C04_SOW.pdf

PDF 438 KB Posted

Attached to
Provide and Install Two Hot Water Heaters Federal contract opportunity
Solicitation number
1232SA26Q1076
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a Statement of Work for the installation of two AO Smith BTR-197 natural gas water heaters at the USDA-ARS Southern Horticulture Research Unit located at 810 Hwy 26W, Poplarville, MS 39470. The project objective requires disconnecting existing water heater units and replacing them with two new AO Smith B38 model units, with proper temperature adjustment and verification that units operate at correct temperatures. The contractor must be registered in the System for Award Management (SAM) prior to quote submission and is encouraged to conduct a site visit with a government representative to confirm locations, dimensions, and existing conditions before bidding.

The base contract scope requires the contractor to provide all equipment, materials, labor, and hardware necessary for successful completion and delivery of a functioning system. Key contractor responsibilities include verifying dimensions and site conditions before work commences, maintaining cleanliness of the work area daily, managing the project and consulting with the government before beginning all work phases, ensuring work minimizes impact on facility operations, maintaining a foreman on-site at all times, providing their own restroom facility and dumpster, and removing all demolished material and debris off-site. The contractor must submit material submittals including shop drawings and specifications to the Engineer Project Manager and Contracting Specialist in electronic or three written copies. Work hours are Monday through Friday, 7:00 A.M. to 4:00 P.M., excluding government holidays, with project completion not to exceed 60 days from Notice to Proceed. The contractor must submit a Site Safety Specific Plan/Accident Prevention Plan within 14 days of contract award, utilize bio-based products to the maximum extent possible, schedule inspection a minimum of 10 days in advance, and repair any damage to government property resulting from contractor activities. The local point of contact is Ray Morris (ray.morris@usda.gov, 601-916-7282) and the Engineer Project Manager is J. Kevin Magee, PE (kevin.magee@usda.gov, 662-686-5289).

View the file

Other files for this federal contract opportunity

Other files attached to Provide and Install Two Hot Water Heaters, newest first.
File Type Posted
Sol_1232SA26Q1076_Amd_0001.pdf PDF
RFI-Responses.docx DOCX document
C04_Sol_1232SA26Q1076.pdf PDF
C04_Wage Determination 2015-5171.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Two Natural Gas Water

Heaters Southern Horticulture Lab

USDA-ARS

Poplarville, Mississippi

Prepared by:

Ray Morris

Table of Contents

Location Map Page 3

Statement of Work Page 4

Pictures Page 5

Contractor Responsibility Page 9

Project Schedule/Contacts Page 10

Location Map

Statement of Work: Installing (2) AO Smith Water Hetaers B38 at USDA ARS Southern Horticulture Research Unit at Poplarville, MS. This project is located at 810 Hwy 26W, Poplarville, MS 39470.

Project Objective: Project goal is to install (2) AO Smith BTR – 197 natural gas water heaters . Disconnect old units and replace with new units, adjust temp properly and make sure units are running properly at right temp .

Horticulture Research Unit in Poplarville, MS.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a quote. Registration can be obtained through: http://www.sam.gov

Site Visit: Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a quote is submitted. The site visit shall be for the purpose of observing firsthand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable. This project is located at USDA-ARS in Poplarville, MS.

Utilization of Bio-Based Products: The contractor shall utilize products and material based from bio-based materials, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user.

All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:

https://www.biopreferred.gov

Safety: The contractor will submit a Site Safety Specific Plan/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award. The Plan shall include phone numbers and maps to the local Dr. Office and nearest Hospital.

Base : Provide all equipment, materials, labor and hardware.

http://www.sam.gov/ https://www.biopreferred.gov/

Pictures:

Figure 1 Building 38

MS Excel format with formulas working.

Contractor Responsibility:

1. Contractor will verify all dimensions and site conditions prior to beginning work.

2. Contractor will perform the work as listed in the above outlined Base.

3. Contractors shall keep work area clean daily and take measures to control debris while work is being performed.

4. Contractors are required to manage the project and consult with the Government prior to beginning all work phases. And, to work in a manner that minimizes the impact of the work on Government operations, research, and functions.

5. All work must be performed in such a manner as to not adversely affect daily operations of the facility, its workers, and the onsite facility operations.

6. Contractor must always have a Foreman on the job while working on this project.

7. Contractors will provide their own restroom facility and dumpster.

8. Contractor will remove all demolished material and debris from the worksite and dispose off-site.

Material / Submittals:

The Contractor shall supply all materials necessary to successfully complete the project and deliver a functioning system as required. Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project shall be submitted to the EPM and Contracting Specialist as noted in this document. Electronic submittals are acceptable otherwise three written submittals are required.

Execution of Work:

Contractor will verify all dimensions and site conditions prior to beginning work. Contractor will schedule the work between working hours as listed below. Contractors are required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor. The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.

Damage to Property:

Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government.

Inspection and Acceptance:

A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 10 days in advance, in writing, to the Contracting Officer.

Project Schedule:

The completion of this project shall not exceed 60 days from date of Notice to Proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

Work Hours:

Contractor’s work hours shall be Monday through Friday, seven (7) A.M. to four (4) P.M. with the exception of Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.

Project Contacts:

LOCAL POINT OF CONTACT (POC):

Ray Morris Email: ray.morris@usda.gov

USDA, ARS SRL

810 Hwy 26 W Poplarville, MS 39470 Phone: 601-916-7282

ENGINEER PROJECT MANAGER

J. Kevin Magee, PE Email: kevin.magee@usda.gov USDA, ARS, SEA Facilities EPM 141 Experiment Station Road Stoneville, MS 38776 Phone: (662) 686-5289 mailto:ray.morris@usda.gov mailto:kevin.magee@usda.gov

Two Natural Gas Water Heaters
Southern Horticulture Lab
USDA-ARS
Table of Contents
Location Map
Pictures:
Material / Submittals:
Execution of Work:
Damage to Property:
Inspection and Acceptance:
Work Hours:
Project Contacts: