industrial Flooring, 201 Polito Avenue, Lyndhurst, NJ 07071, Phone 201.933.8800, Fax 201.933.6225, www.sikafloorusa.com
2.2 SYSTEM
A. Resinous flooring system: Sikafloor 24NA PurCem is a self-leveling, medium to heavy duty, solid color, three-component, water dispersed polyurethane-based/cement and aggregate screed. Typically applied at 3/16in.
.1 Primer: Substrate priming is normally not required under typical circumstances.
Substrate porosity/condition determines if primer/scratch coat is required
.2 Self-Leveling Mortar: Sikafloor 24NA PurCem applied at 3/16 in.
.3 Grout Coat: Sikafloor 264 applied between 16-20 mils.
.4 Topcoat: Sikafloor 340 applied @ 3.5 to 5 mils.
2.3 MATERIALS
A. Primer: Substrate priming is normally not required under typical circumstances.
Substrate porosity/condition determines if primer/scratch coat is required
B. Self-Leveling Mortar: Sikafloor-24NA PurCem is a self-levelling, medium to heavy duty, solid color, three-component, water dispersed polyurethane-based / cement and aggregate screed. It is designed to provide excellent resistance to abrasion, impact, chemical attack and other physical aggression. Sikafloor-24NA has the following properties:
.1 Softening Point: 266°F (130°C)
.2 Density (ASTM C905): 16.84 lb./US gal. (2.02 kg/L)
.3 Flow: Approx. 11.8 in (300 mm)
.4 Service Temperature: - 40°F (- 40°C) min. / 212°F (100°C) max.
.5 Compressive Strength (ASTM 579) 24 hrs 3,191 psi (22 MPa) and Sealed finish of 1/4 in. Page 5 of 8
7 days 5,366 psi (37 MPa)
28 days 5,802 psi (40 MPa)
.6 Tensile Strength (ASTM C307): 1,045 psi (6.5 MPa)
.7 Flexural Strength (ASTM C580): 2,314 psi (14.7 MPa)
.8 Pull-off Strength (ASTM D4541): > 254 psi (> 1.75 MPa) (substrate failure)
.9 Thermal Compatibility (ASTM C884): Pass
.10 Shore D Hardness (ASTM D2240): 80 - 85
.11 Indentation (MIL -PRF -24613): ~ 0%
.12 Impact Resistance (ASTM D2794): 5.02 ft - lb (6.81 joules) at 1/8” (3 mm) of thickness
.13 Abrasion Resistance (ASTM D4060): CS-17/1,000 cycles/2.2 lb (1,000 g) -0.0052 oz (-0.110 g)
H-22/1,000 cycles/2.2 lb (1,000 g) -0.080 oz ( -2.26 g)
.14 Coefficient of Friction (ASTM D1894-61T): Steel 0.3
Rubber 0.5
.15 Coefficient of Thermal Expansion (ASTM D696): 0.89 x 10-5 in/in/ºF
(1.6 x 10-5 mm/ mm/ºC)
.16 Water Absorption (ASTM C413): 0.10%
.17 Flexural Modulus (ASTM C580): 629,025 psi (4,335.7 MPa)
.18 Resistance to Fungi Growth (ASTM G21): Rated 0 (no growth)
.19 Resistance to Mold Growth (ASTM D3273): Rated 10 (highest resistance)
.20 VOC’s Components A+B+C: < 5 g/L
C. Broadcast Aggregate: Sikadur 508 or 509 silica sand.
D. Grout Coat: Sikafloor 264 is a 100 % solids, low VOC, low odor, high gloss epoxy resin used to create premium quality high build coatings, broadcast or trowel-applied surfacing systems
.1 Pull-off Strength (ASTM D4541): > 400 psi (2.7 MPa) with 100% concrete failure.
.2 Shore D Hardness (ASTM D2240): 78 - 82 at 7 days.
.3 Solid Content: ~ 100% (by volume) / ~ 100% (by weight).
.4 VOC Content (ASTM D2369): ≤ 50 g/L.
