This document includes a performance work statement and federal contract opportunity for repairing two 20,000-gallon oily wastewater storage tanks at Puget Sound Naval Shipyard. The performance work statement outlines the scope of work required to clean, weld repair, install new tank lining, replace stainless steel guide cables, and install new high-level alarm sensors and floats. The contractor must develop a quality control plan, attend progress meetings, and provide certified inspectors. The period of performance is 90 days from award. The federal contract opportunity identifies this as a firm fixed price solicitation from the Department of the Navy to repair the two storage tanks located at OWTS Plant 4, as further specified in the attached performance work statement and solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2 Performance Work Statement
N4523A22Q5720
1. General: This is a contract to repair two 20,000-gallon oily wastewater storage tanks (Tanks 4C and 4D) at the Oily Water Treatment System (OWTS) #4. Plant 4 is located at the Puget Sound Naval Shipyard.
1.1. Description of Services: The contractor shall repair OWTS tanks 4C and 4D as defined in this Performance Work Statement (PWS).
1.2. Background: Puget Sound Naval Shipyard (PSNS) has six OWTS plants. Two if the 20,000- gallon vertical, cylindrical, aboveground, double-walled wastewater storage tanks have developed holes, pits, and leaks in the primary tanks. Tank 4C and 4D service OWTS Plant 4 and are located at Drydock 4. The holes, pits, and leaks have developed in the tanks due to excessive corrosion. The corrosion is evident by multiple holes, pits, and leaks on the tank walls and floor, separation of the stainless steel sensor guide wires from the carbon steel floor anchors, and damage to the components located inside the tanks such as the high-level alarm and the emergency shut-off valve system. The tank repair shall meet American Petroleum Institute (API), Steel Tank Institute (STI), Underwriters Laboratories Inc. (UL), and National Fire Protection Association (NFPA) standards. The tank coating shall meet National Association of Corrosions Engineers (NACE) certification standards.
1.3. Objective: Objectives of this contract is to repair OWTS tanks 4C and 4D and to return the tanks to a fully functional and operational condition. Contractor shall perform all work meeting industrial standards and all requirements of this contract. See reference documents in Section 2.1, Referenced documents for technical, legal, and regulatory requirements.
1.4. Period of Performance: The period of performance for this contract is 90 days after the contract is awarded.
1.5. Scope: the contractor shall furnish all supplies, materials, equipment, facilities, and services required to complete all repairs and services on OWTS tanks 4C and 4D that are not listed under section 1.5.5 of this PWS as government provided.
1.5.1. Complete all pre-work documents prior to Notice to Proceed.
1.5.1.1. Quality Control Plan (QCP)
1.5.1.1.1. Develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS.
1.5.1.1.2. Develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services.
1.5.1.1.3. Provide a QCP for the Post Award Conference for review/edits before finalization.
1.5.1.2. Post Award Conference/Periodic Progress Meetings
1.5.1.3. Attend the post award conference in person or by teleconference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation (FAR) Subpart 42.5.
1.5.1.3.1. Attend all progress meetings with the Contracting Officer (KO), Contracting Officers Representative (COR), and other Government Personnel, as appropriate, to review the contractor’s performance at no additional cost to the Government.
1.5.1.3.2. Appraise the Government of problems, if any are experienced during the progress meetings.
1.5.1.3.3. Perform appropriate actions if/when outstanding issues occur.
1.5.2. Clean and prepare tanks for weld repairs.
1.5.2.1. Tanks shall have all rust/pitting removed from the primary tanks. Tanks must be cleaned to a standard that will allow all the remaining contract actions to be performed.
1.5.3. Completed tanks must meet all PWS standards.
1.5.3.1. Primary tanks shall be welded to the PWS standards.
1.5.3.1.1. Welded tanks shall have no remaining holes, pits, or leaks.
1.5.3.1.2.Contractors shall maintain appropriate certifications to perform repairs on Steel Tank Institute (STI) certified tanks throughout the performance period.
1.5.3.2. Tanks shall be completed with cathodic protection installed.
1.5.3.3. Completed tanks shall pass the pneumatic pressure test.
1.5.3.4. Tanks with completed repairs must pass a STI inspection and meet all STI certification requirements for aboveground storage tanks for flammable liquid storage.
1.5.3.5. Tank lining system installation.
1.5.3.5.1. The Contractor shall clean the tank to the appropriate cleanliness level required to prepare the primary tank surfaces and tank bottom for lining and surface finishing.
1.5.3.5.2. The Contractor shall apply the new tank lining system. The tank lining system must meet all industrial standards and certification requirements for aboveground storage tanks for flammable and combustible liquid storage.
1.5.3.5.3. Contractors shall maintain appropriate certifications to meet the National Association of Corrosion Engineers (NACE) certification requirements for installation of aboveground storage tank lining/coating for flammable liquid storage throughout the performance period.
