This is a Request for Quotation (RFQ) for trail repair and mitigation work on the Sand Trail Phase II project located in the Cordova Ranger District, Chugach National Forest, Alaska. The solicitation number is 1240BJ26Q0021, issued by USDA Forest Service on August 7, 2026, with quotations due by 10:00 a.m. Pacific Daylight Time on September 8, 2026. The contract is firm-fixed price with a mandatory period of performance from September 24, 2026, to May 31, 2027 (249 calendar days). The work addresses the first 1.70 miles of the 12.20-mile trail through installation of bank armoring with riprap, placement of subgrade aggregate (3" minus) as backfill, and D-1 aggregate on the trail running surface to harden it for ATV use. Construction must occur during frozen ground conditions (when 5 consecutive days below 30°F are achieved) and is limited to Monday through Friday, 7:00 a.m. to 6:00 p.m. unless approved by the Contracting Officer's Representative (COR). Vegetation removal is prohibited from May 1 to July 15 and in-stream work from July 1 to September 1 to protect migratory birds and fish. Hauling activities on the trail are only permitted during frozen ground conditions.

The pay item schedule includes four base items: Mobilization (LS), Clearing and Grubbing (LS), Placed Class III Riprap for 335 cubic yards, and Aggregate Base Course D-1 for 600 cubic yards, plus four option items totaling up to 600 additional cubic yards of aggregate, five rock barb installations, 20 hours of dozer work, and 50 cubic yards of additional riprap. A Bid Bond (20%) is required for quotes exceeding $150,000, and Performance and Payment Bonds (100% each) are required for awards greater than $150,000. The contractor must provide evidence of comprehensive general liability insurance ($500,000 per occurrence), bodily injury liability ($200,000 per person/$500,000 per occurrence), property damage liability ($1,000,000 per occurrence), and automobile liability coverage. Progress payments are available monthly upon submission of certified requests for work accomplished meeting contract quality standards. Quoters should submit past experience information for no more than five projects within the last five years, demonstrating similar scope and complexity. Award will be made to the responsible quoter whose quote is most advantageous to the Government, with evaluation based on pricing, past experience, and past performance. Contracting Officer: Eric Oldenkamp (eric.oldenkamp@usda.gov, 541-225-6321); COR: Hampton Coogle (hampton.coogle@usda.gov, 740-263-0251).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

USDA-FS CSA NORTHWEST 7

1220 SW 3RD AVE

STE 310

PORTLAND OR 97204-2829

40BJ

All quote documents must be emailed to eric.oldenkamp@usda.gov.

An email copy of the Bid Bond is acceptable for quotes valued at $150,000 or greater.

ERIC OLDENKAMP 541-225-6321

108/07/2026

1. SOLICITATION NO.

1240BJ26Q0021

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Project Name: Sand Trail Phase II

Cordova Ranger District, Chugach National Forest

Period of Performance: 09/24/2026 to 05/31/2027

Amended FAR provision 52.212-1 in this solicitation identifies what must be submitted in a quote.

Solicitation number 1240BJ26Q0021 is issued as a Request for Quotation (RFQ). This

RFQ is prepared in accordance with the format in FAR Part 12.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

1 249 calendar days and complete it within ________________ ________________ calendar days after receiving

Period of Performance

09/08/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

PAY ITEM SCHEDULE OF SERVICE/SUPPLIES

Item Sub- Item

Description Unit Qty Unit Price Total

1 15101 MOBILIZATION LS 1

1 20102

CLEARING AND GRUBBING, DISPOSAL METHOD PILE

OR SCATTER (FOR ACCESS DOWN TRAIL)

LS 1

1 25101A

PLACED CLASS III RIP RAP, RIVER BANK SLOPES AND

ERODED SECTIONS – 3” MINUS BACKFILL IS

INCEDENTAL AND TO BE USED AS BACKFILL (SEE

PAGE 7 OF DRAWINGS)

CY* 335

1 30201

AGGREGATE BASE COURSE, D-1 (AKDOT GRADE)(FOR

TRAIL RUNNING SURFACE)

CY* 600

2 30201

OPTION ITEM 1 - AGGREGATE BASE COURSE,

D-1 (AKDOT GRADE)

CY* 600

3 64805

OPTION ITEM 2 - 15 FT ROCK BARB INSTALLATION,

INCLUDED RIP RAP BANKS FOR 60 FT (SEE PAGE 5-6

OF DRAWINGS)

