B1 Enclosure A Draft Contract 476517 with attachments.pdf

PDF 2 MB Posted

Attached to
Dilution Refrigerator
Solicitation number
BSA476517
Issued by

About this file

This is a federal procurement contract between Brookhaven Science Associates (BSA) and an unnamed contractor for the design, manufacture, installation, commissioning, and training of one Ultralow Temperature Quantum Materials/Devices measurement system (UTQMD) cryogenic dilution refrigerator. The contract number is 476517, designated as Firm Fixed Price, with the overall value amount, period of performance, and specific pricing to be determined (TBD). Mark Brock of BSA serves as the contractual representative.

The contractor must provide a fully integrated cryogen-free dilution refrigerator system equivalent to or superior to a Bluefors Oy LD250 model, featuring a Cryomech PT425-RM pulse tube cryocooler with remote motor, integrated 14 Tesla superconducting magnet, gas handling system with automatic circulation, bottom-loading fast sample exchange capability, extensive DC and RF wiring infrastructure, optical access ports, microwave readout module, and comprehensive control software with programmable logic controller (PLC) system. The system must achieve base temperatures below 10 milliKelvin with typical cooling power of 14 microwatts at 20 mK, support both electronic transport measurements and RF dielectric-loss characterization, and demonstrate proven low-maintenance operation suitable for general user access at a National Science Research Center.

Key deliverables include program plan (week 2), preliminary technical design (week 4), final technical design (week 5), equipment footprint and laboratory requirements (week 6), manufacturing/inspection/test plan (week 6), factory acceptance testing (week 50), installation work plan and job hazard analysis (week 52), delivery of instrument (week 52), site acceptance testing and commissioning report (week 56), and end-item documentation package with all manuals, test data, and certificates of conformance. The contractor must provide hands-on training for two BSA scientific/technical staff for three working days during commissioning. Payment occurs in eight milestone-based installments upon BSA receipt and acceptance, with Net XX payment terms (30 days for large/foreign businesses, 10 days for small businesses). Freight is FOB BSA National Laboratory, 98 Rochester Street, Upton, New York. All electrical components must be NRTL-certificated, and the contractor must comply with comprehensive quality assurance requirements (BNL-QA-101), environmental safety and health standards (NFPA 70, NFPA 70E, ASME codes), and pressure vessel/piping specifications. The contractor shall provide a one-year warranty on all parts and labor commencing with BSA's acceptance and maintain remote diagnostic support availability within 24 hours during regular workdays.

View the file

Other files

File Type Posted
B1 Enclosure C Quotation Pricing Sheet.docx DOCX document
B1 Enclosure D ACH Authorization Form.pdf PDF
B1 Enclosure E_W9 Form.pdf PDF
B1 476517 RFQ.pdf PDF
B1 Enclosure F_W8 Form.pdf PDF
B1 Enclosure B AMS-FORM-050.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 9, 2025 1 Rev. 10

BSA’s Contractual Representative

Overall Value Amount

Contract Type Contract Number

Mark Brock TBD Firm Fixed Price 476517

BROOKHAVEN NATIONAL LABORATORY

Brookhaven Science Associates

P.O. Box 5000

UPTON, L.I., N.Y. 11973-5000

Name and Address of Contractor

CONTRACT

This Contract (the “Contract”) is between the party named above (the “Contractor”), and Brookhaven Science Associates, LLC (“BSA”), the latter acting under a Prime Contract (DE- SC0012704) with the United States of America (the “Government”) represented by the United States Department of Energy (“DOE”).

I. SCOPE OF WORK

The Contractor shall provide one Dilution Refrigerator (Ultralow Temperature Quantum Materials/Devices measurement system (UTQMD)).

All work shall be conducted in strict accordance with the attached BSA, Statement of Work, dated 2/27/2026, and Specification No. SPC-UTQMD-CFN-001, dated 02/05/2026.

A. Reports/Deliverables: The Contractor shall provide the following deliverable(s) to BSA’s Technical Representative (Tech Rep):

Item Deliverable Due 1 Program Plan 2nd week after award of contract 2 Technical and Progress

Teleconference 2nd week after award of contract/monthly

3 Performance Reports 5th of each month after receipt of Program

Plan and within 2 weeks of key project milestones

4 Preliminary Technical Design 4th week after contract award 5 Final Technical Design 5th week after contract award

April 9, 2025 2 Rev. 10

6 Equipment Footprint and Laboratory Requirements

6th week after contract award

7 Manufacturing/Inspection/Test Plan

6th week after contract award

8 Factory Acceptance Testing 50th week after award of contract 9 Installation Work Plan, JHA 52nd week after award of contract 10 Delivery of the Instrument 52nd week after award of contract 11 Site Acceptance Test and

Commissioning Report 56th week after award of contract

II. PERIOD OF PERFORMANCE

This Contract shall be effective as of the date executed by both parties. It shall remain in effect through __TBD________.

