This is a Specifications and Statement of Work document for the GAOA Island Park Administration Site Sewer System Replacement project located in the Caribou-Targhee National Forest, Fremont County, Idaho, approximately 53 miles north of Rexburg.
The base contract scope includes replacement of two existing sewage lift stations with a single lift station featuring a 96-inch diameter wet well, valve vault, and electrical control panels; installation of new PVC gravity sewer lines connecting existing lift stations; installation of a new 4-inch HDPE pressure pipeline connecting to the county pressure main with associated air/vac relief and check valves; installation of RV sewer hookup assemblies; removal and disposal of two existing lift stations including vaults and electrical services; and associated pavement and gravel road restoration. The project also includes five optional work items for gravity sewer mains, services, and connections serving residential structures, an office building, a bunkhouse, and an RV park, each with associated manholes, cleanouts, and surface restoration. The contract start date is May 1, 2027, with 150 calendar days allowed for completion of base work plus options. The project requires construction staking, utility coordination with Fall River Electric and Fremont County Sewer, sediment and erosion control measures, traffic control compliance with MUTCD standards, and comprehensive quality control testing including concrete compression tests, compaction tests, hydrostatic testing for pressure and non-pressure sewerlines, and performance testing of lift station equipment. Specific material requirements include Class A concrete with minimum 3,750 psi compressive strength, precast reinforced concrete utility boxes and manhole structures per ASTM C478, HDPE pipe with bent strap testing, and manufactured sewer lift stations with emergency operations testing. The contractor must submit a quality control plan, construction schedule within five days of work commencement, traffic control and safety plan, sediment and erosion control plan two weeks prior to start, and as-built drawings upon project completion. Mobilization payment is structured in phases tied to work completion percentages, with 50 percent payable at 5 percent completion and remaining amounts at 10 percent completion and final acceptance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
Final – 04/07/2025
1.1 SCOPE OF CONTRACT
A. This project includes the replacement of two sewage lift stations with a single lift station serving the Island Park Administration Site on the Island Park District of the Caribou- Targhee National Forest. Associated work will include installation of connecting gravity sewer pipelines and a relocated pressure sewer pipeline, along with several optional bid items for replacing portions of the site sewer collection system.
B. The work includes:
1. Installation of a sewage lift station to Fremont County Standards including a 96” diameter wet well, adjacent valve vault, and electrical control panels;
2. Design and install required electrical service to the sewage lift station in accordance with Fall River Electric requirements;
3. Installation of new PVC gravity sewer line connecting two existing lifts stations to the new lift station;
4. Connection of existing gravity lines to the new gravity line;
5. Installing associated manholes and cleanouts;
6. Installing a new 4” HDPE pressure pipeline connecting to the existing county pressure main, including associated air/vac relief and check valves with vaults;
7. Installing RV sewer hookup assemblies;
8. Removal of two existing sewage lift stations including vaults and electrical services; and
9. Associated pavement and gravel road restoration.
C. Optional work that may be awarded includes all work associated with:
1. Option #1: Gravity sewer mains, services, and connections associated with four homes; including associated manholes, cleanouts, and surface restoration.
2. Option #2: Gravity sewer mains, services, and connections associated with four homes; including associated manholes, cleanouts, and surface restoration.
3. Option #3: Gravity sewer mains, services, and connections associated an office and one home; including associated manholes, cleanouts, and surface restoration.
4. Option #4: Gravity sewer mains, services, and connections associated with an RV park; including associated RV hookup assemblies, manholes, cleanouts, and surface restoration.
5. Option #5: Gravity sewer mains, services, and connections associated with an office and one bunkhouse; including associated manholes, cleanouts, and surface restoration.
6. Option #5: Gravity sewer service and connections associated with a shop building and two bunkhouses; including associated manholes, cleanouts and surface restoration.
D. Quantities associated with these options are identified in the Schedule of Items.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
1.2 PROJECT LOCATION
A. The project is located in the Island Park Ranger District of the Caribou-Targhee National Forest, Fremont County, Idaho, in Section 27, T 13 N, R 43 E. It is located approximately 53 miles North of Rexburg, Idaho. The project may be accessed from US Highway 20 and Old Chick Creek Road.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. However, Contractor's use of premises is limited to the extent that the work is within a functioning operations and residential setting and must remain open for that use. Portions of the site with active work may be cordoned off for construction purposes so long as regular functions of the site are able to continue. Contractor's use of premises is limited by the Government's right to perform work or to retain other contractors on portions of Project site.
2. Contractor shall conduct his operations to ensure the least inconvenience to the public and employees. Road closures will be permitted, when required, upon written approval of the Contracting Officer (CO). Short duration closures of plumbed facilities will be permitted, when required, upon written approval of the Contracting Officer (CO). Such closures should be timed to have the least impact on site operations.
3. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect Government employees and residents working and living on the site during all construction operations. Contractor shall minimize disturbance of all grounds outside work limits or approved storage and staging areas.
4. All construction equipment shall be pressure-washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
5. Water is available at the site for construction purposes (subject to availability).
6. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and, if signage impacts US Highway 20, Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD).
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.
B. Overnight camping will be allowed on site only with CO and District Ranger approval and will be subject to availability.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 START DATE
A. May 1, 2027
1.8 CONTRACT TIME
A. Base + Options: 150 Calendar Days
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
SECTION 010250 - CONSTRUCTION STAKING
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION 011900 - MOBILIZATION
SECTION 012500 - UTILITY COMPANY COORDINATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 015100 - TEMPORARY TRAFFIC CONTROL
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
SECTION 024100 - WASTE MATERIAL DISPOSAL
SECTION 024102 - REMOVAL AND DISPOSAL OF STRUCTURES AND
OBSTRUCTIONS
SECTION 033015 - CONCRETE FOR MINOR STRUCTURES
SECTION 033540 - CONCRETE SIDEWALK
SECTION 133402 - UTILITY BOXES
SECTION 221103 - PLUMBING APPURTENANCES
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4
SECTION 221104 - EQUIPMENT LABELING FOR WATER AND WASTEWATER
SYSTEMS
SECTION 221300 - ONSITE WASTEWATER TREATMENT SYSTEMS
SECTION 221310 - PACKAGED SEWER LIFT STATION
SECTION 260000 - COMMON WORK RESULTS FOR ELECTRICAL
SECTION 311000 - CLEARING AND GRUBBING
SECTION 312000 - EARTHWORK
SECTION 312010 - SELECT BORROW
SECTION 312100 - PROJECT SITE PREPARATION AND GRADING
SECTION 321200 - HOT-MIX ASPHALT PAVING
SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE
SECTION 322705 - PAVEMENT SAWING
SECTION 330530 - UTILITY LOCATING SYSTEM
END OF SECTION C
August 2026
CONSTRUCTION STAKING 010250-1
USDA FOREST SERVICE, R4
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 010250 - CONSTRUCTION STAKING
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of the construction staking of pipelines and associated utilities and access roads in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.
1.2 QUALITY CONTROL
A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.
1.3 MEASUREMENT AND PAYMENT
A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.
PART 2 - PRODUCTS
2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS
A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include:
1. Control Points - Northing, Easting, Existing Elevations.
2. Roads, Spurs, Parking Areas - Northing, Easting, and Finish Elevations for centerline and edge of roads, spurs, parking areas.
3. Buildings and Other Structures - Northing, Easting, and Finish Elevations for corners of buildings, other structures (septic tanks, fencing, etc).
4. Utility Lines - Northing, Easting, and Existing Ground Elevations for centerline of utilities (Water Line, Sewer Line, Electrical Lines).
2.2 STAKES
A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top
CONSTRUCTION STAKING 010250-2
2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:
1. Roads, parking lots, and parking spurs -Orange
2. Sewer lines, utilities, and culverts -Green
3. Buildings, vaults, excavation and grading -Yellow
2.3 SURVEY NOTE PAPER AND BOOKS
A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.
The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.
B. Accuracy requirements:
1. Minimum position close; 1/1000
2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)
3. Cross section and slope stake precision:
a. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.
b. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross-section points will not exceed: 1.0 ft.
c. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.
3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS
A. Access Roads, Parking Spurs, and Parking lots:
1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the
CONSTRUCTION STAKING 010250-3
grading plans and/or profiles, typical road section templates, as shown on the drawings and the information provided with staking points.
2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25-foot intervals around curves having a radius less than 100 feet.
B. Waterline, Sewerline, & other Utilities
1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.
C. Buildings and Vaults
1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.
3.3 DISCREPANCIES
A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of benchmarks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.
3.4 VERTICAL CONTROL
A. Vertical control for construction shall be as referenced on the Drawings.
3.5 MARKING STAKES
A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;
PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any)
CONSTRUCTION STAKING 010250-4
C Cut F Fill L Centerline D Ditch W Width
3.6 SURVEY NOTES
A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.
B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.
END OF SECTION 010250
MEASUREMENT AND PAYMENT 011250-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
MEASUREMENT AND PAYMENT 011250-2
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
3. Each (EA): One complete unit, which may consist of one or more parts.
4. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
5. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
6. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
7. Lump Sum (LS): One complete unit.
8. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
9. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
10. Square Foot (SF): Measured on a plane parallel to the surface being measured.
11. Square Yard (SY): Measured on a plane parallel to the surface being measured.
12. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, MEASUREMENT AND PAYMENT 011250-3 and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MOBILIZATION 011900-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
UTILITY COMPANY COORDINATION 012500-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 012500 - UTILITY COMPANY COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of coordination with utility companies for connection to their systems.
1.2 COORDINATION
A. Electrical: Fall River Electric, Business Customer Service; 800-632-5726.
B. Communications telephone: CenturyLink.
C. Water: US Forest Service. Coordinate with CO and Ranger District operations personel.
D. Sewer: Fremont County Sewer; P.O. Box 643, Island Park, ID 83429; 208-610-7348.
1.3 FEES FOR UTILITY COMPANIES
A. Tap and connection fees:
1. Sewer system tap fees are to be paid by the contractor.
2. Connection fees are not anticipated.
1.4 TEMPORARY UTILITIES
A. Any costs associated with temporary utility installation as a component of construction, including, but not limited to, distribution lines, distribution equipment, and meter assemblies, will be the responsibility of the contractor.
1.5 INSPECTION
A. If needed, comply with utility company requirements for inspections before final connection is made.
1.6 PERMITS
A. Permits are not anticipated at this time.
1.7 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
UTILITY COMPANY COORDINATION 012500-2
PART 2 – PRODUCTS – not used
PART 3 – EXECUTION – not used
END OF SECTION 012500
FEBRUARY 2022
SUBMITTAL PROCEDURES 013300-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title
Subse ction
Required Submittal
C General Specifications 1.4A Traffic Control Plan 010250 Construction Staking 3.6 A Survey Notes 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 023701 Sediment & Erosion Control
Measures 1.2A Sediment & Erosion Control Plan
033015 Concrete For Minor Structures 1.2A Product Data 133402 Utility Boxes 1.3A Product Data 133402 Utility Boxes 1.3B Shop Drawings 133402 Utility Boxes 1.3C Product Certificates 221103 Plumbing Appurtenances 1.2A Product Data 221103 Plumbing Appurtenances 1.2B Operation and Maintenance Data 221300 Onsite Wastewater Treatment System 1.3A Product Data 221300 Onsite Wastewater Treatment System 1.3B Shop Drawings 221310 Packaged Sewer Lift Station 1.3A Product Data 221310 Packaged Sewer Lift Station 1.3B Shop Drawings 221310 Packaged Sewer Lift Station 1.3C Coordination Drawings 221310 Packaged Sewer Lift Station 1.3D Operation and Maintenance Data 221310 Packaged Sewer Lift Station 1.3E Transition and Operation Plan 260000 Common Work Results for Electrical 1.2A Product Design 260000 Common Work Results for Electrical 1.3A Product Data 260533 Common Work Results for Electrical 1.3 Operation and Maintenance Data 312000 Earthwork 1.3A Bedding and Backfill Certification 312000 Earthwork 1.3A Sieve Analysis 312000 Earthwork 1.3B Product Data 321200 Hot Mix Asphalt Paving 1.3A Product Data 321200 Hot Mix Asphalt Paving 1.3B Job Mix Design 321200 Hot Mix Asphalt Paving 1.3C Material Certificate 321204 Crushed Aggregate Base or Surface
Course 1.2A Aggregate Base – Source, Gradation, Material Properties 321204 Crushed Aggregate Base or Surface
Course 1.2B Compaction Test Results and
Proctor
END OF SECTION 013300
QUALITY CONTROL 014100-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 014100-2
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
QUALITY CONTROL 014100-3
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency 033015 3.5C Mixing and Delivery Each Truck 033015 3.12A Concrete – Slump, Air, Temperature 1 composite per truck load delivered 033015 3.12B Concrete - Compression Test
Specimens at 7 days and 28 days (see spec)
221300 3.2P HDPE Pipe - Bent Strap Test Once Daily 221300 3.8A Hydrostatic Testing for Non-
Pressure Sewerline See Spec.
221300 3.9B Hydrostatic Testing for Pressurized Sewerline
See Spec.
221310 3.6A Performance Testing Until Passing
221310 3.6B Emergency Operations Until Passing
QUALITY CONTROL 014100-4
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency 221310 3.6E Wet Well Leakage Test Until Passing
312000 3.14C Compaction Test – at Pipe Zone One per 600 Feet of
Trench 312000 3.14C Compaction Test – at Pipe Zone One test – at each road crossing 312000 3.14D Compaction Test – above Pipe
Zone One per 600 Feet of
Trench 312000 3.14D Compaction Test – above Pipe
Zone One test every other lift – at each road crossing
312000 3.17A Compaction Test – Backfill/Fills One per Tank, Utility Building or
Utility Box 312000 3.19A Compaction Test – Exterior
Concrete Slabs 1 per slab
312000 3.19A Compaction Test – Backfill/Fills and Subgrade under Buildings and
Driveways
One test every 150
sq. yd. area per lift and at Subgrade 321200 3.10B Gradation and Asphalt Content One per 700 tons or
Min. of 1 per Project 321200 3.10C Field Density Tests – Asphalt One test for every
300 sq. yd. of pavement
321204 3.4A Compaction Tests – Road Base and Surface Course
One test for every 300 sq. yd. of aggregate 321204 3.4A Compaction Tests – Aggregate
Base for Concrete Slabs and Vaults One test for each prefabricated building pad or vault
330530 4.1A Performance Verification Testing Until passing
END OF SECTION 014100
TEMPORARY TRAFFIC CONTROL 015100-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 015100 - TEMPORARY TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of furnishing, maintaining, relocating, and removing temporary traffic control and safety devices and services for the control and protection of public traffic near the project site. Prior to beginning construction the Contractor shall submit a traffic control and safety plan to the Contracting Officer for review and approval. As a minimum the traffic control and safety plan shall address signing in and near the project site and at all road and highway junctions that will be used as access to the project site, material sources, water sources and disposal sites as well as any other areas where the Contractor will be performing work under this contract.
1.2 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 TRAFFIC CONTROL
A. Traffic control and safety device (barricades, cones, tubular markers, vertical panels, drums, portable barriers and so forth) designs and configurations shall conform to the MUTCD. When interpreting the requirements in the applicable MUTCD sections, replace the word should with the word shall.
PART 3 - EXECUTION
3.1 GENERAL
A. All signs shall be constructed to comply with the requirements of MUTCD for the construction operations. Install and maintain temporary traffic control and safety devices adjacent to and within the project as shown on the approved traffic control and safety plan and MUTCD. Install and maintain traffic control and safety devices as follows:
1. Furnish and install traffic control and safety devices before the start of construction operations.
2. Install only those traffic control and safety devices needed for each stage or phase.
3. Relocate temporary traffic control devices as necessary.
4. Immediately replace any device that is lost, stolen, destroyed, or inoperative.
5. Keep temporary traffic control and safety devices clean.
TEMPORARY TRAFFIC CONTROL 015100-2
6. Remove all temporary traffic control devices upon contract completion or when approved.
B. Barricades
1. Perform the work described under MUTCD Part VI. Use type III or IV reflective sheeting. Use wood, metal, or plastic barricades. When type II barricades are used, use barricades that collapse when tipped over.
C. Construction Signs
1. Use type III or IV reflective sheeting. Use wood, metal, fiberglass, or other approved posts.
END OF SECTION 015100
SEDIMENT AND EROSION CONTROL MEASURES 023701-1
GAOA ISLAND PARK ADMINISTRATION SITE SEWER SYSTEM REPLACEMENT
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
PART 1 - GENERAL
1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.
A. General
1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.
2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.
3. Soil disturbing activities include but are not limited to: Clearing and grubbing, excavation for utilities and foundations, roadway and parking lot construction, construction or modification of site drainage, grading, and preparation for final seeding.
1.2 SUBMITTALS
A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 2 weeks prior to start of work.
1.3 PERMITS
A. The Contractor shall apply for and pay for a National Pollutant Discharge Elimination System (NPDES) permit from the state the project resides in.
1.4 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 SYNTHETIC FILTER FABRIC FOR SILT FENCES.
A. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:
Physical Properties (Min.) Requirement Test Method Grab Tensile, lbs. W120/F100 ASTM-D-4632
SEDIMENT AND EROSION CONTROL MEASURES 023701-2
Grab Elongation, % 15 ASTM-D-4632 Mullen Burst, psi 275 ASTM-D-3786 Puncture, lbs. 65 ASTM-D-4833 Trapezoidal Tear, lbs. 50 ASTM-D-4533 UV Resistance, % 80 ASTM-D-4355 AOS, US Sieve # 30/40 ASTM-D-4751 Permittivity gal/min-sq. ft. 90 ASTM-D-4491
B. Filter fabric should contain ultraviolet ray inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 to 120 F.
C. Support Posts: 4 foot - 2 x 2 wood.
2.2 STRAW BALES
A. Oat or wheat straw, free from weeds, viable weed seeds, foreign matter detrimental to plant life, and dry.
1. Grass hay bales are not acceptable.
2. In order to prevent deterioration of the bindings, all bales shall be either wire-bound or string-tied so that bindings are oriented around the sides rather than along the tops and bottoms of the bales.
2.3 STRAW WATTLES OR ROLLS
A. Furnish straw wattles or rolls that are manufactured from weed free straw and wrapped in a tubular photodegradable plastic netting made from 85% high density polyethylene, 14% ethyl vinyl acetate and 1% color for UV inhibition. Conform to the following:
1. Diameter 9 inches min.
2. Netting strand thickness 0.030 inches
3. Netting knot thickness 0.055 inches
4. Mass of netting 0.315 to 0.385 ounces per foot
PART 3 - EXECUTION
3.1 CONSTRUCTION
A. Install straw bales at local drainage ways to prevent silt intrusion upon adjacent drainage courses. Remove straw bales following establishment of vegetation cover and utilize as mulch at swales or on steep slopes.
B. Prior to construction, install silt fence along the…