.5 Compressive Strength (ASTM C579): 7,250 psi (50 N/mm²) at 28 days.
.6 Flexural Strength (ASTM C580): 2,900 psi (20 N/mm²) at 28 days.
E. Topcoat: Sikafloor 340 is an aliphatic urethane with excellent chemical resistance and UV resistance coating in [Refer to Sikafloor color chart] color with the following properties:
A.
.1 VOC Content (ASTM D2369): ≤ 280 g/L.
.2 UV Light Resistance - Q-U-V Accelerated Weather Tester: Excellent and Sealed finish of 1/4 in. Page 6 of 8
.3 Abrasion Resistance (ASTM D4060): 18 mg loss (CS-17 Wheel, 1000 gm load, 1000 cycles).
.4 Flexibility: Bent on 1/8” conical
.5 Gloss at 60°: 90
.6 Slip Resistance: Equivalent to ASTM D2047 Passes.
B. Joint sealant: Sikaflex 2c.
Part 3 Execution
3.1 EXAMINATION
A. Examine surfaces to receive flooring system. Notify Architect/General Contractor/Owner/Owner’s representative if surfaces are not acceptable. Do not begin surface preparation or application until unacceptable conditions have been corrected.
Do not apply to substrate treatments for moisture, repair, or leveling not of the same Manufacturer.
B. Surface must be clean, sound and dry. Remove dust, laitance, grease, curing compounds bond inhibiting impregnations, waxes and any other contaminants. All projections, rough spots, etc. should be dressed off to achieve a level surface prior to the application.
C. Concrete substrate to have a minimum compressive strength of 3,500 psi (24 MPa) at 28 days and a minimum of 215 psi (1.5 MPa) in tension at time of application.
D. Substrate moisture:
.1 Measure and confirm Substrate Moisture Content, Ambient Relative Humidity, Ambient and Surface Temperature and Dew Point.
.2 Confirm and record above values at least once every 3 hours during installation, or more frequently whenever conditions change (e.g. Ambient Temperature rise/fall, Relative Humidity increase/decrease, etc.).
E. Ensure concrete substrate conforms to the minimum requirements of the flooring manufacturer.
F. Flooring system shall not be applied to sand-cement setting beds. Sand-cement beds shall be removed to structural concrete substrate and re-leveled/sloped as necessary to achieve grade and/or adequate drainage.
G. Flooring system shall not be applied to asphaltic or bitumen membranes, soft wood, aluminum, copper or fiberglass reinforced polyester/vinyl ester composites.
H. Application to glazed or vitrified brick and tile, structural wood, steel shall only be permitted with Manufacturer’s written recommendation.
3.2 SURFACE PREPARATION
A. Prepare surface to receive flooring systems in accordance with manufacturer's written instructions.
and Sealed finish of 1/4 in. Page 7 of 8
B. Remove dirt, oil, grease, wax, laitance, curing compounds, water-soluble concrete hardeners, and other surface contaminants. Remove sealers, finishes, and paints.
Remove unsound concrete by appropriate mechanical means.
C. Concrete: Shall be cleaned and prepared to achieve laitance-free and contaminant-free, open textured surface by shot blasting or equivalent mechanical means (CSP level as per ICRI guidelines and manufacturer’s written recommendation).
D. Chemical Surface Preparation: Chemical surface preparation (acid etching) is unacceptable and will void Manufacturer’s warranty.
E. Control joints and cracks: Provide repair and treatment of control joints and surface cracks utilizing manufacturer’s standard materials and installation details.
3.3 APPLICATION
A. Mix and apply material with strict adherence to manufacturer’s written installation procedures and coverage rates.
B. Follow Manufacturer’s written recommendations on terminations and connections to walls, drains, doorways, columns and floor-to-floor transitions.
C. Do not apply while ambient and substrate temperatures are rising.
D. Apply resinous flooring with care to ensure that no laps, voids, or other marks or irregularities are visible, and with an appearance of uniform color, sheen and texture, all within limitations of materials and areas concerned.