III. FIRM FIXED PRICE AND PAYMENT

A. Firm Fixed Price: In full consideration of the Contractor's performance hereunder, BSA shall pay the Contractor the firm fixed price of __TBD__ U.S. Dollars ($0.00).

The said sum shall constitute full compensation for all services and materials furnished hereunder.

B. Payment: Payment will be made upon receipt and approval of properly certified invoices. Payment will be in accordance with the following milestone payment schedule:

Milestone Amount

BSA receipt and acceptance of Preliminary Technical Design Submitted

TBD

BSA receipt and acceptance of Final Technical Design Approved

TBD

BSA receipt and acceptance of Factory Acceptance Test Report

TBD

BSA receipt and acceptance of Installation Work Plan, JHA

TBD

BSA receipt and acceptance of Delivery to BNL

TBD

BSA receipt and acceptance of Commissioning of instrument

TBD

BSA receipt and acceptance of Training on instrument

TBD

BSA receipt and acceptance of Delivery of End Item Documentation Package

TBD

April 9, 2025 3 Rev. 10

Payment terms are Net XX (for large/foreign businesses enter 30, for small businesses enter 10).

Invoices shall be directed to BSA’s Accounts Payable Department via electronic or regular mail.

Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal.

Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov.

Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D.

The Contractor shall indicate the final invoice by clearly marking such invoice as “FINAL.” A copy of the final invoice must be submitted to BSA’s Contractual Representative.

C. Freight: Freight terms shall be (for North American shipments insert: ) FOB BSA

National Laboratory, 98 Rochester Street, Upton, Long Island, New York.

D. Labelling, Packing, and Notification Requirements:

More detailed instructions are available at https://www.bnl.gov/shipping/ or by emailing WarehouseOperations@bnl.gov.

Labeling Requirements

All shipments must comply with the following labelling requirements. Failure to do so may result in delayed payments. Labels must be placed on the upper left portion of the container when possible and contain:

Brookhaven National Laboratory Brookhaven’s Contract Number 98 Rochester St.

Upton, NY 11973 Box Number / Number of Boxes

Packing List Requirements

Every shipping container must include a packing list. The packing list must be clearly identified and affixed to a side of the shipping container. At a minimum, the packing list should contain the following information:

Ship from company name and address Supplier contact name Supplier telephone number Ship to address as instructed by Buyer/Contracts Specialist Brookhaven’s Contract number Part number, description, quantity, unit of measure, and corresponding BNL

Contract line number

April 9, 2025 4 Rev. 10

Special Notification of Delivery

If a shipment is heavier than 3,000 lbs., longer than 8 feet in any direction, or has a high center of gravity, it will require rigging upon receipt and the shipper shall provide a minimum of 3 days’ advance notice of delivery to BNL’s Receiving Department via email to WarehouseOperations@bnl.gov. The shipper must obtain acknowledgement from BNL that delivery notification was received. Failure to contact BNL will result in delays during delivery and any resulting demurrage will be at the shipper’s expense.

Marking of Outer Package

Each shipping container (transport package) with a gross weight equal to or greater than 400 lbs. (180 kilograms) must be marked with the center of gravity location and gross weight on at least one side or end panel. It must also meet the requirements of the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract.

Protection of Material and Equipment

The Contractor shall employ procedures which ensure adequate protection of material and equipment during shipment and while in storage. Such protection shall include special environmental packaging as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the PO or Contract shall comply with the requirements for preservation, packaging, and marking as stated in the latest revision of ASTM Standard D 3951-10, Standard Practice for Commercial Packaging.

Unacceptable Packing Material

Do not use vermiculite as a packaging material inside any shipments to BNL unless required by shipping regulation. “Vermiculite” as defined in this specification means the hydrous, silicate mineral classified as a phyllosilicate that has been expanded by heating. Vermiculite used as a packaging material in shipments must be determined to be free of asbestos (<1% chrysolite, amosite, crocidolite, tremolite, anthophyllite, and actinolite). All shipments containing vermiculite must be accompanied by documentation stating that the vermiculite used is certified asbestos-free. This documentation must be affixed to the outside of the package.

