C-2 Attachment 1 SOW.pdf

PDF 394 KB Posted

Attached to
BBVC Lakefront Trail and Outhouse Replacement Federal contract opportunity
Solicitation number
1240BJ26Q0004
Issued by
Department of Agriculture Forest Service

About this file

This is a Statement of Work (SOW) for the BBVC Lakefront Trail and Outhouse Replacement project located at the Begich Boggs Visitor Center in Portage Valley, Alaska (coordinates 60°47'4.52"N, 148°50'28.47"W), issued by the United States Department of Agriculture Forest Service, Glacier Ranger District, Chugach National Forests.

The project scope includes removal of an existing concrete trail along Portage Lake lakefront and construction of a new trail connecting the Trail of Blue Ice to the Begich Boggs Visitor Center, decommissioning of two existing outhouses and installation of one new double vault outhouse in a new location. Work activities encompass demolition, earthwork, clearing and grubbing, small concrete structures, retaining wall installation, drainage, trail switchbacks, trail surfacing, outhouse installation, erosion control measures, and reseeding. Two option items are available: Option 1 consists of constructing a scenic outlook platform with interpretive panels by the lakefront; Option 2 involves construction of a trail connecting beach access near the building to the parking lot. The project will be governed by Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14, 2014 Edition), Standard Specifications for Construction of Trails and Trail Bridges on Forest Service Projects (2014 revision), and Forest Service Supplemental Specifications.

Contractor submittals required include Traffic Control Plan, Erosion Control Plan, Engineered Spill Prevention Plan, Construction Work Schedule, Safety Plan, Payroll Records, Drug Free Workplace Policy, Disposal Plan, and Quality Control Plan, all with 30 workday approval timelines. Shop drawings are required for the double vault outhouse, railing system, sign plan, and bollards, also with 30 workday approval periods. Material certifications and testing reports for aggregate, concrete mix design, and geotextile are required with 30 workday approvals. A post-award conference via Teams will be held within 15 days of contract award. Construction activities are limited to Monday through Friday, 8:00 a.m. to 6:00 p.m., unless otherwise approved in writing; no vegetation clearing or site preparation activities are permitted during the migratory bird breeding season (May 1 – July 15). All construction and demolition activities in water must be completed between May 15 and July 15. The project area requires compliance with endangered species protection measures, including equipment cleaning certification and weed-free material certification under Alaska Division of Agriculture standards. The project is located in bear habitat requiring proper storage of food, garbage, and fuel. Additional requirements address cultural resource protection, hazardous conditions safety planning, soil disturbance minimization, and erosion control measures. Weather data provided indicates average temperatures ranging from 39°F to 57°F during the construction season (June through October), with average monthly precipitation between 10 and 24.4 inches.

View the file

Other files for this federal contract opportunity

Other files attached to BBVC Lakefront Trail and Outhouse Replacement, newest first.
File Type Posted
C-2 Attachment 5 Quote.docx DOCX document
C-1 RFQ 1240BJ26Q0004 - BBVC Lakefront Trail and Outhouse Replacement.pdf PDF
C-2 Attachment 2 Specifications.pdf PDF
C-2 Attachment 3 Plans and Drawings.pdf PDF
C-2 Attachment 4 Wage Determination.pdf PDF
C-2 Attachment 6 Bid Bond SF24.pdf PDF
C-2 Attachment 5 Quote.docx DOCX document
C-1 RFQ 1240BJ26Q0004 - BBVC Lakefront Trail and Outhouse Replacement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

BBVC Lakefront Trail and Outhouse Replacement Glacier Ranger District

Chugach National Forests Portage Valley, Alaska

STATEMENT OF WORK

1 PROJECT SCOPE

This project involves the removal of an existing concrete trail along the Portage Lake lakefront, and construction of a new trail that connects the existing Trail of Blue Ice to the Begich Boggs Visitor Center (BBVC). Additionally, two (2) existing outhouses will be decommissioned, and one (1) new double vault outhouse will be built in a new location.

a) Option item 1: Work consists of constructing a scenic outlook platform with interpretive panels by the lakefront.

b) Option item 2: Construction of a trail connecting the beach access near the building to the parking lot. Project work will include demolition, earthwork, clearing and grubbing, small concrete structures, retaining wall installation, drainage, trail switchbacks, trail surfacing, outhouse installation, erosion control measures and re-seeding.

2 PROJECT LOCATION

The existing concrete trail along the lakefront of Portage Lake frequently gets flooded, which has caused the supporting materials to be washed out and the concrete to fracture. It is unsafe for use and needs to be removed. The vaults for the two outhouses located in the BBVC parking lot frequently flood and need to be removed and replaced with a new structure in a different location to avoid similar problems in the future. The current Trail of Blue Ice (ToBI) ends at the entrance road of the BBVC parking lot, which poses a threat to hikers, who must share the road to get to the visitor center.

A connecting trail from the visitor center to ToBI will increase safety for hikers as well as visitors who wish to access the lake. Adjacent to the new trail, a loading zone will be designated to allow outfitters and guides, as well as individual visitors, to unload safely, while also reducing traffic congestion in the parking lot.

The project is located at the Begich Boggs Visitor Center in Portage Valley. Latitude: 60°47'4.52"N, Longitude:

148°50'28.47"W.

3 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT

Standard Specifications for Construction of Roads and Bridges on Federal Highway projects, FP-14, 2014 Edition.

Standard Specifications for Construction of Trails and Trail Bridges on Forest Service Projects 2014 rev.

Forest Service Supplemental Specifications are attached to this document

4 PRODUCTS SAMPLES AND/OR SUBMITTALS

Title Referenced by Contract clause or Specification No.

Time of Government Approval After Submittal

Traffic Control Plan Per MUTCD standards and

FP-14 635

30 workdays

Erosion Control Plan FP-14 157 30 days Engineered Spill Prevention Plan Landscape preservation and

Hazardous Materials clause in section H

30 workdays

Construction Work Schedule FP-14 155 30 workdays Safety Plan FAR 52.236-13 30 workdays Payroll Record WH347 Certified Payrolls FAR 52.222-8 N/A Drug Free Workplace Policy FAR 52.226-7 N/A Disposal Plan FP-14 203 30 workdays Quality Control Plan FP-14 153 30 workdays

5 SHOP DRAWINGS

clause or Specification No.

Time of Government Approval After Submittal

Final manufacturers drawings for double vault outhouse

FSSS 726 30 workdays

Final drawings for railing system including sign mounts

FSSS 727 30 workdays

Final sign plan and drawings FP-14 635 30 workdays Final drawing for bollards FP-14 619 30 workdays

6 MATERIAL CERTIFICATIONS AND TESTING REPORTS

clause or Specification No.

Time of Government Approval After Submittal

Aggregate Certification FP-14 703 30 workdays Concrete Mix Design FP-14 601 30 workdays Geotextile FP-14 258 30 workdays

7 POST AWARD CONFERENCE

A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held via Teams.

8 PROTECTION OF HABITAT OF ENDANGERED, THREATENED AND SENSITIVE SPECIES

Location of areas needing special measures for protection of plants or animals listed as threatened or endangered under the Endangered Species Act of 1973, as amended, or as sensitive by the Regional Forester under authority of FSM 2670, are shown on the Plans and identified on the ground. Measures needed to protect such areas have been included elsewhere in this contract or are as follows:

All tools and equipment used by contractors shall be cleaned and free of all plant material and soil prior to entering National Forest land or when moving between campgrounds.

All heavy equipment used by contractors on this project will be inspected by a USFS employee for plant materials and soil prior to entry on USFS lands. The DOI Technical Memorandum No. 86-68220-07-05: Inspection and Cleaning Manual for Equipment and Vehicles to prevent the Spread of Invasive Species should be provided to the contractor prior to implementation to provide clear guidance for equipment cleaning. Contact the zone ecologist, Peter Frank at peter.frank@usda.gov or 907-280-9020 at least two weeks prior to mobilizing equipment to schedule inspections.

All gravel or fill material brought onto the site from outside sources shall be certified as weed free under the State of Alaska’s Division of Agriculture weed free certification program.

Allow natural revegetation where seed source and site conditions are favorable towards achieving revegetation objectives.

