C04b Attachment 2 Drawings 1232SA26Q0648.pdf
PDF 11 MB Posted
- Solicitation number
- 1232SA26Q0648
About this file
This document set comprises the design drawings and specifications for a laboratory exhaust system upgrade project at the USDA Agricultural Research Services facility in Corvallis, Oregon (3420 NW Orchard Avenue). The project involves adding a new laboratory exhaust fan and re-balancing building airflows to maintain proper pressure relationships in laboratory areas while coordinating with existing facility operations and systems.
The primary scope includes installation of a new rooftop exhaust fan (EF-10) rated at 8,470 CFM with 1.75 inches water column static pressure, served by a 7.5 HP motor requiring 208V/3-phase power with a 30-amp breaker. The system incorporates two variable-volume exhaust terminal units (ETU-01 and ETU-02) on the first and second floors respectively, connected to existing ductwork. The contractor is responsible for final crane lift planning and site restoration, including preparation and repair of sprinklers, sidewalks, and asphalt. Construction work requires careful coordination with laboratory staff and facilities teams regarding HVAC shutdowns. The project includes structural roof modifications, mechanical ductwork connections, controls integration with the existing Building Automation System via BACnet, and differential pressure sensors to maintain negative pressurization in laboratory spaces. All work must comply with SMACNA standards, NFPA 90A and 90B, and current NEC codes as adopted by the State of Oregon. Equipment schedules specify an insulated roof curb, birdscreen, isolation damper, and NEMA 4X VFD controller, with basis-of-design equipment identified for mechanical and electrical components.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SUMMARY
THE USDA RESEARCH LAB IN CORVALLIS WAS CONSTRUCTED IN 1971, EXPANDED IN 1993, AND RECENTLY HAD SEVERAL ROOFTOP UNITS REPLACED. THIS PROJECT WILL ADD A NEW LABORATORY EXHAUST FAN AND RE-BALANCE THE BUILDING AIRFLOWS TO MAINTAIN PRESSURE RELATIONSHIPS
IN LABORATORY AREAS.
THE CONTRACTOR SHALL COORDINATE CAREFULLY WITH THE LABORATORY STAFF AND FACILITIES
TEAM REGARDING THE VARIOUS BUILDING HVAC SHUTDOWNS REQUIRED TO COMPLETE THE
PROJECT.
THE ELECTRICAL DRAWINGS DETAIL THE ELECTRICAL-SPECIFIC REQUIREMENTS IN ACCORDANCE
WITH THE ABOVE.
THE FINAL CRANE LIFT PLAN SHALL BE THE RESPONSIBILITY OF THE AWARDED CONTRACTOR. THE CRANE SHALL UTILIZE WOOD OR SIMILAR TO DISTRIBUTE THE OUTRIGGER POINT LOADS WHERE
THEY ARE LOCATED OVER UNDERGROUND UTILITIES. THE CONTRACTOR SHALL BE RESPONSIBLE
FOR PREPARING THE GROUND FOR THE CRANE AND RESTORING THE SITE TO ORIGINAL CONDITION
AS AGREED-UPON AT TIME OF AWARD TO INCLUDE ANY NECESSARY REPAIRS TO SPRINKLERS,
SIDEWALKS, ASPHALT, ETC.
PROJECT AREA
www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:2
:2
A M
02/04/2026
TAH
PJTM
230612
G-001
COVER SHEET
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
USDA AGRICULTURAL
RESEARCH SERVICES
LABORATORY EXHAUST
HORTICULTURAL CROPS RESEARCH LAB
3420 NW ORCHARD AVE.
CORVALLIS OR, 97331
BENTON COUNTY
OREGON STATE
BENTON COUNTY STREET VIEW
01 16
PROJECT SHEET INDEX
SHEET NUMBER SHEET NAME
G-001 COVER SHEET
STRUCTURAL
S-001 GEN. STRUCTURAL NOTES
S-101 EXISTING ROOF FRAMING PLAN
MECHANICAL
M-001 MECHANICAL LEGENDS AND ABBREVIATIONS
MD-101 FIRST FLOOR PLAN WEST MECHANICAL DEMO PLAN
MD-102 SECOND FLOOR PLAN WEST MECHANICAL DEMO PLAN
MD-103 MECHANICAL ROOF DEMO PLAN
M-201 FIRST FLOOR WEST ZONE PLAN
M-202 SECOND FLOOR WEST ZONE PLAN
M-203 FIRST FLOOR WEST MECHANICAL PLAN
M-204 SECOND FLOOR WEST MECHANICAL PLAN
M-205 MECHANICAL ROOF PLAN
M-501 MECHANICAL DETAILS
M-701 MECHANICAL CONTROLS
M-702 MECHANICAL SCHEDULES
ELECTRICAL
E-001 ELECTRICAL LEGEND, SECOND FLOOR & ROOF WEST PLANS & SCHEDULES
REV DATE DESCRIPTION
PROJ. NO.
DRAWN
CHECKED
DATE
SHEET OF
COFFMAN ENGINEERS INC.C
HORTICULTURAL
CROPS RESEARCH LAB
3420 NW ORCHARD
AVE., CORVALLIS, OR
97331
USDA ARS
LABORATORY
EXHAUST
230612
02/04/26
SHEET TITLE:
SHEET NO:
A
B
C
D
A
B
C
D
E
E
2 3 4 5 6
2 3 4 5 6
FINAL TURNOVER
21P:
\S
PO
\23
JO
BS
\23
C
OR
VA
LL
IS
A
RS
A
HU
R
EP
LA
CE
ME
NT
S\ 0.0
D W
GS
\S
\23
_S
-0
.D W
G.
_S -0
: C
LIN
E, K
EV
IN
: L
AS
T
SA
VE
D:
Ja nu ar y 9 , 2
6 :
P
LO
T
DA
TE
: 2
/3/ www.coffman.com ph 509.328.2994
10 N. Post Street, Spokane, WA 99201 Suite 500
CEI# 230612
(A) ABOVE
AB ANCHOR BOLT
AC ASPHALT CONCRETE
ACI AMERICAN CONCRETE INSTITUTE
ADDL ADDITIONAL
ADH ADHESIVE
ADJ ADJACENT
ADESS ARCHITECTURALLY EXPOSED STRUCTURAL STEEL
AFF ABOVE FINISHED FLOOR
AISC AMERICAN INSTITUTE OF STEEL CONSTRUCTION
AISI AMERICAN IRON AND STEEL INSTITUTE
ALT ALTERNATE
ALUM ALUMINUM
ARCH ARCHITECTURAL
ASPH ASPHALT
ASCE AMERICAN SOCIETY OF CIVIL ENGINEERS
ASNT AMERICAN SOCIETY OF NON-DESTRUCTIVE TESTING
ASTM AMERICAN SOCIETY FOR TESTING AND MATERIALS
AWS AMERICAN WELDING SOCIETY
(B) BELOW
BLKG BLOCKING
BLDG BUILDING
BOC BOTTOM OF CONCRETE
BOD BOTTOM OF DECKING
BOS BOTTOM OF STEEL
BOT BOTTOM
BP BASE PLATE
BRNG BEARING
BS BOTH SIDES
BTWN BETWEEN
CANT CANTILEVER
CBF CONCENTRIC BRACED FRAME
CFS COLD FORMED STEEL
CHAN CHANNEL
CIP CAST IN PLACE
CJ CONTROL OR CONSTRUCTION JOINT
CJP COMPLETE JOINT PENETRATION
CL CENTER LINE
CLR CLEAR, CLEARANCE
CM CUBIC METER
CMP CORRUGATED METAL PIPE
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTINUOUS
CONTR CONTRACTOR
COORD COORDINATE
CP COMPLETE PENETRATION
CTR CENTER, CENTERED
CY CUBIC YARD
D BEAM DEPTH
DP DEEP
DBA DEFORMED BAR ANCHOR
DBL DOUBLE
DEG DEGREE
DEMO DEMOLITION
DET DETAIL
DIAA DRILLED IN ADHESIVE ANCHOR
DIAG DIAGONAL
DIAM,Ø DIAMETER
DIEA DRILLED IN EXPANSION ANCHOR
DIM DIMENSION
DISA DRILLED IN SCREW ANCHOR
DIST DISTANCE
DN DOWN
DO DITTO
DWG DRAWING(S)
DWL DOWEL
E EAST, MODULUS OF ELASTICITY
(E) EXISTING
EA EACH
EF EACH FACE
EJ EXPANSION JOINT
EL ELEVATION
ELEC ELECTRICAL
ELEV ELEVATION OR ELEVATOR
EMBED EMBEDMENT
ENGR ENGINEER
EQ EQUAL
EQUIP EQUIPMENT
ES EACH SIDE
ESC ESCALATOR
EW EACH WAY
EXIST EXISTING
EXP EXPANSION, EXPOSURE
EXT EXTERIOR
F'c CONCRETE COMPRESSIVE STRENGTH
FCAW FLUX CORED ARCH WELDING
FDN FOUNDATION
FEMA FEDERAL EMERGENCY MANAGEMENT AGENCY
FIN FINISH
FLG FLANGE
F'm CONCRETE MASONRY COMPRESSIVE STRENGTH
FLR FLOOR
FP FIREPROOFING, FULL PENETRATION
FRD FACILITIES REQUIREMENTS DOCUMENT
FS FAR SIDE
FT FEET OR FOOT
FTG FOOTING
GA GAGE OR GAUGE
GALV GALVANIZED
GEN GENERAL
GLB GLUED LAMINATED BEAM
GR GRADE
GWB GYPSUM WALLBOARD
GYP GYPSUM
H HIGH
HAS HEADED ANCHOR STUD
HDR HEADER
HGR HANGER
HORIZ HORIZONTAL
HS HEADED STUD
HSB HIGH STRENGTH BOLT
HSS HOLLOW STRUCTURAL SECTION
HT HEIGHT
HVAC HEATING/VENTILATING/AIR CONDITIONING
I MOMENT OF INERTIA
IBC INTERNATIONAL BUILDING CODE
ICBO INTERNATIONAL CONFERENCE OF BUILDING OFFICIALS
