01-123073_SPC_A.pdf

PDF 7 MB Posted

Attached to
STEM Courtyard at Chabot College
Solicitation number
147948
Issued by
Alameda County, California

About this file

This is a Project Manual and Specifications document for the construction of Chabot College Building 2000 Demolition and New STEM Courtyard located at 2555 Hesperian Boulevard, Hayward, California. The project is administered by the State of California's Division of the State Architect (DSA) under architect SVA Architects, Inc., with DSA identification number 01-123073. The scope of work includes demolition of Building 2000 and construction of a new STEM Courtyard, with the project manual encompassing comprehensive specifications across multiple divisions including general requirements, existing conditions, concrete, metals, wood, thermal and moisture protection, openings, finishes, specialties, furnishings, earthwork, exterior improvements, and utilities. The document was submitted for DSA resubmittal on May 1, 2026, with final approval dated January 31, 2027. The specifications address work sequencing, contractor use of premises, field engineering requirements using California registered land surveyors and professional engineers, and coordination with Owner occupancy during construction.

The specifications establish detailed administrative and procedural requirements for contract performance, including payment procedures, submittal schedules, quality requirements, and structural testing and inspection protocols. The contractor must submit a Schedule of Values using AIA Document G703 within fifteen working days of contract award and comply with comprehensive quality control requirements including independent testing by Owner-employed testing agencies. Special inspection and testing requirements apply to structural elements including concrete formwork and reinforcement, cast-in-place concrete with specified strength testing, concrete masonry units, structural steel connections and welds, and steel deck installation. The document mandates compliance with California Building Code sections, ASTM standards, and AWS welding standards, with specific requirements for nondestructive testing of welds, proof testing of adhesive and mechanical anchors, and concrete strength verification through cylinder testing and core sampling. Attic stock materials for future maintenance may be required as approved by the Owner, with associated costs determined through a pre-construction meeting and incorporated via Change Order.

View the file

Other files

File Type Posted
B26-27-08_AD COPY Rev1.pdf PDF
Building 2000 Pre-Demolition Hazmat Report.pdf PDF
01-123073_DWG_A.pdf PDF
RFQ B26 27-08 B2000 Demo and New STEM Courtyard.pdf PDF
RFI Template.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

INCLUDING SPECIFICATIONS

FOR

CONSTRUCTION

OF

Chabot College Building 2000 Demolition and

STEM Courtyard

2555 Hesperian Blvd.

Hayward, California 94545

ARCHITECTS

SVA ARCHITECTS, INC.

7901 Stoneridge Dr., Suite 100 Pleasanton, California 94588

T: 510.267.3180

August 28, 2026 DSA Resubmittal

Chabot College Building 2000 Demolition 5/1/26 and New STEM Courtyard Hayward, California

00 00 01 - 1 Stamps Page

SECTION 00 00 01

STAMPS PAGE

L

No. C-18301 Jan 31, 2027

CIC

ENSED ARCHITE

TR

OOBERT M. SIM

NS

S

TA

TE

OF CALIFOR

N

IA

49.00

6204.01

DSA

D E P A R T M E N T O F G E N E R A L S E R V I C E S

DIVISION OF THE STATE ARCHITECT

DSA

DIVISION OF THE STATE ARCHITECT

DSA

DIVISION OF THE STATE ARCHITECT

DSA

DIVISION OF THE STATE ARCHITECT

IDENTIFICATION STAMP

DIV. OF THE STATE ARCHITECT

APP: INC:

REVIEWED FOR

SS FLS ACS

DATE:

4 4 4

01-123073

10/14/2026

00 01 10 - 1 Table of Contents

SECTION 00 01 10

TABLE OF CONTENTS

PROJECT MANUAL

INTRODUCTORY INFORMATION

Document 00 00 05 Certifications Page Document 00 01 10 Table of Contents

SPECIFICATIONS GROUP

DIVISION 01 – GENERAL REQUIREMENTS

Section 01 11 00 Summary of Work 01 20 00 Payment Procedures 01 23 00 Alternates 01 25 00 Substitution Procedures 01 26 00 Contract Modification Procedures 01 30 00 Administrative Requirements 01 31 00 Project Management and Coordination 01 40 00 Quality Requirements 01 45 00 Structural Tests and Inspections 01 50 00 Temporary Facilities and Controls 01 56 39 Tree and Plant Protection 01 60 00 Product Requirements 01 70 00 Execution Requirements 01 73 00 Cutting and Patching 01 74 10 Waste Management 01 77 00 Closeout Procedures 01 78 00 Warranties 01 79 00 Demonstration and Training 01 81 15 CALGreen Environmental Requirements

DIVISION 02 – EXISTING CONDITIONS

Section 02 41 10 Structure Demolition 02 41 20 Selective Building Demolition

DIVISION 03 – CONCRETE

Section 03 10 00 Concrete Formwork 03 20 00 Concrete Reinforcement and Embedded Assemblies 03 30 00 Cast-In-Place Concrete

DIVISION 04 – MASONRY

Not used.

00 01 10 - 2 Table of Contents

DIVISION 05 – METALS

Section 05 40 00 Cold-Formed Metal Framing 05 52 00 Metal Railings

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

Section 06 10 00 Rough Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 07 21 00 Thermal Insulation 07 25 00 Weather-Resistive Barriers 07 26 00 Below-Grade Vapor Retarder 07 41 13 Metal Roof Panels 07 46 10 Drainage Mat Furring 07 46 40 Fiber Cement Siding 07 60 00 Flashing and Sheet Metal 07 90 00 Joint Sealants

DIVISION 08 – OPENINGS

Section 08 11 10 Hollow Metal Doors and Frames 08 42 30 Automatic Entrances (Not a part of this submittal.)

08 71 00 Door Hardware

DIVISION 09 – FINISHES

Section 09 21 00 Gypsum Board Assemblies 09 24 00 Portland Cement Plaster 09 65 10 Resilient Base 09 67 20 Decorative Epoxy Resin Flooring 09 90 00 Painting and Coating

DIVISION 10 – SPECIALTIES

Section 10 14 00 Signage 10 44 00 Fire Extinguisher Cabinets 10 56 10 Metal Storage Shelving

DIVISION 11 – EQUIPMENT

Not used.

DIVISION 12 – FURNISHINGS

Section 12 93 00 Site Furnishings

00 01 10 - 3 Table of Contents

DIVISION 13 – SPECIAL CONSTRUCTION

Not used.

DIVISION 14 – CONVEYING EQUIPMENT

Not used.

DIVISION 21 – FIRE SUPPRESSION

Not used.

DIVISION 22 – PLUMBING

Not used.

DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING

Not used.

DIVISION 26 – ELECTRICAL

Section 26 00 00 General Electrical

DIVISION 27 – COMMUNICATIONS

Not used.

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

Not used.

DIVISION 31 – EARTHWORK

Section 31 05 13 Soils for Earthwork 31 10 00 Site Clearing 31 22 13 Rough Grading 31 23 00 Excavation and Fill 31 23 16 13 Trenching 31 23 23.13 Backfill 31 23 23.14 Controlled Low Strength Material

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 11 23 Aggregate Base Courses 32 11 23.1 Aggregate Base Courses (Landscape) 32 12 16 Asphalt Pavement 32 13 13 Concrete Paving 32 13 13.1 Concrete Work (Landscape) 32 84 00 Planting Irrigation 32 90 00 Planting

00 01 10 - 4 Table of Contents

32 92 00 Turf Planting

DIVISION 33 –UTILITIES

Section 33 40 00 Storm Drainage Utilities

END OF SECTION

Chabot College Building 2000 Demolition 2/27/26

01 11 00 - 1 Summary of Work

SECTION 01 11 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Project consists of construction of the Chabot College Building 2000 Demolition and New STEM Courtyard as indicated in Contract Documents.

1. Items noted "NIC" (Not in Contract) will be furnished and installed by Owner or under separate contract.

a. Hazardous Materials Removal: Known hazardous materials will be removed under separate contract (NIC); inform Owner immediately where materials suspected of being hazardous are encountered.

b. Hazardous Materials Removal: Where materials suspected as being hazardous are encountered, inform Owner immediately. Work directly with Owner relating to hazardous materials.

1) Architect shall not be involved in determination, removal, or disposal of hazardous materials.

2. Owner reserves right to remove and retain possession of existing items prior to start of Contract.

B. Division 01: Where provisions of General Conditions relate to Project administration or work-related requirements of the Contract, those paragraphs are expanded in Division 01 - General Requirements.

1. General Conditions, Supplementary Conditions and Division 01 - General Requirements contain information necessary for completion of every part of Project.

2. Where items of Work are done under subcontracts, each item shall be subject to these conditions.

1.2 REQUIREMENTS INCLUDED

A. This section includes administrative provisions:

1. Work sequence.

2. Contractor use of premises.

3. Building occupancy.

4. Field engineering.

5. Lines and levels.

6. Regulatory requirements and reference standards.

7. Owner furnished Contractor installed (OFCI) products.

8. Owner pre-ordered products.

01 11 00 - 2 Summary of Work

9. Special definitions.

1.3 WORK SEQUENCE

A. Coordinate construction schedule and operations with Owner and Architect.

1. Construct Work to accommodate Owner's occupancy requirements during construction period.

B. Perform construction in phases as indicated.

1.4 CONTRACTOR USE OF PREMISES

A. Limit use of premises for Work and construction operations and to allow for:

1. Building occupancy.

2. Work by other contractors.

3. Authorized access to restricted areas.

4. Public access to public areas.

B. Coordinate use of premises and access to site under direction of Owner or Architect.

1.1 BUILDING OCCUPANCY

A. Building will be occupied during construction for conduct of normal operations;

cooperate with Owner to minimize conflict and to facilitate building operations.

1.2 FIELD ENGINEERING

A. Provide field engineering services; establish lines and levels by use of recognized engineering survey practices.

1. Surveyor: Engage California registered land surveyor to perform land surveying services required.

2. Engineer: Engage California registered professional engineer of discipline required to perform required engineering services.

B. Locate and protect control and reference points.

1. Surveyor's Log: Maintain a surveyor's log of control and other survey work. Log to be available for reference.

a. Record deviations from required lines and levels.

b. Advise Architect when deviations that exceed indicated or recognized tolerances are detected.

c. Project Record Drawings: Record deviations that are accepted and not corrected.

01 11 00 - 3 Summary of Work

d. Upon completion of foundation walls, major site improvements, and other work requiring field engineering services, prepare certified survey showing dimensions, locations, angles, and elevations of construction and sitework.

1.3 LINES AND LEVELS

A. Establish lines and levels by use of recognized engineering practices.

B. Locate and protect control and reference points.

1.4 REGULATORY REQUIREMENTS AND REFERENCE STANDARDS

A. Regulatory Requirements:

1. Architect has contacted governing authorities and reviewed design requirements of local, state, and federal agencies for applicability to Project.

2. Contractor shall be responsible for contacting governing authorities directly for necessary information and decisions bearing upon performance of Work.

B. Reference Standards:

1. For Products specified by association or trade standards, comply with requirements of referenced standard, except when more rigid requirements are specified or are required by applicable codes.

2. Applicable date of each standard is that in effect as of date on proposal or date on Contract where no proposal is available, except when a specific date is specified.

1.5 OWNER FURNISHED CONTRACTOR INSTALLED (OFCI) PRODUCTS

A. Select products are to be furnished and paid for by Owner and installed by Contractor:

1. Refer to Drawings and Specifications.

B. Owner's Responsibilities:

1. Arrange for and deliver shop drawings, product data, and samples to Contractor.

2. Arrange and pay for product delivery to site.

3. Inspect products jointly with Contractor on delivery.

4. Submit claims for transportation damage.

5. Arrange for replacement of damaged, defective, or missing items.

6. Arrange for manufacturer's warranties, inspections, and service.

C. Contractor's Responsibilities:

1. Review shop drawings, product data, and samples.

2. Receive and unload products at site.

3. Inspect jointly with Owner for completeness and damage.

4. Handle, store, and install products.

5. Finish products as required after installation.

01 11 00 - 4 Summary of Work

6. Repair or replace items damaged by Work of this Contract.

1.6 OWNER PRE-ORDERED PRODUCTS

A. Select products have been pre-ordered by Owner:

1. Refer to Drawings.

B. Owner has negotiated purchase orders for these products for incorporation into Project.

1. Purchase orders are assigned to Contractor; costs shall be included in the base bid.

2. Contractor's responsibilities are same as if Contractor negotiated purchase orders.

1.7 SPECIAL DEFINITIONS

A. Approved: Approved, directed, selected, required, ordered, designated, accepted, acceptable, and satisfactory shall require written action by Architect.

B. Equal, Approved Equal: Equal and approved equal shall require requests for substitutions for products or manufacturers not specified.

1. Requests for substitutions shall be in accordance with requirements of Section 01 25 00 - Substitution Procedures.

C. Furnish: Furnish means supply and deliver to Project, unless otherwise defined in greater detail.

D. Install: Install is used to describe operations at Project, from inspecting and unloading, to completion in place, ready for intended use.

E. Provide: Provide means furnish and install, complete and ready for intended use, unless otherwise defined in greater detail.

Building 2000 Demolition and New STEM Courtyard 2/27/26

01 20 00 - 1 Payment Procedures

SECTION 01 20 00

PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Special administrative and procedural requirements necessary to prepare and process Application for Payment.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in Schedule of Values with other required administrative forms and schedules, including application for Payment forms with Continuation Sheets, Submittals Schedule, and Contractor's Construction Schedule.

2. Submit Schedule of Values to Architect at earliest possible date but no later than seven days before date scheduled for submittal of initial Application for Payment.

B. Format and Content: Use Project Manual table of contents as guide to establish line items for Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include following Project identification on Schedule of Values.

a. Project name and location.

b. Name of Architect.

c. Architect's Project number.

d. Contractor's name and address.

e. Date of submittal.

2. Submit draft of AIA Document G703 Continuation Sheets or comparable format approved in advance by Architect.

3. Provide breakdown of Contract Sum in enough detail to facilitate continued evaluation of Application for Payment and progress reports. Coordinate with Project Manual table of contents.

a. Provide several line items for principal subcontract amounts where appropriate.

4. Round amounts to nearest whole dollar; total shall equal Contract Sum.

5. Provide separate line item in Schedule of Values for each part of Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

01 20 00 - 2 Payment Procedures

6. Provide separate line items in Schedule of Value for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of Work.

7. Each item in Schedule of Values and Application for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in Schedule of Values or distributed as general overhead expense at Contractor's option.

8. Schedule Updating: Update and resubmit Schedule of Values before next application for Payment when Change Orders or Construction Change Directives result in a change in Contract Sum.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment: Application for Payment at time of Completion, and final Application for Payment involves additional requirements.

B. Payment Application Times: Date for each progress payment is indicated in Agreement between Owner and Contractor. Period of construction Work covered by each Application for Payment is period indicated in Agreement.

C. Payment Application Forms: AIA Document G702 and AIA Document G703 Continuation Sheets as form for Application for Payment unless comparable forms have been approved in advance by Architect.

D. Application Preparation: Complete every entry on form. Execute by person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

E. Transmittal:

1. Contractor shall provide copy of Application for Payment one week prior to Payment Request ("Draw") Meeting, for review of team members.

2. Contractor shall provide ten wet signed copies of Application for Payment at Payment Request ("Draw") Meeting, alternate methods subject to prior Architect review and approval.

01 20 00 - 3 Payment Procedures

a. Provide each copy with transmittal form listing attachments and recording appropriate information about application.

b. Copies shall include waivers of lien and similar attachments if required.

F. Waivers of Mechanic's Lien: With each Application for Payment submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of Contract and related to Work covered by payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit final or full waivers.

3. Owner reserves right to designate which entities involved in Work submit waivers.

4. Waiver Forms: Submit waivers of lien on executed forms acceptable to Owner.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following.

1. List of subcontractors.

2. Schedule of Values.

3. Contractor's Construction Schedule (preliminary if not final).

4. Schedule of unit prices.

5. Submittals Schedule (preliminary if not final).

6. List of Contractor's staff assignments.

7. List of Contractor's principal consultants.

8. Copies of building permits.

9. Copies of authorizations and licenses from authorities having jurisdiction for performance of Work.

10. Initial progress report.

11. Report of preconstruction conference.

12. Certificates of insurance and insurance policies.

H. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted including but not necessarily limited to following.

1. Evidence of completion of Project closeout requirements.

01 20 00 - 4 Payment Procedures

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement accounting for final changes to Contract Sum.

4. Provide following documents or comparable documents approved in advance by Architect.

a. AIA Document G706, Contractor's Affidavit of Payment of Debts and Claims.

b. AIA Document G706A, Contractor's Affidavit of Release of Liens.

c. AIA Document G707, Consent of Surety to Final Payment.

5. Evidence that claims have been settled.

6. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Completion.

7. Final liquidated damages settlement statement.

01 23 00 - 1 Alternates

SECTION 01 23 00

ALTERNATES

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes a description of alternate work.

B. Related Requirements:

1. Pricing Documents: Quotation of each alternate’s cost.

2. Owner-Contractor Agreement: Alternates accepted by Owner for incorporation into Work.

3. Sections of Specifications identified in each Alternate.

1.2 PROCEDURES

A. Alternates will be exercised at Owner's option.

B. Coordinate related work and modify surrounding work as required to complete Work, including changes under each alternate, when acceptance is designated in Owner- Contractor Agreement.

1.3 ALTERNATES

A. Alternates: To be determined.

01 25 00 - 1 Substitution Procedures

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. General: Procedures are described for requesting substitution of unlisted materials in lieu of materials named in Specifications or approved for use in addenda.

1. Provide products listed in Contract Documents, products by manufacturers listed in Contract Documents, and products meeting specified requirements.

a. Contract Amount: Base on materials and products included in Contract Documents.

b. Where materials and products are listed in Contract Documents, materials and products by manufacturers not listed shall not be used without Owner’s and Architect’s approval of Contractor's written request for substitution.

2. Purpose: After bidding, substitutions will only be considered where Owner will receive benefit or because specified materials are no longer available due to no fault of Contractor.

B. Related Sections:

1. Section 01 60 00: Product requirements.

1.2 SUBSTITUTIONS

A. Within a period of 35-days after award of Contract, Owner and Architect will consider formal requests for substitutions only from Contractor as specified in 1.1 Summary.

1. Owner and Architect will consider only one request for substitution for each material; where requests are denied Contractor shall be required to provide specified materials.

2. After initial 35-day period, requests will be considered only when a product becomes unavailable through no fault of Contractor; more than one request for substitution will be considered if necessary.

B. Submit each request with sequentially numbered “Substitution Request Transmittal” acceptable to Owner and Architect; submit separate request for each product and support each request with:

1. Product identification with manufacturer's literature and samples where applicable.

2. Name and address of similar projects on which product has been used, and date of installation.

01 25 00 - 2 Substitution Procedures

C. Submit itemized comparison of proposed substitution with specified products and list significant variations.

D. Submit data relating to changes in construction schedule.

E. Note effect of substitution on other work, products, or separate contracts.

1. Note if acceptance of substitution could require revision of Contract Documents, Drawings, details, or Specifications.

F. Include accurate cost data comparing proposed substitution with product and amount of net change in Contract price.

1. Include costs to other contractors and costs for revisions to Drawings, details or Specifications.

G. Substitutions will not be considered for acceptance when:

1. They are indicated or implied on submittals without a formal request from Contractor.

2. They are requested directly by a subcontractor or supplier.

3. Acceptance will require substantial revision of Contract Documents.

H. Substitute products shall not be ordered without written acceptance of Owner and Architect.

I. Owner and Architect will determine acceptability of proposed substitutions and reserves right to reject proposals due to insufficient information.

1.3 CONTRACTOR'S REPRESENTATION

A. Requests constitute a representation that Contractor:

1. Has investigated proposed product and determined whether it meets or exceeds, in all respects, specified product.

2. Will provide same warranty or longer warranty for substitution as for specified product.

3. Will coordinate installation and make other changes that may be required for Work to be complete in all respects.

4. Waives claims for additional costs that subsequently become apparent.

5. Will pay costs of changes to Contract Documents, Drawings, details, and Specifications required by accepted substitutions.

1.4 ARCHITECT DUTIES

A. Review Contractor's requests for substitutions with reasonable promptness.

01 25 00 - 3 Substitution Procedures

1. Architect will recommend that Owner accept or reject substitution request.

2. Upon request, Architect will provide cost for changes to Contract Documents, Drawings, details, and Specifications required for substitutions.

B. Notify Contractor in writing of decision to accept or reject requested substitution.

01 26 00 - 1 Contract Modification Procedures

SECTION 01 26 00

CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: This section specifies administrative and procedural requirements governing Contract modification procedures.

1. Requests for Information (RFI).

2. Change Order.

3. Allowances.

4. Construction Change Directive.

B. Related Requirements:

1. Section 01 25 00: Substitution procedures.

2. Section 01 30 00: Administrative requirements.

1.2 MINOR CHANGES IN WORK

A. Architect will issue supplemental instructions authorizing minor changes in Work, not involving adjustment to Contract Sum or Contract Time, on AIA Form G710, Architect’s Supplemental Instructions or similar form approved in advance by Architect.

1.3 REQUESTS FOR INFORMATION

A. Contractor may submit a written Request for Information (RFI) in format approved by Architect relating to perceived inconsistencies and omissions in Contract Documents.

1. A record of RFI's is to be maintained by Contractor along with information regarding origin of request, date of request, and date request was received from Architect. Number RFI's sequentially based on date of request.

B. Requests for Information shall be used only as a means of obtaining clarification of information not included in Contract Documents and shall not be used to assist Contractor in preparation of shop drawings or other information required by Contract.

1. Contract Documents are intended to contain enough information to show aesthetic and design intent and to provide information such that construction procedures (means and methods) may be reasonably inferred.

2. Contract Documents are not intended to provide specific information related to means and methods of construction nor are they intended to be exhaustive in content.

C. Contractor shall carefully review requests for information by subcontractors and suppliers to ascertain if information is in Contract Documents prior to submitting a Request for Information to Architect based on requests by others.

01 26 00 - 2 Contract Modification Procedures

1. Contractor may suggest possible solutions to fit Project conditions where appropriate.

D. Architect reserves right to return RFI's that do not reasonably relate to necessary clarification of intent of Contract Documents and to charge Contractor for time and materials involved in answering RFI's where information is in Contract Documents.

1. RFI’s shall not be used as a request for substitutions; refer to Section 01 25 00 – Substitution Procedures.

1.4 CHANGE ORDERS

A. Owner-Initiated Proposal Requests: Architect will issue detailed description of proposed changes in Work that require adjustment to Contract Sum or Contract Time. If necessary, description will include supplemental or revised Drawings and Specifications.

1. Proposal requests issued by Architect are for information only. Do not consider changer order proposal requests as instruction either to stop work in progress or to execute proposed change.

2. Within 10 days of receipt of a proposal request, submit estimate of cost necessary to execute change to Architect for Owner’s review.

a. Include list of quantities of products required and unit costs, with total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental and amounts of trade discounts.

c. Include a statement indicating effect of proposed change in Work will have on Contract Time.

B. Contractor-Initiated Proposals: When latent or unforeseen conditions require modifications to Contract, Contractor may propose changes by submitting a request for a change to Architect and Owner.

1. Include statement of reasons for change and effect of change on Work. Provide a complete description of proposed change. Indicate effect of proposed change on Contract Sum and Contract Time.

2. Include a list of quantities of products required and unit costs with total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental and amounts of trade discounts.

4. Comply with requirements in Section 01 25 00 - Substitution Procedures if proposed change requires substitution of unspecified product or system for specified product or system.

C. Proposal Request Form: Use AIA Document G709 for Change Order Proposal Requests; other formats to be submitted to Owner and Architect for prior approval.

01 26 00 - 3 Contract Modification Procedures

D. Change Order Procedures: Contractor shall be directed to proceed with Work upon Owner’s approval of Proposal.

1. Architect will issue Change Order for signatures of Owner and Contractor on AIA Form G701 or similar form approved in advance by Owner and Architect, including approved Change Order proposals for that period.

2. Amounts for each Change Order shall be indicated in each Request for Payment including payment status for each individual Change Order.

1.5 ALLOWANCES

A. Allowance Adjustment: For Contract items bid based on allowance, submit Change Order Proposal on difference between actual purchase amount and allowance, based on work-in-place.

1. Include installation cost in purchase amount only where indicated as part of allowance.

2. When requested, prepare explanations and documentation to substantiate amounts claimed for work done based on allowances.

3. Submit substantiation of a change in Scope of work claimed in Change Orders related to allowances.

4. Owner reserves right to establish actual quantity of work-in-place by independent quantity survey, measure, or count.

B. Submit claims for increasing costs because of a change in scope or nature of allowance described in Contract Documents, whether for purchase order amount or Contractor’s handling, labor, installation, overhead and profit.

1. Submit claims within 21-days of receipt of Change Order or Construction Change Directive authorizing work to proceed. Owner will reject claims submitted later than 21-days.

2. Do not include Contractor’s or subcontractor’s indirect expense in Change Order cost amount unless it is clearly shown that nature or extent of work has changed from what could have been foreseen from information in Contract Documents.

3. No change to Contractor’s indirect expense is permitted for selection of higher or lower-priced materials or systems of same scope and nature as originally indicated.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: When Owner and Contractor disagree on terms of Proposal Request, Architect may issue a Construction Change Directive per AIA Form G714 or similar form approved in advance by Owner and Architect.

1. Construction Change Directive instructs Contractor to proceed with change in Work, for subsequent inclusion in Change Order.

01 26 00 - 4 Contract Modification Procedures

2. Construction Change Directive contains a complete description of change in Work. It also designates method to be followed to determine change in Contract Sum or Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of Work required by Construction Change Directive. Coordinate scheduling with Construction Manager to allow monitoring by Owner if desired.

1. After completion of change, submit itemized account and supporting data necessary to substantiate cost and time adjustments to Contract.

Chabot College Building 2000 Demolition 8/28/26

01 30 00 - 1 Administrative Requirements

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This section describes general procedural requirements for ongoing submittals.

1. Construction progress schedules.

2. Schedule of values.

3. Product data and manufacturer’s literature.

4. Shop drawings.

5. Samples.

6. Manufacturers' certificates.

7. Excess materials and attic stock.

B. Related Requirements:

1. Section 01 40 00: Test reports, manufacturer's field reports, and mock-ups.

2. Section 01 70 00: Manufacturers’ instructions.

3. Section 01 77 00: Closeout requirements including Project Record Documents.

4. Section 01 78 00: Warranties.

1.2 GENERAL SUBMITTAL PROCEDURES

A. Submittals: Transmit each item using form approved by Architect; submit sample to Architect for approval prior to use.

1. Identify Project, Contractor, subcontractor, major supplier.

a. Attach sequential identification number for each new submittal.

b. Identify each resubmittal using original submittal number and sequential identification clearly indicating item is resubmitted.

2. Identify pertinent Drawing sheet and detail number, and Specification section number as appropriate.

3. Identify deviations from Contract Documents.

4. Provide space for Contractor and Architect review stamps.

5. Contractor: Review and stamp submittals from subcontractors prior to submitting to Architect.

a. Review submittals and indicate where conflicts occur with Contract Documents and with work of other subcontractors.

01 30 00 - 2 Administrative Requirements

b. Return submittals that vary significantly from Contract Documents for correction and resubmittal prior to submitting to Architect.

c. Submittals that vary significantly from Contract Documents and that fail to indicate thorough Contractor review prior to submission to Architect will be returned without review.

d. Cursory review and stamping of subcontractor submittal by Contractor shall not be acceptable.

B. Initial Schedules: Submit initial progress schedule and schedule of value within 15 working days after award of Contract in format acceptable to Owner and Architect.

1. After review by Owner and Architect revise and resubmit where required.

C. Comply with progress schedule for submittals related to Work progress. Coordinate submittal of related items.

D. After Architect review of submittal, revise and resubmit as required, identify changes made since previous submittal.

1. Submittals Requiring Architect Response: Allow reasonable time for Architect review as well as time for preparation of resubmittals where required by Architect.

a. Architect will attempt to respond within 10 working days, however, extent (multiple submittals received at same time) and difficulty of some submittals may require longer review period.

b. Do not delay submittals and do not consider Architect review time as part of Project Schedule as multiple submittals and reviews may be required.

E. Distribute copies of reviewed submittals to concerned persons. Instruct recipients to promptly report any inability to comply.

1.3 TYPES OF SUBMITTALS

A. General: Project requires various types of submittals to maintain communications, minimize misunderstandings, avoid unnecessary conflicts, and to ensure complete documentation for Project Record Documents.

1. Maintain complete set of submittals including required revisions.

B. Construction Schedules: Submit construction progress schedules for Design Team and Owner review and maintain entire team up to date on construction activities.

C. Schedule of Values: Submit Schedule of Values indicating division of Work, subcontractors to perform work, products being used, and values attributed to each to inform Design Team and Owner.

01 30 00 - 3 Administrative Requirements

D. Action Submittals: Submittals relating to product data and manufacturer’s literature, shop drawings, and samples for Design Team review and comment; do not begin fabrication, delivery, or installation until Design Team review is complete.

E. Information Submittals: Submittals relating to certifications, qualifications, reports, including test reports, and instructions are for information; Design Team may choose to comment but action is not generally anticipated.

1. Manufacturer installation instructions and recommendations shall be considered information submittals.

F.

G. Maintenance Materials Submittals: Compile maintenance information and materials during Work to ensure complete set of documents, maintenance manuals, and operation instructions.

H. Closeout Submittals: Compile closeout submittals, organize, and submit to Owner prior to or at time of Substantial Completion. Project will not be considered Substantially Complete until closeout submittals have been received by Owner.

1.4 CONSTRUCTION PROGRESS SCHEDULES

A. Submit construction progress schedule with separate item for each major trade and operation, identifying first day of each week.

1. Show complete sequence of construction by activity, identifying work of separate stages and logically grouped activities.

2. Show projected percentage of completion for each item of Work as of time of each progress Application for Payment.

3. “Submittal Schedule”: Show Contractor submittal dates required for shop drawings, product data, and samples, and product delivery dates; deliver to Architect per approved “Submittal Schedule.”

a. “Submittal Schedule” may be incorporated into construction progress schedule or may be separate, Contractor option.

b. Architect’s Review Period: Architect will be expedient in review however Contractor shall schedule submittals recognizing possibility Architect may reject and may require resubmittal.

c. Contract extension shall not be allowed for Contractor’s failure to properly schedule submittals to allow for Architect requiring resubmittal.

B. Progress Schedule Format: Submit both horizontal bar chart and network analysis system using critical path method as approved by Owner.

1. Submit revised progress schedules with each Application for Payment reflecting changes since previous submittal, not less than monthly.

01 30 00 - 4 Administrative Requirements

1.5 SCHEDULE OF VALUES

A. Submit typed schedule on AIA Form G703 or another Owner and Architect pre-approved format; Contractor's standard media-driven printout will be considered on request. Submit within 15-days after award of Contract.

B. Format: Table of Contents of this Project Manual, with modifications as pre-approved by Owner and Architect; identify each line item with number and title of major Specification sections.

C. Owner reserves right to assume each line item relates to a directly proportional amount of Contractor overhead and profit where listed as a single amount, unless otherwise indicated in Schedule of Value.

D. Revise schedule to list change orders for each Application for Payment.

1. Submit subschedule for each phase of Work.

1.6 PRODUCT DATA/MANUFACTURERS' LITERATURE

A. Action Submittals: Mark each copy to identify applicable Products, models, options, and other data; supplement manufacturers' standard data to provide information unique to the Work.

B. Information Submittals: Include manufacturers' installation instructions only when required by Specifications or specifically requested by Architect.

1. Maintain copy of manufacturer installation instructions and recommendations in Contractor's field office for review.

C. Product data shall be submitted as electronic PDF files unless otherwise noted or approved by Architect in advance.

1. Where paper copies are permitted, submit number of copies Contractor requires, plus one copy to be retained by Architect.

D. Submit number of copies Contractor requires, plus one copy to be retained by Architect.

1.7 SHOP DRAWINGS

A. Shop drawings to illustrate requirements of Contract Documents, accurately show relevant field conditions, dimensions, quantities, kinds of materials, methods of assembly, and data required for fabrication, erection, and installation.

B. Shop drawings shall be submitted as electronic PDF files unless otherwise noted or approved by Architect in advance.

1. Where prints are permitted submit one reproducible print, minimum sheet size 8-1/2” by 11”.

01 30 00 - 5 Administrative Requirements

C. Distribution: After review, reproduce and distribute.

1.8 SAMPLES

A. Submit full range of manufacturers' standard colors, textures, and patterns for Architect's selection.

B. Submit samples to illustrate functional characteristics of Product, with integral parts and attachment devices.

C. Coordinate submittal of different categories for interfacing work.

D. Include identification on each sample, giving full information.

E. Submit number of samples required by Contractor plus one to be retained by Architect.

1. Maintain one set of approved samples at Project Field Office.

F. Sizes: Provide following sizes unless otherwise specified.

2. Flat or Sheet Products: Minimum 6" square, maximum 12" by 12".

3. Linear Products: Minimum 6", maximum 12" long.

4. Bulk Products: Minimum one pint, maximum one gallon.

G. Full size samples may be used in the Work upon approval.

1.9 MANUFACTURERS' CERTIFICATES

A. Submit certificates as electronic PDF files unless otherwise noted or approved by Architect in advance, and in accordance with requirements of each Specification section.

1.10 EXCESS MATERIALS AND ATTIC STOCK

A. Excess Materials: Excess materials shall be considered property of Owner; inform Owner of extent of excess materials and methods required for handling and storage;

remove from site excess materials not required by Owner for maintenance stock.

B. Attic Stock: Owner may choose to obtain additional attic stock for maintenance purposes where excess materials are not considered adequate.

1. Owner may require as much as 5% extra materials for maintenance purposes.

Exact amount of each material shall be determined by Owner based on following meeting and additional costs determined by Contractor.

a. Contractor shall be prepared to order up to 5% extra materials on items that may not be readily available in future such as custom colors, offshore manufacture, anticipated life span under 5 years, and potential for damage.

01 30 00 - 6 Administrative Requirements

1) Do not order extra attic stock until extent is determined and agreed to by Owner including which materials require extra stock and exactly how much those materials will cost including shipping and handling.

b. Excess Materials: Furnish excess materials only for materials that have a shelf-life of more than two years.

2. Meeting: Conduct meeting prior to beginning Work to discuss extent of materials Owner would like to receive at Project Closeout for attic stock for maintenance materials. Where available include personnel from Owner’s maintenance crew.

a. Estimate excess materials to be anticipated to be ordered in addition to materials for handling and storage and how those materials will be invoiced and identified regarding material and location in Project.

b. Determine area necessary for adequate storage, handling, and identifying excess materials and attic stock and discuss with Owner.

c. Submit information regarding equipment necessary for handling of excess materials and attic stock due to weight, size, and storage requirements.

d. Assist Owner in determining where on-site or off-site additional attic stock for maintenance purposes will be delivered and stored.

3. Additional Costs: After meeting submit to Owner detailed listing of additional costs for each material Owner may like to receive for attic stock and assist Owner in modifying listing to determine acceptable final costs.

a. Include unit prices for desired attic stock where excess materials are not adequate for Owner maintenance stock.

4. Substantial Completion: Submit Construction Bulletin at Substantial Completion indicating changes to Contract Amount for attic stock including unit price totals for materials where excess materials are not adequate.

5. Final Completion: Ensure attic stock has been received, identified, cataloged, and stored at locations agreed upon with Owner based on Change Order indicating amounts finally agreed to by Owner.

01 31 00 - 1 Project Management and Coordination

SECTION 01 31 00

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Description of Project management and coordination including but not necessarily limited to the following:

1. General Project coordination procedures.

2. Coordination drawings.

3. Staff names.

4. Administrative and supervisory personnel.

5. Project meetings.

B. Related Sections:

1. Section 01 30 00: Administrative requirements.

2. Section 01 79 00: Demonstration and training.

1.2 COORDINATION

A. Coordination: Coordinate construction operations included in various Specifications sections to ensure efficient and orderly installation of each part of Work.

1. Coordinate construction operations that depend on each other for proper installation, connection, and operation.

2. Coordinate work to assure efficient and orderly sequence of installation of construction elements.

3. Make provisions for accommodating items installed by Owner or under separate contracts.

B. Prepare memoranda for distribution to each party involved as needed, outlining special procedures required for coordination.

1. Include required notices, reports, and list of attendees at meetings; include Architect and Owner in distribution.

C. Verify characteristics of interrelated operating equipment are compatible; coordinate work having interdependent responsibilities for installing, connection to, and placing such equipment in service.

01 31 00 - 2 Project Management and Coordination

D. Coordinate space requirements and installation of mechanical and electrical work indicated diagrammatically on Drawings.

1. Follow routing shown for pipes, ducts, and conduits as closely as possible; make runs parallel with lines of building.

2. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

E. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated, coordinate locations of fixtures and outlets with finish elements.

F. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities and activities of other contractors to avoid conflicts and ensure orderly progress of Work.

1.3 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings for areas where space availability is limited and necessitates maximum utilization of space for components and where separate entities, products, and materials require coordination.

1. Require each subcontractor with items located in ceiling space to furnish coordination drawings of their items to assist in preparation of Contractor’s Coordination Drawings.

2. Indicate relationship of components shown on separate Shop Drawings.

3. Indicate required installation sequences.

4. Ceiling Spaces: Take special care to coordinate structure, ceiling systems, equipment located in ceiling spaces, fire protection systems, mechanical systems, and electrical systems.

B. Staff Names: Immediately after receipt of notice to proceed or immediately after signing of Contract by Owner and Contractor, submit list of principal staff assignments, including superintendent and other personnel in attendance at Project site.

1. Post copies of list in Project meeting room, in temporary field office, and by each temporary telephone.

1.4 SUPERVISORY AND ADMINISTRATIVE PERSONNEL

A. Provide supervisory personnel, in addition to Project Superintendent, as required for proper and timely performance of Work and coordination of subcontracts.

B. Provide administrative staff as required to allow Project Superintendent and supervisory personnel to allocate maximum time to Project supervision and coordination.

01 31 00 - 3 Project Management and Coordination

1.5 PROJECT MEETINGS

A. Schedule and administer Project meetings throughout progress of Work:

1. Pre-construction meeting.

2. Progress meetings at weekly intervals.

3. Pre-installation conferences.

4. Coordination meetings.

5. Special meetings.

B. Make physical arrangements for meetings, prepare agenda with copies for participants, preside at meetings, record minutes, and distribute copies within two days to Architect, Owner, participants, and those affected.

C. Attendance: Job superintendent, major subcontractors, and suppliers as appropriate to agenda; Architect, Owner, and Owner and Architect’s consultants as appropriate to agenda topics for each meeting.

D. Suggested Agenda: Review of Work progress, status of progress schedule and adjustments, delivery schedules, submittals, requests for information, maintenance of quality standards, pending changes and substitutions, and issues needing resolution.

01 40 00 - 1 Quality Requirements

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This section describes general quality control requirements.

1. General quality control.

2. Manufacturers' field services.

3. Mock-ups.

4. Independent testing laboratory services and inspections.

B. Related Requirements:

1. Refer to applicable codes and Specifications sections for test requirements.

1.2 QUALITY CONTROL, GENERAL

A. Maintain quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.

1.3 MANUFACTURERS’ FIELD SERVICES

A. When specified in respective Specification sections require manufacturer or supplier to have qualified personnel to provide on-site observations and recommendations.

1. Observe field conditions, including conditions of surfaces and installation.

2. Observe quality of workmanship.

3. Provide recommendations to assure acceptable installation and workmanship.

4. Where required, start, test, and adjust equipment as applicable.

B. Representative shall submit written report to Architect and Owner, listing observations and recommendations.

1.4 MOCK-UPS

A. Erect field samples and field mock-ups at locations on site as approved in advance and in accordance with requirements where included in Specifications section.

1. Test mock-ups requiring special equipment may be erected at location having access to necessary equipment. Coordinate with Architect.

B. Field samples and mock-ups not approved and not capable of being acceptably revised shall be removed from site.

C. Approved field samples and mock-ups may be used as part of Project.

01 40 00 - 2 Quality Requirements

1.5 TESTING LABORATORY SERVICES AND INSPECTIONS

A. Testing laboratory services and inspections specified and required by applicable codes and regulations will be performed by firms independent of firms related to construction operations and shall be acceptable to applicable authorities.

1. Notify Owner immediately where potential conflict of interest may be involved with testing laboratories or inspection services for Project.

2. Owner or Architect may also require independent testing of items where doubts exist that product or system does not conform to Contract Documents.

3. Owner will employ and pay for testing laboratory and special inspectors to provide Project specific testing and inspections under applicable codes and Specification sections except where indicated otherwise.

a. Owner employment of testing laboratory and inspectors shall not relieve Contractor of obligation to perform Work in accordance with requirements of applicable codes and Contract Documents.

1) Laboratory and inspectors may not release, revoke, alter, or enlarge on requirements of Contract Documents.

b. Retesting required because of non-conformance to specified requirements shall be performed by Owner's testing laboratory.

1) Payment for retesting shall be charged to Contractor by deducting inspection and testing charges from Contract amount.

c. Owner provided testing shall be limited to Project specific testing and shall not include general tests or approvals of materials, equipment, or systems.

d. Owner-provided inspections shall be limited to Project design team inspections and special inspectors required by applicable authorities.

B. Perform services in accordance with requirements of governing authorities and with specified standards.

C. Reports will be submitted to Architect in duplicate giving observations and results of tests and inspections, indicating compliance or non-compliance with specified standards and with Contract Documents.

1. Where required, testing laboratory and inspectors will submit copy of tests and inspections directly to enforcing agency.

D. Contractor shall cooperate with testing laboratory and inspection personnel; furnish tools, samples of materials,…