1.5.3.5.4. Using a STI/NACE certified inspector, the Contractor shall have the newly installed tank lining inspected.
1.5.4. Contractor provided equipment.
1.5.4.1. Contractor shall purchase and install new stainless steel guide cables.
1.5.4.1.1. Contractors shall follow manufacturer’s instruction for installation of the stainless steel guide cables.
1.5.4.1.2. Contractors shall provide the Operation and Maintenance manuals from the manufacture as a deliverable.
1.5.5. Government furnished equipment.
1.5.5.1. The government will provide the Contractors with new high-level sensor and control floats for the emergency shut-off valves.
1.5.5.1.1. Contractors shall install the provided new high-level sensor and control floats for the emergency shut-off valves.
1.5.5.1.2. Contractors shall follow the manufacturer’s instructions for installation of the equipment.
1.5.5.1.3. Contractors shall perform an operation test to ensure proper operation.
1.6. General Information:
1.6.1. Recognized Holidays:
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
Juneteenth Christmas Day
Independence Day
1.6.2. Hours of Operation: The Contractor is responsible for conducting business, between the hours of 0720 to
1602 Monday through Friday, except Federal Holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closing.
For other than firm fixed price contracts, the Contractor will not be reimbursed when the Government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.6.3. Place of Performance: The work to be performed under this contract will be performed at Puget
Sound Naval Shipyard, OWTS 4.
1.6.4. Type of Contract: The Government will award a Firm Fixed Price contract.
1.6.5. Security Requirements: Contract personnel performing work under this contract will have to submit a Visitor Badge Request provided by the COR to be able to get access to the Controlled Industrial Area (CIA). The security requirements are in accordance with the attached DD254.
1.6.5.1. Physical Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials, shall be secured.
1.6.5.2. Key Control: Not applicable.
1.6.5.3. Lock Combinations: Not applicable.
1.6.5.4. Special Qualifications: The Contractor is responsible for ensuring the following:
1.6.5.4.1. All painters possess and maintain certifications to perform industrial painting work.
1.6.5.4.2. All welders possess and maintain certifications to weld on STI certified tanks.
1.6.5.4.3. The Contractor shall provide one independent STI Certified Inspector to evaluate the tanks and certify them STI certified, upon completion of the pneumatic test.
1.6.5.4.4. The Contractor shall provide one independent NACE/STI qualified independent Inspector to evaluate the applied tank lining and certify the tank lining as acceptable per NACE standards.
1.6.5.5. Facilities: The Government will provide equipment laydown space near the tanks.
1.6.5.6. Utilities: The Government will provide compressed air at 80-90 PSI and electricity at 120 volts.
The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities, which includes turning off the water faucets or valves after using the required amount to accomplish cleaning equipment. The Contractors shall be responsible for any costs incurred in connecting, converting, and transferring the utilities to the work.
2. Referenced Documents:
2.1. Washington Administrative Code (WAC) WAC-173-303 Washington Dangerous Waste Regulations.
2.2. Washington Administrative Code (WAC) WAC-173-60 Maximum Environmental Noise Levels.
2.3. Washington Administrative Code (WAC) WAC-173-304 Minimum Functional Standards for Solid Waste Handling.
2.4. Military Standards MIL-STD-2035 Nondestructive testing acceptance criteria.
2.5. UFC 3-430-07 Operations and Maintenance: Inspection and Certification of Boilers and Unfired Pressure Vessels.
2.6. Attachment A Site Specific Requirements for Puget Sound Naval Shipyard & Intermediate Maintenance Facility, Bremerton Site and Nave Base Kitsap.
2.7. Attachment B Contractors guide to Environmental and Safety Compliance, Puget Sound Naval Shipyard & Intermediate Maintenance Facility Bremerton, Washington.
PERFORMANCE REQUIREMENTS SUMMARY
Requirement PWS
Paragraph Performance
Standards Allowable Deviation
Surveillance Method
Complete Pre- Work Documents Prior to Notice- to-
Proceed
1.5.1 Contractor shall
provide a QCP for the
Post Award Conference for either in person or teleconference review/edits
Contractor shall not deviate from the requirement
Contracting Officer, COR, Contract
Specialist, and other applicable
Government personnel will review the finalized copy of the QCP, submitted within one business day after
Post Award Conference
The Contractor Shall open and clean the tank to the appropriate cleanliness level required to prepare the primary tank surfaces and tank bottom for weld repair.
1.5.2 The Contractor shall
follow the requirements of:
1) NFPA 30
Flammable and
Combustible Liquids and Code
2) API Standard
2015, Requirement for Safe Entry and
Cleaning of Petroleum Storage Tanks.
3) API
Recommended Practice 2016, Guidelines and Procedures for
Entering and Cleaning Petroleum Storage Tanks
Contractor shall not deviate from the standards
COR will perform random inspections
Paragraph
Performance Standards
Allowable Deviation
Surveillance Method
The Contractor shall weld repair the primary tank pits and holes
1.5.3.1 The Contractor shall
1) API Standard 653, Tank
Inspection, Repair, Alteration, and Reconstruction
2) STI SP031,
Standard for repair of
Shop Fabricated Aboveground Tanks for Storage of
Flammable and Combustible Liquids
Contractor shall not deviate from the requirements
COR will perform random inspections
Using a STI certified inspector, the Contractor shall have the tank STI certified.