ICC INTERNATIONAL CODE COUNCIL
ID INSIDE DIAMETER
IE INVERT ELEVATION
IF INSIDE FACE
IJ ISOLATION JOINT
IN INCHES
INFO INFORMATION
INSUL INSULATE, INSULATION
INV INVERT
J JOULES
JST JOIST
JT JOINT
K KIP (1,000 POUNDS)
KSI KIPS PER SQUARE INCH
L LENGTH
LB POUND
LD REINF DEVELOPMENT LENGTH
LDh REINF DEVELOPMENT LENGTH (HOOKED BARS)
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LO LOW
LOC LOCATION
Ls REINF TENSION LAP SPLICE
LS LANDSCAPE
LSH LONG SLOTTED HOLE
LT LIGHT
LVF LOW VELOCITY FASTENER
LVL LEVEL, LAMINATED VENEER LUMBER
M METER
MAS MASONRY
MAX MAXIMUM
MECH MECHANICAL
MEZZ MEZZANINE
MF MOMENT FRAME
MFR MANUFACTURER
MH MANHOLE
MIN MINIMUM
MISC MISCELLANEOUS
MM MILLIMETER
MT MAGNETIC PARTICLE TEST
(N) NEW
N NORTH
NA NOT APPLICABLE
NAAMM NATIONAL ASSOCIATION OF ARCH METAL MANUFACTURERS
NFS NON FROST SUSCEPTABLE
NIC NOT IN CONTRACT
NIP NOT IN PERMIT
NO NUMBER
NORM NORMAL
NS NEAR SIDE
NTS NOT TO SCALE
OC ON CENTER
OD OUTSIDE DIAMETER
OF OUTSIDE FACE
OH OPPOSITE HAND
OPNG OPENING
OPP OPPOSITE
OVS OVERSIZE
OWJ OPEN WEB JOIST
PAF POWDER ACTUATED FASTENER
PC PRECAST
PCF POUND PER CUBIC FOOT
PEN PENETRATION
PIL PILASTER
PJP PARTIAL JOINT PENETRATION
PL PLATE
PLCS PLACES
PLWD PLYWOOD
PLF POUNDS PER LINEAR FOOT
PLWD PLYWOOD
PNL PANEL
PP PARTIAL PENETRATION
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT POINT, PENETRANT TEST, POINT OF TANGENCY
PRESSURE TREATED
R RADIUS
RAD RADIUS
RD ROOF DRAIN
REF REFERENCE
REINF REINFORCE, REINFORCING
REQD REQUIRED
RO ROUGH OPENING
RT RADIOGRAPHIC TEST
S SOUTH, SECTION MODULUS
SB STRAP BEAM
SC SLIP CRITICAL
SCBF SPECIAL CONCENTRIC BRACED FRAME
SCHD SCHEDULE
SD SNOW DRIFT
SDI STEEL DECK INSTITUTE
SEC SECTION
SFRS SEISMIC FORCE RESISTING SYSTEM
SHT SHEET
SHTG SHEATHING
SIM SIMILAR
SJ SEISMIC JOINT
SJ SLAB JOINT
SJRO SEISMIC JOINT ROUGH OPENING
SL SLOPE
SLB SNOW LOAD, BALANCED
SLRS SEISMIC LOAD RESISTING SYSTEM
SMAW SHIELDED METAL ARC WELDING
SOG SLAB ON GRADE
SPCS SPACES
SPEC SPECIFICATION
SQ SQUARE
SS STAINLESS STEEL
SSH SHORT SLOTTED HOLE
SSMA STEEL STUD MANUFACTURERS ASSOCIATION
STD STANDARD
STIFF STIFFENER
STL STEEL
STRUCT STRUCTURAL
SW SHEAR WALL
SYM SYMMETRICAL
TBC THREADED BAR COUPLER
TBD TO BE DETERMINED
TBR TO BE REMOVED
TC TENSION/COMPRESSION CHORD
TEMP TEMPORARY, TEMPERATURE
Tf FLANGE THICKNESS
THK THICK
TL TOTAL LOAD
T.A. TOP OF
TOC TOP OF CONCRETE
TOD TOP OF DECKING
TOF TOP OF FOOTING
TOS TOP OF STEEL, TOP OF SLAB
TOW TOP OF WALL
TS TUBE STEEL
Tw WEB THICKNESS
TYP TYPICAL
T&B TOP AND BOTTOM
UBC UNIFORM BUILDING CODE
UNO UNLESS NOTED OTHERWISE
UT ULTRASONIC TESTING
VERT VERTICAL
W WIDTH, WEST, WIDE FLANGE DESIGNATION
WF WIDE FLANGE
WHS WELDED HEADED STUD
WP WORK POINT, WATER PROOFING
WT WEIGHT
WWF WELDED WIRE FABRIC
W/ WITH
W/C WATER/ CEMENT RATIO
W/CM WATER/ CEMENTITIOUS MATERIALS RATIO
W/O WITHOUT
ABBR
STANDARD STRUCTURAL ABBREVIATIONS
DESCRIPTION
REVISION CLOUD AND REVISION NUMBER
ELEVATION SYMBOL
SECTION CUT LINE INDICATOR
GENERAL LEGEND
DETAIL SYMBOL:
SECTION SYMBOL:
B
SYMBOL
B
IDENTIFYING LETTER
SHEET WHERE SECTION IS SHOWNB =
A =
IDENTIFYING NUMBER
SHEET WHERE DETAIL IS SHOWN
A B
DESCRIPTION
INDICATES STEP IN ELEVATION
INDICATES STEP IN FOOTING ELEVATIONSS
INDICATES DECK SPAN DIRECTION
INDICATES MOMENT CONNECTION
DRAWING INDEX
DWG. NO. TITLE
S-001 GENERAL STRUCTURAL NOTES
S-101 EXISTING ROOF FRAMING PLAN
CMU (CONCRETE MASONRY UNIT) WALL (PLAN VIEW)
INDICATES DIAGONAL BRACING (PLAN VIEW)
ABBR DESCRIPTION
X INDICATES FOOTING MARK, SEE PLAN AND SCHEDULE
1 INDICATES PIER/PEDESTAL MARK, SEE PLAN AND SCHEDULE
INDICATES SHEAR WALL MARK, SEE PLAN AND SCHEDULEXXX
INDICATES GRADE BEAM MARK, SEE PLAN AND SCHEDULEGB1
GENERAL:
THE STRUCTURAL CONTRACT DRAWINGS AND SPECIFICATIONS REPRESENT THE FINISHED STRUCTURE. THEY DO NOT INDICATE THE METHOD OF CONSTRUCTION. THE STRUCTURE IS DESIGNED TO BE A STABLE UNIT AS A COMPLETED WHOLE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DESIGN, ERECT AND INSPECT TEMPORARY SHORES, BRACES, ETC. TO SUPPORT THE STRUCTURE AGAINST ALL ANTICIPATED LOADS INCLUDING GRAVITY, WIND AND LATERAL EARTH PRESSURE UNTIL ITS COMPLETION. OBSERVATION VISITS TO THE SITE BY THE STRUCTURAL ENGINEER SHALL NOT INCLUDE INSPECTION OF THESE METHODS OF CONSTRUCTION.
CONSTRUCTION MATERIAL SHALL BE PLACED ON FRAMED FLOORS AND ROOFS SUCH THAT THE DESIGN LIVE
LOADS ARE NOT EXCEEDED.
WORKMANSHIP AND MATERIALS SHALL COMPLY WITH THE EDITIONS OF THE INTERNATIONAL BUILDING CODE AND TESTING STANDARDS ACCEPTED BY THE AUTHORITY HAVING JURISDICTION AND APPLICABLE AT THE TIME THE
PROJECT WAS PERMITTED.
NOTES AND DETAILS ON THE DRAWINGS TAKE PRECEDENCE OVER THE GENERAL STRUCTURAL NOTES AND TYPICAL DETAILS. WHERE NOTES AND DETAILS ON DRAWINGS AND THESE GENERAL NOTES AND TYPICAL DETAILS ARE IN CONFLICT WITH THE PROJECT SPECIFICATION, THE MOST STRINGENT SHALL APPLY. WHERE NO SPECIFIC DETAILS ARE SHOWN, CONSTRUCTION SHALL CONFORM TO SIMILAR WORK ON THE PROJECT SUBJECT TO REVIEW BY THE ARCHITECT AND ENGINEER. "TYPICAL" DETAILS ARE NOT FLAGGED ON THE DRAWINGS, BUT APPLY
UNLESS NOTED OTHERWISE.
FRAMING MEMBERS WHICH ARE NOT DIMENSIONED SHALL BE ASSUMED EQUALLY SPACED BETWEEN
DIMENSIONED POINT OF MEMBERS SUBJECT TO REVIEW BY THE ARCHITECT AND ENGINEER.
COORDINATION:
ALL DRAWINGS ARE CONSIDERED TO BE PART OF THE CONTRACT DOCUMENTS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING THE STRUCTURAL DRAWINGS AND SPECIFICATIONS WITH THE DRAWINGS AND SPECIFICATIONS OF ALL OTHER DISCIPLINES, INCLUDING BUT NOT LIMITED TO ARCHITECTURAL, CIVIL, MECHANICAL, ELECTRICAL, FIRE PROTECTION, AND AMONG THE SUBCONTRACTORS PRIOR TO START OF CONSTRUCTION. ANY DISCREPANCIES THAT ARE FOUND SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT PRIOR TO START OF CONSTRUCTION. ANY WORK PERFORMED IN CONFLICT WITH THE CONTRACT DOCUMENTS OR ANY CODE REQUIREMENTS SHALL BE CORRECTED BY THE CONTRACTOR AT HIS OWN EXPENSE
AND AT NO EXPENSE TO THE OWNER OR DESIGN TEAM.
THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS, ELEVATIONS AND SITE CONDITIONS PRIOR TO STARTING
CONSTRUCTION. RESOLVE ANY DISCREPANCY WITH THE ENGINEER.
COORDINATION SHALL INCLUDE, BUT NOT BE LIMITED TO, VERIFYING THE LOCATION AND WEIGHT OF ALL MECHANICAL AND ELECTRICAL EQUIPMENT, AS WELL AS, THE SIZE AND LOCATION OF ALL MECHANICAL OPENINGS IN ROOFS, FLOORS AND WALLS. UNLESS OTHERWISE NOTED ON THE DRAWINGS, DO NOT PENETRATE ANY STRUCTURAL ELEMENTS SUCH AS BEAMS, COLUMNS, WALLS, HEADERS, JAMBS, SLABS, ETC. WITHOUT PRIOR
WRITTEN APPROVAL OF THE STRUCTURAL ENGINEER.
SPECIAL INSPECTIONS:
THE OWNER WILL EMPLOY AN ICC CERTIFIED SPECIAL INSPECTOR TO PROVIDE INSPECTION OF REQUIRED ITEMS
PER IBC CHAPTER 17 AND THE REQUIREMENTS OF THE APPROPRIATE LOCAL JURISDICTION:
POST INSTALLED ANCHORS; SEE INFORMATION THIS SHEET.
