C04_Attachment 3 Statement of Work.pdf

PDF 116 KB Posted

Attached to
GAOA Cordova Outhouse Replacement Chugach NF
Solicitation number
1240BH26Q0041
Issued by

About this file

This is a Statement of Work for a construction project on the Cordova Ranger District of the Chugach National Forest near Cordova, Alaska.

The base item involves replacing two single vault toilets at mile 18.1 and 18.2, and one double vault outhouse at Alaganik Slough recreation area. Five option items are included: Option 1 provides aggregate for Mile 22 picnic structure and parking area; Option 2 constructs one sheltered picnic structure at Mile 22 recreation area; Option 3 constructs two sheltered picnic structures at Alaganik Slough recreation area; Option 4 builds one new camping pad with parking at Alaganik Slough recreation area; and Option 5 widens three existing parking pads and regrades four existing camping pads at Alaganik Slough recreation area. Project locations are specified with geographic coordinates for all sites.

The SOW establishes applicable specifications including Sections 100-149 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), with Supplemental Specifications taking precedence in case of discrepancies. Contractors must submit multiple items for Government approval within specified timeframes: Traffic Control Plan and Safety Plan (30 workdays), Erosion Control Plan (30 days), Engineered Spill Prevention Plan (30 workdays), Construction Work Schedule (30 workdays), shop drawings for vault outhouses and picnic shelters (30 workdays each), material certifications for aggregate and concrete mix design (30 workdays each), and payroll records with certified payrolls and Drug Free Workplace Policy certification (N/A approval timeframe).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

C-1 PROJECT SCOPE

Base item of this project is to replace two (2) single vault toilets at mile 18.1 and 18.2, and one (1) double vault outhouse at Alaganik Slough recreation area. Option item No. 1 of this project consists of providing aggregate for Mile 22 picnic structure and parking area. Option item No. 2 consists of constructing one (1) sheltered picnic structure at Mile 22 recreation area. Option item No. 3 consists of constructing two (2) sheltered picnic structures at Alaganik Slough recreation area. Option item No. 4 consists of building one

(1) new camping pad with parking at Alaganik Slough recreation area. Option item No.

5 consists of widening three (3) existing parking pads and regrading four (4) existing camping pads at Alaganik Slough recreation area.

C-2 PROJECT LOCATION

This project is located on the Cordova Ranger District on the Chugach National Forest, near Cordova, AK. From Cordova Ranger Station travel Federal Ave for 0.2 miles. Turn left onto First Street/ Copper River Highway. To access the Alaganik Recreation Area, travel for 15 miles on the Copper River Highway. Turn right onto Alaganik Slough Road.

Follow until the end of the road to reach the Alaganik project site (60.429474, - 145.299628). 18 Mile (60.46092, -145.31006), One-Eyed Pond (60.4601, -145.30814), and Mile 22 Recreation Area (60.436434, -145.214454) are all accessible from the highway.

C-3 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT

The attached “List of Specifications” and “Supplemental Specifications” apply. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.

Section 100 through 149 of the Standard Specifications For Construction of Roads and Bridges on Federal Highway Projects (FP-14) and all other Standard or supplemental specifications shown in the Specification Listing are applicable to this contract. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.

Supplemental Specifications refine, revise, and add to the requirements stated in the Standard Specifications, and shall be included at the BPA call level when appropriate.

The Standard Specifications and Supplemental Specifications must be read as a whole to gain a full understanding of the work required. In the case of discrepancies, however, between these specifications, the Supplemental Specifications will take precedence over the Standard Specifications.

C-4 PRODUCTS SAMPLES AND/OR SUBMITTALS

Title Referenced by Contract clause or Specification No.

Time of Government Approval After Submittal

Traffic Control Plan Per MUTCD standards and FP-14 635

30 workdays

Erosion Control Plan FP-14 157 30 days Engineered Spill Prevention Plan Landscape preservation and Hazardous Materials clause in section H

30 workdays

Construction Work Schedule FP-14 155 30 workdays Safety Plan FAR 52.236-13 30 workdays Payroll Record WH347 Certified Payrolls

FAR 52.222-8 N/A

Drug Free Workplace Policy FAR 52.226-7 N/A

C-5 SHOP DRAWINGS

clause or Specification No.

Time of Government Approval After Submittal

Final manufacturers drawings for double vault outhouse with sheltered entrance

FSSS 726 30 workdays

Final manufacturers drawings for single vault outhouse

FSSS 726 30 workdays

Final selections for vault anchors, including all cables and fasteners Sheet D-04

30 workdays

Final shop drawings for picnic shelter FSSS 727

30 workdays

C-6 MATERIAL CERTIFICATIONS AND TESTING REPORTS

clause or Specification No.

Time of Government Approval After Submittal

Aggregate Certification FP-14 703 30 workdays Concrete Mix Design FP-14 601 30 workdays

STATEMENT OF WORK
C-2 PROJECT LOCATION
C-3 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT

File details come from the government source that posted it. Updated .