EA 5

4 62201 OPTION ITEM 3 - DOZER, D4 OR LARGER HR 20

5 25101A

OPTION ITEM 4 - PLACED CLASS III RIP RAP,

RIVER BANK SLOPES AND ERODED SECTIONS – 3”

MINUS BACKFILL IS INCEDENTAL AND TO BE

USED AS BACKFILL (SEE PAGE 7 OF DRAWINGS)

CY* 50

GRAND TOTAL:

Schedule Notes:

All quantities are Actual Quantity unless marked with an (*) (*) Denotes Contract Quantity items.

This is a firm-fixed price contract.

A Bid Bond (20%) will be required of quoters whose total priced quote exceeds $150,000.

Performance and Payment Bonds (100% each) will be required of awardee for an award greater than $150,000.

Payment for bond premiums in accordance with AGAR clause 452.232-71, Progress Payments for Commercial Construction Contracts, and shall not be in addition to the contract price. Include bond payments under Mobilization.

Option items will not be exercised if either the contractor completes base items and demobilizes, or if they are not exercised before 11/1/2026.

STATEMENT OF WORK (SOW)

1 PROJECT SCOPE

This project is located on the Cordova Ranger District. This contract aims to repair and mitigate future failures of the USFS Sand Trail infrastructure, trail number 229. The total trail length is 12.20 miles long; this contract will only address the first 1.70 miles of failing trail. The mitigation consists of installing bank armoring with rip rap, and placing sub grade aggregate along the trail. The sub grade aggregate (3” minus) is to be placed as backfill behind the riprap and is incidental to item 201501A. Backfill quantities will vary but the end product is to have ~2-4 ft of 3” minus behind the placed riprap. The D-1 aggregate is to be placed on the trail running surface to harden the trail for ATV use.

The majority of trail 229 is 6 to 8 feet in width and will require additional clearing and minor excavation depending on type of equipment used.

Construction must occur during low water times of year, diversion of smaller channels within the project location will be needed to dewater bank locations. Small diversion for bank armoring is assumed to be conducted with either a dozer or excavator that may operate in the stream channel or along the stream bank.

Work must be performed when there is 5 consecutive days below 30F degrees are reached, or as approved by the Contracting Officer Representative (COR).

Option items consist of the following

Option Item #1 – Consists of placing additional aggregate along the trail at locations determined by the COR.

Option Item #2 – Consists of installing stream barbs at locations determined by the COR. Currently no known locations have been identified.

Option Item #3 – Consists of using a dozer along or within the stream channel to move stream channel material along banks for additional protection and also divert some braided channels further into the middle of the stream.

Option Item #4 – Consists of placing additional rip rap along stream banks as determined by the COR.

Assumed construction process: (note – the following is assumed and is not a contract requirement. The contractor has ability to determine their own methods of construction) It was assumed the contractor would install work during frozen ground conditions and low water. The assumed process would be to utilize and excavator to clear the trail and allow for passage of a 10-12 CY dump truck and install 1 dump truck turnaround at a location determined by the contractor along the trail. Clearing would occur outside of the migratory bird window. The contractor would stockpile aggregate near the existing trailhead during summer or at any convenient time of the year during the Period of Performance. Once frozen ground conditions are met and low flow is achieved, the contractor would load rip rap and aggregate from the trailhead and transport down the trail for installation. Installation of bank armoring was assumed to be an excavator with bucket tamping installation of aggregate in the trail corridor, to either be an excavator with blade or small dozer.

2 PROJECT LOCATION

The location of this project is in the Cordova Ranger District, located in the Chugach National Forest. The nearest town is Cordova, and is only accessible by boat or plane, no road access to Cordova is possible.

Directions from Cordova to the Project location are as follows: from Cordova travel East along the Copper River Highway. Follow the Copper River Highway for approximately 9 miles. The project location will be on drivers left just prior to the first bridge that crosses the Scott River.

3 PRODUCT SAMPLES AND/OR SUBMITTALS

The following submittals, shop drawings, material certifications and/or testing reports are required.

Title Referenced by Contract clause or Specification No.

Time of Government

Approval After Submittal

Traffic Control Plan Standard specifications (FP-14) 7 days

Safety Plan, including Blasting Plan where applicable

FAR Clause 52.236-13 N/A

Hazardous Material Spill Prevention Plan FAR Clause 52.236-9 & 52.236-13 2 days

Fire Plan FAR Clause 52.236-9 & 52.236-13.

