C04b Attachment 3 USU PPRL Surg. Specifications CD.pdf

PDF 4 MB Posted

Attached to
HVAC upgrade at the USDA ARS PPRL in Logan, UT
Solicitation number
1232SA26Q0549
Issued by

About this file

This is a combined project manual and specification document for HVAC upgrades at the USDA Agricultural Research Service Potato and Pest Research Laboratory (PPRL) in Logan, Utah. The project is issued as RFQ 1232SA26Q0549, a Total Small Business Set-Aside with a project value between $250,000 and $500,000. The North American Industry Classification Standard Code is 236220, with a small business size standard of $19.0M.

The project encompasses comprehensive HVAC system modifications including fire sprinkler systems, building automation systems, duct work, equipment insulation, vibration and seismic controls, testing and balancing, and site civil work. Key specifications require a 4500 psi minimum compressive strength concrete mix with air entrainment of 6.5% (±1.5%), water-cement ratio of 0.44 maximum, and specialized finishing techniques for exterior concrete flatwork. The building automation system must utilize Johnson Controls Metasys or approved equivalent with open architecture BACnet protocol compatibility, supporting multi-vendor environments. Fire suppression work includes wet pipe sprinkler systems with quick-response sprinklers, mechanical tees, and seismic bracing on riser stacks. All HVAC equipment requires vibration isolation with specific deflection requirements based on equipment type and horsepower ratings, plus seismic restraint certification. The project demands submittal of working drawings, product data sheets, manufacturer certifications, operation and maintenance manuals in PDF format with bookmarks, and testing and balancing reports. Contractor must provide one-year material and labor warranty commencing from Substantial Completion, with site-specific control system design by registered professional engineer and factory-authorized equipment startup service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utah State University USU PPRL Surgery Bldg

Logan, Utah

Prepared by C-MECH Engineering

1150 E 1400 N

Logan Utah 84341 Project Number 25004

PROJECT

MANUAL

25004

Table of Contents - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

000110 Table of Contents

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP

DIVISION 01 - GENERAL REQUIREMENTS

013300 SUBMITTAL PROCEDURES

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

FACILITY SERVICES SUBGROUP

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230150 TEMPORARY USE OF EQUIPMENT AND

