C04a PWS_12444326Q0066.pdf
PDF 384 KB Posted
- Solicitation number
- 12444326Q0066
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Performance Work Statement (PWS) for injection molding services issued by the US Department of Agriculture Forest Service, National Technology & Development Program (NTDP), Wildland Fire Chemical Systems (WFCS) Laboratory located in Missoula, Montana.
The WFCS Laboratory requires a vendor to design, fabricate, and tool injection molds for four distinct PEEK resin parts used in corrosion testing equipment. The four parts are: Threaded Rim-Ring Top, Dipping Shaft–Pincher, Dipping Shaft–Galvanic, and Dipping Shaft–Crevice. These parts are currently 3D-printed prototypes that must be converted to injection-molded production versions. The base year initial order consists of 1,000 interchangeable Rim-Ring tops and 500 of each dipping shaft type, with eventual requirements of 6,000–7,500 Rim-Ring tops and 2,000–2,500 of each shaft type per product line (retardant, foam, and gels). The vendor must provide a pricing schedule with volume discounts and minimum quantity information, as the government reserves discretion over order quantities. All deliverables include a first batch of 20 parts per design for testing, with mold specifications, designs, and renderings retained by NTDP for future production batching.
The contractor must provide subject matter expert technical consultation on mold design, durability optimization, production yield per cycle, and cleaning durability for dishwasher reuse. Work is performed at the vendor's facility with an estimated six-week timeline for initial mold fabrication and tooling from contract award. All intellectual property rights, including the molds themselves, are owned by NTDP with unlimited utilization rights. Quality assurance is conducted by the government using visual inspection and agency review, with rework required for unsatisfactory deliverables. No specific response date, award date, or contract vehicle is identified in this document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12444326Q0066 AMEND 0002 Question and Answer.pdf | ||
| Questions Answers_12444326Q0066 Updated as of 11SEP2026.pdf | ||
| 12444326Q0066 AMEND 0001 Question and Answer.pdf | ||
| C04 Solicitation_12444326Q0066.pdf | ||
| C04b SOI_12444326Q0066.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Performance Work Statement
NTDP – Wildland Fire Chemical Systems
Injection Molding for Corrosion Tests Modernization
Contents Project Title General Information
1.0 Background and Purpose
2.0 Definitions
Agreement Statement of Work
3.0 Technical Requirements / Tasks
4.0 Deliverable / Schedule
5.0 Work Location
6.0 Travel
7.0 Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 -
11.0 Performance Requirement Measures
Project Title Injection Molding for Corrosion Tests Modernization
General Information
1.0 Background and Purpose
The US Forest Service (USFS), National Technology & Development Program (NTDP), Wildland Fire Chemical System (WFCS) Laboratory is in the process of completing a revision update of the specifications for Qualified Product List (QPL).
These specifications include a variety of tests and evaluation of the different product’s physical characteristics. Corrosion testing is part of each of the specifications, and within this testing category there are three different tests conducted.
Testing is done for uniform, galvanic and crevice corrosion using metal alloy and low-density polyethylene (LDPE) test specimen coupons. The setup for these tests is similar and goal and deliverable parts from this acquisition will modernize that setup and increase efficiency saving staff time and improving the overall test setup and process. The testing involves the assembly and test specimens being suspended in a standard 32 OZ straight sided glass jar, (figure 1) and a lid is screwed onto the top prior to the jar and assembly being place in either a 70-or 120-degree Fahrenheit incubator for an exposure duration of 28 to 90 days depending on the test.
The parts designed for this modernization of the setup and test process were created using a 3D printer for proof of concept. These four separate parts are to have injection molds fabricated and tooled so that a large number of individual parts can be manufactured from injection molding using PEEK resin. The four separate parts are, a Threaded Rim-Ring Top , (figure 2), a Dipping Shaft – Pincher, (figure 3), a Dipping Shaft – Galvanic, (figure 4) and a Dipping Shaft – Crevice, (figure 5). Figures 2 – 5 are 3D printed examples of the parts to be produced, proprietary PDF’s and CAD drawing files will be available to vendors upon request. These drawing files are the intellectual property of the USDA Forest Service, Wildland Fire Chemical Systems at the National Technology and Development Program in Missoula Montana. Requests for the proprietary PDF’s and CAD drawing files shall be sent to michael.simpson@usda.gov. These parts will be created using injection molding of PEEK resin so all the Threaded Rim-Rings can be used interchangeably with any of the Threaded Dipping Shafts depending on the test being performed. These parts will be able to withstand being cleaned in a domestic dish washer for reuse and be durable for conducting numerous test cycles.