1.5.3.4 The Contractor shall use
a STI certified inspector to perform the task.
Contractor shall not deviate from this requirement
COR will perform final inspection on the STI certified tanks
Paragraph
Performance Standards
Allowable Deviation
Surveillance Method
The Contractor shall clean the tank to the appropriate cleanliness level required to prepare the primary tank surfaces and tank bottom for lining and surface finishing
1.5.3.5.1 The Contractor shall
1) The manufacturer’s requirements
2) API
Practices 652
Linings of Aboveground
Petroleum Storage Tank Bottoms
Contractor shall not deviate from the requirements
COR will perform random inspections
The Contractor shall install the new tank interior lining
1.5.3.5.2 The Contractor shall
follow the following requirements of:
1) API
Practices 652 Linings of
Aboveground Petroleum Storage
Tank Bottoms
2) NACE SP0178-
2007, Standard and
Practice Design, Fabrication, and Surface Finish
Practices for Tanks and vessels to be lined for
Immersion Services
Contractor shall not deviate from this requirement
COR will perform random inspections
Paragraph
Performance Standards
Allowable Deviation
Surveillance Method
The Contractor shall purchase and install new stainless steel guide cables. The Government will provide new high-level alarm sensors and float control for emergency shut- off valves. The Contractor shall install new stainless high- level alarm sensors, and float controls for the emergency shut- off valve
1.5.4 & 1.5.5
The Contractor shall follow the requirements of:
1) The manufacturer’s instructions for installation
Contractor shall not deviate from the requirements
COR will perform final inspection
Using a NACE certified inspector, the Contractor shall have the newly installed lining inspected
1.5.3.5.4 The Contractor shall use
the following for inspection:
1) A STI/NACE certified inspector to perform this task
Contractor shall not deviate from this requirement
COR will perform final inspection on
STI/NACE
certified tanks.
DELIVERABLE SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit to
Provide Gantt Chart Schedule
Reports shall be submitted at Post
Award Conference for review and any revisions shall be submitted within 3 days after Post Award Conference
Submit 1 original And 3 copies
The format shall be 3 hard copies and 1 CD copy in MS Word
Submit the deliverables to PSNS & IMF 1400
Farragut Ave Bremerton, WA 98314. Building
448, Mail Stop 2001
Comprehensive QCP and all changed
Reports shall be submitted at Post Award
Conference and any revision shall be submitted within 3 days after Post Award
Conference
Submit 1 original and 3 copies
The format shall be 3 hard copies and CD copy in MS Word
Submit the deliverables to PSNS & IMF 1400
Farragut Ave Bremerton, WA 98314. Building
448, Mail Stop 2001
Certified STI Inspector Reports
Reports shall be submitted within 3 days after inspection
Submit 1 original and 3 copies within 3 days after the inspection
The format shall be 3 hard copies and CD copy in MS Word
Submit the deliverables to PSNS & IMF 1400
Farragut Ave Bremerton, WA 98314. Building
448, Mail Stop 2001
Certified STI/NACE Inspectors final reports
(i.e.
Certification that the tank is STI/NACE certified
Reports shall be submitted within 3 days after inspection
Submit 1 original and 3 copies within 3 days after the inspection
The format shall be 3 hard copies and CD copy in MS Word
Submit the deliverables
PSNS & IMF 1400
Farragut Ave Bremerton, WA 98314. Building 448, Mail Stop 2001
Completed ASTM F718-07
Reports shall be submitted within 3 days after inspection
Submit 1 original and 3 copies within 3 days after the inspection
The format shall be 3 hard copies and CD copy in MS Word
Submit the deliverables to PSNS & IMF 1400
Farragut Ave Bremerton, WA 98314. Building
448, Mail Stop 2001
Table 1: Metal Bearing Oily Wastewater Contaminants and Concentrations
Contaminants
Concentration mg/L
Normal Recorded High
1. Total Suspended Solids (TSS) 400 1,440
2. Total Dissolved Solids (TDS) 12,480 16,620
3. Chemical Oxygen Demand (COD) 10,155 66,000
4. Total Organic Carbon (TOC) 2,310 19,040
5. Total Phosphorus 3.50 3.90
6. Biological Oxygen Demand (BOD) 3,300 >14,000
7. Oil and Grease (O & G) 146.0 12,900
8. Total Petroleum Hydrocarbon (TPH) 73.0 6,450
8. Phenols 0.19 5.40
9. Cu 1.42 1,230
10. Cd 0.02 0.61
11. Cl- 8,317 9,742
12. Ag 0.023 1.44
13. Ni 0.98 100.0
14. Mn 0.63 3.00
15. Pb 0.10 3.36
16. As .006 0.018
17. Ba 0.014 3.30
2- 18. SO4 918 1,290
19. Fe 10.7 46.0
20. Sulfide 8.80 10.0
21. Ca 130 172.5
22. Na 3,585 5,000
23. Zn 1.36 97.0
24. Total Toxic Organic (TTO)** 0.238 8.10
25. Ammonia 6.95 68.0
26. Chlorine 0.21 1.60
27. Surfactants -------- 0.807
DELIVERABLE SCHEDULE