This document contains details for two federal contract opportunities. The Regional Maintenance Center at Puget Sound Naval Shipyard & Intermediate Maintenance Facility intends to award firm-fixed price contracts to accomplish maintenance, preservation, and repair of two Naval vessels, TWR-7 and TWR-8. The work will be performed at the contractor's facility and includes tasks such as hull repairs, tank cleaning and inspection, engine maintenance, and sea trials. The period of performance is July 15, 2020 to November 17, 2020. Offerors must be registered in the System for Award Management and this is a 100% small business set-aside under NAICS code 336611 with a size standard of 1,250 employees. The solicitation number is N4523A20R1066 and the contracting agency is the Department of the Navy Naval Supply Systems Command.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TWR-8
| INSERT CONTRACTOR/COMPANY NAME HERE | |||||||||||
| Project = | TWR-8 | DATE: = | |||||||||
| PRIME | SUBCONTRACTOR | PRIME | PRIME | ||||||||
| PARAGRAPH No. | TITLE | M/H | MATERIAL PRICE | TOTAL | Labor Cost | Material Cost | TOTAL | Other Direct Cost (ODC)* | G&A | PROFIT | Line Item Total |
| GENERAL REQUIREMENTS | |||||||||||
| 1.4 | Arrival Conference | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.5 | Required Documents | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.6 | Progress Meetings | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.7 | Availabillity Requirements | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.8 | Care of Vessel | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.13 | Safety Requirements | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.14 | Hot Work/Welding | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.16 | Preservation | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.17 | Environmental & Hazwaste Management | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.21 | Integrated Logistics Report | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.22 | Gas Free | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 1.24 | Process Control Procedure (PCP Requirements) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| DOCKING & UNDOCKING THE VESSEL | |||||||||||
| 3.1.1 | Personal & Equipment | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.2 | Docking Procedure | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.3 | Blocking Plan | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.4 | Crib and Brace Blocking | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.5 | Setting & Alignment of Docking Blocks | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.6 | Stability Calculations | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.7 | Docking Conference | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.8 | Docking the Vessel | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.9 | Post Docking | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.10 | Shifting the Vessel | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.11 | Undocking the Vessel | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.1.13 | Final Docking Report | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| HULL REPAIRS | |||||||||||
| 3.2.1 | Identify Distinguishing Figures & Markings-Hull | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.2.2 | Rubber Fenders | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.2.3 | Zinc Anodes | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.2.4 | Hull & Freeboard Blasting & Preservation | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.2.5 | Hull Structural Opening-Visual Inspection | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.2.6 | Hull & Freeboard Visual Inspection | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.2.7 | Hull & Freeboard Ultrasonic Testing (UT Reports) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| STRUCTURAL REPAIRS | |||||||||||
| 3.3.1 | Hull/Structural Repairs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| TANKS & VOIDS | |||||||||||
| 3.4.1. | Marine Sanitation Device (PCP) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.2 | Open, Pump, Clean, Vent, Gas Free, & Close Tanks | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.3 | Tank & Void Visual Inspection | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.4 | Tank & Void Preservation | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.5 | Preliminary Air Test | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.6 | Clean, Flush, & Disinfection of Fresh Water System | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.7 | Certification of Fresh Water Piping and Tank | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.8 | Start-Up Procedure for MSD System | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.9 | Final Air Test | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.10 | Tanks & Void Closeout Inspection | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.11 | Tanks & Void Gasket Repair | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.4.12 | On-Load Fuel | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| MAIN DECK REPAIRS AND PRESERVATION | |||||||||||
| 3.5.1 | Identify Color Schemes & Markings- Main Deck | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.5.2 | Main Deck Non-skid Repair | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.5.3 | Visual Inspection for Structural Defects | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.5.4 | Ultrasonic Testing Inspections (UT Reports) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.5.5 | Hatch Repairs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.5.6 | Vent Trunk Inspections | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| SUPERSTRUCTURE REPAIRS | |||||||||||
| 3.6.1 | Deck House - Top Non-skid Repairs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.2 | Visual Inspection for Structural Defects | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.3 | Ultrasonic Testing Inspections (UT Reports) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.4 | Pilot House - Top Non-skid Repairs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.5 | Visual Inspection for Structural Defects | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.6 | Ultrasonic Testing Inspections (UT Reports) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.7 | Deck House Exterior Preservation | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.8 | Pilot House Exterior Preservation | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.9 | Mast Exterior Preservation | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.6.10 | Main Mast Wire Seal Repair | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| MAIN PROPULSION REPAIRS | |||||||||||
| 3.7.1 | Waterborne Shaft Position - Shaft Coupling Alignment | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.7.2 | Removal of Propellers, Shafts, Couplings, & Bearings | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.7.3 | Inspections for Wear & Defects | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.7.4 | Clean, Polish, Inspect, Balance Propellers | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.7.5 | Propulsion Re-Assembly | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.7.6 | Propulsion System(s) Operational Testing | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| STEERING REPAIRS | |||||||||||
| 3.8.1 | Rudder Swing Test | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.8.2 | Steering Removals | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.8.2.1 | Rudder Stock Bearing | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.8.3 | Re-Assembly | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.8.4 | Rudder Swing Test - Final | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| MACHINERY SYSTEMS | |||||||||||
| 3.9.1 | Hydraulic Power Systems & Component Operational Testing | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.9.2 | Diesel Engine/Generator System & Component Operational Testing & Top-End Overhaul | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.9.3 | Heat Exchanger & After Cooler Inspection & Repairs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| ELECTRICAL SYSTEMS | |||||||||||
| 3.10.1 | Electrical Systems & Components Operational Testing | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.10.2 | Lighting Systems Operational Testing | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.10.3 | Clean Electrical Contacts & Relays/Repairs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| PIPING REPAIRS | |||||||||||
| 3.11.1 | Rinse & Flush Potable Water & Piping | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.11.2 | Potable Water Piping Tightness Test | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| 3.11.3 | Hull Valve Cycle/Inspections | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| DOCK & SEA TRIALS | |||||||||||
| 3.12 | Dock & Sea Trials | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| Total | 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |
| Labor Rate/MH: | G&A Rate: | Profit Rate: | |||||||||
| Total Bid: | $0.00 |
&C********DOLLAR ENTRIES ARE AUTOMATICALLY ROUNDED UP TO THE NEAREST WHOLE DOLLAR********* =MH*Labor Rate*G&A =(Prime Material Price+Subcontractor Total)*Profit Rate =SUM(Prime Total+Subcontractor Total+ODC+G&A+Profit) =(MH*Labor Rate)+Material Price =Sub Cost (F) *ODC-Defined as anything other than labor, subcontracts, and/or material that is directly attributable to a contract per FAR 31.202. Examples include rental charges and travel etc.
NOTE: Please fill in within the yellow highlighted boxes, the fixed labor rate, proposed G&A and proposed Profit rates.
NOTE: Labor rates and Profit rates used to calculate for the overall price of the base contract award shall be the basis for pricing on all modifications under this contract.
File details come from the government source that posted it. Updated .