E. Match colors and textures of approved samples.
F. Install cove base [...] high with [...] radius in accordance with manufacturer’s written instructions.
3.4 CLEAN UP
A. Disposal of this product, solution and any by-products should at all times comply with the requirements of environmental protection and waste disposal legislation and any regional local authority requirements.
B. Empty containers should be taken to an approved waste handling site for recycling or disposal.
3.5 PROTECTION
A. Freshly applied material should be protected from dampness, condensation and water for at least 72 hrs.
B. Beware of air flow and changes in air flow. Introduction of dust, debris, and particles, etc. may result in surface imperfections and other defects.
C. Follow manufacturer’s written recommendation with respect to cure, wait time and return to service.
and Sealed finish of 1/4 in. Page 8 of 8
END OF SECTION
All information provided by Sika Corporation (“Sika”) concerning Sika products, including but not limited to, any recommendations and advice relating to the application and use of Sika products, is given in good faith based on Sika’s current experience and knowledge of its products when properly stored, handled and applied under normal conditions in accordance with Sika’s instructions. In practice, the differences in materials, substrates, storage and handling conditions, actual site conditions and other factors outside of Sika’s control are such that Sika assumes no liability for the provision of such information, advice, recommendations or instructions related to its products, nor shall any legal relationship be created by or arise from the provision of such information, advice, recommendations or instructions related to its products. The user of the Sika product(s) must test the product(s) for suitability for the intended application and purpose before proceeding with the full application of the product(s).
Sika reserves the right to change the properties of its products without notice. All sales of Sika product(s) are subject to its current terms and conditions of sale that are available at www.sikacorp.com or by calling 201-933-8800.
Prior to each use of any Sika product, the user must always read and follow the warnings and instructions on the product’s most current Technical Data Sheet, product label and Material Safety Data Sheet that are available at www.sikaconstruction.com or 1-800-933-7452. Nothing contained in any Sika materials relieves the user of the obligation to read and follow the warnings and instruction for each Sika product as set forth in the current Technical Data Sheet, product label and Material Safety Data Sheet prior to product use.
Sikafloor® & PurCem® are registered trademarks of Sika Corporation, all rights reserved.
CONTRACTOR INFORMATION SHEETS
(These sheets must be completed and included with proposal)
COMPANY NAME: ________________________________________
ADDRESS: ______________________________________________
PHONE #______________________
ESTABLISHED: _____________________ ___________
(Month) (Year)
TYPE OF ORGANIZATION: (Circle One)
A) Individual B) Partnership C) Corporation D) Joint Venture E) Other __________________________________ (Specify)
(If Applicable)
FORMER FIRM NAMES(S) YEARS IN BUSINESS
YEARS OF WORK IN A RELATED FIELD:
(Described Any Related Work)
USE OF SUBCONTRACTORS:
To provide all services listed in the specifications, would any services be handled by subcontractors? ______ Yes/No If “Yes”, please explain:
Subcontractor Name(s): ____________________________________________
PROJECT MANAGER:
Would your company be able to provide a single project manager for this work? ___ Yes/No
Name: __________________________ Credentials: (Please List)
Title: ____________________________ _________________________________
REFERENCES: List (3) clients who have had work meeting (or similar to) the Specifications:
COMPANY ADDRESS CONTACT PHONE
1) ____________________________________________________________
2) _____________________________________________________________
3) _____________________________________________________________
EQUIPMENT: List equipment, owned by the company to be used while completing the job:
THE FOREGOING IS A TRUE STATEMENT OF FACTS:
I/we hereby certify under penalty of law that we are not an Iran linked business as defined in PA 517 of 2012.
Signature of Authorized Company Representative: __________________________
Company _________________________________
Address _________________________________
Date _________________________________
Phone # _________________________________
E-Mail Address _________________________________
Representative’s Name _________________________________ (Please Print)
| Floor Coating Fire 3 2025 Cover |
| RFP Fire 3 Bay coating |
| Charter Township of Canton |
| Fire Three Floor Plan- Highlighted |
| Spec 24na 264 340 Fire Dept |
| Contractor info sheets 2025 |
File details come from the government source that posted it. Updated .