CODE:
2022 EDITION OF THE OREGON STRUCTURAL SPECIALTY CODE.
DESIGN LOADS:
ROOF SNOW LOAD---------------------------------------------------------------------- SEE SNOW LOADS BELOW
RISK CATEGORY------------------------------------------------------------------------- II
WIND:
WIND SPEED (3 SECOND GUST) -------------------------------------------------- 96 MPH EXPOSURE CATEGORY--------------------------------------------------------------- B INTERNAL PRESSURE COEFFICIENT GCpi------------------------------------- +/- 0.18
SEISMIC:
IMPORTANCE FACTOR (Ie) ---------------------------------------------------------- 1.0 Ss -------------------------------------------------------------------------------------------- 0.885 S1 -------------------------------------------------------------------------------------------- 0.468 Sds ------------------------------------------------------------------------------------------ 0.676 Sd1 ------------------------------------------------------------------------------------------ 0.571 SITE CLASS-------------------------------------------------------------------------------- D
SEISMIC DESIGN CATEGORY------------------------------------------------------- D
SEISMIC FORCE RESISTING SYSTEM ------------------------------------------ REINFORCED MASONRY SHEAR
WALLS
RESPONSE MODIFICATION COEFFICIENT (Rp) ----------------------------- 6 SEISMIC RESPONSE FACTOR (Fp) ----------------------------------------------- 0.20 Wp OVERSTRENGTH FACTOR (Ω) ----------------------------------------------------- 2.5 ANALYSIS PROCEDURE ------------------------------------------------------------- EQUIVALENT LATERAL FORCE
SNOW:
GROUND SNOW LOAD --------------------------------------------------------------- 14 PSF FLAT ROOF SNOW LOAD ------------------------------------------------------------ 25 PSF SNOW EXPOSURE FACTOR (Ce) ------------------------------------------------- 1.0 SNOW LOAD IMPORTANCE FACTOR (Is) -------------------------------------- 1.0 THERMAL FACTOR (Ct) --------------------------------------------------------------- 1.0 SLOPE FACTOR ------------------------------------------------------------------------- 1.0
COLD-FORMED STEEL:
ALL COLD-FORMED STEEL FRAMING SHALL BE FABRICATED AND ERECTED IN ACCORDANCE WITH THE LATEST EDITION OF "SPECIFICATIONS FOR THE DESIGN OF COLD-FORMED STEEL STRUCTURAL MEMBERS" BY THE AMERICAN IRON AND STEEL INSTITUTE AND IN ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDATIONS.
STEEL FOR ALL 54 MIL OR GREATER STUDS AND JOISTS, TRACK AND ALL THICKNESS OF DIAGONAL TENSION STRAPS SHALL HAVE A MINIMUM YIELD STRENGTH Fy = 50 KSI. STEEL FOR ALL 43 AND 33 MIL STUDS AND JOISTS, TRACK, AND ALL THICKNESS OF BRIDGING AND ACCESSORIES SHALL HAVE A MINIMUM YIELD STRENGTH Fy = 33 KSI.
STEEL SHALL BE GALVANIZED AT LOCATIONS EXPOSED TO WEATHER AND WHENEVER NOTED ON THE DRAWINGS IN ACCORDANCE WITH ASTM A653, GRADE D, FOR Fy = 50 KSI AND ASTM A653, GRADE A, FOR Fy = 33 KSI.
ALL STUDS SHALL BE SECURELY SEATED FOR FULL END BEARING ON TOP AND BOTTOM TRACK. SPLICING OF STUDS SHALL NOT BE PERMITTED. UNLESS NOTED OTHERWISE, PROVIDE DOUBLE STUDS AT ALL BEAM BEARINGS, JAMBS, WALL CORNERS AND INTERSECTIONS. UNLESS NOTED OTHERWISE, ALL TRACK SHALL BE OF THE SAME MATERIAL AND GAGE AS THE STUDS. BRIDGING SHALL BE INSTALLED PER MANUFACTURERS RECOMMENDATIONS WITH THE
FOLLOWING MINIMUM REQUIREMENTS:
FOR NON-BEARING WALLS, PROVIDE BRIDGING AT MID-HEIGHT FOR WALLS LESS THAN OR EQUAL TO 10'-0" HIGH AND 5'-0" OC MAXIMUM FOR WALLS GREATER THAN 10'-0" HIGH. FOR BEARING WALLS, PROVIDE BRIDGING EQUALLY SPACED AT 4'0" OC MAXIMUM. IN ADDITION, BRIDGING SHALL BE PROVIDED AT ROOF LINES, FLOOR LINES AND ELSEWHERE AS SHOWN ON THE DRAWINGS. SOLID BLOCKING SHALL BE INSTALLED IN LIEU OF
BRIDGING WHERE NOTED ON THE DRAWINGS.
ALL WELDING SHALL BE PERFORMED BY AWS CERTIFIED WELDERS EXPERIENCED IN LIGHTGAGE STEEL FRAMING
WORK. USE E60 (MINIMUM) SERIES LOW HYDROGEN RODS.
STUDS SHOWN ARE NOTED USING STEEL STUD MANUFACTURERS ASSOCIATION (SSMA) DESIGNATIONS AND SHALL
MEET THE MINIMUM REQUIREMENTS SHOWN IN THE LATEST EDITION OF THE SMA CATALOG.
FASTENERS:
HOT-DIPPED ZINC COATED STEEL FASTENERS CONFORMING TO THE REQUIREMENTS OF THE CURRENT EDITION OF
ASTM A153. SUBMIT TECHNICAL INFORMATION SHOWING CONFORMANCE.
FRAMING CONNECTORS:
FRAMING CONNECTORS SHALL BE ZINC COATED SHEET STEEL (GALVANIZED) BY THE HOT-DIP OR MATTE FINISH PROCESS. THE CORROSION RESISTANT COATING SHALL BE 1.25 OZ. POT YIELD COMMERCIAL CLASS HOT-DIPPED ZINC COATING, OR 0.625 OZ. MATTE FINISH HOT-DIPPED ZINC COATING EACH SIDE AND MAY BE APPLIED TO THE STEEL SHEET BEFORE THE CONNECTOR IS STAMPED OUT. FASTENERS FOR USE WITH THE FRAMING CONNECTORS
SHALL CONFORM WITH THE REQUIREMENTS ABOVE.
BASIS OF DESIGN IS SIMPSON STRONG-TIE OR SCAFCO PRODUCTS.
WOOD:
GENERAL:
DO NOT NOTCH OR DRILL JOISTS, BEAMS OR LOAD BEARING STUDS WITHOUT PRIOR APPROVAL OF THE STRUCTURAL ENGINEER THROUGH THE ARCHITECT. DOUBLE UP FLOOR JOISTS UNDER PARTITIONS. PROVIDE 1 x 3 OR METAL CROSS BRIDGING AT MIDSPAN OF ALL JOISTS. UNLESS NOTED OTHERWISE IN DRAWINGS OR DETAILS, DOUBLE UP STUDS AT JAMBS, AT GIRDER TRUSSES, AND UNDER BEAMS IN BEARING WALLS, STACKED CONTINUOUS TO FOUNDATION. AT BEAMS PERPENDICULAR TO BEARING WALLS, PROVIDE BUNDLED STUDS FOR FULL WIDTH OF BEAM STACKED CONTINUOUS TO FOUNDATION UNLESS NOTED OTHERWISE. PROVIDE 2 X SOLID BLOCKING AT MID-HEIGHT OF LOAD BEARING STUD WALLS. ALL NAILS SHALL BE COMMON NAILS. ALL NAILING NOT NOTED SHALL BE IN ACCORDANCE WITH TABLE 2304.10.1 OF THE LATEST EDITION OF THE INTERNATIONAL BUILDING CODE. ALL FRAMING ANCHORS AND CONNECTORS SHALL BE AS MANUFACTURED BY SIMPSON COMPANY OR OTHER APPROVED EQUAL WITH ICC CERTIFICATION. ALL NAIL HOLES IN FRAMING ANCHORS AND CONNECTORS SHALL BE FILLED WITH NAILS PER MANUFACTURERS PUBLISHED NAIL SIZES. ALL BOLTS SHALL BE
ASTM A307 BOLTS INSTALLED WITH STEEL WASHERS.
FRAMING LUMBER:
JOISTS
BEAMS
4x MEMBERS (MAX) 6x AND OVER
POSTS
4x MEMBERS (MAX) 6x AND OVER
STUDS
LEDGERS, TOP
AND BOT PLATES
1,350
1,200
1,600,000
1,600,000 1,600,000
1,600,000 1,600,000 1,600,000
1,600,000
1,350
1,350
1,350 1,000 1,350
1,350
DOUG FIR-LARCH #2
DOUG FIR-LARCH #2
DOUG FIR-LARCH #1
DOUG FIR-LARCH #2
DOUG FIR-LARCH #1
DOUG FIR-LARCH #2
DOUG FIR-LARCH #2
MEMBER Fb (PSI) Fv (PSI) E (PSI) Fc// (PSI). SPECIES & GRADE
ROOF 5/8" 32/16 8d @ 6" OC 8d @ 12" OC
ITEM THICKNESS
SPAN/INDEX
RATIO
EDGE
NAILING
INTERMEDIATE
NAILING
STRUCTURAL SHEATHING PROPERTIES AND ATTACHMENT
STRUCTURAL SHEATHING INCLUDES ALL-VENEER PLYWOOD:
ALL STRUCTURAL SHEATHING SHALL BE APA RATED SHEATHING WITH AN EXTERIOR OR EXPOSURE 1 DURABILITY CLASSIFICATION AND SHALL BEAR THE STAMP OF AN APPROVED TESTING AGENCY. LAY UP FLOOR AND ROOF WITH THE LONG DIMENSION PERPENDICULAR TO SUPPORTS AND PROVIDE PANEL LENGTHS TO BE CONTINUOUS OVER TWO OR MORE SUPPORTS. ALL WEATHER WOOD PLYWOOD SHALL BE BONDED WITH AN EXTERIOR GLUE AND BE GRADE MARKED INDICATING CONFORMANCE WITH THE CURRENT EDITION OF U.S. DEPARTMENT OF COMMERCE PRODUCT STANDARD PS 1 "STRUCTURAL PLYWOOD (WITH TYPICAL APA TRADEMARKS)", AND
STAMPED WITH AN APA GRADE MARK.
PRESSURE TREATMENT OF LUMBER AND PLYWOOD:
ALL LUMBER TO BE PRESERVATIVE TREATED SHALL BE PRESSURE TREATED IN ACCORDANCE WITH AMERICAN WOOD PRESERVERS BUREAU STANDARD AWPB-FDN AND BEAR THE QUALITY MARK OF AN APPROVED INSPECTION AGENCY PER AWPB-FDN. PLATES AND STUDS WITH ENDS CUT AFTER PRESSURE TREATING AND PLACED BELOW GRADE SHALL HAVE THE ENDS BELOW GRADE BRUSHED, DIPPED OR SOAKED WITH PRESERVATIVE UNTIL THE WOOD ABSORBS NO MORE PRESERVATIVE. USE THE FOLLOWING PRESERVATIVE FOR FIELD TREATMENT:
COPPER NAPHTHENATE CONTAINING A MINIMUM OF 2 PERCENT METALLIC COPPER IN SOLUTION.
ALL WEATHER WOOD FASTENERS:
NAILS: HOT-DIPPED ZINC COATED STEEL NAILS CONFORMING TO THE REQUIREMENTS OF THE CURRENT EDITION
OF ASTM A153. SUBMIT TECHNICAL INFORMATION SHOWING COMPLIANCE.