SYSTEMS

230500 COMMON WORK RESULTS FOR HVAC

230513 COMMON MOTOR REQUIREMENTS FOR HVAC

EQUIPMENT

230529 HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT

230548 VIBRATION AND SEISMIC CONTROLS FOR

HVAC

230550 OPERATION AND MAINTENANCE OF HVAC

SYSTEMS

230553 IDENTIFICATION FOR HVAC PIPING AND

EQUIPMENT

230593 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

230713 DUCT INSULATION

230716 230900 230993

HVAC EQUIPMENT INSULATION

BUILDING AUTOMATION SYSTEM

SEQUENCE OF OPERATION FOR HVAC

CONTROLS

233001 COMMON DUCT REQUIREMENTS

233113 METAL DUCTS

233119 HVAC CASINGS

233300 AIR DUCT ACCESSORIES

233600 AIR TERMINAL UNITS

237413 PACKAGED, OUTDOOR, ROOFTOP UNITS

237433 DEDICATED OUTDOOR-AIR UNITS

MartinCarrillo Snapshot

MartinCarrillo Text Box

21 - FIRE SUPPRESSION

MartinCarrillo Text Box

211000 FIRE SPRINKLER SYSTEM

Table of Contents - 2

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

ELECTRICAL SERVICES SUBGROUP

DIVISION 26 - ELECTRICAL REQUIREMENTS

260500 COMMON WORK RESULTS FOR ELECTRICAL -

SEE SHEET E002

260519 LOW VOLTAGE ELECTRICAL POWER

CONDUCTORS AND CABLES - SEE SHEET

E002

260526

260529

260533

260548

260553

262726 262816

262913 283111

GROUNDING AND BOUNDING FOR

ELECTRICAL SYSTEMS - SEE SHEET E002

HANGERS AND SUPPORTS FOR ELECTRICAL

SYSTEMS - SEE SHEET E002

RACEWAYS AND BOXES FOR ELECTRICAL

SYSTEMS - SEE SHEET E002

VIBRATION AND SEISMIC CONTROLS FOR

ELECTRICAL SYSTEMS - SEE SHEET E002

IDENTIFICATION FOR ELECTRICAL SYSTEMS -

SEE SHEET E002

WIRING DEVICES - SEE SHEET E002

ENCLOSED SWITCHES AND CIRCUIT

BREAKERS - SEE SHEET E002

ENLCOSED CONTROLLERS - SEE SHEET E002

DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

- SEE SHEET E002

CIVIL SERVICES SUBGROUP

DIVISION 33 - CIVIL REQUIREMENTS

312200 SITE EXCAVATION AND ROUGH GRADING

312300 EARTHWORK

321313 334100

EXTERIOR CONCRETE

STORM DRAINAGE

END OF TABLE OF CONTENTS

SUBMITTAL PROCEDURES 013300 - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Architect's and Construction Manager's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's and Construction Manager's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.3 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Architect.

4. Name of Construction Manager.

5. Name of Contractor.

6. Name of firm or entity that prepared submittal.

7. Names of subcontractor, manufacturer, and supplier.

8. Unique submittal number, including revision identifier. Include Specification

Section number with sequential alphanumeric identifier and alphanumeric suffix for resubmittals.

9. Category and type of submittal.

10. Submittal purpose and description.

11. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

12. Drawing number and detail references, as appropriate.

13. Indication of full or partial submittal.

14. Location(s) where product is to be installed, as appropriate.

15. Other necessary identification.

16. Remarks.

17. Signature of transmitter.

SUBMITTAL PROCEDURES 013300 - 2

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

B. Options: Identify options requiring selection by Architect.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Architect and Construction Manager on previous submittals. Indicate by highlighting deviations on each submittal or noting on an attached separate sheet.

D. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

E. Electronic submittals shall be submitted as a single packaged document and bookmarked by section.

1.4 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package and transmit to Architect by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Architect.

a. Architect, through Construction Manager, will return annotated file.

Annotate and retain one copy of file as a digital Project Record Document file.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections, so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional

SUBMITTAL PROCEDURES 013300 - 3

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 15 days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Architect's consultants, Owner, or other parties is indicated, allow 21 days for initial review of each submittal.

5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to Architect and to Architect's consultants, allow 15 days for review of each submittal. Submittal will be returned to Construction Manager, through Architect, before being returned to Contractor.

a. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Architect and Construction Manager.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block, and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Architect's and Construction Manager's action stamp.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's and Construction Manager's action stamp.

1.5 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data is unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

SUBMITTAL PROCEDURES 013300 - 4

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required for other construction, if not indicated on accompanying Shop Drawings.

5. Submit Product Data before Shop Drawings, and before or concurrently with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data unless submittal based on Architect's digital data drawing files is otherwise permitted.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

C. Samples: Submit Samples for review of type, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components, such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

e. Number and title of applicable Specification Section.

f. Specification paragraph number and generic name of each item.

3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity.

Sample sets may be used to determine final acceptance of construction associated with each set.

SUBMITTAL PROCEDURES 013300 - 5

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units, showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect, through Construction Manager, will return submittal with options selected.

5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit three sets of Samples. Architect and Construction Manager will retain two Sample sets; remainder will be returned. Mark up and retain one returned Sample set as a project record Sample.

1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.

2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.

Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

4. Location within room or space.

E. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign

SUBMITTAL PROCEDURES 013300 - 6

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

documents on behalf of that entity. Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead, certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead, certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead, certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead, certifying that product complies with requirements in the Contract Documents.

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of AWS B2.1/B2.1M on AWS forms. Include names of firms and personnel certified.

F. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for substrate preparation and primers required.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

a. Name of evaluation organization.

b. Date of evaluation.

c. Time period when report is in effect.

d. Product and manufacturers' names.

e. Description of product.

f. Test procedures and results.

g. Limitations of use.

SUBMITTAL PROCEDURES 013300 - 7

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

1.6 DELEGATED DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Architect.

B. Delegated Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

1.7 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect and Construction Manager.

B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Architect will not review submittals received from Contractor that do not have Contractor's review and approval.

1.8 ARCHITECT'S AND CONSTRUCTION MANAGER'S REVIEW

A. Action Submittals: Architect and Construction Manager will review each submittal, indicate corrections or revisions required, and return.

1. PDF Submittals: Architect and Construction Manager will indicate, via markup on each submittal, the appropriate action.

2. Architect/Engineer shall be provided 14 calendar days for submittal review from the time the submittal is received.

B. Informational Submittals: Architect and Construction Manager will review each submittal and will not return it or will return it if it does not comply with requirements.