Figure 1 – Glass Jar Figure 2 – Threaded Rim-Ring Top Figure 3 – Dipping Shaft – Pincher
Figure 4 – Dipping Shaft – Galvanic Figure 5 – Dipping Shaft – Crevice mailto:michael.simpson@usda.gov
The Wildland Fire Chemical Systems Program would eventually like to have 6,000 to 7,500 of the interchangeable dripper top (Rim Rings) and 2,000 to 2,500 of each type of dipper shafts for each product we test. (These will be used for each product we test retardant, foam, gels).
The base year/initial batch of 1,000 interchangeable dripper top (Rim Rings) and 500 of each type of dipper shafts would be used for testing and to develop a cleaning process for them and to reuse them as many times as possible in the first year to determine the durability of the injection mold parts. If no further modification is required, we would purchase a mix of the parts to acquire the number of each to have the desired additional individual part numbers to support the testing of each product.
2.0 Definitions
QPL – Qualified Product List LDPE – Low-density polyethylene NTDP – National Technology and Development Program USFS – United States Forest Service WFCS – Wildland Fire Chemical Systems
Agreement Statement of Work
3.0 Technical Requirements / Tasks
3.1 For Injection Mold Fabrication and Tooling and Part Production
• Collaborate and consult on the design, development, fabrication and tooling of the parts molds.
• Maximize the number of individual parts that can be produced per mold injection cycle to batch individual parts.
• Provide a pricing schedule for the manufacturing of the parts. (For example, if there are minimum quantities or bulk pricing discounts depending upon the quantity of parts ordered). The government reserves the right to order quantities based on the vendor's provided pricing schedule. The government is not obligated to purchase a minimum number of parts in any ordering period/option year.
• To provide subject matter expert technical input and assistance regarding the best practices and mold creation to provide the most durable mold and deliverable parts from the injection molding process.
• To provide subject matter expert technical input and assistance regarding recommendations, for the number of parts possible per mold or family mold.
• To provide a “first batch set of 20 of each part for initial lab use testing to determine proper dimensions, functionality, durability and ease of cleaning for reuse prior to large batching of individual parts.
• To share the mold specification designs and renderings and retain the molds for future batching of all four parts.
4.0 Deliverable / Schedule
The schedule and deliverables are driven by the timing of contract award and the initial coordination on the initial mold fabrication and tooling estimated to be 6 weeks from initiation of contract award. Approval of all molds and refinement of design features and initial injection molding of parts will be coordinated and provided by the contractors estimated delivery schedule.
5.0 Work Location
The work within this agreement will be performed at the vendors’ facilities.
6.0 Travel
No travel will be required virtual coordination meetings can be arranged with the vendor, if the vendor awarded the contract is within the local commuting area of the National Technology and Development Program (NTDP) center in Missoula Montana the staff from the Wildland Fire Chemical Systems (WFCS) laboratory can make arrangement to meet with the vendor in person at their facility.
7.0 Key Personnel
N/A
8.0 Security Requirements
N/A
9.0 Data Rights
NTDP have unlimited rights to all documents and materials produced under this contract. All documents and materials, including the molds shall be NTDP owned with all rights and privileges of ownership to utilize these molds to generate additional batching of parts for purchase.
10.0 Section 508 - Electronic and Information Technology Standards N/A
11.0 Performance Requirement Measures
Quality assurance will be performed by the Government during the agreement period of performance at regular intervals.
Methods may include visual survey and/or agency comments. Incomplete or unsatisfactory work may include rework to achieve the acceptable outputs and/or deliverable.
| Project Title |
| General Information |
| 1.0 Background and Purpose |
| 2.0 Definitions |
| Agreement Statement of Work |
| 3.0 Technical Requirements / Tasks |
| 3.1 For Injection Mold Fabrication and Tooling and Part Production |
| 4.0 Deliverable / Schedule |
| 5.0 Work Location |
| 6.0 Travel |
| 7.0 Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 - Electronic and Information Technology Standards |
| 11.0 Performance Requirement Measures |
File details come from the government source that posted it. Updated .