FRAMING ANCHORS:
FRAMING ANCHORS SHALL BE OF ZINC COATED SHEET STEEL (GALVANIZED) BY THE HOT-DIP OR MATTE FINISH PROCESS. THE CORROSION RESISTANT COATING SHALL BE 1.25 OZ. POT YIELD COMMERICAL CLASS HOT-DIPPED ZINC COATING, OR 0.625 OZ. MATTE FINISH HOT-DIPPED ZINC COATING EACH SIDE, AND MAY BE APPLIED TO THE STEEL SHEET BEFORE THE ANCHOR IS STAMPED OUT. NAILS/SCREWS FOR USE WITH FRAMING ANCHORS SHALL
CONFORM WITH THE REQUIREMENTS ABOVE. BASIS OF DESIGN ANCHORS ARE SIMPSON.
STEEL JOIST HANGERS SHALL BE TESTED AND APPROVED IN ACCORDANCE WITH IBC SECTION 1709.
SUBSTITUTIONS:
CONTRACTOR REQUESTED CHANGES OR SUBSTITUTIONS MUST BE SUBMITTED IN WRITING TO THE ENGINEER FOR APPROVAL PRIOR TO FABRICATION OR CONSTRUCTION. CHANGES SHOWN ON THE SHOP DRAWINGS ONLY WILL NOT SATISFY THIS REQUIREMENT. CONTRACTOR WILL BE RESPONSIBLE FOR ANY ADDITIONAL ENGINEERING EFFORT AND ASSOCIATED FEES REQUIRED FOR REVIEW AND APPROVAL OF REQUESTED CHANGES AND
SUBSTITUTIONS.
1. MECHANICAL EQUIPMENT CURBS.
SHOP DRAWINGS:
SUBMIT SHOP DRAWINGS FOR STRUCTURAL ENGINEER REVIEW PRIOR TO FABRICATION/ERECTION/INSTALLATION.
THE CONTRACTOR SHALL REVIEW AND APPROVE ALL SHOP DRAWINGS PRIOR TO ENGINEERING REVIEW.
ENGINEERS REVIEW IS ONLY FOR GENERAL CONFORMANCE WITH WITH THE DESIGN CONCEPT OF THE PROJECT AND GENERAL COMPLIANCE WITH THE INFORMATION GIVEN IN THE CONTRACT DOCUMENTS. SUBMIT ELECTRONIC COPY FOR ENGINEERING REVIEW THAT INCLUDES CONTRACTOR'S REVIEW COMMENTS. DOCUMENT WILL BE
MARKED AND RETURNED ELECTRONICALLY.
THE CONTRACTOR SHALL ALLOW 2 WEEKS FOR ENGINEER'S REVIEW OF SUBMITTALS. COMMENTS
OR MARKS ON SUBMITTALS ARE A NORMAL AND EXPECTED PART OF THE SUBMITTAL PROCESS AND SHALL NOT BE USED AS A BASIS FOR CHANGE ORDERS. TIME REQUIRED TO REVISE AND SUBMIT ANY SUBMITTAL SHALL BE CONSIDERED INHERENT TO THE SUBMITTAL REVIEW PROCESS AND SHALL NOT BE DEEMED A CHANGE ORDER.
RE-SUBMITTALS SHALL HAVE ALL REVISIONS CLEARLY IDENTIFIED WITH DRAWINGS CLOUDS AND REVISION DATES.
THE STRUCTURAL ENGINEER SHALL NOT BE RESPONSIBLE FOR THE REVIEW OF ANY UNMARKED REVISIONS.
SHOP DRAWINGS SHALL BE SUBMITTED FOR THE FOLLOWING ITEMS IN ADDITION TO ANY SUBMITTAL
REQUIREMENTS SPECIFIED ON THESE PLANS OR IN THE PROJECT SPECIFICATIONS:
DOUG FIR/LARCH (NORTH) IS NOT AN ACCEPTABLE ALTERNATIVE TO DOUG FIR/LARCH LUMBER. CONTRACTOR TO SUBMIT A SUBSTITUTION REQUEST TO THE ENGINEER OF RECORD PRIOR TO START OF CONSTRUCTION IF DOUG
FIR/LARCH (NORTH) SUBSTITUTION IS DESIRED.
FRAMING LUMBER SHALL COMPLY WITH THE LATEST EDITION OF THE GRADING RULES OF THE WESTERN WOOD PRODUCTS ASSOCIATION (WWPA) OR THE WEST COAST LUMBER INSPECTIONS BUREAU (WCLIB). ALL SAWN LUMBER SHALL BE STAMPED WITH THE GRADE MARK OF AN APPROVED GRADING AGENCY. MOISTURE CONTENT
SHALL NOT EXCEED 19%.
STRUCTURAL SHEATHING:
POST-INSTALLED ANCHORAGE:
REBAR
HILTI HIT-RE 500 V3
SIMPSON SET-XP
DEWALT PURE 110+
EXPANSION ANCHORS
HILTI KWIK BOLT TZ2
SIMPSON STRONG-BOLT 2
DEWALT PURE 110+
ADHESIVE ANCHORS
HILTI HIT-HY 200 V3
SIMPSON SET-XP OR AT-XP
DEWALT PURE 110+
SCREW ANCHORS
HILTI KWIK KH-EZ
SIMPSON TITEN HD
DEWALT SCREW-BOLT+
ANCHORAGE TO GROUT FILLED CMU
EXPANSION ANCHORS
HILTI KWIK BOLT TZ2
STRONG BOLT 2
DEWALT POWER-STUD+SD1
SCREW ANCHORS
HILTI KWIK KH-EZ
SIMPSON TITEN HD
DEWALT SCREW-BOLT+
ADHESIVE ANCHORS
HILTI HIT-HY 270
SIMPSON SET-XP OR AT-XP (AT-XP CANNOT BE USED FOR ANCHORS IN THE TOP OF THE WALL) DEWALT
AC+100 GOLD
REBAR
HILTI HIT-HY 270
SIMPSON SET-XP
POWDER ACTUATED FASTENERS (SHOT PINS) IN CONCRETE OR GROUT FILLED CMU
HILTI X-U AND X-U 15 (0.157 ” )
SIMPSON PDP SERIES (0.145 ” MIN)
INSTALLATION AND SPECIAL INSPECTION:
ADHESIVE ANCHORS MUST BE INSTALLED IN CONCRETE AGED A MINIMUM OF 21 DAYS (ACI 318-14 17.1.2) AND IN GROUTED MASONRY THAT HAS REACHED IT'S MINIMUM SPECIFIED COMPRESSIVE STRENGTH.
ADHESIVE ANCHORS INSTALLED IN HORIZONTAL OR UPWARDLY INCLINED ORIENTATIONS TO RESIST SUSTAINED TENSION LOADS SHALL BE CONTINUOUSLY INSPECTED DURING INSTALLATION BY AN INSPECTOR SPECIALLY APPROVED FOR THAT PURPOSE BY THE BUILDING OFFICIAL (ACI 318-14 17.8.2.4) PROVIDE SPECIAL INSPECTION FOR ALL MECHANICAL AND ADHESIVE ANCHORS PER THE APPLICABLE
BUILDING CODE AND PER THE CURRENT ICC-ES REPORT (IBC 2018 TABLE 1705.3 NOTE B).
ANCHOR CAPACITY IS DEPENDENT UPON SPACING BETWEEN ADJACENT ANCHORS AND PROXIMITY OF ANCHORS TO EDGE OF CONCRETE OR CMU. INSTALL ANCHORS IN ACCORDANCE WITH SPACING AND EDGE
CLEARANCES INDICATED ON THE DRAWINGS.
EXISTING REINFORCING BARS IN THE CONCRETE OR CMU STRUCTURE MAY CONFLICT WITH SPECIFIC ANCHOR LOCATIONS. UNLESS NOTED ON THE DRAWINGS THAT THE BARS CAN BE CUT, THE CONTRACTOR SHALL REVIEW THE EXISTING STRUCTURAL DRAWINGS AND SHALL UNDERTAKE TO LOCATE THE POSITION OF THE REINFORCING BARS AT THE LOCATIONS OF THE CONCRETE OR CMU ANCHORS, BY HILTI FERROSCAN, GPR, X-RAY OR OTHER MEANS APPROVED BY ENGINEER OF RECORD. DO NOT CUT REBAR, RELOCATE ANCHOR, OR REDUCE EMBEDMENT WITHOUT WRITTEN APPROVAL BY THE ENGINEER OF
RECORD.
THREADED RODS FOR ADHESIVE ANCHORS SHALL BE CLEAN THREADED ROD. FOR USE IN INTERIOR LOCATIONS THREADED ROD TO BE ASTM F1554, GRADE 36. THREADED ROD FOR USE IN INTERIOR APPLICATIONS WITH HILTI ADHESIVE TO CONCRETE AND WITH DEWALT ADHESIVE TO GROUTED MASONRY SHALL HAVE A 0.0002-INCH THICK ZINC ELECTROPLATED COATING COMPLYING WITH ASTM B633 SC 1. THREADED ROD USED AT EXTERIOR CONDITIONS OR WHERE THE ANCHOR IS IN CONTACT WITH PRESERVATIVE-TREATED OR FIRE -RETARDANT-TREATED LUMBER SHALL BE EITHER STAINLESS STEEL OR SHALL HAVE A ZINC COATING. STAINLESS STEEL THREADED RODS SHALL CONFORM TO ASTM A193, GRADE B6, B8, OR B8M FOR SIMPSON ADHESIVE PRODUCTS TO MASONRY AND WITH REBAR TO CONCRETE AND SHALL CONFORM TO ASTM F593 (AISI 304 OR 316) FOR HILTI AND DEWALT ADHESIVE PRODUCTS AND FOR SIMPSON
ADHESIVE WITH THREADED ROD TO CONCRETE. ZINC COATING ON THREADED RODS SHALL BE
HOT-DIPPED IN ACCORDANCE WITH ASTM A153 CLASS C OR D COATING.OATING.
GENERAL STRUCTURAL NOTES
SWH
KLC
GENERAL STRUCTURAL
NOTES
S-001
2-3-2026
02 16 http://www.coffman.com http://www.coffman.com http://www.coffman.com http://www.coffman.com http://www.coffman.com
75'-0"
'-0
(E ) 2 x1 2 D
F
JO
IS
TS
" O C
SP
AC
IN
G
(T
YP
D E
D.2 D.5 D.7
(E) 5/8" PLYWOOD
SHEATHING (TYP)
THROUGHOUT
(E) ROOF HATCH
(E) SKYLIGHT
(E ) 1 x3 B
RI
DG
IN
G
(T
YP
(E) RTU-2
(E) RTU-4
(E) RTU-1
(E) DUCT OPENINGS
TO BE RE-USED
(E) RTU-3
(E) SKYLIGHT
A B C
(E) ELEVATOR
CAP
(E) HCP
CONCRETE
ROOF
36'-3" 17'-8" 20'-8" 20'-0"9'-3"41'-6"
36'-3"
'-0
'-0
152'-9"
'-0
'-0
'-9
1/ 4"
'-9
1/ 4"
(E) RTU-6
(E) 5" PIPE COLUMN,
TYP (3) PLACES
(E ) 1
4B x2
(E ) 1
4B x2
(E
) 1 4B x2
(E ) 1
4B x2
(E
) 1 4B x2
16'-8"
(E) RTU-5
(E) STEEL DECK OVER
LIGHTGAGE STEEL ROOF JOISTS
(E) WALLS BELOW
(E) 14FJ1200 JOISTS
(E) 12FJ1200 JOISTS @ 4'-0" OC
(E ) 1
2x
FJ
JO
IS
TS
2' -0
" O C
(E ) W x
(E ) 1
2x
FJ
JO
IS
TS
" O
C (E
) L
IG
HT
G
AU
GE
S
TE
EL
R
OO
F
TR
US
SE
S
(E ) 1
4F J1
0 J
OI
ST
S
" O
C
(E) W14x22
(E) W14x22
(E) INFILLED
ROOF TO REMAIN
(E) 2x6 @ 16" OC
D ED.2 D.5 D.7A B C
(E) 26 GA METAL B DECK
(E ) 2
6 G A
ME
TA
L B D
EC
K
(E ) W x
(E) STEEL DECK OVER
LIGHTGAGE STEEL ROOF JOISTS
DEMO (E) ROOF SYSTEM
FOR NEW EHAUST
OPENING
(N) EF-10
3'-9 7/8"
3'- 9 7
/8"
(N) 2x6 EA END
OF UNIT
S-101
S-101
CONTRACTOR TO SUBMIT
PROPOSED METHOD OF
SUPPORTING AND BRACING
NEW EXHAUST TERMINAL
UNITS BELOW ROOF AND 2ND
FLOOR FOR APPROVAL BY
STRUCTURAL ENGINEER
(N) ETU-02
(E) 3" RIGID INSULATION
(E) 2 1/2" CONC TOPPING
SLAB
(E) 8" CONC HOLLOW CORE
PLANK
SIMPSON LUS26 HANGER
(TYP)
(E) DECKING AND MEMBRANE
CONT 2x6 LEDGER W/ 1/2" x 6"
SCREW ANCHORS @ 16" OC
(TYP)
SHEATHING
PER PLAN
8" 2 1 /2"
3"
ADD 3" RIGID INSULATION
AND SHEATHING TO MATCH (E)
AT INFILLED OPENING
10d NAILS
@6" OC (TYP)
(E) WOOD JOIST
PER PLAN
SCALE:1 SECTION: INFILL DETAIL @ ROOF OPENING (AS REQUIRED)
3/8" = 1'-0" SCALE:2 FUME EXHAUST UNIT SUPPORT
3/8"=1'-0" HOLLOW CORE PLANK CONCRETE ROOF
(E) COVERBOARD &
ROOF MEMBRANE
(E) 3" RIGID INSULATION
3'-9"
(E) 8" CONC HOLLOW
CORE PLANK
DEMO (E) INFILLED ROOF
STRUCTURE AS REQ'D FOR
NEW EXHAUST DUCT
(N) EXHAUST
FUME UNIT
TOTAL WT
1,466 LBS
1'- 6"
(N) UNIT CURB BY OTHERS.
SUBMIT STAMPED DRAWING
OF CURB AND STAMPED
STRUCTURAL CALCULATIONS
FOR CURB
2 1 /2"
1 7/16" 1 7/16"
3'-9 7/8"
3'-7" 1" 1"
DUCT TRANSITION AS REQ'D,
BY MECH CONTRACTOR TYP
(E) 2 1/2" CONC
TOPPING SLAB
CONNECTION TO CURB BY
MECH CONTRACTOR, TYP
5" 5"
(E) 3" RIGID INSULATION
(E) ROOFING MEMBRANE,
REPAIR, INSULATE, FLASH,
AND SEAL AROUND CURB
AS REQUIRED FOR A
WATERPROOF ROOF
3'-7"
CURB CONNECTION TO CONCRETE ROOF
STRUCTURE BY CURB DESIGNER. SUBMIT
STAMPED STRUCTURAL CALCULATIONS
FOR CURB CONNECTION TO ROOF
STRUCTURE. NOTE THAT CONCRETE
ANCHORS REQUIRE SPECIAL INSPECTION
REV DATE DESCRIPTION
PROJ. NO.
DRAWN
CHECKED
DATE
SHEET OF
COFFMAN ENGINEERS INC.C
HORTICULTURAL
CROPS RESEARCH LAB
3420 NW ORCHARD
AVE., CORVALLIS, OR
97331
USDA ARS
LABORATORY
EXHAUST
230612
02/04/26
SHEET TITLE:
SHEET NO:
A
B
C
D
A
B
C
D
E
E
2 3 4 5 6
2 3 4 5 6
FINAL TURNOVER
21P:
\S
PO
\23
JO
BS
\23
C
OR
VA
LL
IS
A
RS
A
HU
R
EP
LA
CE
ME
NT
S\ 0.0
D W
GS
\S
\23
_S
-1
.D W
G.
_S -1
: C
LIN
E, K
EV
IN
: L
AS
T
SA
VE
D:
F eb ru ar y 3
, 2
6 :
P
LO
T
DA
TE
: 2 /3/ www.coffman.com ph 509.328.2994
10 N. Post Street, Spokane, WA 99201 Suite 500
CEI# 230612
SCALE:
PROJECT
NORTH 3/16" = 1'-0"
ROOF FRAMING PLAN
0 2 4 8 12 16
3/16"=1'-0"
SWH
KLC
EXISTING ROOF
FRAMING PLAN
S-101
2-3-2026
03 16 http://www.coffman.com http://www.coffman.com http://www.coffman.com http://www.coffman.com
GENERAL HVAC NOTES
1. SHEET METAL DUCTWORK AND COMPONENTS INCLUDING HANGING, SEALING, PLENUMS, & ACCESSORIES SHALL BE CONSTRUCTED IN STRICT ACCORDANCE WITH THE LATEST EDITION OF SMACNA STANDARDS FOR HVAC DUCT CONSTRUCTION, NFPA 90A, & 90B STANDARDS.
2. ALL DUCTWORK OPENINGS SHALL BE COVERED DURING CONSTRUCTION.
3. ALL DAMPERS SHALL BE SET FULLY OPEN PRIOR TO BALANCING.
4. CONTRACTOR TO PROVIDE TRANSITION TO CONNECT TO ALL MECHANICAL EQUIPMENT. PROVIDE FLEXIBLE CONNECTION ON INTAKE AND DISCHARGE
OF ALL MECHANICAL EQUIPMENT.
5. DUCT DIMENSIONS SHOWN ARE INSIDE SHEET METAL DIMENSIONS OR CLEAR OPENING INSIDE LINED DUCT.
6. DRAWINGS ARE DIAGRAMMATIC IN NATURE AND DO NOT ATTEMPT TO SHOW ALL REQUIRED OFFSETS. COORDINATE WITH OTHER TRADES AND
PROVIDE ALL NECESSARY OFFSETS.
7. PROVIDE 1" THICK DUCT LINER IN ALL TRANSFER AIR DUCTWORK UNLESS NOTED OTHERWISE.
8. ALL ELBOWS SHALL BE LONG RADIUS ELBOWS WHEREVER POSSIBLE, OR SHALL HAVE TURNING VANES WHERE INDICATED ON PLANS. NO SQUARE
THROAT OR ZERO RADIUS ELBOWS ALLOWED.
9. ALL DUCT BRANCH CONNECTIONS TO DIFFUSER OR GRILLES, TO OR FROM MAIN DUCTS, SHALL INCLUDE MANUAL VOLUME DAMPERS. ALL SPIN-IN FITTINGS SHALL BE CONICAL, RECTANGULAR BRANCH DUCT TAKEOFFS SHALL HAVE 45° TAKEOFFS.
10. PROVIDE CONCEALED DAMPER REGULATORS OR ACCESS DOORS FOR ALL MANUAL VOLUME DAMPERS LOCATED THAT ARE INACCESSIBLE. REFER TO ARCHITECTURAL DRAWINGS FOR CEILING TYPES. ALL FINAL ACCESS DOOR LOCATIONS SHALL BE APPROVED BY ARCHITECT PRIOR TO
INSTALLATION.
11. 24"x24" ACCESS DOORS SHALL BE PROVIDED FOR ALL MECHANICAL EQUIPMENT LOCATED ABOVE GYPSUM BOARD CEILINGS. ALL FINAL ACCESS
DOOR LOCATIONS SHALL BE APPROVED BY ARCHITECT PRIOR TO INSTALLATION.
12. PROVIDE DIFFUSER AND GRILLE FRAMES COMPATIBLE WITH ARCHITECTURAL CEILING TYPES AND COORDINATE LOCATIONS WITH THE
ARCHITECTURAL REFLECTED CEILING PLAN AND ELECTRICAL LIGHTING LAYOUT.
13. ALL DUCTWORK VISIBLE THROUGH RETURN OR SUPPLY GRILLES TO BE PAINTED FLAT BLACK.
14. ALL SUPPLY, RETURN AND EXHAUST AIR DUCTS SHALL HAVE THE TRANSVERSE JOINTS, LONGITUDINAL SEAMS, AND DUCT WALL PENETRATIONS
SEALED AIRTIGHT WITH DUCT SEALANT (SMACNA SEAL CLASS "A").
15. COORDINATE EXACT LOCATIONS OF ALL ROOM THERMOSTATS AND/OR ROOM TEMPERATURE SENSORS WITH ARCHITECT/OWNER PRIOR TO
INSTALLATION.