COR will provide form R6-FS-6300 N/A

Proposed Progress Schedule FAR Clause 52.236-15 N/A

Payroll Record WH347 Certified Payrolls submitted weekly

FAR Clause 52.222-8 N/A

Product and Material Certifications and Literature (gradations) As required by Specifications (FP-14) 7 days

4 SPECIFICATIONS

"FHWA FP-14 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS” are included by reference only. The requirements contained in these Specifications are hereby made a part of the Solicitation and any resultant contract.

Copies of the "FHWA FP-14 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS" are available for download at the following URL:

https://flh.fhwa.dot.gov/resources/specs/

The following sections of “FHWA FP-14 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included by reference only. The requirements contained in these Specifications are hereby made a part of the solicitation and any resultant contract.

The following Standard Specifications are applicable to this contract and are included by reference:

Spec No Title Section 101 – Terms, Format, and Definitions Section 102 – Bid, Award, and Execution of Contract

Section 103 – Scope of Work Section 104 – Control of Work Section 105 – Control of Material

Section 106 – Acceptance of Work Section 107 – Legal Relations and Responsibility to the Public Section 108 – Prosecution and Progress Section 109 – Measurement and Payment Section 151 – Mobilization Section 153 – Contractor Quality Control Section 154 – Contractor Sampling and Testing Section 155 – Schedules for Construction Contracts Section 156 – Public Traffic Section 157 – Soil Erosion and Sediment Control Section 204 – Excavation and Embankment Section 207 – Earthwork Geosynthetics Section 251 – Riprap Section 301 – Untreated Aggregate Courses Section 302 – Minor Crushed Aggregate Section 303 – Roadway Reconditioning Section 622 – Rental Equipment Section 635 – Temporary Traffic Control Section 703 – Aggregate Section 704 – Soil Section 705 – Rock Section 714 – Geotextile

5 SUPPLEMENTAL SPECIFICATOINS

See attachments for Forest Service Supplemental Specifications (FSSS).

6 RESPONSIBILITY FOR QUALITY CONTROL

The Contractor is responsible for quality control and management actions to meet the performance requirements and terms of the Contract. The Government performs quality assurance to assess the quality of services rendered, and to verify the services meet the contract requirements, and contract standards are achieved.

7 DRAWINGS

See attachments for plans.

8 CONTRACTING STAFF

All communications pertaining to contractual and/or administrative matters under this contract shall be sent to:

Task Order Contracting Officer Name: Eric Oldenkamp Email: eric.oldenkamp@usda.gov

Task Order Contracting Officer's Representative (COR) Name: Hampton Coogle Phone: (w) 740-263-0251, (c) 740-263-0251 Email: hampton.coogle@usda.gov

9 STORAGE AND STOCKPILING OF MATERIALS

Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by the Forest Service, may be used for storage purposes and for the placing of Contractor's equipment.

All storage sites provided by the Forest Service shall be restored at Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered lands.

10 PROSECUTION OF WORK – WORK HOUR LIMITS – WORK ITEM LIMITS

Construction activity may be performed Monday through Friday and shall be limited to the hours between 7:00 a.m. and 6:00 p.m., unless other hours are approved in writing by the COR. No work will be allowed on Federal Holidays unless approved by COR in writing. All ground disturbing construction activity shall be performed during the period of frozen ground conditions.

11 OTHER REQUIREMENTS

1. All work shall be coordinated with the Contracting Officer’s Representative 7 days prior to the work date.

2. For description of work items that require clarification, the contractor shall submit written Requests for Information, allowing seven working days for the Government’s review.

3. Project material submittals shall be submitted prior to ordering and allow 7 calendar days for the Government’s review.

4. Written project schedules shall be submitted at the pre-work meeting and updated weekly.

5. The contractor shall meet all FP-14 Specifications and Forest Service Supplemental Specifications.

6. Contractor may not perform vegetation removal from May 1 –July 15 due to migratory bird window

7. Contractor may not perform in stream work July 1 – September 1 due to fish window.

8. Contractor may not perform hauling activities on the trail during non-frozen ground conditions. Frozen ground conditions are 1 week of below 30 degree F air temperatures are achieved.

