This Scope of Work document outlines plumbing modifications, accessibility improvements, and facility upgrades required at the Tijuana River Estuary Restrooms in San Diego County, California. The project encompasses comprehensive work across the alleyway area and men's and women's restroom facilities. In the alleyway, the contractor must relocate drain lines for sinks, toilets, and urinals closer to the finished floor per code requirements while maintaining the existing underground main drain line; relocate eleven drain vent connections (ranging from 2 to 4 inches) to the south wall using ABS piping; convert two urinals to waterless units and remove associated plumbing; relocate Sloan flush valves to restroom areas; replace copper lines as necessary; evaluate and potentially replace the primary vent stack with ABS piping; and maintain existing lighting. Within the men's and women's restrooms, the scope requires replacing eight light fixtures (four can lights and four strip lights in each restroom) with energy-efficient, motion-activated units; replacing existing light switches with lockable versions; repairing or replacing the air handler access located on the men's side while cleaning and maintaining existing ductwork; potentially sealing flooring with garage-grade epoxy coating; replacing existing stainless steel sinks and toilets with porcelain fixtures while retaining five existing Chicago faucets and maintaining fixture mounting heights; installing six new porcelain toilets compatible with new Sloan valves in each stall; repainting walls and ceilings; preserving existing stall dividers; installing four new interior and exterior ADA-compliant doors with appropriate hardware; and providing gender-specific restroom signage in accordance with applicable codes.
The document does not provide pricing terms, cost estimates, set-asides, funding sources, response dates, bid submission deadlines, site visit requirements, bidder conference details, or award dates. The scope specifies that all work shall be performed in accordance with applicable codes, manufacturer requirements, and industry standards to result in fully functional and safe restroom facilities. No incumbent information, current environment details, or renewal options are addressed in this scope of work document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C25935012_TJ_Estuary_Bid_Forms.pdf | ||
| 25MLD006_IFB_REBID_-_FINAL2.pdf | ||
| C25935012_Invitation_for_Bid_Soliciation_Letter.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit A, Attachment I
Scope of Work
Alleyway Scope:
1. Bring drains for sinks, toilets, and urinals as close to the finished floor as permitted by applicable code requirements. This shall allow staff to safely step over drain lines that currently sit above typical working height.
2. The main drain line, which is currently buried underground, shall remain in its existing location to avoid additional costs. The system includes a total of eleven (11) connections ranging in size from 2 inches to 4 inches.
3. The drain vents associated with the eleven (11) connections shall be relocated to the right-hand side of the alleyway (south wall) and replaced with ABS piping.
4. Convert two (2) urinals to waterless units and remove all associated plumbing serving those fixtures.
5. Remove Sloan valves for toilets from the alleyway and relocate them to be installed within the restroom areas.
6. No hot water lines shall be installed or required under this scope.
7. Replace existing copper lines as necessary to accommodate new venting and water supply configurations.
8. The primary vent stack shall be evaluated and replaced with ABS piping if deemed necessary.
9. Existing alleyway lighting shall be maintained in its current condition and configuration.
Men’s and Women’s Restrooms:
1. Replace four (4) light fixtures in each restroom, for a total of eight (8) fixtures, with energy-efficient, motion-activated lighting. This includes four (4) can lights and four (4) strip lights. Motion activation may be integral to the fixtures or controlled via motion sensors.
2. Remove existing light switches and replace with lockable light switches.
3. Access to the restroom air handler, located on the men’s side, shall be repaired or replaced as necessary.
a. Existing ductwork shall be cleaned and remain in place.
b. The exterior vent shall be inspected and repaired or replaced as needed.
4. (Potential) Flooring may be sealed with a garage-grade epoxy coating for aesthetic purposes. Color shall be determined (TBD).
5. Existing stainless steel sinks and toilets shall be replaced with porcelain fixtures.
a. Existing Chicago faucets shall be retained for all sinks (five [5] sinks total).
b. Existing mounting heights of toilets, sinks, and urinals shall be maintained.
c. Toilets shall be porcelain fixtures compatible with new Sloan valves installed within each stall (six [6] toilets total).
i. Mounting flanges for toilets shall be replaced as required to accommodate new fixtures.
6. Restroom painting shall include repainting walls in a color to be determined and repainting ceilings white.
7. Existing stall dividers shall be preserved and remain in place.
8. Provide and install new interior and exterior doors, including ADA-compliant handles and deadbolts (four [4] doors total).
9. 9. Provide and install signage identifying Gender-Specific Restrooms in accordance with applicable code and accessibility requirements.