16. BALANCE AIR SYSTEM TO QUANTITIES SHOWN, AND SUBMIT A COPY OF THE BALANCE REPORT TO THE ENGINEER FOR REVIEW.
GENERAL ABBREVIATIONS
ø ROUND or DIAMETER
AAV AUTOMATIC AIR VENT
ABV ABOVE
AD ACCESS DOOR
AFF ABOVE FINISH FLOOR
AHU AIR HANDLING UNIT
AL ACOUSTIC LINED
AP ACCESS PANEL
APD AIR PRESSURE DROP
ASME AMERICAN SOCIETY OF MECHANICAL
ENGINEERS
AWT AVERAGE WATER TEMPERATURE
BB BASEBOARD
BBD BACKDRAFT DAMPER
BFF BELOW FINISH FLOOR
BHP BRAKE HORSEPOWER
BG BELOW GROUND/GRADE
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNITS PER HOUR
C CENTIGRADE
CC COOLING COIL
CD CEILING DIFFUSER
CFM CUBIC FEET PER MINUTE
CG CEILING GRILLE
CI CAST IRON
CLG CEILING
CO CLEANOUT
COG CLEANOUT TO GRADE
CMU CONCRETE MASONRY UNIT
CM CONDENSATE METER
CONC CONCRETE
CONN CONNECT or CONNECTION
CONST CONSTRUCTION
CONT CONTINUATION
(D) DEMOLISH
DB DECIBEL or DRY BULB
DDC DIRECT DIGITAL CONTROL
DIA DIAMETER
DIM DIMENSION
DN DOWN
DOAS DEDICATED OUTDOOR AIR SYSTEM
DPR DAMPER
DPS DIFFERENTIAL PRESSURE SWITCH
DWG DRAWING
(E) EXISTING
EA EACH
EAT ENTERING AIR TEMPERATURE
EF EXHAUST FAN
EG EXHAUST GRILLE
ELEC ELECTRIC or ELECTRICAL
ELEV ELEVATION
EMCS ENERGY MANAGEMENT CONTROL
SYSTEM
ERV ENERGY RECOVERY VENTILATOR
ESP EXTERNAL STATIC PRESSURE
EWT ENTERING WATER TEMPERATURE
EXH EXHAUST
EXST EXISTING
F FAHRENHEIT
FCO FLOOR CLEANOUT
FCU FAN COIL UNIT
FD FLOOR DRAIN
FD FIRE DAMPER
FFD FUNNEL FLOOR DRAIN
FF FINAL FILTER
FLR FLOOR
FPM FEET PER MINUTE
FPS FEET PER SECOND
FS FLOOR SINK
FSD COMBINATION FIRE/SMOKE DAMPER
FT FOOT/FEET
FTR FINNED TUBE RADIATION
FV FACE VELOCITY
GA GAGE or GAUGE
GAL GALLON
GALV GALVANIZED
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GRD GRILLE, REGISTER, OR DIFFUSER
H HEIGHT
HB HOSE BIBB
HD HEAD
HP HORSEPOWER
HRV HEAT RECOVERY VENTILATOR
HTG HEATING
HVAC HEATING, VENTILATION AND
AIR CONDITIONING
HWG HIGH WALL GRILLE
HWR HIGH WALL REGISTER
HZ HERTZ
ID INSIDE DIAMETER
IE INVERT ELEVATION
IN INCH or INCHES
INSUL INSULATION
INV INVERT
KH KICKSPACE HEATER
KW KILOWATT
KWH KILOWATT HOUR
L LENGTH
LAT LEAVING AIR TEMPERATURE
LBS POUNDS
LF LINEAR FOOT/FEET
LVG LEAVING
LWG LOW WALL GRILLE
LWR LOW WALL REGISTER
LWT LEAVING WATER TEMPERATURE
MAX MAXIMUM
MAV MANUAL AIR VENT
MBH 1000 BRITISH THERMAL UNITS
PER HOUR
MCA MINIMUM CIRCUIT AMPACITY
MCC MOTOR CONTROL CENTER
MFR MANUFACTURER
MOP MAXIMUM OVERCURRENT
PROTECTION
MUA MAKEUP AIR UNIT
MIN MINIMUM
MISC MISCELLANEOUS
MTD MOUNTED
MTG MOUNTING
(N) NEW
(NL) NEW LOCATION
N/A NOT APPLICABLE
N/C NORMALLY CLOSED
N/O NORMALLY OPEN
NC NOISE CRITERIA
N.I.C. NOT IN CONTRACT
NPT NATIONAL PIPE THREAD
NTS NOT TO SCALE
OA OUTSIDE AIR
OBD OPPOSED BLADE DAMPER
O/C ON CENTER
OD OUTSIDE DIAMETER
OPNG OPENING
PVC PRESSURE CONTROL VALVE
PD PRESSURE DROP
PH PHASE
PLCS PLACES
POC POINT OF CONNECTION
POUA POINT OF USE ALARM
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH (GAGE)
(REL) RELOCATE
RA RETURN AIR
RAG RETURN AIR GRILLE
REQD REQUIRED
R.O. ROUGH OPENING
RPBP REDUCED PRESSURE BACKFLOW
PREVENTER
RPM REVOLUTIONS PER MINUTE
SA SUPPLY AIR
SD SMOKE DETECTOR
SF SUPPLY FAN
SHT SHEET
SIM SIMILAR
SL SOUNDLINING
SP STATIC PRESSURE
SQ SQUARE
SQ FT SQUARE FOOT/FEET
SS STAINLESS STEEL
STD STANDARD
TAB TESTING, ADJUSTING & BALANCING
THK THICK
TP TRAP PRIMER or TEST PLUG
TSP TOTAL STATIC PRESSURE
TYP TYPICAL
TU TERMINAL UNIT
UBC UNIFORM BUILDING CODE
UFC UNIFORM FIRE CODE
UMC UNIFORM MECHANICAL CODE
UPC UNIFORM PLUMBING CODE
UG UNDERGROUND
UH UNIT HEATER
UNO UNLESS NOTED OTHERWISE
VA VALVE
VAC VACUUM
VAV VARIABLE AIR VOLUME
VD VOLUME DAMPER
VEL VELOCITY
VFD VARIABLE FREQUENCY DRIVE
VRF VARIABLE REFRIGERANT FLOW
VTR VENT THRU ROOF
W WIDE
W/ WITH
W/O WITHOUT
WB WET BULB
WC WATER COLUMN
WCO WALL CLEANOUT
WG WATER GAGE
WGE WASTE GAS EVACUATION
WH WALL HYDRANT
WPD WATER PRESSURE DROP
WT WEIGHT
HVAC DUCTWORK LEGEND
DUCTWORK
24x12 S/A
RECTANGULAR DUCT
SIZE (INCHES) FIRST
DIMENSION IS SIDE OF
DUCT SHOWN
DUCT SIZES SHOWN ON DRAWINGS ARE CLEAR INSIDE DIMENSIONS OF DUCT. DUCT SIZE
SHOWN DOES NOT INCLUDE INSULATION OR LINING UNLESS NOTED OTHERWISE. SEE
BELOW FOR DUCT SIZE TAG LEGEND.
DUCT SIZE
DUCT SYSTEM ABBREVIATION
(NOT ALWAYS BE SHOWN)
INSULATED DUCT
SOUND LINED DUCT
24x12ø
FLAT OVAL DUCT
SIZE (INCHES) FIRST
DIMENSION IS SIDE OF
DUCT SHOWN
24ø ROUND DUCT
18ø24x12
CHANGE IN DUCT SIZE
AND/OR SHAPE
SUPPLY AIR (SA)
OUTSIDE AIR (OSA)
RECTANGULAR DUCT
TURNED UP/SECTION
ROUND/FLAT OVAL DUCT
TURNED UP/SECTION
RECTANGULAR DUCT
TURNED DOWN/AWAY
ROUND/FLAT OVAL DUCT
TURNED DOWN/AWAY
RETURN AIR (RA)
RECTANGULAR DUCT
TURNED UP/SECTION
ROUND/FLAT OVAL DUCT
TURNED UP/SECTION
RECTANGULAR DUCT
TURNED DOWN/AWAY
ROUND/FLAT OVAL DUCT
TURNED DOWN/AWAY
EXHAUST AIR (EA)
RECTANGULAR DUCT
TURNED UP/SECTION
ROUND/FLAT OVAL DUCT
TURNED UP/SECTION
RECTANGULAR DUCT
TURNED DOWN/AWAY
ROUND/FLAT OVAL DUCT
TURNED DOWN/AWAY
DAMPERS
VOLUME/BALANCING
DAMPER
FIRE DAMPER (FD)
SMOKE DAMPER (SD)
FIRE/SMOKE DAMPER
(FSD)
BACKDRAFT DAMPER
MOTORIZED DAMPER
DUCT SYSTEM ABBREVIATIONS
M
SUPPLY AIRSA
OUTSIDE AIROSA
COMBUSTION AIRCA
RETURN AIRRA
TRANSFER AIRTA
EXHAUST AIREA
FLEXIBLE DUCT
DUCT SYMBOLS
DUCT END CAP
DUCT ACCESS DOOR
AD
SUPPLY AIR (SA)
TERMINAL
RETURN AIR (RA) OR
TRANSFER AIR (TA) TERMINAL
AIR TERMINAL
IDENTIFICATION
EXHAUST AIR (EA) TERMINAL
GRILLE, REGISTER, OR OPEN
DUCT
X
CFM
AIRFLOW DIRECTION
SOUND ATTENUATOR
OR X-CFM
PIPING LEGEND
CS
CR
CWS
CWR
CONDENSER
WATER SUPPLY
CONDENSER
WATER RETURN
CHILLED WATER
SUPPLY
CHILLED WATER
RETURN
HWS
HWR
HEATING HOT
WATER SUPPLY
HEATING HOT
WATER RETURN
HGS
HGR
HEATING GLYCOL
SUPPLY
HEATING GLYCOL
RETURN
FOS
FOR
FUEL OIL SUPPLY
FUEL OIL RETURN
SMS
SMR
SNOWMELT
GLYCOL SUPPLY
SNOWMELT
GLYCOL RETURN
RL
REFRIGERANT
LIQUID LINE
RS
REFRIGERANT
SUCTION LINE
HRS
HIGH PRESSURE
REFRIGERANT
SUCTION LINE
GWS
GWR
GEOTHERMAL
WATER SUPPLY
GEOTHERMAL
WATER RETURN
G NATURAL GAS
PG PROPANE GAS
LPG
LIQUID PETROLEUM
GAS
CA COMPRESSED AIR
LPS
LOW PRESSURE
STEAM SUPPLY
LPR
LOW PRESSURE
STEAM RETURN
LPC
LOW PRESSURE
CONDENSATE
MPS
MEDIUM PRESSURE
STEAM SUPPLY
MPR
MEDIUM PRESSURE
STEAM RETURN
MPC
MEDIUM PRESSURE
CONDENSATE
HPS
HIGH PRESSURE
STEAM SUPPLY
HPR
HIGH PRESSURE
STEAM RETURN
HPC
HIGH PRESSURE
CONDENSATE
D
CONDENSATE
DRAIN (D)
VAC VACUUM (VAC)
PLUMBING/PIPING SYMBOLS LEGEND
VALVE
GATE VALVE
BALL VALVE
GLOBE VALVE
PLUG VALVE
BUTTERFLY VALVE
SPECIALTY VALVE
OS & Y VALVE
STOP COCK
PRESSURE REDUCING
VALVE
PRESSURE REGULATING
VALVE
CHECK VALVE
SPRING CHECK VALVE
STRAINER
STRAINER W/
BLOWDOWN
BACKFLOW PREVENTER
BALANCING VALVE
AUTOMATIC BALANCING
VALVE
A
RELIEF VALVE
FUEL ANTI-SIPHON
VALVE
F
FUSIBLE OIL SAFETY
VALVE
MOTORIZED VALVE
NEEDLE VALVE
M M
SOLENOID VALVE
S S
AUTOMATIC CONTROL
VALVE
FLOW SWITCH
PRESSURE SWITCH
FS
PS
PIPE ELBOW DOWN
(OR AWAY)
PIPE ELBOW UP
(OR TOWARDS)
PIPE TEE DOWN
(OR AWAY)
PIPE TEE UP
(OR AWAY)
FLOW DIRECTION
PIPE SLOPE
& DIRECTION
REDUCER, CONCENTRIC
REDUCER, ECCENTRIC
UNION
FLANGES
BLIND FLANGE
END CAP
PT PLUG (TEST PORT)
FLEX CONNECTOR/
COUPLING
EXPANSION JOINT
EXPANSION GUIDE
PIPE ANCHOR
HOSE QUICK
DISCONNECT
HOSE THREAD DRAIN
BALL VALVE
HOSE BIBB
WALL HYDRANT
HOSE THREAD DRAIN
VALVE
FIRE DEPARTMENT
CONNECTION
WATER HAMMER
ARRESTOR
THERMOWELL
THERMOMETER
DIAL THERMOMETER
T
PRESSURE GAUGE
W/ COCK
P
PRESSURE GAUGE
W/ COCK & SIPHON
P
AIR VENT
A - AUTOMATIC
C - COIN
M - MANUAL
H - HIGH VOLUME
A
BASKET STRAINER
AIR FILTER W/
COALESCER & DRAIN
AIR FILTER W/
COALESCER, DRAIN,
REGULATOR & GAUGE
PUMP (SYMBOLIC -
ARROW INDICATES
FLOW DIRECTION)
WATER METERM
WATER HAMMER
ARRESTOR (PLAN)
V#
S=2%
GENERAL LEGEND
THERMOSTAT. ADJACENT NUMBER
INDICATES TERMINAL UNIT CONTROLLED
HUMIDISTAT
SENSOR
CO2 SENSORCO2
T
H
S
PLUMBING FIXTURE TAG, SEE PLUMBING SCHEDULES
NOTES:
XX-X
SPECIFIC TO LOCATION(S) INDICATED.