12 USE OF PREMISES

The contractor shall comply with regulations governing the operation of premises which are occupied and shall perform the contract in such a manner as not to interrupt or interfere with the conduct of Government business.

13 INCIDENTAL PAYMENT ITEMS

The intent of the contract is to provide for the complete construction of the project described in the contract.

Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the pay item schedule. All other work and materials will be considered as incidental to the pay items in the schedule.

14 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

15 BARRICADES, WARNING SIGNS, AND OTHER DEVICES

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

16 PROTECTION OF EXISTING FACILITY

The current trailhead is a paved parking lot. The contractor shall protect the pavement and shall not cause damage due to equipment operations. Damage to existing facilities including pavement and trails shall be repaired by the contractor at no cost to the Government. Repair methods shall be replaced in kind and shall be approved by the CO prior to commencement of repair work.

17 INSURANCE COVERAGE

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of 1,000,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

18 LIST OF ATTACHMENTS

1. SAND TRAIL PHASE II PLANS (7 Pages)

2. SANDTRAIL FSSS (43 Pages)

3. GEOREFRENCED PDF MAP (1 Page)

4. WAGE DETERMINATION (16 Pages)

(End of SOW)

CLAUSES

Definitization of Equitable Adjustments for Change Orders

Pursuant to FAR 36.101-4(b), information regarding USDA’s definitization of equitable adjustments for change orders under construction contracts may be found at Contracting with USDA under “Federal Acquisition Regulation 36.101-4”. USDA’s procedures that apply to the definitization of equitable adjustments for change orders under construction contracts may be found in AGAR 443.304 -70.

Federal Acquisition Regulation (FAR) and United States Department of Agriculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation.

The terms and conditions set forth herein supersede all other terms and conditions. Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference (Feb 1998)

This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

The following clauses are mandatory in all solicitations and contracts - Do not delete these.

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)

This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:

(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).

(d) Changes. Changes will be handled in accordance with the following FAR clause(s):

☒ FAR 52.243-4, Changes (Nov 2025) ☐ FAR 52.243-5, Changes and Changed Conditions (Nov 2025)

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☒ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I (Nov 2021) of 52.203-6

☐ 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) ☐ 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 ☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☐ 52.204-91 Contractor identification (Nov 2025) ☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☒ 52.209-9 Updates of Publicly Available Information Regarding Responsibility

Matters (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☐ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov

2025) ☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025)

☐ Alternate I (Mar 2020).

☒ 52.219-8 Utilization of Small Business Concerns (Nov 2025) ☐ 52.219-9 Small Business Subcontracting Plan (Nov 2025)

☐ Alternate III (Nov 2025) of 52.219-9.

☐ Alternate IV (Nov 2025) of 52.219-9

☒ 52.219-14 Limitations on Subcontracting (Nov 2025) ☐ 52.219-16 Liquidated Damages—Subcontracting Plan (Nov 2025) ☐ 52.219-33 Nonmanufacturer Rule (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☐ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025) ☒ 52.222-35 Equal Opportunity for Veterans (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-35 ☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-36 ☒ 52.222-37 Employment Reports on Veterans (Nov 2025) ☒ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ☒ 52.222-54 Employment Eligibility Verification (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026) ☒ 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Nov

2025) ☐ 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items

(May 2008) ☐ Alternate I (May 2008) of 52.223-9

☐ 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Nov 2025)

☐ 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Nov 2025)

☒ 52.223-23 Sustainable Products and Services (Nov 2025) ☐ 52.224-3 Privacy Training (Jan 2017)

☐ Alternate I (Jan 2017) of 52.224-3 ☐ 52.225-1 Buy American-Supplies (Nov 2025)

☐ Alternate I (Oct 2022) of 52.225-1 ☐ 52.225-3 Buy American--Free Trade Agreements--Israeli Trade Act (Nov 2025)

☐ Alternate II (Nov 2025) of 52.225-3.

☐ Alternate III (Nov 2025) of 52.225-3.

☐ Alternate IV (Oct 2022) of 52.225-3

☐ 52.225-5 Trade Agreements (Nov 2023) ☐ 52.226-4 Notice of Disaster or Emergency Area Set-Aside (Nov 2007) ☐ 52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area (Aug 2025) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018) ☐ 52.232-34 Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) ☐ 52.232-36 Payment by Third Party (Nov 2025) ☒ 52.242-13 Bankruptcy (July 1995) ☒ 52.246-21 Warranty of Construction (Mar 1994)

The Contractor shall comply with the following FAR Clauses for Commercial Construction.

