This specification document from the Maine Army National Guard outlines requirements for Bid #14-014 to procure two ultra-high pressure oil burners for installation at existing boiler systems. The project involves replacing fuel oil burners at two facility locations: Houlton Armory (86 Pleasant Street, Houlton, Maine 04730) and Sanford Armory (88 William Oscar Emery Drive, Sanford, Maine 04073). The burners must be specifically designed for boilers with capacity ranges of 1,000,000 to 1,500,000 BTU/hr and are intended to reduce oil consumption and greenhouse gas emissions. Installation and full service training for at least two technicians must be completed within 30 days of award. Bidders must submit quotes using the specified spreadsheet format and provide contact information including name, telephone number, and email address. All inquiries should be directed to David Pelletier at 207-430-5697 or 207-557-2011, or Allen Ballard at 207-430-5679.
The specification requires ultra-high pressure oil burners meeting strict performance standards including 900-1800 PSI fuel injection, 30-40 percent air input reduction, and ETL or UL safety ratings compliant with standards UL 296, 296A, and 343. Anticipated benefits include 15-18 percent annual fuel use reduction and significant emissions reductions including 20 percent SO2, 25 percent NO and NOx, 15 percent CO2, 50 percent CO, and 60 percent SO reductions. The burner system must include an ultra-high pressure pump, one micron fuel filter, pressure accumulator, high-pressure fuel hose, and internal block fuel heater. Electrical requirements specify 110-volt operation integrated with existing boiler power. Warranty coverage includes two years for parts and one year for labor, excluding damage deemed user error. No substitutions are permitted, and bidders must coordinate delivery and installation by calling the designated contacts before items arrive at either facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Terms, Conditions, and Instructions to Bidders rev 1-25-12.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid #14-014
Ultra High Pressure Oil Burner Specification Provide (2) ultra-high efficient oil burners specifically designed to reduce oil consumption and green house gases on existing boilers that range from 1,000,000 – 1,500,000 BTU/hr.
OVERVIEW
This specification outlines the performance requirements to provide an ultra-high pressure replacement fuel oil burner to existing Maine Army National Guard boilers. The replacement burner system must conform to and/or exceed the following design and performance standards and specifications. Performance at levels less than those specified below are not acceptable.
| ITEM |
| DESCRIPTION |
| MINIMUM STANDARD |
| FUEL INJECTION PSI |
| Range of pounds per square inch (PSI) that fuel oil is injected |
| 900-1800 PSI |
| AIR INJECTION |
| Amount or air input reduction over standard oil burner |
| 30-40% reduction |
| CONSTRUCTION |
| System configuration components |
| Ultra-high pressure pump |
1 micron high pressure fuel filter
Pressure accumulator
High pressure fuel hose
Burner modified to accept ultra-high pressure fuel injection
Block fuel heater (internal)
| SAFETY RATINGS |
| Level of safety ratings required |
| ETL or UL fuel oil burner safety ratings required include UL 296, 296A, and 343 safety standards. |
| FUEL USE REDUCTION TARGET |
| Anticipated fuel use reduction amount |
| 15-18% per year |
| ELECTRICAL |
| System electrical requirements |
| 110volt |
Wire in line with existing boiler power source
| EMISSIONS |
| Target impact on emissions |
| 20% reduction in SO2 |
25% reduction in NO
25% reduction in NOx
15% reduction in CO2
50% reduction in CO
60% reduction in SO
| WARRANTY |
| Warranty coverage and limitations |
| Full two year warranty for parts and 1 year for labor unless inoperability is deemed user error |
| INSTALLATION AND TRAINING – Completed Within 30 Days of Award |
| Included |
| Full installation and service training for at least two technicians |
| LOCATION |
| Facility location |
| To be installed in two Armories - Houlton Armory and Sanford Armory (see address below) |
TOTAL: _______________________
1. There are no Substitution's on any of these items.
2. Need to Submit Quote using this spreadsheet - ONLY
3. Deliver to Houlton Armory - 86 Pleasant Street, Houlton, Maine 04730 and
Sanford Armory - 88 William Oscar Emery Drive, Sanford, Maine 04073.
(Call David Pelletier at 207-430-5697 and/or Allen Ballard at 207-430-5679 before items are to be Delivered and Installed.)
4. Any questions please call David Pelletier at 207- 430-5697 or (c)207-557-2011.
5. I need a Name, telephone number and email address of person submitting the Quote.