C06_Murphysboro HVAC Replacement QA_12444526Q0038.pdf
PDF 681 KB Posted
- Attached to
- FY26 Murphysboro Dispatch HVAC Replacement
- Solicitation number
- 12444526Q0038
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Questions and Answers document for the Murphysboro HVAC Replacement contract opportunity. The document addresses 20 questions from potential contractors regarding the scope, specifications, site conditions, and procedural requirements for replacing HVAC equipment at a Murphysboro facility.
The project involves two line items: Item 0001 covers replacement of a gas furnace and A/C unit, while Item 0002 addresses replacement of an A/C system. Replacement specifications are detailed in attachment CO2 SOW and include a York furnace (Model P4HUC20N0001A, Serial WGLM0E368) with 100,000 BTU input and 80,000 BTU output, and an Advanced Distributor Products air handler unit (Model YE50160E210B2705AP, Serial 7112D20501). Contractors must meet or exceed specifications but are not required to match brands or AHRI-certified systems; however, all units must function together. The existing furnace is located in the basement with an upflow configuration in a very small space with ductwork above the units. A site visit is not required but recommended to assess unit placement. The contractor is responsible for verifying all field measurements, obtaining permits and inspections, and coordinating work schedules with the building manager during normal business hours (8 am to 4:30 pm). Underground refrigerant lines are anticipated to be reused and flushed rather than replaced, and field transitions or modifications to accommodate the new evaporator coil are acceptable. No electrical upgrades, crane services, hazardous materials, or thermostat/control replacements are anticipated. Additional required documentation includes forms referenced in CO1 Attachment A on page 8 regarding evaluation and basis for award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Murphysboro HVAC Replacement Q&A
1. Q: Are the specifications for the replacement furnace and A/C units available (manufacturer, model, tonnage, efficiency requirements, etc.)?
A: The replacement units are in attachment CO2 SOW.
2. Q: Is a site visit required or recommended prior to submitting a quote?
A: Site visit is not required but it is recommended to assess placement of the units.
3. Q: Are there any preferred brands or approved equipment manufacturers for this project?
A: There is no preferred brand, the specifications may be met by several manufacturers.
4. Q: Will the government provide any existing equipment information, or is the contractor responsible for verifying all field measurements?
A: Contractor is responsible for verifying all field measurements.
5. Q: Are there any additional forms or documents required with the quotation besides the pricing proposal?
A: Please see CO1 Attachment A starting on page 8 Evaluation and Basis for Award
6. Q: In reference to the attached SOW, what is the existing model and serial number of the furnace that will remain in place and the model and serial number of its respective condenser that requires replacement?
A. See Attachments below.
7. Q: In reference to the system to be replaced, is the furnace in the attic? Is it a horizontal flow or upflow? Is the attic accessible from the floor with a ladder or an attic stairwell?
A. The furnace is in the basement with a walk-in exterior door. I believe it is an upflow unit.
The 3 units are in a very small space, and the ductwork is above the units.
8. Q: Under Item 0001, Replacement of Gas Furnace & A/C, can the Government confirm that a complete AHRI-matched system is required, including a matching condensing unit, evaporator coil, and furnace?
A. The contractor is to meet or exceed the specifications listed. Brand names or matching models are not a requirement, but all units should be able to function together.
9. Q: Under Item 0002, Replacement of A/C System, the Statement of Work specifies a 21-inch-wide evaporator coil to match the existing furnace width. Are there any required dimensions for the evaporator coil depth and length, or will field transitions and modifications be acceptable?
A. Field transitions and modifications are acceptable. The unit should fit the same space as the one being replaced.
10. Q: The Statement of Work references "Flush refrigerant lines (underground)." Can the
Government confirm whether the existing underground refrigerant line set is to remain in service and be flushed and reused, or if replacement will be required if the lines fail pressure testing or are otherwise determined to be unsuitable for reuse?
A. It is anticipated the original lines will be reused and remain in service.
11. Q: Are equipment model numbers, serial numbers, nameplate information, or photographs of the existing systems available?
A. See Attachments below.
12. Q: Is a site visit available prior to quote submission?
A: Site visit is not required but it is recommended to assess placement of the units.
13. Q: Are there any known electrical deficiencies or electrical service upgrades anticipated as part of this project?
A. Electrical service repairs or upgrades are not anticipated at this time.
14. Q: Will permits and inspections be required, and if so, is the contractor responsible for obtaining and paying for them?
A. All permits and inspections needed are the responsibility of the contractor.
15. Q: Are crane services or other special access equipment anticipated or required to complete the work?
A. Use of a crane or other special access is not anticipated.
16. Q: Are there any restrictions regarding working hours, building occupancy, noise, or scheduling that could impact installation activities?
A. The office is not open to the public at this time. However, employees will be present. Normal business hours are from 8 am until 4:30 pm. Contractor should coordinate access and work schedules with the building manager.
17. Q: Will the Government provide access to staging and storage areas for equipment and materials during replacement?
A. There is space onsite if staging or storage is needed. Locations will be coordinated with the building manager.
18. Q: Is asbestos, lead paint, or any other hazardous material known to be present in the areas where work will be performed?
A. At this time there are no hazardous materials anticipated to be present in the work areas.
19. Q: Are controls, thermostat replacements, or building automation integrations required as part of the project?
A. This contract is for the removal and replacement of the units identified only.
20. Q: If unforeseen site conditions or conditions not reasonably identifiable from the solicitation documents are encountered during performance, what is the Government's process for addressing such conditions and determining whether additional work is outside the original scope?
A. Please reference the FAR clauses in the contract, both those referenced and those included by reference.
Attachments
Unit to be replaced, Furnace
Air Handler Units