Use only native species for rehabilitation or restoration efforts, if natural revegetation conditions are not favorable. All seed products used shall not exceed the maximum allowable tolerances for noxious weed seed established in Alaska Administrative Code Title 11, Chapter 34. Contact the zone ecologist, Peter Frank at peter.frank@usda.gov or 907-280- 9020 for recommendation of species and sources of plant material.

Contractor shall complete all construction and demolition activities in water between May 15 and July 15.

If any cultural resources are discovered during construction, contractor shall cease work and notify the CO immediately.

Soils:

Minimize soil disturbance and avoid disturbing soils outside the footprint of the project area.

Apply erosion control measures on exposed soils and establish permanent groundcover to prevent accelerated erosion.

Locate trails to conform to the terrain. Install and maintain suitable drainage measures to collect and disperse runoff and avoid or minimize erosion of trail surface and adjacent areas.

Limit operation of ground-based equipment when ground conditions could result in excessive rutting, soil puddling, or runoff of sediments directly into waterbodies. Avoid creating ruts greater than 6 inches deep. Heavy equipment requires the use of puncheon, slash mattress, or geotextile fabric/matting on some sites to provide adequate bearing strength and prevent rutting. Puncheon or slash mat should be scattered upon completion. Slopes over 25 percent gradient may not be suitable for heavy machinery under some soil moisture conditions

Project area is in bear habitat. During project implementation, ensure that human and pet food, garbage, and odorous attractants (fuel) is attended by humans or stored in a bear resistant manner when not being used (bear cans or lockers, containment barrels or inside of vehicles). Garbage shall be removed daily.

To prevent disturbance to migratory birds (from CNF LMP pg. 53, Migratory Bird Treaty Act, and MOU between USFS and USFWS): Contractor shall refrain from any vegetation clearing, site preparation, and other activities related to vegetation removal, i.e., burning, decked-log sawing, tree hauling, skidding, during the breeding season of migratory birds from May 1 through July 15.

9 HAZARDOUS CONDITIONS SAFETY PLAN

The following conditions have been identified as inherently hazardous to a degree that failure to take the proper precautions could lead to serious injury or loss of life. This listing shall not be construed as all inclusive. The Contractor shall provide a written job-specific hazard analysis and safety plan that addresses and conforms to the requirements of 29 CFR 1910 and 1926 and the clause entitled Accident Prevention (FAR 52.236-13) included herein. Appropriate actions shall be taken by the Contractor to implement this plan during performance and to take any and all other necessary steps to mitigate the dangers from hazards.

Tree felling Temporary excavation / deep trenching / slope stability Fall hazard from work heights exceeding six feet Heavy equipment operation Fire hazards Hazardous materials handling (including concrete clean-up disposal) Hydraulic and/or pneumatic and/or other high pressure hazards Mechanical hazards such as pulleys, springs etc.

10 PROSECUTION OF WORK – WORK HOUR LIMITS – WORK ITEM LIMITS

Construction activity may be performed Monday through Friday and shall be limited to the hours between 8:00 a.m. and 6:00 p.m., unless other hours are approved in writing by the COR. No work will be allowed on Federal Holidays unless approved by CO in writing. No vegetation clearing, site preparation, or other vegetation removal activities shall take place during the breeding season of migratory birds from May 1 – July 15. (MOU between U.S. Fish and Wildlife Service and U.S. Forest Service to Promote Conservation of Migratory Birds (2008).

11 PROTECTION OF CULTURAL RESOURCES

Location of known historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C.

470) and the Archaeological Resources Protection Act of 1969 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by the Forest Service. Forest Service may unilaterally modify, or cancel, this contract to protect an area, object of antiquity, artifact or similar object which is, or may be, entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.

The Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destructions, obliteration, removal or damage during Contractor’s Operations. In accordance with 36 CFR 296.14(c), the Contractor shall bear costs of restoration, provided that such payment shall not relieve the Contractor from civil or criminal remedies otherwise provided by law.

Wheeled or track-laying equipment shall not be operated within such areas, except on roads. Unless agreed otherwise, trees will not be felled into such areas.

12 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor.

(a) Weather Table