April 9, 2025 5 Rev. 10

Ocean Shipments

Foreign shipments transported via ocean freight must use the 10+2 REQUIREMENTS Form (PDF). The form must be completed by the Contractor 72 hours before departure of the vessel. Send form to the following:

Interfreight Harmonized Logistics, Inc.

Fax: 516-371-6880 bnl@interfreight.net

Brookhaven National Laboratory WarehouseOperations@bnl.gov

Once the form is submitted to customs, an acceptance number will be provided.

Freight will not be loaded onto a vessel without an acceptance number. Failure to submit the 10+2 form may result in fines. It is the Contractor's responsibility to make sure the 10+2 form is submitted 72 hours prior to the vessel sailing. BSA shall withhold payment from the Contractor's final invoice for any penalties incurred by BSA due to late or incorrect ISF filing by the Contractor.

IV. AUTHORIZED REPRESENTATIVES

A. BSA’s Technical Representative: _TBD___________, telephone no.

__TBD________, __TBD_________(email), is BSA's Technical Representative, and shall act as liaison between BSA and the Contractor in technical matters only.

B. BSA’s Contractual Representative: _TBD_______, telephone no.

_TBD__________, _TBD_________ (email), is BSA's Contractual Representative. Any change or modification in the terms and conditions of this Contract shall require the written approval of BSA's Contractual Representative or designee.

C. Contractor’s Technical Representative: _TBD_______, telephone no.

_TBD_________, _TBD__________(email), is the Contractor’s authorized Technical Representative, and shall act as point of contact between BSA and the Contractor in technical matters only.

D. Contractor’s Contractual Representative: _TBD_____________, telephone

no. _TBD_________, _TBD__________(email), is the Contractor’s authorized Contractual Representative and shall act as liaison between BSA and the Contractor.

V. PATENT CERTIFICATION

Upon Contract expiration and completion of all work authorized under this Contract, the Contractor shall complete and execute Attachment D “Patent Certification” clearance form and forward it to the Contractual Representative. Failure to do so may result in the withholding of final payment or a portion thereof.

April 9, 2025 6 Rev. 10

VI. GOVERNMENT PROPERTY Reserved

VII. ADDITIONAL TERMS

The provisions of Brookhaven Science Associates, LLC, General Terms and Conditions for Commercial Items and Services, (Rev 23, May 2025) are incorporated herein and made a part hereof.

The provisions of Brookhaven Science Associates, LLC, General Terms and Conditions for Non-Commercial Items, (Rev.23, May 2025) are incorporated herein and made a part hereof.

The provisions of Brookhaven Science Associates, LLC, Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory, (Rev.23, May 2025) are incorporated herein and made a part hereof. In accordance with Article 8 of these Supplemental Terms and Conditions, the Contractor is required to provide a Phase Hazard Analysis (PHA).

This Contract is issued pursuant to Brookhaven Science Associates General and/or Supplemental Terms and Conditions listed above, which are incorporated herein by reference. The complete text of these terms and conditions can be viewed at PPM | Terms and Conditions. Should the Contractor have any questions and/or not have access to these terms and conditions, contact the Buyer or Contracts Specialist immediately.

The following documents attached hereto and made a part hereof, contain additional provisions of this Contract:

Attachment A Statement of Work, 2/27/2026 Attachment B Specification No. SPC-UTQMD-CFN-001, 2/5/2026 Attachment C BNL QA 101 Attachment D Patent Certification Form

This Contract does not bind nor purport to bind the Government of the United States.

ACCEPTED:

CONTRACTOR BROOKHAVEN SCIENCE

ASSOCIATES, LLC.

By: By: TBD_

Name: Name: Mark Brock

Title: Title: Subcontracts Supervisor

Date: Date: See Electronic Signature

April 9, 2025 7 Rev. 10

The Contractor shall sign and return one (1) copy of this contract via email to the attention of Mark Brock, Procurement and Property Management Division at mbrock @bnl.gov.