52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship

The following clauses are applicable when checked:

☐ 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Pricing Method (Aug 2018)

☐ 52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method) (Aug 2018)

☐ 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (Nov 2025)

☒ 52.225-9 Buy American-Construction Materials (Nov 2025) ☐ Alternate I (Oct 2022) of 52.25-9

☐ 52.225-11 Notice of Buy American Requirement-Construction Materials under Trade Agreements (Nov 2025)

☐ Alternate I (Nov 2025) (of 52.225-11 ☐ Alternate II (Oct 2022) of 52.225-11

☒ 52.228-2 Additional Bond Security (Oct 1997) ☒ 52.228-5 Insurance-Work on Government Installation (Jan 1997) ☒ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☐ 52.228-13 Alternative Payment Protections (Jul 2020) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☒ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☒ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☒ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.336-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025)

☐ Alternate I (Nov 1991) of 52.236-13 ☐ 52.236-14 Availability and Use of Utility Services (Jul 2025) ☒ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☐ 52.236-16 Quantity Surveys (Jul 2025)

☐ Alternate I (Apr 1984) of 52.236-16 ☐ 52.236-17 Layout of Work (Jul 2025) ☒ 52.236-21 Specifications and Drawings for Construction (Jul 2025)

☐ Alternate I (Apr 1984) of 52.236-21 ☐ Alternate II (Apr 1984) of 52.236-21

☒ 52.242-14 Suspension of Work (Apr 1984) ☐ 52.248-3 Value Engineering (Oct 2025)

☐ Alternate I (Apr 1984) of 52.248-3

Other Applicable Clauses

52.217-7 Option for Increased Quantity -- Separately Priced Line Item (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within the date of award to 10/30/2026. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of Clause)

AGAR Clauses

452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)

(a) By entering into this contract, the contractor certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to contractor’s compliance with the above requirements and/or eligibility for the contract may subject the contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) The contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

AGAR 452.203-72 Unenforceable Supplier Terms (MAY 2026)

(a) Definitions.

Supplier terms mean provisions customarily drafted by vendors of supplies or services and intended to create a binding legal obligation on the end user. The term applies:

(1) Regardless of the format or style of the document. For example, supplier terms may appear in standard terms of sale or lease, Terms of Service (TOS), End User License Agreement (EULA), or another similar legal instrument or agreement, and may be presented as part of a proposal or quotation responding to a solicitation for a contract or order or otherwise become effective after the contract date.

(2) Regardless of the media or delivery mechanism used. For example, supplier terms may be presented as one or more paper documents or may appear on a computer or other electronic device screen during a purchase, software installation, other product delivery, registration for a service, or another transaction.

(b) Applicability. When any supply or service acquired under this contract is subject to supplier terms, the supplier terms are deemed part of the contract only to the extent they are consistent with this clause. Supplier terms that conflict with any part of this clause, the contract, or Federal law are void and will not be considered incorporated into a contract, even if they are physically present in a contract documentation or systems. In the event of any inconsistency between supplier terms and this contract, this clause and the terms of the Government contract must govern and supersede any supplier terms in all cases.

(c) Authorization Required. Notwithstanding any other provision, no supplier terms must be binding on the Government unless the term is expressly authorized on the USDA Supplier Terms Authorization Form signed by the Contracting Officer, and the completed Authorization Form has been incorporated into the contract.

(d) Unenforceable Terms. Any supplier terms that impose obligations or restrictions inconsistent with applicable Federal law are unenforceable against the Government and deemed stricken from the agreement.

This includes, but is not limited to, any clause that:

(1) Requires the Government to pay future fees, penalties, interest, legal costs, early‑termination fees, cancellation fees, minimum purchase commitments, true‑up payments, seat‑count minimums, usage minimums, continued‑use charges, or any other financial obligation not expressly authorized by the contract.

(2) Requires the Government to indemnify the contractor or any other entity.

(3) Restricts the Government’s ability to obtain similar supplies or services from another source.

(4) Imposes any penalty, financial or otherwise, based on the Government’s decision not to exercise an option.

(5) Subjects the United States Government to the laws of any U.S. state, territory, district, municipality, or foreign nation, except where Federal law expressly permits such application.