Architect and Construction Manager will forward each submittal to appropriate party.

SUBMITTAL PROCEDURES 013300 - 8

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Architect and Construction Manager.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Architect and Construction Manager will discard submittals received from sources other than Contractor.

F. Submittals not required by the Contract Documents will be returned by Architect without action.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)

END OF SECTION 013300

CLOSEOUT PROCEDURES 017700 - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

SECTION 017700 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for Contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures.

2. Final Completion procedures.

3. List of incomplete items.

4. Submittal of Project warranties.

5. Final cleaning.

B. Related Requirements:

1. Section 017823 "Operation and Maintenance Data" for additional operation and maintenance manual requirements.

2. Section 017839 "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.

3. Section 017900 "Demonstration and Training" for requirements to train Owner's maintenance personnel to adjust, operate, and maintain products, equipment, and systems.

1.2 DEFINITIONS

A. List of Incomplete Items: Contractor-prepared list of items to be completed or corrected, prepared for the Architect's use prior to Architect's inspection, to determine if the Work is substantially complete.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of cleaning agent.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Certified List of Incomplete Items: Final submittal at Final Completion.

1.4 CLOSEOUT SUBMITTALS

A. Certificates of Release: From authorities having jurisdiction.

B. Certificate of Insurance: For continuing coverage.

C. Field Report: For pest-control inspection.

CLOSEOUT PROCEDURES 017700 - 2

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

1.5 MAINTENANCE MATERIAL SUBMITTALS

A. Schedule of Maintenance Material Items: For maintenance material submittal items required by other Sections.

1.6 SUBSTANTIAL COMPLETION PROCEDURES

A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's "punch list"), indicating the value of each item on the list and reasons why the Work is incomplete.

B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction, permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

2. Submit closeout submittals specified in other Division 01 Sections, including Project Record Documents, operation and maintenance manuals, damage or settlement surveys, property surveys, and similar final record information.

3. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

4. Submit testing, adjusting, and balancing records.

5. Submit sustainable design submittals not previously submitted.

6. Submit changeover information related to Owner's occupancy, use, operation, and maintenance.

C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

1. Advise Owner of pending insurance changeover requirements.

2. Make final changeover of permanent locks and deliver keys to Owner. Advise

Owner's personnel of changeover in security provisions.

3. Complete startup and testing of systems and equipment.

4. Perform preventive maintenance on equipment used prior to Substantial

Completion.

5. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems. Submit demonstration and training video recordings specified in Section 017900 "Demonstration and Training."

6. Advise Owner of changeover in utility services.

7. Participate with Owner in conducting inspection and walkthrough with local emergency responders.

8. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.

9. Complete final cleaning requirements.

10. Touch up paint and otherwise repair and restore marred exposed finishes to

CLOSEOUT PROCEDURES 017700 - 3

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

eliminate visual defects.

D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 10 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Architect and Construction Manager will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Architect, that must be completed or corrected before certificate will be issued.

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

1.7 FINAL COMPLETION PROCEDURES

A. Submittals Prior to Final Completion: Before requesting final inspection for determining Final Completion, complete the following:

1. Submit a final Application for Payment in accordance with Section 012900 "Payment Procedures."

2. Certified List of Incomplete Items: Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Architect. Certified copy of the list will state that each item has been completed or otherwise resolved for acceptance.

3. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements.

4. Submit Final Completion photographic documentation.

B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Architect and Construction Manager will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.8 LIST OF INCOMPLETE ITEMS

A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

1. Organize list of spaces in sequential order, starting with exterior areas first and proceeding from lowest floor to highest floor, listed by room or space number.

2. Organize items applying to each space by major element, including categories

CLOSEOUT PROCEDURES 017700 - 4

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

for ceilings, individual walls, floors, equipment, and building systems.

3. Include the following information at the top of each page:

a. Project name.

b. Date.

c. Name of Architect and Construction Manager.

d. Name of Contractor.

e. Page number.

1.9 SUBMITTAL OF PROJECT WARRANTIES

A. Time of Submittal: Submit written warranties on request of Architect for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranties might limit Owner's rights under warranty.

B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

C. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual.

D. Warranty Electronic File: Provide warranties and bonds in PDF format. Assemble complete warranty and bond submittal package into a single electronic PDF file with bookmarks enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

1. Submit on digital media acceptable to Architect.

E. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 2 - PRODUCTS

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning.

Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:

CLOSEOUT PROCEDURES 017700 - 5

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

a. Clean Project site of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are not planted, mulched, or paved to a smooth, even-textured surface.

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Remove snow and ice to provide safe access to building.

f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

g. Remove debris and surface dust from limited-access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

h. Clean flooring, removing debris, dirt, and staining; clean in accordance with manufacturer's instructions.

i. Vacuum and mop concrete.

j. Vacuum carpet and similar soft surfaces, removing debris and excess nap;

clean in accordance with manufacturer's instructions if visible soil or stains remain.

k. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, vision-obscuring materials. Polish mirrors and glass, taking care not to scratch surfaces.

l. Remove labels that are not permanent.

m. Wipe surfaces of mechanical and electrical equipment, elevator equipment, and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

n. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure.

o. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

p. Clean luminaires, lamps, globes, and reflectors to function with full efficiency.

q. Clean strainers.

r. Leave Project clean and ready for occupancy.

s. Clean ductwork and diffusers where explicitly noted in the plan documents.

C. Pest Control: Comply with pest control requirements in Section 015000 "Temporary Facilities and Controls." Prepare written report.

D. Construction Waste Disposal: Comply with waste-disposal requirements in Section 015000 "Temporary Facilities and Controls" and Section 017419 "Construction Waste Management and Disposal."

3.2 CORRECTION OF THE WORK

A. Complete repair and restoration operations required by "Correction of the Work" Article

CLOSEOUT PROCEDURES 017700 - 6

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

in Section 017300 "Execution" before requesting inspection for determination of Substantial Completion.

END OF SECTION 017700

OPERATION AND MAINTENANCE DATA 017823 - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

SECTION 017823 - OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Operation and maintenance documentation directory manuals.

2. Emergency manuals.

3. Systems and equipment operation manuals.

4. Systems and equipment maintenance manuals.

5. Product maintenance manuals.

B. Related Requirements:

1. Section 011200 "Multiple Contract Summary" for coordinating operation and maintenance manuals covering the Work of multiple contracts.

2. Section 013300 "Submittal Procedures" for submitting copies of submittals for operation and maintenance manuals.

3. Section 018626 "Electrical Performance Requirements" for requirements for Electrical Preventative Maintenance (EPM) Program binders that form part of the operation and maintenance data of this Section and include additional requirements for operation, maintenance, and emergency procedures, for electrical systems and equipment.

4. Section 019113 "General Commissioning Requirements" for verification and compilation of data into operation and maintenance manuals.

1.2 DEFINITIONS

A. System: An organized collection of parts, equipment, or subsystems united by regular interaction.

B. Subsystem: A portion of a system with characteristics similar to a system.

1.3 CLOSEOUT SUBMITTALS

A. Submit operation and maintenance manuals indicated. Provide content for each manual as specified in individual Specification Sections, and as reviewed and approved at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section.

1. Architect and Commissioning Authority will comment on whether content of operation and maintenance submittals is acceptable.

2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions.

OPERATION AND MAINTENANCE DATA 017823 - 2

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

B. Format: Submit operation and maintenance manuals in the following format:

1. Submit on digital media acceptable to Architect. Enable reviewer comments on draft submittals.

2. Submit three paper copies. Architect, through Construction Manager, will return two copies.

C. Comply with Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation.

1.4 FORMAT OF OPERATION AND MAINTENANCE MANUALS

A. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required.

1. Electronic Files: Use electronic files prepared by manufacturer where available.

Where scanning of paper documents is required, configure scanned file for minimum readable file size.

2. File Names and Bookmarks: Bookmark individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily navigated file tree. Configure electronic manual to display bookmark panel on opening file.

B. Manuals, Paper Copy: Submit manuals in the form of hard-copy, bound and labeled volumes.

1. Binders: Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.

a. If two or more binders are necessary to accommodate data of a system, organize data in each binder into groupings by subsystem and related components. Cross-reference other binders if necessary to provide essential information for proper operation or maintenance of equipment or system.

b. Identify each binder on front and spine, with printed title "OPERATION AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents, and indicate Specification Section number on bottom of spine.

Indicate volume number for multiple-volume sets.

2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.

3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software storage media for computerized electronic equipment.

OPERATION AND MAINTENANCE DATA 017823 - 3

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

Enclose title pages and directories in clear plastic sleeves.

4. Supplementary Text: Prepared on 8-1/2-by-11-inch white bond paper.

5. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.

a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.

b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.

1.5 REQUIREMENTS FOR EMERGENCY, OPERATION, AND MAINTENANCE

MANUALS

A. Organization of Manuals: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual to contain the following materials, in the order listed:

1. Title page.

2. Table of contents.

3. Manual contents.

B. Title Page: Include the following information:

1. Subject matter included in manual.

2. Name and address of Project.

3. Name and address of Owner.

4. Date of submittal.

5. Name and contact information for Contractor.

6. Name and contact information for Construction Manager.

7. Name and contact information for Architect.

8. Name and contact information for Commissioning Authority.

9. Names and contact information for major consultants to the Architect that designed the systems contained in the manuals.

10. Cross-reference to related systems in other operation and maintenance manuals.

C. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project Manual.

1. If operation or maintenance documentation requires more than one volume to accommodate data, include comprehensive table of contents for all volumes in each volume of the set.

D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

E. Identification: In the documentation directory and in each operation and maintenance

OPERATION AND MAINTENANCE DATA 017823 - 4

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

manual, identify each system, subsystem, and piece of equipment with same designation used in the Contract Documents. If no designation exists, assign a designation in accordance with ASHRAE Guideline 4, "Preparation of Operating and Maintenance Documentation for Building Systems."

1.6 SYSTEMS AND EQUIPMENT OPERATION MANUALS

A. Systems and Equipment Operation Manual: Assemble a complete set of data indicating operation of each system, subsystem, and piece of equipment not part of a system. Include information required for daily operation and management, operating standards, and routine and special operating procedures.

1. Engage a factory-authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system.

2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel.

B. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:

1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents.

2. Performance and design criteria if Contractor has delegated design responsibility.

3. Operating standards.

4. Operating procedures.

5. Operating logs.

6. Wiring diagrams.

7. Control diagrams.

8. Piped system diagrams.

9. Precautions against improper use.

10. License requirements including inspection and renewal dates.

C. Descriptions: Include the following:

1. Product name and model number. Use designations for products indicated on Contract Documents.

2. Manufacturer's name.

3. Equipment identification with serial number of each component.

4. Equipment function.

5. Operating characteristics.

6. Limiting conditions.

7. Performance curves.

8. Engineering data and tests.

9. Complete nomenclature and number of replacement parts.

D. Operating Procedures: Include the following, as applicable:

1. Startup procedures.

OPERATION AND MAINTENANCE DATA 017823 - 5

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

2. Equipment or system break-in procedures.

3. Routine and normal operating instructions.

4. Regulation and control procedures.

5. Instructions on stopping.

6. Normal shutdown instructions.

7. Seasonal and weekend operating instructions.

8. Required sequences for electric or electronic systems.

9. Special operating instructions and procedures.

E. Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed.

F. Piped Systems: Diagram piping as installed, and identify color coding where required for identification.

1.7 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS

A. Systems and Equipment Maintenance Manuals: Assemble a complete set of data indicating maintenance of each system, subsystem, and piece of equipment not part of a system. Include manufacturers' maintenance documentation, preventive maintenance procedures and frequency, repair procedures, wiring and systems diagrams, lists of spare parts, and warranty information.

1. Engage a factory-authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system.

2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel.

B. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranties and bonds as described below.

C. Source Information: List each system, subsystem, and piece of equipment included in manual, identified by product name and arranged to match manual's table of contents.

For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable.

D. Manufacturers' Maintenance Documentation: Include the following information for each component part or piece of equipment:

1. Standard maintenance instructions and bulletins; include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include more than one item in a tabular format, identify each item using appropriate references from the Contract Documents. Identify data applicable to the Work and delete references to information not applicable.

OPERATION AND MAINTENANCE DATA 017823 - 6

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

a. Prepare supplementary text if manufacturers' standard printed data are not available and where the information is necessary for proper operation and maintenance of equipment or systems.

2. Drawings, diagrams, and instructions required for maintenance, including disassembly and component removal, replacement, and assembly.

3. Identification and nomenclature of parts and components.

4. List of items recommended to be stocked as spare parts.

E. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures:

1. Test and inspection instructions.

2. Troubleshooting guide.

3. Precautions against improper maintenance.

4. Disassembly; component removal, repair, and replacement; and reassembly instructions.

5. Aligning, adjusting, and checking instructions.

6. Demonstration and training video recording, if available.

F. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

1. Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly,…