Pre-Demolition Hazardous Materials Survey Report Summary
This is a pre-demolition hazardous materials survey report prepared by North Tower Environmental for the Chabot-Las Positas Community College District regarding Building 2000 at Chabot College located at 25555 Hesperian Boulevard in Hayward, California. The survey was conducted on May 15, 2026 and July 14, 2026 by Cal/OSHA certified asbestos consultants Pedro Rico and Carolyn Henry to identify hazardous materials present in the building prior to its planned demolition. The scope of work included inspection and sampling for asbestos-containing materials (ACM), lead-based paint (LBP) and lead-containing paint (LCP), polychlorinated biphenyls (PCB) in exterior caulks and sealants, and identification of universal wastes including mercury-containing fluorescent light tubes and PCB-containing ballasts. A total of 109 asbestos bulk samples representing 37 distinct homogeneous areas were collected and analyzed by Polarized Light Microscopy, along with 37 lead samples and 10 PCB samples.
The survey identified asbestos-containing materials (greater than 1% chrysotile) in joint compound and taping mud throughout interior wall and ceiling systems (36,500 square feet and 5,650 square feet respectively), vinyl floor tile and associated black mastic systems totaling approximately 11,700 square feet, and exterior building sealants in approximately 1,250 linear feet. Lead-based paint was identified in 7 of 35 paint samples tested, while lead-containing paint was found in 22 additional samples. No PCB-containing materials were detected in any of the 10 caulk and sealant samples analyzed. Additional hazardous materials identified include PCB and DEHP-containing light ballasts, mercury-containing fluorescent lamps, and tritium exit signs throughout the building that require proper management and disposal in accordance with applicable state and federal regulations prior to demolition.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01-123073_SPC_A.pdf | ||
| B26-27-08_AD COPY Rev1.pdf | ||
| 01-123073_DWG_A.pdf | ||
| RFQ B26 27-08 B2000 Demo and New STEM Courtyard.pdf | ||
| RFI Template.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1485 Bayshore Boulevard, #185, San Francisco, CA 94124 Phone (415) 466-6561
PRE-DEMOLITION
HAZARDOUS MATERIALS SURVEY REPORT
CHABOT COLLEGE
BUILDING 2000
25555 HESPERIAN BOULEVARD
HAYWARD, CALIFORNIA
PREPARED FOR:
Chabot-Las Positas Community College District
7600 Dublin Boulevard, 3rd Floor
Dubin, California
PREPARED BY:
North Tower Environmental
1485 Bayshore Boulevard, #185
San Francisco, California
September 10, 2026
PRE-DEMOLITION
HAZARDOUS MATERIALS SURVEY REPORT
CHABOT COLLEGE
BUILDING 2000
25555 HESPERIAN BOULEVARD,
HAYWARD, CALIFORNIA
TABLE of CONTENTS
A. Executive Summary
………………………………………. Page Number 1
B. Introduction
………………………………………. Page Number 2
C. Asbestos Survey and Findings
………………………………………… Page Number 3
D. Lead Paint Survey and Findings
……………………………………… Page Number 5
E. PCB Survey and Findings
……………………………………… Page Number 7
F. Other Hazardous Materials
……………………………………… Page Number 8
G. Limitations
……………………………………… Page Number 9
H. Conclusions and
Recommendations
………………………………………. Page Number 10
ATTACHMENTS
Table 1 - Summary of Asbestos Sample Results
Table 2 - Summary of Lead Sample Results
Table 3 – Summary of PCB Sampling Results
APPENDICES
Appendix A Consultant Certificates
Appendix B Asbestos Laboratory Reports
Appendix C Lead Laboratory Reports
Appendix D PCB Laboratory Reports
Appendix E Sample Location Maps
Hazardous Materials Pre-Demolition Survey Page 1 of 10
Chabot-Las Positas Community College District September 10, 2026
Chabot College – Building 2000
A. EXECUTIVE SUMMARY
This summary is not to be read as a stand-alone document. The report shall be read in its entirety.
The reader must review the detailed information provided in the accompanying text. Any interpretation, use and conclusion resulting from the data contained in this report is the responsibility of the reader.
North Tower Environmental, Inc. (NTE) was retained by the Chabot-Las Positas Community
College District (CLPCCD) to perform a pre-demolition hazardous materials survey for Building
2000 located at the Chabot College campus at 25555 Hesperian Boulevard, Hayward, California.
The sampling scope of work included the following:
• Inspect and sample for the presence of visible and accessible Asbestos Containing Material
(ACM).
• Inspect and sample representative painted/coated surfaces for Lead-Based Paint (LBP) and
Lead-Containing Paint (LCP).
• Inspect and sample exterior caulks/sealants for the presence of Polychlorinated Biphenyls
(PCB).
• Identify visible universal wastes such as PCB ballasts, mercury-containing fluorescent light tubes and other related hazardous lighting fixtures.
Note that the building remained in operation at the time of the survey. NTE did not conduct destructive sampling (i.e. opening wall cavities, removal of sub-floor assemblies, removal of mirrors, etc.).
Suspect material not sampled or identified in this report shall be considered asbestos-containing material and/or lead-based until sampling is performed to determine otherwise.
Summary of Results: Asbestos
A total of 109 bulk samples of suspect asbestos-containing materials, representing 37 distinct homogeneous areas, were collected and submitted for analysis by Polarized Light Microscopy
(PLM). Asbestos Containing Material (ACM) was identified at concentrations greater than 1% in joint compound/taping mud associated with gypsum board wall systems and gypsum board ceiling systems; green and brown 9” x 9” vinyl floor tile and associated black mastic systems, 12” x 12” non-ACM vinyl floor tile with ACM residual black mastic, and exterior column, wall, and column arch sealant. Trace concentrations of asbestos, less than 1% Chrysotile, were also identified in exterior stucco and exterior penetration mastic. Laboratory results for the remaining samples reported no detectable concentrations of asbestos. Information regarding material type, general location, quantity, and asbestos content can be found in the Summary of Asbestos Results table in
Section C of this report. Table 1 includes a detailed list of all materials sampled along with the lab results. Suspect asbestos-containing materials not identified in this report that are present or discovered must be assumed to contain asbestos until sampling and analysis determines otherwise.
Hazardous Materials Pre-Demolition Survey Page 2 of 10
Chabot College – Building 2000
Summary of Results: Lead
A total of 37 samples of suspected lead-based paint and/or lead-containing materials were collected, consisting of 35 paint chip samples and 2 ceramic floor tile samples. Lead-Based Paint
(LBP) was identified in 7 of the 35 paint samples. Lead-Containing Paint (LCP) was identified in
22 additional paint samples. The remaining 6 paint samples and both ceramic tile samples reported no detectable concentrations of lead above the laboratory method reporting limit.. Information showing the lead-based and lead-containing material locations can be found in the Summary of
Lead Sampling Results table in Section D of this report. Table 2 includes a detailed list of all materials sampled along with the lab results. Based on the age of the building, all painted, coated, or varnished materials not sampled as part of this report must be assumed to contain lead until sampling and analysis determines otherwise.
Summary of Results: PCB
Ten (10) bulk caulk and sealant samples were collected and submitted for PCB Aroclor analysis.
Laboratory results reported no detectable concentrations of PCBs in any of the samples analyzed;
the sampled caulks and sealants can be treated as non-PCB-containing material. Table 3 contains a summary of the PCB analytical results.
Summary of Results: Other Hazardous Material
Other potential hazardous material and/or universal wastes were identified and are present in the building, including fluorescent lamps (containing mercury vapor), PCB and DEHP containing lighting ballasts.
B. INTRODUCTION
North Tower Environmental, Inc. (NTE) was retained by the Chabot-Las Positas Community
College District (CLPCCD) to perform a pre-demolition hazardous materials survey for Building
2000 located at the Chabot College campus at 25555 Hesperian Boulevard, Hayward, California.
The sampling scope of work included the following:
• Inspect and sample for the presence of visible and accessible Asbestos Containing Material
(ACM).
• Inspect and sample representative painted/coated surfaces for Lead-Based Paint (LBP) and
Lead-Containing Paint (LCP).
• Inspect and sample exterior caulks/sealants for the presence of Polychlorinated Biphenyls
(PCB).
• Identify visible universal wastes such as PCB ballasts, mercury-containing fluorescent light tubes and other related hazardous lighting fixtures.
The scope of the survey was limited to areas and materials expected to be impacted by the planned building demolition activities throughout the interior and exterior of the building.
Hazardous Materials Pre-Demolition Survey Page 3 of 10
Chabot College – Building 2000
Note that the building remained in operation at the time of the survey. NTE did not conduct destructive sampling (i.e. opening wall cavities, removal of sub-floor assemblies, removal of mirrors, etc.).
Suspect material not sampled or identified in this report shall be considered asbestos-containing material and/or lead-based until sampling is performed to determine otherwise.
The survey report and bulk sampling for asbestos-containing materials and lead-based paint were completed by Pedro Rico and Carolyn Henry, Cal/OSHA Certified Asbestos Consultants and
CDPH accredited professionals. Sampling was conducted on May 15, 2026 and July 14, 2026.
Consultant certifications are contained in Appendix A.
C. ASBESTOS SURVEY AND FINDINGS
Asbestos Bulk Sampling
Bulk samples of suspect asbestos-containing materials were collected from the interior and exterior of Building 2000 in areas anticipated to be impacted by the planned demolition activities. The materials were visually inspected and separated into homogenous areas of material. A homogeneous area is defined under AHERA (40 CFR 763.83) and Cal/OSHA (8 CCR, 1529) as an area of surfacing material, thermal system insulation, or miscellaneous material that is uniform in color and texture. Samples were collected with basic hand tools such as chisels, razor knives and hammers.
A total of 109 bulk samples representing 37 distinct homogeneous areas were collected and submitted under chain-of-custody to Eurofins Built Environment Testing West, LLC (NVLAP Lab
Code 200757-0). Samples were analyzed by Polarized Light Microscopy (PLM) in accordance with EPA 40 CFR Appendix E to Subpart E of Part 763 and EPA 600/R-93-116. When "None
Detected" (ND) appears in the laboratory results, it should be interpreted as meaning asbestos was not observed in the sample material A summary of the laboratory results is contained in Table 1.
The laboratory reports are contained in Appendix B.
Asbestos Analytical Results
The NESHAP and AHERA regulations define ACM as material containing more than 1% asbestos; materials containing less than 1% asbestos are not ACM under NESHAP or AHERA.
However, Cal/OSHA worker protection regulations define asbestos containing construction material (ACCM) to be any material containing greater than 0.1% asbestos by weight. The
California Division of Occupational Safety and Health (Cal/OSHA) defines four classes of asbestos-related construction work (Class I, Class II, Class III, and Class IV) which are regulated under the Construction Safety Orders for Asbestos. These work classes and their respective requirements pertain to materials containing more than 1% asbestos.
Of the 109 samples analyzed, 32 samples across 9 homogeneous areas reported layer asbestos content greater than 1%. An additional 3 samples (2 homogeneous areas) reported trace asbestos content of less than 1%. The table below summarizes the sample locations, descriptions, analytical results, and estimated quantities based on field quantity take-off.
Hazardous Materials Pre-Demolition Survey Page 4 of 10
Chabot College – Building 2000
Suspect asbestos-containing materials not identified in this report that are present or discovered at the site must be assumed to contain asbestos until sampling and analysis determines otherwise.
Summary of Asbestos Sampling Results
SUMMARY OF ASBESTOS SAMPLING RESULTS
Material Location % Asbestos
(Chrysotile)
Estimated
Quantity
Gypsum Board and
Taping Mud Wall
Systems
Throughout Building Interior, Except Bathrooms (Beneath Non-ACM Wall
Coverings and Acoustical Tiles)
2% in Taping Mud 36,500 sf
Gypsum Board and
Taping Mud Ceiling
Systems
Hallways, Lobbies, and Rooms
2002, 2003, 2004, 2005, 2006, and 2061(Beneath Non-ACM
Acoustical Tiles)
2% in Taping Mud 5,650 sf
Blue 12” x 12” Vinyl
Floor Tile with Residual
Black Mastic
Hallways and Lobbies (Trace Amounts of Black Mastic
Detected)
2% in Black
Mastic 5,650 sf
Brown 9” x 9” Vinyl
Floor Tile and Mastic Rooms 2003 and 2005
2% in Tile
3% in Mastic 500 sf
Green 9” x 9” Vinyl
Floor Tile and Mastic
Throughout Office Floors, Rooms 2061, 2008, and 2002 2% in Tile
3% in Mastic
5,150 sf
Rooms 2006 & 2004 (Beneath 12” x 12” Non-ACM
Vinyl Floor Tile) 400 sf
Exterior Building Wall, Column, and Arch Sealant
Throughout Exterior Seams at
Building Walls, Columns, and
Column Arch Systems
7% in Sealant 1,250 lf
Stucco Exterior Building Fascia and
Overhang
<1% (trace) in
Stucco 2,750 sf
Roof Penetration Mastic Roof Pipe Penetrations
Throughout
<1% (trace) in
Mastic 10 sf
Thermal System
Insulation (TSI)
Throughout Inaccessible Wall and Ceiling Cavities Presumed ACM 500 lf
Fire Doors Throughout Assumed ACM N/A
Sealants and Mastics Throughout (beneath mirrors, panels, casework, and trims Assumed ACM N/A
Waterproofing Membrane
Beneath Ceramic Tile
Flooring
Bathrooms Assumed
ACM
N/A
Hazardous Materials Pre-Demolition Survey Page 5 of 10
Chabot College – Building 2000
NESHAPS Category: Based on the sample analysis and findings, below is a list of the materials that have been determined to contain asbestos along with the corresponding NESHAPS category:
Category I and II materials are not RACM unless they have become friable or will be cut, sanded, ground, or abraded or otherwise made friable during the project.
D. LEAD PAINT SURVEY AND FINDINGS
Background
The U.S. Department of Housing and Urban Development (HUD) is the federal agency responsible for assessing public housing for Lead-Based Paint (LBP) hazards. HUD and the U.S. EPA define
“lead-based paint” as paint having a concentration of lead equal to or greater than 1.0 milligram per square centimeter (1.0 mg/cm²) by X-ray fluorescence (XRF) analyzer, or equal to or greater than 0.5% by weight (5,000 parts per million [ppm]) by laboratory analysis.
For the purposes of this report, lead sample results indicating equal to or greater than 0.5% by weight (5,000 ppm) are considered Lead-Based Paint (LBP). Samples reported as having a lower, but detectable, lead content are considered Lead-Containing Paint (LCP).
OSHA-Specific Requirements
The Cal/OSHA Construction Industry Safety Orders for Lead (8 CCR 1532.1) apply to all construction work where an employee may be occupationally exposed to lead, and the standard regulates construction work practices involving any detectable concentrations of lead. Therefore, all construction-related work performed on surface coatings or building components containing detectable concentrations of lead must be done in compliance with the requirements of this standard.
The presence of lead, lead-contaminated dust and/or lead-containing paint requires that specialized work practices be used during construction or renovation work to ensure that individuals involved in the work are adequately protected against elevated exposure to lead. Cal/OSHA regulates lead exposures in construction in its Construction Safety Orders for Lead (8 CCR 532.1).
Asbestos Material NESHAPS Category
Floor Tile/Mastic Category I Non-Friable
Joint Compound / Taping Mud Category I Non-Friable
Column, Wall, and Column Arch Sealant Category I Non-Friable
Thermal System Insulation (Presumed) Regulated Asbestos Containing Material -
Friable
Hazardous Materials Pre-Demolition Survey Page 6 of 10
Chabot College – Building 2000
California Department of Public Health (CDPH) Requirements
The California Department of Public Health (CDPH) also regulates lead-related construction (as well as the generation and control of lead hazards) in residential and public buildings. CDPH defines lead-based paint as equal to or greater than 0.5% by weight (5,000 ppm). CDPH enforces
Title 17 of the California Code of Regulations, Division 1, Chapter 8 governing the Accreditation, Certification, and Work Practices for Lead-Based Paint and Lead Hazards.
Lead Waste Disposal Requirements
The California Department of Toxic Substances Control (DTSC) regulates the disposal of lead-containing waste within California. The hazardous waste determination is dependent, in part, upon the physical state of the waste. If, for example, lead-containing paint is separated from its respective substrate building material during the renovation or dismantling of the building (e.g., chemically or physically removed), the paint debris should be evaluated independently from the substrate material to which paint is still adhered to determine its proper management and disposal.
Lead Bulk Paint Sampling
Samples were collected using hand tools to obtain all layers of paint down to the substrate, where feasible. Each sample was assigned a unique identification number, placed in a clean, labeled container, and submitted under chain-of-custody documentation to Eurofins Built Environment
Testing West, LLC for analysis by Flame Atomic Absorption Spectrometry.
Lead Testing Results and Findings
A total of 37 samples (35 paint chip samples and 2 ceramic tile bulk samples) were submitted for analysis. Lead-Based Paint (≥ 5,000 ppm) was identified in 7 samples. Lead-Containing Paint
(detectable, below 5,000 ppm) was identified in 22 additional samples across a range of interior and exterior painted surfaces. The remaining 6 paint samples and both ceramic tile samples (men's and women's restroom floor tile) reported no detectable lead above the laboratory reporting limit.
Any paints applied to the subject building that were not sampled should be assumed to contain lead unless bulk paint chip sampling and laboratory analysis determines otherwise. Appendix C contains the lead laboratory reports and chain of custody documentation. The table below provides a summary of the lead sampling results.
Lead Paint Sampling Summary
LEAD PAINT SAMPLING SUMMARY
Material Location
Lead-Based Paints White Paint: Exterior metal stairwell systems
Lead-Containing Paints
White, yellow, blue and various other colors: Concrete and plaster walls; exterior stairwells; and all other painted/coated surfaces.
Hazardous Materials Pre-Demolition Survey Page 7 of 10
Chabot College – Building 2000
E. PCB SURVEY AND FINDINGS
Background
Polychlorinated biphenyls (PCBs) are a group of synthetic organic chemicals that were widely used in industrial and commercial applications due to their chemical stability, non-flammability, and insulating properties. Common uses included electrical equipment, hydraulic systems, fluorescent light ballasts, adhesives, and building materials such as caulks and sealants. PCBs are regulated by the EPA under 40 CFR 761 (Toxic Substances Control Act). Exposure to PCBs is also regulated by Cal/OSHA 8 CCR Subchapter 7, Section 5155.
Sampling Procedures
Samples for PCB analysis were collected from suspect exterior caulks and sealants in accordance with industry standards, using a clean utility knife or similar tool to extract the suspect material from associated building components. Samples were placed in labeled sample collection bags and submitted to McCampbell Analytical, Inc. of Pittsburg, California, under chain-of-custody procedures for analysis by U.S. EPA Method SW846 8082A.
PCB Bulk Waste
TSCA regulations use specific definitions and terminology for different categories of regulated
PCBs, which must be understood to manage PCB wastes in compliance with the law. General
California and TSCA regulatory waste classifications based on PCB concentration are as follows:
• Non-RCRA Hazardous: ≥ 5 ppm in liquids and/or ≥ 50 ppm in non-liquids.
• TSCA-regulated PCB-Contaminated: > 50 ppm and < 500 ppm (liquids and non-liquids), or non-porous surface contamination > 10 µg/100 cm² and < 100 µg/100 cm².
• TSCA-regulated PCBs: > 500 ppm, or non-porous surface contamination > 100 µg/100 cm².
PCB Testing Results
Ten (10) samples – one bulk building material sample and nine exterior caulk samples – were collected and analyzed for PCBs. All 10 samples reported non-detect (ND) for total PCBs at the laboratory reporting limit. No PCB-containing materials were identified; the sampled caulks and sealants can be treated as non-PCB-containing material for demolition purposes, though disposal facility acceptance criteria should be confirmed prior to demolition. The PCB laboratory analytical report is contained in Appendix D.
Hazardous Materials Pre-Demolition Survey Page 8 of 10
Chabot College – Building 2000
F. OTHER HAZARDOUS MATERIALS
Universal Waste
California DTSC defines certain “Universal Wastes” and mandates how they must be managed.
Universal wastes are defined in 22 CCR, Division 4.5, Chapter 23 (22 CCR 66261.9, et seq.).
Common universal wastes include, but are not limited to, mercury-containing equipment (pressure or vacuum gauges, switches, and thermostats), various types of common batteries, lamps
(including fluorescent tubes, high intensity discharge lamps, sodium vapor lamps and any other lamps that exhibit a characteristic of a hazardous waste), and non-empty aerosol cans.
PCB- and/or DEHP-Containing Light Fixture Ballasts
During this survey, NTE noted the presence of fluorescent light fixtures throughout all buildings.
Although this survey did not include extensive inspection of ballasts for labeling regarding the presence or absence of PCBs, any ballast found to be without a label indicating “No PCBs” or
“PCB free” should be assumed to contain regulated quantities of PCBs. Any lighting fixture ballasts displaying a label indicating they contain “No PCBs” or are “PCB Free” and are not dry ballasts should be assumed to contain Di(2-ethylhexyl)phthalate or DEHP and be recycled according to applicable state and federal regulations.
Mercury-Containing Switches/Thermostats
Mercury-containing thermostats or switches were not observed during the survey. Any such devices should be managed and disposed of in accordance with applicable state and federal regulation if they are in fact mercury-containing.
Fluorescent Light Tubes and Universal Waste Lamps
During this survey, fluorescent light tubes and universal waste lamps were observed throughout.
Fluorescent light tubes typically contain mercury and other metals and their disposal is regulated under the California EPA’s Universal Waste Rules. Fluorescent light tubes to be removed during the renovation should be handled and packaged so as to prevent breakage and, if discarded, must be sent to an appropriately permitted recycler. Other lamps exhibiting a characteristic of hazardous waste should be discarded appropriately.
OTHER HAZARDOUS MATERIALS
Material Location Estimated Quantity
PCB, Non-PCB and DEHP containing light ballasts
Throughout Building Interior and Exterior Field Verify
Universal waste lamps and mercury-added lamps
Throughout Building Interior and Exterior Field Verify
Mercury-Containing and (Other
Universal Waste) Thermostats
Throughout Building Interior and Exterior Field Verify
Tritium Exit Signs Throughout Building Interior and Exterior Field Verify
Hazardous Materials Pre-Demolition Survey Page 9 of 10
Chabot College – Building 2000
G. LIMITATIONS
The reported results in this report are intended for discussion and informational purposes only.
These results should not be solely used in the preparation or design of specific asbestos abatement response options without the supplement of additional field-specific and material-specific information.
The judgments, conclusions, and recommendations described in this report pertain to the conditions judged to be present or applicable at the time the work was performed. Future conditions may differ from those described herein and this report is not intended for use in future evaluations of the facility unless an update is conducted by a Certified Asbestos Consultant and CDPH professional familiar with currently used asbestos and lead survey practices and this subject facility.
North Tower Environmental performed its services using that degree of care and skill ordinarily exercised under similar conditions by reputable members of our profession practicing in the same or similar locality. No other warranty, expressed or implied, is made or intended by our performance of consulting services or by furnishing our written report. This report has been prepared on behalf of and exclusively for the use of CLPCCD. This report shall not, in whole or in part, be disseminated or conveyed to any other party, or be used or relied upon by any other party, in whole or in part, without the prior written consent of North Tower Environmental.
Use of this report is provided to CLPCCD solely for their exclusive use and shall be subject to the terms and conditions in the applicable agreement between CLPCCD and North Tower
Environmental. Any third-party use of this report shall also be subject to the terms and conditions governing the work in the agreement between CLPCCD and North Tower Environmental. Any unauthorized release or misuse of this report shall be without risk to North Tower Environmental.
Certain information contained in this report may have been rightfully provided to North Tower by third parties or other outside sources. North Tower Environmental does not make any warranties or representations, whether expressed or implied, regarding the accuracy of such information, and shall not be held accountable or responsible in the event that any such inaccuracies are present.
Hazardous Materials Pre-Demolition Survey Page 10 of 10
Chabot College – Building 2000
H. CONCLUSIONS AND RECOMMENDATIONS
• The scope of the survey was limited to areas and materials expected to be impacted by the planned demolition activities throughout the interior and exterior of Building 2000.
• A total of 109 asbestos bulk samples were collected. ACM (>1%) was identified in joint compound/taping mud throughout interior wall and ceiling assemblies, in vinyl floor tile and associated mastics, and in exterior column, wall, and column arch sealants. Trace asbestos (<1%) was also identified in exterior stucco and roof pipe penetration mastics.
• Construction and demolition work involving the disturbance or removal of ACM (materials containing greater than 0.1% asbestos) must be performed by an appropriately licensed, certified, and registered contractor, in accordance with a project-specific abatement work plan compliant with applicable federal, state, and local regulations.
• A total of 37 lead samples were collected. Lead-Based Paint (≥5,000 ppm) was identified in 7 samples and Lead-Containing Paint in 22 additional samples. The remaining 8 samples
(6 paint chip, 2 ceramic tiles) reported no detectable lead above the laboratory reporting limit; however, based on the age of the building, lead is presumed present in all unsampled painted/coated surfaces.
• Lead-related demolition work must be performed by workers trained in accordance with the Cal/OSHA Construction Safety Orders – Lead (8 CCR 1532.1) and applicable CDPH regulations (Title 17, Division 1, Chapter 8). Waste generated by lead-related work should be segregated into discrete waste streams and characterized for its hazardous waste characteristics prior to disposal.