(6) Requires dispute resolution in a forum or venue other than one prescribed by applicable Federal law.

(7) Establishes a period of limitations for bringing an action that differs from that provided by applicable Federal law.

(8) Grants the contractor rights to use, mine, access, aggregate, analyze, or otherwise exploit Government data, usage data, or metadata.

(9) Deems the Government to have accepted initial or revised terms based on silence, continued performance, or failure to object.

(10) Grants the supplier the right to audit Government facilities, systems, records, or use of the product or service, except as expressly authorized by the contract and applicable Federal law.

(11) Requires the Government to accept supplier security requirements, network access requirements, monitoring, penetration testing, or other technical or security measures.

(12) Permits the supplier to suspend, degrade, or terminate access to products or services based on alleged non‑payment, alleged breach, automated security triggers.

(13) Limits the Government’s right to use, install, access, test, evaluate, or transfer the licensed product or service in any manner consistent with the contract and Federal law.

(14) Requires the Government to store, process, maintain, or transmit data in a particular geographic location, or permits the supplier to transfer Government data outside the United States, except as expressly authorized by applicable Federal law.

(15) Authorizes the supplier to use the Government’s name, seal, trademark, logo, or any reference to the Government as an end user or customer for marketing, publicity, promotional activities, press releases, or similar purposes.

(16) Incorporates by reference, or requires the Government to accept, terms or conditions imposed by any third party, subcontractor, or upstream service provider, unless such terms are expressly incorporated into the contract by bilateral modification.

(17) Limits, conditions, or negates the contractor’s performance obligations, service levels, or remedies through a supplier‑provided service level agreement (SLA).

(18) Uses Government data, usage data, metadata, prompts, content, or interactions to train, fine‑tune, improve, or derive any artificial intelligence, machine learning, or automated decision‑making model.

(19) Subjects the Government to automated decision‑making, automated risk scoring, automated content moderation, or any algorithmic process that may affect access, performance, or rights under the contract.

(20) Utilizes artificial intelligence or algorithmic tools that produce decisions, recommendations, or outputs affecting contract performance without providing transparency, explainability, auditability, and bias‑mitigation consistent with applicable Federal law and policy.

(21) Profiles, tracks, or analyzes Government user behavior, preferences, communications, or interactions for personalization, marketing, or algorithmic optimization purposes.

(e) Non-binding Actions. Neither the Government nor any Government authorized end user is deemed to have consented to any term, condition, or clause by virtue of its inclusion in the supplier agreement or through the use of clickwrap, browsewrap, “I agree” mechanisms, or similar means. Execution of such mechanisms does not bind the Government or its authorized end users to any unenforceable terms.

(f) End user. The supplier agreement must bind the ordering activity as the end user to the extent it does not conflict with the terms of this clause, but it must not bind or impose personal liability on any Government employee or any person acting on behalf of the Government in their personal capacity.

(g) Law and disputes. The supplier agreement is governed by Federal law.

(h) Statutory exception. This clause does not apply to indemnification or any other payment by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(i) Continued performance. The supplier or licensor must not unilaterally revoke, terminate, or suspend any rights granted to the Government except as allowed by the contract. If the supplier or licensor believes the ordering activity to be in breach of the supplier agreement, it must pursue its rights under the Contract Disputes Act or other applicable Federal statute while proceeding diligently with performance, pending final resolution of any dispute in accordance with the Disputes Clause at FAR 52.212‑4(d) or FAR 52.233‑1, as applicable.

(j) Arbitration. Binding arbitration must not be used unless specifically authorized by agency guidance.

(k) Equitable or injunctive relief. Equitable or injunctive relief, including the award of attorney fees, costs, or interest, may be awarded against the United States Government only when explicitly provided by statute (e.g., the Prompt Payment Act or the Equal Access to Justice Act).

(l) Revisions to supplier agreements. Any revisions to the supplier agreement must be incorporated into the contract using a bilateral modification. Unilateral revisions are not binding on the Government.

(m) No automatic renewals. If any license or service tied to periodic payment is provided under the supplier agreement (e.g., annual software maintenance or annual lease term), such license or service must not renew automatically upon expiration of its current term without prior express written consent from an authorized Government representative.

(n) Indemnification. Any clause of the supplier agreement requiring the supplier or licensor to defend or indemnify the end user is amended to provide that the U.S. Department of Justice has the sole right to represent the United States in any such action, in accordance with 28 U.S.C. 516.

(o) Taxes or surcharges. Any taxes or surcharges which the supplier or licensor seeks to pass along to the Government as end user will be governed by the terms of the associated Government contract or order and must be submitted to the Contracting Officer for a determination of applicability prior to invoicing unless specifically agreed otherwise.

(p) Non‑assignment. The supplier agreement may not be assigned, nor may any rights or obligations thereunder be delegated, without the Government’s prior approval, except as expressly permitted by FAR 52.212-4(b) or FAR 52.232-23, as applicable.

(q) Confidential information. If the supplier agreement includes a confidentiality clause, such clause is amended to state that neither the agreement nor the contract price list, as applicable, must be deemed “confidential information.” Issues regarding release of “unit pricing” will be resolved consistent with the Freedom of Information Act. Notwithstanding anything in the supplier agreement to the contrary, the Government may retain any confidential information as required by law, regulation, or its internal document retention procedures for legal, regulatory, or compliance purposes; provided, however, that all such retained confidential information will continue to be subject to the confidentiality obligations of the supplier agreement.

(r) Conflict with Federal law. If any other language, provision, or clause of the supplier agreement conflicts or is inconsistent with Federal law or the terms and conditions of this contract, such language, provisions, or clauses will be considered null and void and will not be binding on the United States Government.

(End of Clause)

452.204–70 Modification for Contract Closeout (Apr 2026)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) may issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but is not required to provide a signature. The Contracting Officer will immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) For commercial contracts not exceeding the simplified acquisition procedure threshold under FAR 12.001(c), if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral deobligation modification. Only the modification requires the contractor’s signature, though a Release of Claims may be requested. If the required documents are not returned within 60 days, the Contracting Officer will issue a unilateral modification and proceed with closeout once performance is complete, acceptance is confirmed, and final payment is made.

(c) For all other non-commercial or non–cost‑reimbursement contracts, if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral deobligation modification and a Release of Claims, both requiring contractor signature. If these documents are not returned within 120 days, the Contracting Officer will issue a unilateral modification u and proceed with closeout upon completion of performance, acceptance, and final payment.

(End of Clause)

452.232-71 Progress Payments for Commercial Construction Contracts (May 2026)

(a) Contractor entitlement to progress payments. The contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.

(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:

(1) Materials delivered on site and preparatory work;

(2) Materials delivered to the contractor at locations other than the site, if:

i. Specifically authorized by the contract; and

ii. The contractor provides satisfactory evidence of title and intended use in the contract.

(c) Contractor request for progress payments. The contractor’s request for progress payments must include the following:

(1) An itemization of the amounts requested, related to the various elements of work required by the contract;

(2) A listing of the amount included for work performed by each subcontractor;

(3) A listing of the total amount of each subcontract;

(4) A listing of the amounts previously paid to each subcontractor; and

(5) Additional supporting data in a form and detail required by the Contracting Officer.

(d) Contractor Certification. Each request for progress payment must be accompanied by the following certification:

I hereby certify, to the best of my knowledge and belief, that—

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.

________________________________________________(name)

________________________________________________(title)

________________________________________________(date)

(e) Access for verification of payment entitlement. To verify the contractor’s entitlement to progress payments under this contract, the contractor must provide the Government, upon request and during normal business hours, access to the following:

(1) Records and Documentation:

i. Certified progress payment requests and supporting documentation;

ii. Subcontractor and supplier invoices, payment records, and lien waivers;

iii. Updated schedule of values and progress schedules;

iv. Quality assurance and inspection reports;

v. Payroll records, if applicable under labor provisions.

(2) Facilities and Worksite Access:

i. Physical access to the construction site for inspection of work progress;

ii. Access to off-site storage locations for materials billed but not yet incorporated into the work; or

iii. Access to any fabrication facilities where contract-related work is being performed.

(3) Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.

(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests must be paid within 30 days of submitting a proper request for payment.

(g) Liquidation of progress payments. Progress payments must be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item must be clearly delineated in each request for progress payment submitted by the contractor.

(h) Security for progress payments. In the event that the contractor fails to provide adequate security as required in this contract, no progress payment must be made under this contract. Upon receipt of adequate security, progress payments must be made, including all previous payments to which the contractor is entitled, in accordance with the terms of the contract.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .