This is a Statement of Work (SOW) for utility infrastructure development at the Upper Baker Site in Monticello, Utah (133 S Pinion Dr, Monticello, UT 84535). The primary scope includes installing water, sewer, and electrical utility lines with connections to existing infrastructure and trailer pads. The water system requires connecting a 2" HDPE blue poly line to the existing 2" poly line between the meter and bunkhouse, with one stop and waste valve installed within 5 feet of the connection point. The sewer system requires a 6" main line connected to the existing bunkhouse sewer with 6" to 3" Wye connections for trailer pads, maintaining drainage slope between 1/8" and 1/4" per foot in compliance with state code. The electrical work requires coordinating with Empire Electric for transformer and drop-down meter installation, with the contractor responsible for determining appropriate conduit and wiring sizing. Water and sewer lines must be maintained 10 feet apart throughout the project.
Option items include trenching and backfilling to 36 inches deep to meet frost line requirements, Grade G Road Base crushed aggregate for trailer pads and roadway, and asphalt apron installation. The contractor is responsible for all communications, permits, and coordination with utility companies. The project location is on National Forest System lands, requiring all construction equipment to be pressure washed before site entry to prevent noxious weed transportation. No water or utilities are available on-site for construction purposes; the contractor must provide temporary toilet facilities (porta-potty) as needed. The contract timeline is 60 calendar days with a start date of Spring/Summer 2027. Staging areas and overnight camping require written approval from the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04 Utility Plan 1240LT26Q0126.pdf | ||
| C04 water details 1240LT26Q0126.pdf | ||
| C04 SF-1442 1240LT26Q0126.pdf | ||
| C04 Merged Specs 1240LT26Q0126.docx | DOCX document | |
| C04 trailer pad 1240LT26Q0126.pdf | ||
| C04 1240LT26Q0126.docx | DOCX document | |
| C04 Project Map 1240LT26Q0126.pdf | ||
| C04 WD San Juan County Utah 1240LT26Q0126.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
GENERAL SPECIFICATIONS
Upper Baker Site Development Final – 5/30/2026
SCOPE OF CONTRACT
This contract is comprised of installing utility lines, connections to existing lines and connections to trailer pads. Utilities included are electrical, water and sewer. Option items included are trenching, providing and spreading gravel and installation of an asphalt apron. Water and Sewer lines and connections must be kept 10ft apart. Contractor must work with and is responsible for all communications, supplies and permits with utility companies associated. All utilities will be installed in compliance with State and/or San Juan County code.
Utilities – Water - The new water line will be connected to the existing water line between the meter and bunkhouse. Main water line will remain same size as existing line. Existing line is a 2” poly line. New water line will be a 2” HDPE blue Poly and connect to existing. One stop and waste to be installed within 5ft of new and existing line connection.
Sewer – The new sewer line will be connected to the existing sewer line at the bunkhouse. Main line will be 6” with trailer connections being 6” to 3” Wye’s. Drainage must remain between 1/8” – ¼” per ft across the entirety of the line. Must meet state code.
Electrical – A transformer and drop-down meter will need to be coordinated and installed with Empire Electric and conduit and wiring ran from meter to the trailer pads. Contractor will be responsible for determining sizing of conduit and wiring. Must meet state code.
Option Items – Trenching and Backfilling – Trenching will need to be 36” deep to meet frost line requirements.
Crushed Aggregate – Grade G Road Base for the trailer pads and roadway
PROJECT LOCATION
This Project is in the town of Monticello Ut, 84535. The address is 133 S Pinion Dr, Monticello, UT 84535
SITE INFORMATION AND LIMITATIONS
The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will not be open to the public during construction.
2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brush guard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
3. No water is available at the site for construction purposes. No utilities are available at the site for construction purposes.
4. Toilet facilities are not available at the Site. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work if necessary.
WORK CAMPS, STAGING AND STORAGE AREAS
Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers.
Overnight camping will be allowed on site with CO approval.
INSPECTION OF WORKSITE
The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. All quantities of materials and or labor have been verified by the contractor. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
START DATE
Spring/Summer 2027
CONTRACT TIME
60 Calendar Days
SPECIFICATIONS
The contract specifications are attached as a separate document.