A. NOTE APPLIES TO ENTIRE SHEET.
EXISTING
NEW
(E)
(N)
EXISTING (THIN)
NEW (MEDIUM)
POINT OF CONNECTION (POC)
EXISTING TO BE DEMOLISHED
MECHANICAL EQUIPMENT, SEE MECHANICAL SCHEDULES.XX-X
x
SD DUCT SMOKE DETECTOR
SP DUCT STATIC PRESSURE
LINETYPES:
B
A
A
B
DETAIL SYMBOL:
A = IDENTIFYING NUMBER
B = SHEET WHERE DETAIL IS SHOWN
SECTION SYMBOL:
A = IDENTIFYING NUMBER
B = SHEET WHERE DETAIL IS SHOWN
NEW LOCATION(NL)
RELOCATE(REL)
GENERAL NOTES
1. CONTRACTOR SHALL SECURE, MAINTAIN, AND PAY FOR ALL REQUIRED PERMITS, LICENSES, AND INSPECTIONS FOR DURATION OF WORK UNLESS
DIRECTED OTHERWISE.
2. ALL WORK SHALL COMPLY WITH THE OWNER'S REQUIREMENTS, AND WITH ALL APPLICABLE STATE AND LOCAL CODES, OR AUTHORITY HAVING
JURISDICTION.
3. SUBSTITUTIONS OF EQUIPMENT OTHER THAN AS SPECIFIED SHALL BE THE COMPLETE RESPONSIBILITY OF THE CONTRACTOR, ANY ADDITIONAL ELECTRICAL, STRUCTURAL, MECHANICAL, OR ARCHITECTURAL REQUIREMENTS SHALL BE PROVIDED AT NO ADDITIONAL EXPENSE TO THE OWNER.
4. DRAWINGS ARE DIAGRAMMATIC IN NATURE AND DO NOT ATTEMPT TO SHOW ALL REQUIRED OFFSETS. COORDINATE WITH OTHER TRADES AND PROVIDE ALL NECESSARY OFFSETS. REFER TO ARCHITECTURAL AND STRUCTURAL DRAWINGS FOR CONSTRUCTION DETAILS.
5. REFER TO PROJECT MANUAL (SPECIFICATIONS) FOR ADDITIONAL REQUIREMENTS. PLANS AND SPECIFICATIONS SHALL BE TAKEN TOGETHER.
PROVIDE ALL WORK CALLED FOR IN EITHER. IN CASE OF CONFLICT BETWEEN SPECIFICATIONS AND PLANS THE MORE STRINGENT SHALL APPLY.
6. ALL EQUIPMENT AND MATERIAL ON THE JOB SITE PRIOR TO INSTALLATION SHALL BE COVERED AND PROTECTED FROM RAIN, DIRT, DUST, AND
DAMAGE.
7. VERIFY PHYSICAL DIMENSIONS OF EQUIPMENT TO ENSURE THAT ACCESS CLEARANCES CAN BE MET. COORDINATE FINAL EQUIPMENT LOCATIONS W/ GENERAL CONTRACTOR AND OTHER TRADES TO ALLOW FOR REQUIRED MECHANICAL EQUIPMENT CLEARANCES.
8. PROVIDE AN UNOBSTRUCTED PASSAGEWAY MEASURING NO LESS THAN 36" WIDE BY 80" HIGH FROM DOOR INTO THE SPACE TO SERVICEABLE MECHANICAL EQUIPMENT. A LEVEL WORKING SPACE MEASURING NO LESS THAN 30" WIDE BY 36" DEEP MUST BE PROVIDED IN FRONT OF CONTROL
SIDE OF EQUIPMENT FOR SERVICING.
9. PROVIDE NEC CODE MINIMUM HORIZONTAL AND VERTICAL WORKING CLEARANCES FOR ALL ELECTRICAL PANELS AND EQUIPMENT. OFFSET
MECHANICAL WORK AS REQUIRED.
10. CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF INSTALLATION STANDARDS AND CONSTRUCTION CONDITIONS. CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND EXISTING CONDITIONS PRIOR TO SHOP FABRICATION AND/OR FIELD INSTALLATION. DISCREPANCIES BETWEEN EXISTING CONDITIONS AND THE CONSTRUCTION DRAWINGS SHALL BE CALLED TO THE ATTENTION OF THE ENGINEER.
11. ALL MECHANICAL EQUIPMENT, MATERIALS, AND INSTALLATION SHALL BE PROVIDED BY THE CONTRACTOR. ALL EQUIPMENT SHALL BE COMPLETE, INSTALLED, AND FULLY FUNCTIONAL PRIOR TO FINAL ACCEPTANCE OF THE WORK.
12. INSTALL ALL EQUIPMENT PER MANUFACTURERS RECOMMENDATIONS AND REQUIREMENTS. ANY CONFLICTS BETWEEN THE MANUFACTURERS DOCUMENTATION AND THE CONTRACT DOCUMENTS SHALL BE BROUGHT TO THE ATTENTION OF THE ENGINEER.
13. DO NOT ALLOW ANY WORK TO BE COVERED UP OR ENCLOSED UNTIL INSPECTED, TESTED AND APPROVED BY OWNER'S REPRESENTATIVE OR
AUTHORITY HAVING JURISDICTION.
14. MECHANICAL EQUIPMENT SHALL NOT BE USED FOR TEMPORARY HEATING OR COOLING DURING CONSTRUCTION.
15. PIPES AND WIRING IN PLENUM SHALL BE RATED FOR PLENUM USE. PVC, ABS, AND PLASTIC PIPING IS NOT ACCEPTABLE IN PLENUM APPLICATIONS.
16. ALL DETAILS ARE TYPICAL UNLESS NOTED OTHERWISE.
DESIGN CONDITIONS
OUTDOORS
VENTILATION
INDOOR
ELEVATION
COOLING
HEATING
COOLING
HEATING
USDA ARS 242.1M 2024
250 FT ABOVE SEA LEVEL
LOCATION CORVALLIS, OR
CLIMATE ZONE 4C (BENTON COUNTY)
92.7°F DB / 67.0°F WB
11.8°F DB
72°F
68°F www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:1
:5
P
M
02/04/2026
TAH
PJTM
230612
M-001
MECHANICAL
LEGENDS AND
ABBREVIATIONS
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
MECHANICAL SHEET INDEX
SHEET NUMBER SHEET NAME
M-001 MECHANICAL LEGENDS AND ABBREVIATIONS
MD-101 FIRST FLOOR PLAN WEST MECHANICAL DEMO PLAN
MD-102 SECOND FLOOR PLAN WEST MECHANICAL DEMO PLAN
MD-103 MECHANICAL ROOF DEMO PLAN
M-201 FIRST FLOOR WEST ZONE PLAN
M-202 SECOND FLOOR WEST ZONE PLAN
M-203 FIRST FLOOR WEST MECHANICAL PLAN
M-204 SECOND FLOOR WEST MECHANICAL PLAN
M-205 MECHANICAL ROOF PLAN
M-501 MECHANICAL DETAILS
M-701 MECHANICAL CONTROLS
M-702 MECHANICAL SCHEDULES
04 16
M
A B C D
OFFICE
TECHNICIAN'S OFFICE
OFFICE
LAB
110 PREP ROOM
COLD ROOM
LAB
LAB
OFFICE
HALLWAY
EQUIPMENT ROOM
MECHANICAL ROOM
JANITOR
ELEVATOR EQUIP.
ELECTRICAL ROOM
RECEPTION/OFFICE
VESTIBULE
HALLWAY
MENS
WOMENS
(E) AIR SEPARATOR
FD
T
T
T
T T T HC-6HC-1
HC-2
HC-3
12x6
8ø
8ø x1 x1
10ø
8ø x6
12ø ø ø ø
36x14 24 x1 x1
12x6
24x18
8ø x1
6ø ø ø
10ø x1
8ø
24x10
12ø
12ø ø
9ø
10ø
6ø x1 x6
8ø
8ø
10ø
10ø
10ø 18x16 x1
18x10 12x8
S-190
S-320
T-190
S-160
S-430
S-430
S-430
S-430
S-170
S-170
S-410
S-600
S-230
S-200
T-300R-900
S-260
S-260
S-120
E-300
T-300
E-50
T-170
T-170
T-230
12x8
T-230
S-150
T-190
T-160
T-160
T HC-5
(E) HC-3
(E) HC-4
(E) SF-1 M
(E) HC-4
(E) HC-6
(E) HC-2
(E) HC-1
(E) B-1
(E) EF-3
(E) 12x12 LOUVER(E) 28x20 COMBUSTION
AIR LOUVERS (ONE
HIGH, ONE LOW)
(E) HC-5
(E) FILTER RACK
(E) 12x12 LOUVER
THIS UNIT
ABANDONED
IN PLACE
SP
6YCSTN
FUME HOOD
ENVIRO
CHAMBER
INCUBATOR
LAMINAR
FLOW HOOD
-80C
FREEZER
AUTOCLAVE
STEAM
WASHER
FRIDGES
FUME HOOD
BIOSAFETY
CABINET
INCUBATOR
ENVIRO
CHAMBER
FREEZER
M
(E) HWP-1
GENERAL NOTES
A. THESE DRAWINGS HAVE BEEN PREPARED USING OWNER
PROVIDED RECORD DRAWINGS DATED 06-01-93 AND THROUGH
FIELD OBSERVATIONS. VERIFY EXISTING CONDITIONS AS THEY
APPLY TO THIS PROJECT AND INCLUDE IN BID A SUFFICIENT
ALLOWANCE TO COVER ANY DISCREPANCY BETWEEN THE
DRAWINGS AND THE ACTUAL CONDITIONS AS THEY CURRENTLY
EXIST.
B. EXISTING WORK IS SHOWN WITH LIGHT LINES AND DEMO WORK IS
SHOWN WITH BOLD BROKEN LINES, TYP.
C. CONTRACTOR SHALL BE RESPONSIBLE FOR DISPOSAL OF ALL
EQUIPMENT THE OWNER DOES NOT WISH TO RETAIN FOR FUTURE
USE.
D. CONTRACTOR SHALL COORDINATE ANY SHUT DOWN OF SYSTEMS
WITH OWNER.
E. AIRFLOWS SHOWN ON DEMO SHEETS CORRESPOND WITH
PREVIOUS DESIGN AND TAB REPORTS.
www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:1
:5
P
M
02/04/2026
TAH
PJTM
230612
MD-101
FIRST FLOOR PLAN
WEST MECHANICAL
DEMO PLAN
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
1/4" = 1'-0"
FIRST FLOOR PLAN WEST MECHANICAL DEMO PLAN
KEY NOTES
1 LOCATE AND DEMOLISH EXISTING MOTORIZED DAMPER AND
STATIC PRESSURE SENSOR. DUCT WILL BE RECONNECTED
WITH NEW EXHAUST TERMINAL UNIT.
05 16
OFFICE
TECHNICIANS OFFICE
OFFICE
STORAGE
LAB
LAB
LAB
PREP ROOM
COLD ROOM
EQUIPMENT ROOM
OFFICE
HALLWAY
CONFERENCE ROOM
HALLWAY
HALLWAY
12x8
12x6 x6
10ø
10ø x1 x1
8ø
8ø ø ø ø ø
12ø
8ø x6 ø x1
24x16 x1 x1
36x18 x1 x1
10ø 8ø x1 x1
9ø
18x10
18x10 x8
18x10 18x10
18x14 x1 x1 x1 ø
10ø ø ø ø
22x12
8ø
9ø ø
24x16 x1 x1
12ø
10ø ø
10ø
10ø 18x18
10ø
8ø
S-210
T-210
T-210
S-505
S-505
S-505
S-505
S-350
S-180
T-180
T-180
S-140 S-140
S-280
S-250
R-560
R-525
S-300
S-400
S-365S-365
S-170
R-730
R-0
R-0
8ø
THC-8
T
HC-7
T HC-12
T
HC-13
T
HC-10
T SF-2
THC-9
3/4"
3/4"
3/4"
1"
1 1/4"
2"
2"
3/4"
2"
3/4" 3/4"
HC-9
(E) HC-11
HC-10
(E) HC-8
(E) HC-7
(E) HC-13
(E) HC-14
S-275
S-240
T-240
T-240
S-630
S-500
S-170
T-170
T-170
M
UP TO
RTU-6
UP TO RTU-5
(E) HC-12
10" SS FUME HOOD
EXHAUST UP TO
ROOF, TYP. 7
(E) 12x12 LOUVER
(E) FILTER RACK
THIS UNIT
ABANDONED
IN PLACE
SP
INCUBATOR
FRIDGE/FREEZER
SAFETY
CABINET
SPECTROMETER
MICROWAVE
REACTION
SYSTEMFUME HOOD
ARGON
TANKS
CORROSIVE
STORAGE
FUME HOOD
FUME HOOD
LECO
TENNEY
EQUITY
LAMINAR
FLOW HOOD
GROW
RACK
FLAM
GENERAL NOTES
A. THESE DRAWINGS HAVE BEEN PREPARED USING OWNER
PROVIDED RECORD DRAWINGS DATED 06-01-93 AND THROUGH
FIELD OBSERVATIONS. VERIFY EXISTING CONDITIONS AS THEY
APPLY TO THIS PROJECT AND INCLUDE IN BID A SUFFICIENT
ALLOWANCE TO COVER ANY DISCREPANCY BETWEEN THE
DRAWINGS AND THE ACTUAL CONDITIONS AS THEY CURRENTLY
EXIST.
B. EXISTING WORK IS SHOWN WITH LIGHT LINES AND DEMO WORK IS
SHOWN WITH BOLD BROKEN LINES, TYP.
C. CONTRACTOR SHALL BE RESPONSIBLE FOR DISPOSAL OF ALL
EQUIPMENT THE OWNER DOES NOT WISH TO RETAIN FOR FUTURE
USE.
D. CONTRACTOR SHALL COORDINATE ANY SHUT DOWN OF SYSTEMS
WITH OWNER.
E. AIRFLOWS SHOWN ON DEMO SHEETS CORRESPOND WITH
PREVIOUS DESIGN AND TAB REPORTS.
www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:1
:5
P
M
02/04/2026
TAH
PJTM
230612
MD-102
SECOND FLOOR
PLAN WEST
MECHANICAL
DEMO PLAN
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
1/4" = 1'-0"
SECOND FLOOR PLAN WEST MECHANICAL DEMO PLAN
KEY NOTES
1 EXISTING DUCT UP TO ROOF IS CURRENTLY CAPPED BELOW
ROOF INFILL. REMOVE CAP AND PREPARE THE DUCT TO
CONNECT TO NEW EXHAUST FAN.
2 LOCATE AND DEMOLISH EXISTING MOTORIZED DAMPER AND
STATIC PRESSURE SENSOR IN CEILING SPACE. DUCT WILL BE
RECONNECTED WITH NEW EXHAUST TERMINAL UNIT. REMOVE
EXISTING ACOUSTIC GPY. BOARD FROM AROUND DUCTWORK
AS NECESSARY TO REPLACE THE TERMINAL UNIT.
06 16
A B C D D.2 D.5 D.7 E
(E) ROOF DRAINS
(E) PLUMBING VENT(E) HYDRONIC
BOILER VENT
(E) PLUMBING
VENT
(E) ROOF DRAIN
(E) PLUMBING
VENT
(E) PLUMBING
VENT
(E) PLUMBING
VENT
(E) STEAM
BOILER FLUE
STACK
(E) PLUMBING
VENT
(E) CU
(E) PLUMBING
VENT
(E) PLUMBING
VENT
(E) PLUMBING
VENT
(E) EF-4
(E) EF-5
(E) EF-6
(E) EF-7
(E) EF-8
(E) EF-9
(E) RTU-6
(E) CU
(E) CU
(E) RTU-4
(E) CU
(E) RTU-2
(E) EF-2
(E) EF-4
(E) EF
(E) CU
(E) RTU-1
(E) EF-1(E) EF-3
(E) RTU-3
(E) RTU-5
GENERAL NOTES
A. THESE DRAWINGS HAVE BEEN PREPARED USING OWNER
PROVIDED RECORD DRAWINGS DATED 06-01-93 AND THROUGH
FIELD OBSERVATIONS. VERIFY EXISTING CONDITIONS AS THEY
APPLY TO THIS PROJECT AND INCLUDE IN BID A SUFFICIENT
ALLOWANCE TO COVER ANY DISCREPANCY BETWEEN THE
DRAWINGS AND THE ACTUAL CONDITIONS AS THEY CURRENTLY
EXIST.
B. EXISTING WORK IS SHOWN WITH LIGHT LINES AND DEMO WORK IS
SHOWN WITH BOLD BROKEN LINES, TYP.
C. CONTRACTOR SHALL BE RESPONSIBLE FOR DISPOSAL OF ALL
EQUIPMENT THE OWNER DOES NOT WISH TO RETAIN FOR FUTURE
USE.
D. CONTRACTOR SHALL COORDINATE ANY SHUT DOWN OF SYSTEMS
WITH OWNER.
E. AIRFLOWS SHOWN ON DEMO SHEETS CORRESPOND WITH
PREVIOUS DESIGN AND TAB REPORTS.
www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:1
:5
P
M
02/04/2026
TAH
PJTM
230612
MD-103
MECHANICAL ROOF
DEMO PLAN
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
3/16" = 1'-0"
MECHANICAL ROOF DEMO PLAN
KEY NOTES
1 CREATE ROOF OPENING AS NECESSARY TO ACCESS EXISTING
CAPPED DUCTWORK AND INSTALL NEW EXHAUST FAN CURB.
07 16
OFFICE
TECHNICIAN'S OFFICE
OFFICE
LAB
LAB
LAB
OFFICE
EQUIPMENT ROOM
COLD ROOM
PREP ROOM
HALLWAY
JANITOR
ELEVATOR EQUIP.
MECHANICAL ROOM
ELECTRICAL ROOM
RECEPTION/OFFICE
VESTIBULE
HALLWAY
MENS
WOMENS
T
T
HC-02
HC-03 T HC-01
T HC-06
T SF-01
T HC-04
T HC-05
DP +-
(N) ETU-1
www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:2
:2
A M
02/04/2026
TAH
PJTM
230612
M-201
FIRST FLOOR WEST
ZONE PLAN
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
1/4" = 1'-0"
FIRST FLOOR WEST ZONE PLAN
KEY NOTES
1 INSTALL NEW DIFFERENTIAL PRESSURE SENSOR ABOVE
EXISTING DOORWAY BETWEEN LABORATORY AND HALLWAY.
SENSOR SHALL CONNECT TO THE BAS AND WILL BE USED TO
CONTROL ETU AIRFLOW SETPOINT. SEE 4/M-501.
2 EXISTING THERMOSTAT FOR EXHAUST FAN
ABANDONED-IN-PLACE. SHOWN FOR CLARITY, NO SCOPE IN
THIS PROJECT.
08 16
OFFICE
TECHNICIANS OFFICE
OFFICE
LAB
LAB
LAB
OFFICE
EQUIPMENT ROOM
COLD ROOM
PREP ROOM
STORAGE
HALLWAY
HALLWAY
HALLWAY
CONFERENCE ROOM
T HC-08
T HC-09
T HC-07
T HC-12
T HC-14T HC-13
T SF-2
T HC-10
T HC-11
DP +-
(N) ETU-2
www.coffman.com
221 N. Wall Street, Suite 500
Spokane, WA 99201 ph 509.328.2994
SHEET OF
DATE
CHECKED
DRAWN
PROJ. NO.
A
B
D
54321
D
C
B
A
1 2 3 4 5
SHEET NO:
SHEET TITLE:
C
EE
COFFMAN ENGINEERS INC.C
/3
/2
:2
:2
A M
02/04/2026
TAH
PJTM
230612
M-202
SECOND FLOOR
WEST ZONE PLAN
FINAL
TURNOVER
HORTICULTURAL
CROPS RESEARCH
LAB
USDA ARS
LABORATORY
EXHAUST
3420 NW ORCHARD AVE.,
CORVALLIS, OR 97331
REV DATE DESCRIPTION
1/4" = 1'-0"
SECOND FLOOR WEST ZONE PLAN
KEY NOTES
1 INSTALL NEW DIFFERENTIAL PRESSURE SENSOR ABOVE
EXISTING DOORWAY BETWEEN LABORATORY AND HALLWAY.
SENSOR SHALL CONNECT TO THE BAS AND WILL BE USED TO
CONTROL ETU AIRFLOW SETPOINT. SEE 4/M-501.
2 EXISTING THERMOSTAT FOR EXHAUST FAN
ABANDONED-IN-PLACE. SHOWN FOR CLARITY, NO SCOPE IN
THIS PROJECT.
09 16
A. INSTALL NEW EXHAUST…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .