This is a Statement of Work for HVAC equipment replacement at the Murphysboro facility, Shawnee National Forest, Mississippi Bluffs Ranger District, Jackson County, Illinois.

The work scope requires removal, disposal, and replacement of one gas furnace and two air conditioning units. The project includes two distinct work packages: (1) complete replacement of both a gas furnace and A/C system, and (2) A/C system replacement only with the existing gas furnace remaining in place. For the combined replacement, specifications include a 3 1/2 ton A/C unit with 14 SEER2 rating using R-454B refrigerant, a 3 1/2 ton evaporator coil, a 90,000 BTU gas furnace with 80% AFUE efficiency, and a minimum 10-year parts/20-year heat exchanger warranty. For the A/C-only replacement, specifications include a 3 1/2 ton A/C unit with 14 SEER2 rating using R-454B refrigerant, a 3 1/2 ton evaporator coil with thermostatic expansion valve sized at 21" width to match furnace dimensions, and a minimum 10-year parts warranty. All work must include equipment installation, electrical connections, duct and flue adaptations, refrigerant line preparation and copper adaptations, and condensate drain materials. Work shall comply with current building, electrical, plumbing, and gas codes. Contractor work hours must be coordinated with the onsite building manager during office hours of 8:00 a.m. to 4:30 p.m., Monday through Friday. The contractor is responsible for daily removal of all trash and debris and must provide proof of proper disposal when requesting payment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MURPHYSBORO HVAC REPLACEMENT

Shawnee National Forest

Mississippi Bluffs Ranger District

Jackson County Illinois

Part I - STATEMENT OF WORK:

All work materials, supplies, and labor to remove, dispose of and replace one (1) Gas Furnace and two (2) Air Conditioning Units.

Part II - REQUIREMENTS:

A. Replacement of Gas Furnace & A/C.

a. This includes, but not limited to, Equipment installation, High and low voltage electrical connections to new equipment, Duct adaptations, Flue adaptations, Flush refrigerant lines, Copper refrigerant line adaptations, Condensate drain materials

b. Minimum System Specifications:

3 1/2 Ton A/C

14 SEER2

R-454B Refrigerant

3 1/2 Ton Evaporator Coil

90,000 BTU Gas Furnace

80% AFUE

Minimum Warranty - 10 yr parts / 20 yr heat exchanger

2. Replacement of A/C system –

a. This includes new indoor evaporator coil, New outdoor condenser, Refrigerant line set copper adaptations, Flush refrigerant lines (underground), Duct adaptations, Condensate drain materials, Existing gas furnace to remain in place

b. Minimum A/C specifications:

3 1/2 Ton A/C

14 SEER2

R-454B refrigerant

3 1/2 Ton Evaporator Coil (TXV)

21" Width to match furnace width

Minimum Warranty - 10 yr parts

B. All work shall be done in accordance with current building, electrical, plumbing and gas codes as applicable.

C. Office hours are 8:00 am until 4:30pm, Monday thru Friday. Work hours should be coordinated with the onsite building manager.

D. Contractor is responsible for removing all trash and debris from their work from the worksite daily and leaving the sit in the same condition as when they stated.

E. Contractor shall provide proof of proper disposal when requesting payment.