• Ten (10) caulk/sealant samples were analyzed for PCBs; all reported non-detect. The sampled caulks and sealants can be treated as non-PCB-containing material, though disposal facility acceptance criteria should be confirmed prior to demolition.
• Suspect asbestos and lead-containing materials that are present or discovered at the site, not identified in this report, or not sampled as part of this survey, should be assumed to contain asbestos and/or lead until an inspection and sampling is conducted by an accredited inspector.
TABLE 1
Sample Number Building Material Location Asbestos Content
1-1 Stone Pattern Wallpaper /
Board / Taping Mud
Hallway Southwest Near
Exit Door
2% Chrysotile in Taping
Mud; <1% Composite
1-2 Stone Pattern Wallpaper /
Board / Taping Mud
Hallway Southeast Near
Exit Door
2% Chrysotile in Taping
Mud; <1% Composite
1-3 Stone Pattern Wallpaper /
Board / Taping Mud Lobby East Near Exit Door
2% Chrysotile in Taping
Mud; <1% Composite
1-4 Stone Pattern Wallpaper /
Board / Taping Mud
Near Atrium Window -
Northeast
2% Chrysotile in Taping
Mud; <1% Composite
1-5 Stone Pattern Wallpaper /
Board / Taping Mud
Near Atrium Window -
Northwest
2% Chrysotile in Taping
Mud; <1% Composite
1-6 Stone Pattern Wallpaper /
Board / Taping Mud West Lobby Corner
2% Chrysotile in Taping
Mud; <1% Composite
1-7 Stone Pattern Wallpaper /
Board / Taping Mud
Lobby Hallway Near Room
2003 Door Entrance
2% Chrysotile in Taping
Mud; <1% Composite
2-1
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2057 Southeast
Corner
2% Chrysotile in Taping
Mud; <1% Composite
2-2
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2033 Southwest
Corner
2% Chrysotile in Taping
Mud; <1% Composite
2-3
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2007 Northwest
Corner
2% Chrysotile in Taping
Mud; <1% Composite
2-4
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2044 Northwest
Corner
2% Chrysotile in Taping
Mud; <1% Composite
2-5
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2046 Northeast
Corner
2% Chrysotile in Taping
Mud; <1% Composite
2-6
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2058 Northeast
Corner
2% Chrysotile in Taping
Mud; <1% Composite
TABLE 1
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
2-7
Burlap Pattern Wallpaper /
Gypsum Board / Taping
Mud
Room 2006 Southeast
Corner
2% Chrysotile in Taping
Mud; <1% Composite
3-1 6" Green Vinyl Basecove /
Mastic
Lobby Hallway Exterior
Room 2005 No Asbestos Detected
3-2 6" Green Vinyl Basecove /
Mastic
Southwest Hallway -
Exterior Of Men's Restroom No Asbestos Detected
3-3 6" Green Vinyl Basecove /
Mastic
North Hallway Wall -
Exterior Wall Between
Room 2040 & 2036
2% Chrysotile In Off-White
Compound
4-1 12" x 12" Blue Vinyl Floor
Tile and Mastic
Northeast Atrium Corner
Near Window No Asbestos Detected
4-2 12" x 12" Blue Vinyl Floor
Tile and Mastic
South Hallway Wall
Between Room 2035 &
Room 2031
2% Chrysotile In Black
Mastic (Residual Mastic)
4-3 12" x 12" Blue Vinyl Floor
Tile and Mastic
Lobby Hallway Exterior Of
Room 2061
2% Chrysotile In Black
Mastic (Residual Mastic)
5-1 4" Brown Vinyl Basecove and Mastic
Room 2061 Near Door
Frame No Asbestos Detected
5-2 4" Brown Vinyl Basecove and Mastic
Room 2013 Northwest
Corner No Asbestos Detected
5-3 4" Brown Vinyl Basecove and Mastic Room 2008 Near Exit Door No Asbestos Detected
6-1 9" x 9" Green Vinyl Floor
Tile and Mastic Northeast In Room 2005
2% Chrysotile In Green
Floor Tile; 3% Chrysotile In
Black Mastic
6-2 9" x 9" Green Vinyl Floor
Tile and Mastic Southeast In Room 2002
3% Chrysotile In Black
Mastic; 2% Chrysotile In
Green Floor Tile
6-3 9" x 9" Green Vinyl Floor Tile and Mastic
Southeast Corner Room
3% Chrysotile In Black
Mastic; 2% Chrysotile In
Green Floor Tile
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
7-1 12" x 12" Fissured Glue-On
Acoustical Tile Room 2026 No Asbestos Detected
7-2 12" x 12" Fissured Glue-On
Acoustical Tile Ceiling Lobby Hallway East No Asbestos Detected
7-3 12" x 12" Fissured Glue-On
Acoustical Tile Ceiling Northwest Hallway No Asbestos Detected
7-4 12" x 12" Fissured Glue-On
Acoustical Tile Ceiling Southwest Hallway No Asbestos Detected
7-5 12" x 12" Fissured Glue-On
Acoustical Tile Room 2027 No Asbestos Detected
8-1 Gypsum Board and Taping
Mud Ceiling East Lobby Hallway No Asbestos Detected
8-2 Gypsum Board and Taping
Mud Ceiling Northwest Hallway
2% Chrysotile in Taping
Mud; <1% Composite
8-3 Gypsum Board and Taping
Mud Ceiling Southwest Hallway
2% Chrysotile in Taping
Mud; <1% Composite
8-4 Gypsum Board and Taping
Mud
Ceiling Northwest Corner
Room 2008
2% Chrysotile in Taping
Mud; <1% Composite
8-5 Gypsum Board and Taping
Mud
Ceiling Northeast Corner
Room 2005
2% Chrysotile in Taping
Mud; <1% Composite
9-1 9" x 9" Brown Vinyl Floor
Tile and Mastic Room 2003 Southwest
2% Chrysotile In Brown
Floor Tile; 3% Chrysotile In
Black Mastic
9-2 9" x 9" Brown Vinyl Floor
Tile and Mastic Room 2003 North
2% Chrysotile In Brown
Floor Tile; 3% Chrysotile In
Black Mastic
9-3 9" x 9" Brown Vinyl Floor
Tile and Mastic Room 2003 East
2% Chrysotile In Brown
Floor Tile; 3% Chrysotile In
Black Mastic
10-1 Window Glazing (Interior
Window) Southwest Atrium Window No Asbestos Detected
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
10-2 Window Glazing (Interior
Window) Northwest Atrium Window No Asbestos Detected
10-3 Window Glazing (Interior
Window) Northeast Atrium Window No Asbestos Detected
11-1 Sink Undercoat Room 2008 No Asbestos Detected
11-2 Sink Undercoat Room 2008 No Asbestos Detected
12-1 12" x 12" Brown Vinyl
Floor Tile and Mastic Room 2006 Northwest
2% Chrysotile In Green
Floor Tile; 2% Chrysotile In
Black Mastic
12-2 12" x 12" Brown Vinyl
Floor Tile and Mastic Room 2004 Northeast
2% Chrysotile In Green
Floor Tile; 2% Chrysotile In
Black Mastic
13-1 2" x 2" Pink Ceramic Wall
Tile / Grout Men'S Restroom No Asbestos Detected
13-2 2" x 2" Pink Ceramic Wall
Tile / Grout Women'S Restroom No Asbestos Detected
14-1 1" x 1" White and Pink
Ceramic Floor Tile Men'S Restroom No Asbestos Detected
14-2 1" x 1" White and Pink
Ceramic Floor Tile Women'S Restroom No Asbestos Detected
15-1 2' x 4' Lay-In Pinhole
Ceiling Tile Men'S Restroom No Asbestos Detected
15-2 2' x 4' Lay-In Pinhole
Ceiling Tile Women'S Restroom No Asbestos Detected
16-1 Gypsum Board Behind
Acoustic Tile Ceiling Room 2026 No Asbestos Detected
16-2 Gypsum Board Behind
Acoustic Tile Ceiling Room 2007 No Asbestos Detected
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
16-3 Gypsum Board Behind
Acoustic Tile Ceiling Room 2051 No Asbestos Detected
17-1 HVAC Vibration Cloth Mechanical Room No Asbestos Detected
17-2 HVAC Vibration Cloth Mechanical Room No Asbestos Detected
17-3 HVAC Vibration Cloth Mechanical Room No Asbestos Detected
18-1 Fiberglass Insulation Lobby East Entrance No Asbestos Detected
18-2 Fiberglass Insulation Room 2061 No Asbestos Detected
18-3 Fiberglass Insulation Mechanical Room No Asbestos Detected
19-1 Hard-Pack Insulation Women'S Restroom No Asbestos Detected
19-2 Hard-Pack Insulation Room 2061 No Asbestos Detected
19-3 Hard-Pack Insulation Men'S Restroom No Asbestos Detected
20-1 Concrete Mechanical Room No Asbestos Detected
20-2 Concrete Mechanical Room No Asbestos Detected
20-3 Concrete Mechanical Room No Asbestos Detected
21-1 Red Concrete Southwest Atrium No Asbestos Detected
21-2 Red Concrete North Atrium No Asbestos Detected
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
21-3 Red Concrete West Exterior On Column No Asbestos Detected
21-4 Red Concrete West Exterior On Floor No Asbestos Detected
22-1 Concrete with Pebbles Central North Atrium No Asbestos Detected
22-2 Concrete with Pebbles Northeast Atrium No Asbestos Detected
23-1 Concrete Floor Slab West Atrium No Asbestos Detected
23-2 Concrete Floor Slab North Atrium - East No Asbestos Detected
24-1 Column Sealant West Exterior Building 7% Chrysotile In Gray
Sealant
24-2 Column Sealant South Exterior Building 7% Chrysotile In Gray
Sealant
24-3 Column Sealant Northeast Exterior Building 7% Chrysotile In Gray
Sealant
25-1 Door Frame Sealant Metal-To-Metal Seam -
West Lobby Entrance No Asbestos Detected
25-2 Door Frame Sealant Metal-To-Metal Seam -
Southwest Hallway Exit No Asbestos Detected
25-3 Door Frame Sealant Metal-To-Metal Seam - East
Lobby Entrance No Asbestos Detected
26-1 Pebble Concrete Wall
Moisture Barrier West Exterior Wall No Asbestos Detected
26-2 Pebble Concrete Wall
Moisture Barrier South Exterior Wall No Asbestos Detected
26-3 Pebble Concrete Wall
Moisture Barrier East Exterior Wall No Asbestos Detected
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
27-1 Stucco South Overhang Exterior
<1% Chrysotile In White
Stucco; <1% Chrysotile In
Gray Stucco
27-2 Stucco North Overhang Exterior
<1% Chrysotile In White
Stucco; <1% Chrysotile In
Gray Stucco
29-1 Roof Field North Of Building 3000 No Asbestos Detected
29-2 Roof Field North Of Building 3000 No Asbestos Detected
29-3 Roof Field North Of Building 3000 No Asbestos Detected
30-1 Penetration Mastic Central East Of Building
No Asbestos Detected
30-2 Penetration Mastic Northwest Of Building 3000 No Asbestos Detected
30-3 Penetration Mastic Southwest Of Building 3000 <1% Chrysotile In Black
Mastic (Trace)
31-1 Stucco Men'S Restroom No Asbestos Detected
31-2 Stucco Women'S Restroom No Asbestos Detected
32-1 HVAC Sealant Women'S Restroom No Asbestos Detected
32-2 HVAC Sealant Men'S Restroom No Asbestos Detected
33-1 Carpet / Mastic / 12" x 12"
Blue Vinyl Floor Tile East Corner Lobby Entrance No Asbestos Detected
33-2 Carpet / Mastic / 12" x 12"
Blue Vinyl Floor Tile
West Corner Lobby
Entrance No Asbestos Detected
Asbestos Sampling Results - Polarized Light Microscopy (PLM) Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot-Las Positas Community College District (CLPCCD)
Chabot College, Building 2000 - Pre-Demolition Hazardous Materials Survey
34-1
Expansion Sealant (Metal
Door Frame to Pebble
Stucco)
West Lobby Door Frame No Asbestos Detected
34-2
Expansion Sealant (Metal
Door Frame to Pebble
Stucco)
West Lobby Door Frame No Asbestos Detected
34-3
Expansion Sealant (Metal
Door Frame to Pebble
Stucco)
East Lobby Door Frame No Asbestos Detected
35-1 Vent Sealant Mechanical Room - West
Exterior No Asbestos Detected
35-2 Vent Sealant Mechanical Room - West
Exterior No Asbestos Detected
36-1 Asphalt Southeast Exterior Corner -
Hallway Exit Doorway No Asbestos Detected
36-2 Asphalt Northeast Exterior Corner -
Hallway Exit Doorway No Asbestos Detected
37-1 Red Paint / Silver Paint
(Vent) Central West No Asbestos Detected
37-2 Red Paint / Silver Paint
(Vent)
West Above Mechanical
Room No Asbestos Detected
38-1 Equipment Curb HVAC Curb - Central West
Area No Asbestos Detected
38-2 Equipment Curb HVAC Curb - Central West
Area No Asbestos Detected
TABLE 2
Sample
Number Sample Information Sample Location
Sample Results
(ppm)
L-01 Light Brown Paint Window Trim Interior (Rm 2002) 4700
L-02 Dark Brown Paint Window Trim Interior (Rm 2005) 1100
L-03 Light Green Paint Fire Extinguisher Panel 930
L-04 Dark Brown Paint Heater Vent (Rm 2005) 990
L-05 Light Brown Paint Heater Vent (2006) 170
L-06 Light Green Paint Atrium Window Trim Southwest 16000
L-07 Light Green Paint Heater Vent Southwest Hallway 3200
L-08 Tan Paint Heater Vent (Rm 2013) 3600
L-09 Brown Paint Door Frame (Interior) (Rm 2005) 2100
L-10 Seafoam Green Paint Wood Panel (Rm 2005) <85
L-11 Blue Pant Hallway Trim (Lobby Entrance) 1200
L-12 White Paint On Gibson Board (Rm 2008) 940
L-13 White Paint On Doorframe Interior
(Women's Restroom)
L-14 Green Paint On Doorframe Interior (Rm 2030) 1900
L-15 Blue Paint On Doorframe Interior (Rm 2032) 1600
TABLE 2
Lead Paint Chip Sampling Data - Flame AA Analysis
Chabot College - Building 2000 Pre-Demolition Survey
Hayward , California
Sample Information Sample Location
Sample Results
(ppm)
TABLE 2
Lead Paint Chip Sampling Data - Flame AA Analysis
Chabot College - Building 2000 Pre-Demolition Survey
Hayward , California
L-16 Blue Paint On Door (Women's Restroom) <140
L-17 Tan Paint On Door (Rm 2026) 2100
L-18 Turquoise Paint On Door (Rm 2003) 6800
L-19 brown Paint On Door (Rm 2002) 5900
L-20 Brown Paint On Window Trim (Rm 2002) 2200
L-21 Green Paint On Window Trim Frame
(Rm 2026)
L-22 Green Paint On Electrical Panel
Northeast Hallway
L-23 Green Paint On Conduit Box Northeast Lobby
Entrance <100
L-24 Green Paint On Wood Panel (Rm 2002) <71
L-25 Light Green Paint On Wallpaper (Room 2046) 66
L-26 Grey Paint On Wall Paper (Rm 2040) 63
L-27 Off-White Paint On Wallpaper (Rm2034) 60
L-28 Dark Blue/Green Paint On Wallpaper (Rm 2011) 95
L-29 Brown Paint On Window Trim (Atrium) 5000
L-30 Brown Paint On Down Pipe Spout (Atrium) Exterior 1900
Sample Information Sample Location
Sample Results
(ppm)
TABLE 2
Lead Paint Chip Sampling Data - Flame AA Analysis
Chabot College - Building 2000 Pre-Demolition Survey
Hayward , California
L-31 Brown Paint On Wood Panel (Atrium) Exterior <83
L-32 White Paint On Stucco (South Doorway) <69
L-33 Green Paint On Door Frame (Mechanical Room)
Exterior 10000
L-34 Green Paint On Door (Mechanical Room) Exterior 23000
L-35 Pink Paint On Door Frame (Mechanical Room)
Exterior 13000
LB-01 1" x 1" Ceramic Floor Tile Men's Restroom Floor < 47 ppm
LB-02 1" x 1" Ceramic Floor Tile Women's Restroom Floor < 42 ppm
TABLE 3
Sample Number Sampled Date Building Material Location PCB Content
PCB-1-1 7/14/2026 Fiberglass Insulation Mechanical Room - 3" Pipe Run None Detected
PCB-2-1 7/14/2026 Exterior Sealant West Floor Slab Expansion Joint None Detected
PCB-2-2 7/14/2026 Exterior Sealant West Metal Door Frame None Detected
PCB-2-3 7/14/2026 Exterior Sealant West Concrete Column None Detected
PCB-2-4 7/14/2026 Exterior Sealant Mechanical Room Metal Vent None Detected
PCB-2-5 7/14/2026 Exterior Sealant East Concrete Column None Detected
PCB-3-1 7/14/2026
Door and Window
Rubber Gaskets Northwest Window None Detected
PCB-3-2 7/14/2026
Door and Window
Rubber Gaskets Northwest Door None Detected
PCB-3-3 7/14/2026
Door and Window
Rubber Gaskets Southwest Door None Detected
PCB-4-1 7/14/2026 Window Glazing Northeast Atrium Upper Window None Detected
TABLE 3
Polychlorinated Bipheyls (PCB) Sampling Results - EPA Method 8082A Analysis
25555 Hesperian Boulevard, Hayward, California
Chabot College, Building 2000 - Pre-Demolition Survey
Chabot-Las Positas Community College District (CLPCCD)
APPENDIX A
APPENDIX B
Approved by:
Approved Signatory Philip Newton
Report for:
Carolyn Henry, Pedro Rico, CAC North Tower Environmental 1485 Bayshore Boulevard San Francisco, CA 94124
Regarding:
Eurofins Built Environment Testing West, LLC Project: NT-5160; Chabot College - Building 1600 Pre-Demolition Survey
EML ID: 4539081
All samples were received in acceptable condition unless noted in the Report Comments portion in the body of the report. The results relate only to the samples as received and tested. The results include an inherent uncertainty of measurement associated with estimating percentages by polarized light microscopy. Measurement uncertainty data for sample results with >1% asbestos concentration can be provided when requested.
Eurofins Built Environment Testing West, LLC ("the Company"), a member of the Eurofins Built Environment Testing group of companies, shall have no liability to the client or the client's customer with respect to decisions or recommendations made, actions taken or courses of conduct implemented by either the client or the client's customer as a result of or based upon the Test Results. In no event shall the Company be liable to the client with respect to the Test Results except for the Company's own willful misconduct or gross negligence nor shall the Company be liable for incidental or consequential damages or lost profits or revenues to the fullest extent such liability may be disclaimed by law, even if the Company has been advised of the possibility of such damages, lost profits or lost revenues. In no event shall the Company's liability with respect to the Test Results exceed the amount paid to the Company by the client therefor.
Dates of Analysis:
Asbestos PLM: 05-20-2026
Service SOPs: Asbestos PLM (EPA 40CFR App E to Sub E of Part 763 & EPA 600/R-93-116, EBET-PLM-SOP83921) NVLAP Lab Code 200757-0
EMLab ID: 4539081, Page 1 of 38Eurofins Built Environment Testing West, LLC
Eurofins Built Environment Testing West, LLC 2841 Dow Avenue, Suite 300, Tustin, CA 92780
(833) 465-5857 www.eurofinsus.com/BuiltClient: North Tower Environmental C/O: Carolyn Henry, Pedro Rico, CAC Re: NT-5160; Chabot College - Building 1600 Pre- Demolition Survey
Date of Submittal: 05-15-2026 Date of Receipt: 05-15-2026 Date of Report: 05-20-2026
ASBESTOS PLM REPORT
Total Samples Submitted: 109 Total Samples Analyzed: 109
Total Samples with Layer Asbestos Content > 1%: 32
Location: 1-1, Stone Patterm Wallpaper / Board/ Taping Mud, hallway southwest near exit door Lab ID-Version‡: 22860594-1
Sample Layers Asbestos Content Cream Tape ND
Off-White Joint Compound 2 2% Chrysotile White Drywall with Brown Paper ND
Gray Wallpaper ND Off-White Joint Compound 2% Chrysotile
Composite Asbestos Fibrous Content: < 1% Asbestos Composite Non-Asbestos Content: 15% Cellulose Sample Composite Homogeneity: Poor
Comments: Composite asbestos content provided is only for Drywall/Joint Compound. Composite content provided for this analysis has been performed by following the NESHAP guidelines.
Location: 1-2, Stone Patterm Wallpaper / Board/ Taping Mud, hallway southeast near exit door Lab ID-Version‡: 22860595-1
Sample Layers Asbestos Content Gray Wallpaper ND
Off-White Joint Compound 2% Chrysotile Cream Tape ND
Off-White Joint Compound 2 2% Chrysotile White Drywall with Brown Paper ND
Composite Asbestos Fibrous Content: < 1% Asbestos Composite Non-Asbestos Content: 15% Cellulose Sample Composite Homogeneity: Poor
Comments: Composite asbestos content provided is only for Drywall/Joint Compound. Composite content provided for this analysis has been performed by following the NESHAP guidelines.
EMLab ID: 4539081, Page 2 of 38Eurofins Built Environment Testing West, LLC
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certification, approval, or endorsement by NVLAP, NIST, or any agency of the federal government. The Company reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
All components not quantified as asbestos content and non-asbestos content are considered to be non-fibrous matrix components. Matrix components may include, but are not limited to, gypsum, paint, silicate minerals, vinyl, binder, calcium carbonate, tar, and foam.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detection and reporting limit is less than 1% unless point counting is performed. Floor tile samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detection limit and to aid in asbestos identification.
‡ A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is reflected by the value of "x".
(833) 465-5857 www.eurofinsus.com/BuiltClient: North Tower Environmental C/O: Carolyn Henry, Pedro Rico, CAC Re: NT-5160; Chabot College - Building 1600 Pre- Demolition Survey
Date of Submittal: 05-15-2026 Date of Receipt: 05-15-2026 Date of Report: 05-20-2026
ASBESTOS PLM REPORT
Location: 1-3, Stone Patterm Wallpaper / Board/ Taping Mud, lobby east near exit door Lab ID-Version‡: 22860596-1
Sample Layers Asbestos Content Gray Wallpaper ND
Off-White Joint Compound 2% Chrysotile Cream Tape ND
Off-White Joint Compound 2 2% Chrysotile White Drywall with Brown Paper ND
Composite Asbestos Fibrous Content: < 1% Asbestos Composite Non-Asbestos Content: 15% Cellulose Sample Composite Homogeneity: Poor
Comments: Composite asbestos content provided is only for Drywall/Joint Compound. Composite content provided for this analysis has been performed by following the NESHAP guidelines.
Location: 1-4, Stone Patterm Wallpaper / Board/ Taping Mud, near atrium window -northeast Lab ID-Version‡: 22860597-1
Sample Layers Asbestos Content Gray Wallpaper ND
Off-White Joint Compound 2% Chrysotile Cream Tape ND
Off-White Joint Compound 2 2% Chrysotile White Drywall with Brown Paper ND
Composite Asbestos Fibrous Content: < 1% Asbestos Composite Non-Asbestos Content: 15% Cellulose Sample Composite Homogeneity: Poor
Comments: Composite asbestos content provided is only for Drywall/Joint Compound. Composite content provided for this analysis has been performed by following the NESHAP guidelines.
EMLab ID: 4539081, Page 3 of 38Eurofins Built Environment Testing West, LLC
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certification, approval, or endorsement by NVLAP, NIST, or any agency of the federal government. The Company reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
All components not quantified as asbestos content and non-asbestos content are considered to be non-fibrous matrix components. Matrix components may include, but are not limited to, gypsum, paint, silicate minerals, vinyl, binder, calcium carbonate, tar, and foam.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detection and reporting limit is less than 1% unless point counting is performed. Floor tile samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detection limit and to aid in asbestos identification.
‡ A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is
(833) 465-5857 www.eurofinsus.com/BuiltClient: North Tower Environmental C/O: Carolyn Henry, Pedro Rico, CAC Re: NT-5160; Chabot College - Building 1600 Pre- Demolition Survey
Date of Submittal: 05-15-2026 Date of Receipt: 05-15-2026 Date of Report: 05-20-2026
ASBESTOS PLM REPORT
Location: 1-5, Stone Patterm Wallpaper / Board/ Taping Mud, near atrium window -northwest Lab ID-Version‡: 22860598-1
Sample Layers Asbestos Content Gray Wallpaper ND
Off-White Joint Compound 2% Chrysotile Cream Tape ND
Off-White Joint Compound 2 2% Chrysotile White Drywall with Brown Paper ND
Composite Asbestos Fibrous Content: < 1% Asbestos Composite Non-Asbestos Content: 15% Cellulose Sample Composite Homogeneity: Poor
Comments: Composite asbestos content provided is only for Drywall/Joint Compound. Composite content provided for this analysis has been performed by following the NESHAP guidelines.
Location: 1-6, Stone Patterm Wallpaper / Board/ Taping Mud, west lobby corner Lab ID-Version‡: 22860599-1
Sample Layers Asbestos Content Gray Wallpaper ND
Off-White Joint Compound 2% Chrysotile Cream Tape ND
Off-White Joint Compound 2…
This is the start of the file's text. The full file is on GovTribe.