C04c_Attachment 2 - Statement of Work.pdf

PDF 111 KB Posted

Attached to
Feed Silo Maintenance Federal contract opportunity
Solicitation number
1232SA26Q0952
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a Statement of Work (SOW) for feed silo maintenance services. The contractor shall perform cleaning, waste removal, and inspection of a 30-ton feed silo to restore full storage capacity and proper feed flow through the cone discharge. The work scope includes site preparation with silo isolation and confined-space entry compliance; material removal using mechanical or manual methods with tools such as pneumatic hammers, augers, vacuum systems, or high-pressure air/water jets; cleaning of all internal surfaces to remove residual dust and feed particles; and inspection with photographic documentation and written condition reporting on structural condition and maintenance needs. The contractor is responsible for all labor, equipment, personal protective equipment, and supervision, while the government provides site access, silo isolation from production lines, and disposal instructions for waste material.

Work must be completed within 60 days after contract award during standard business hours (Monday–Friday, 8 AM to 4 PM USA Central Time), excluding 12 federal holidays. All personnel must comply with OSHA 29 CFR 1910.146 confined-space entry protocols and use appropriate PPE including respiratory protection when dust levels require. Deliverables include complete removal of hardened and loose feed from the silo and cone, verification that discharge flow is restored, and confirmation that the silo is ready for refilling. The contractor must also demobilize the site by removing all equipment, tools, and debris and restoring the area to a clean, safe condition for normal operations.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Project Title: Feed Silo Maintenance: Cleaning, Waste Removal and Inspection

1. Objective

The purpose of this work is to safely and effectively remove feed residue, compacted material, and solidified feed mass from within the 30-ton feed silo, restoring full storage capacity and proper feed flow through the cone discharge.

2. Scope of Work

The Contractor shall provide labor, equipment, and materials necessary to perform the following tasks:

1. Site Preparation

a. Confirm isolation of the silo from any live feed systems or electrical/mechanical connections.

b. Establish safe access points and fall protection in compliance with confined-space entry regulations.

2. Material Removal

a. Mechanically or manually break up solidified feed material at the base of the silo cone.

b. Remove all feed residue, caked material, and buildup from silo walls and cone interior.se tools such as pneumatic hammers, augers, vacuum systems, or high-pressure air/water jets, as appropriate.

3. Cleaning

a. Clean all accessible internal surfaces of the silo to remove residual dust and feed particles.

b. Collect and remove all waste materials for on-site disposal.

4. Inspection and Reporting

a. Inspect internal surfaces for corrosion, structural damage, or material buildup points.

b. Provide photos and a written condition report summarizing work performed and any areas requiring further maintenance.

3. Demobilization

a. Remove all equipment, tools, and debris from the site.

b. Restore the area to clean, safe condition for normal operations

4. Safety Requirements.

a. All personnel must follow confined-space entry protocols (OSHA 29 CFR

1910.146 or relevant local standard).

b. Use appropriate personal protective equipment (PPE), including respiratory protection when dust levels require.

5. Deliverables

a. Removal of all hardened and loose feed from the silo and cone.

b. Verification that discharge flow is restored and the silo is ready for refilling.

6. Schedule

a. Business Days’ – Standard business days Monday – Friday, 8AM to 4PM USA

Central Time with holiday exceptions as noted: Listed below are official Government holidays:

i. New Year’s Day January 1*

ii. Martin L. King Birthday Third Monday in January

iii. President's Day Third Monday in February

iv. Memorial Day Last Monday in May

v. Juneteenth As Indicated

vi. Independence Day July 4*

vii. Labor Day First Monday in September

viii. Columbus Day Second Monday in October

ix. Veterans Day November 11*

x. Thanksgiving Day Fourth Thursday in November

xi. Christmas Day December 25*

xii. *In accordance with Federal regulations, if these holidays fall on a

Saturday, the holiday will be observed on Friday, if Sunday, holiday will be observed on Monday.

b. Work will be coordinated to minimize disruption to operation.

7. Responsibilities

a. Government: Provide site access, isolation of the silo from production lines, and disposal instructions for waste material

b. Contractor: Provide all labor, equipment, PPE, and supervision to complete the scope of work safely and efficiently.

8. Period oof Performance:

a. Work is to be completed within 60 days after award.

Statement of Work (SOW)