STATEMENT OF WORK (SOW)

for

Ultralow Temperature Quantum Materials/Devices measurement system

(UTQMD)

Prepared by:

Date

2/27/2026

Aaron Stein, Technical Representative

Center for Functional Nanomaterials

Approvers:

02/18/2026

Jiho Sung, Staff Scientist, Center for Functional Nanomaterials;

Quality Assurance Nicole Magliulo 2/23/2026

Nicole Magliulo Quality Management Office

ESH Coordinator 02/19/2026

Wai-Lin Ng Center for Functional Nanomaterials

Contents

1. SCOPE

1.1 BACKGROUND

1.2 DEFINITIONS/ACRONYMS

2 APPLICABLE DOCUMENTS

3 REQUIREMENTS

3.1 CONTRACTOR RESPONSIBILITIES

3.1.1 Technical Performance

3.1.2 Tooling/Fixtures/Test Equipment

3.1.3 Factory Acceptance Testing

3.1.4 Installation

3.1.5 Acceptance Testing at BNL

3.1.6 Commissioning

3.1.7 Training

3.2 DESIGN AND DESIGN REVIEW REQUIREMENTS

3.3 MANUFACTURING REQUIREMENTS

3.3.1 Acceptance Test Procedure

3.3.2 Commissioning Reports

3.4 MANAGEMENT

3.4.1 Program Plan

3.4.2 Progress Teleconference

3.4.3 Manufacturing/Inspection/Test Plan

3.4.4 Performance Reporting

3.5 DOCUMENTATION AND DATA MANAGEMENT

3.6 CONFIGURATION MANAGEMENT

3.7 SOFTWARE REQUIREMENTS

3.8 ENVIRONMENT, SAFETY AND HEALTH (ESH)

3.8.1 Contractor Work on Site at BNL

3.8.2 Electrical Safety

3.8.3 Pressure Safety

3.8.4 Fire Safety

3.8.5 Attachment Points and Lifting Fixture

3.8.6 Radio Frequency Safety

3.9 PACKAGING

3.10 WARRANTY

4 QUALITY ASSURANCE

4.1 QUALITY ASSURANCE REQUIREMENTS

4.2 NOTIFICATION OF CHANGE TO DESIGN, METHODS, OR PROCESSES

4.3 RECORDS

4.4 FRANCHISED / LICENSED “DISTRIBUTOR” TRACEABILITY

4.5 MATERIAL REVIEW BOARD (MRB) AUTHORITY

4.6 QA FLOW-DOWN

4.7 CERTIFICATE OF CONFORMANCE

5 DELIVERABLES

6 SCHEDULE/ MILESTONES

7 VALUE ENGINEERING

iii

This page intentionally left blank, to accommodate back-to-back printing.

"This document contains BNL procurement requirements specifications for solicitation and technical evaluation. The information is high-level and does not include the detailes necessary for "development" or "production" as defined under 15CFR § 772.1, 22 CFR §120.33, or 10 CFR Part 810; therefore, it does not constitute export-controlled technology or technical data."

Statement of Work for the Ultralow Temperature Quantum Materials/Device measurement system

1. SCOPE

This Statement of Work (SOW) will be the basis for the procurement of an ultralow temperature quantum materials/devices measurement system (UTQMD) for the Center for Functional Nanomaterials (CFN) & the Co-design Center for Quantum Advantage (C2QA) at Brookhaven National Laboratory. The UTQMD instrument, hereafter referred to as “Instrument” shall be designed as a cryostat with an integrated high-field magnet, providing an ultralow base temperature. The system uses a helium-4 pulse tube to precool to 4K and a helium-3/helium-4 mixture to reach <10 mK temperature. The low temperature helps to minimize thermal fluctuations and thus improve the quantum coherence of the qubits/enable to observe quantum phenomena such as superconductor, exciton condensate physics. It shall support (1) electronic transport and optical spectroscopy of two-dimensional heterostructure devices and (2) RF dielectric-loss characterization using high-Q microwave resonators for superconducting qubit materials – both at temperatures < 10 mK, with expected cooling power of (typical 14 µW) on the experimental flange at 20 mK. The UTQMD should be a cryogen-free (“dry”) dilution refrigerator system and should include two separate vacuum and radiation shield set to support these two measurements. As an instrument offered to general users in a NSRC, the Instrument shall be engineered for safe, user-friendly operation (hardware and control software) and demonstrate a proven track record of low-maintenance, low-downtime operation. This document outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.

1.1 Background

BNL’s mission and vision emphasizes integrating strengths in materials, nanoscale science, photon science, and computer science capabilities and expertise to drive the information science revolution in Quantum

Information Science and Technology (QIST). Consistent with the Lab Plan’s “Future Quantum Materials”

QIST thrust, CFN is developing state-of-the-art instrumentation for the user community, and the UTQMD is expected to create strong synergies with the Quantum Materials Press (QPress) by enabling feedback-driven cycles of materials discovery, device fabrication and low-temperature characterization. This effort will be carried out in partnership with the Co-design Center for Quantum Advantage (C2QA) to align measurement capabilities with quantum information device performance needs. The installation of UTQMD will strengthen BNL’s leadership in quantum materials discovery and characterization.

1.2 Definitions/Acronyms

ASME American Society of Mechanical

Engineers

ATP Acceptance Test Procedure

BNL Brookhaven National Laboratory

BSA Brookhaven Science Associates

C2QA Co-design Center for Quantum

Advantage

CFN Center for Functional Nanomaterials

DC Direct Current

DR Dilution Refrigerator

ESH Environment, Safety, and Health

FAT Factory Acceptance Test

GHS Gas Handling Unit

GUI Graphic User Interface

JHA Job Hazard Analysis

MRB Material Review Board

MRP Material Requirements Planning

MXC Mixing Chamber

NFPA National Fire Protection Association

NRTL Nationally Recognized Test Laboratory

QA Quality Assurance

QIST Quantum Information Science and

Technology

QPress Quantum Materials Press

RF Radio Frequency

SOW Statement of Work

UTQMD Ultralow Temperature Quantum

Materials/Devices Measurement System

2 APPLICABLE DOCUMENTS

In the event of a conflict between the Technical Specification and the SOW, the Contractor shall immediately notify the BSA Contractual Representative who shall in each instance determine which document takes precedence and advise the Contractor accordingly. Failure to notify BSA of a document conflict shall not relieve the Contractor’s responsibility to ensure full compliance to all requirements.

The following documents are an integral part of the SOW; the applicable revision level will be the latest that is in effect at the time of award:

Document Number Document Title

10CFR851 DOE Worker Safety and Health Program

BNL QA-101 Supplier Quality Assurance Requirements

ASME B30.26 Rigging Hardware

ANSI Z136.1 Safe Use of Lasers

ASME BPV Boiler and Pressure Vessel Code

ASME B31.3 Process Piping -2015 Edition

NFPA 70

National Electrical Code – 2020 Edition http://www.nfpa.org/aboutthecodes/AboutTheCodes.asp?DocNum=70

NFPA 70E

Standard for Electrical Safety in the Workplace – 2021 Edition or the most current version in place

ASMEY14.5M-2008 Dimensioning and Tolerancing

JHA BNL Job Hazard Analysis Template (Attached)

3 REQUIREMENTS

In accordance with the applicable specifications, referenced documents, and instructions as defined in this Statement of Work, the contractor shall be responsible for the engineering, purchase of all materials, manufacturing, assembly, inspecting, testing, delivering, installing, commissioning and training on the Instrument.

Safety and code compliance must be paramount at every stage of a project, from the initial concept to the final installation and use. Electrical design and installation must follow the National Electrical Code NFPA 70 and

Standard for Electrical Safety in the Workplace NFPA 70E.

Statement of Work for the Dilution Refrigerator for Superconducting Quantum Circuits

3.1 Contractor Responsibilities

3.1.1 Technical Performance

In accordance with SOW/Technical Specification document and all referenced documents, the

Contractor shall engineer, manufacture and assemble the Instrument. The Contractor shall first test the Instrument at the Contractor’s facility, then deliver, test and commission the Instrument at BNL.

It is the Contractor’s responsibility to ensure that the Instrument complies with all the specification requirements and the safety codes and standards referenced herein.

3.1.2 Tooling/Fixtures/Test Equipment

The Contractor shall be responsible for supplying all materials, including (but not limited to) the construction of all tools, jigs, fixtures, and test equipment required to complete the engineering, manufacturing, assembly, inspecting, testing, delivering, and installing the Instrument. Gases, cryogens, and samples for testing will be supplied by BNL.

3.1.3 Factory Acceptance Testing

The Instrument shall be tested at the Contractor’s facility to demonstrate full compliance with the

SOW/Technical Specification. The Instrument shall be fully assembled and be representative of the final as-delivered configuration for Final Acceptance Test (FAT). The tests listed in the SOW/

Technical Specification shall be conducted on the Instrument at the Contractor’s facility according to the approved Acceptance Test Procedure (ATP), prior to delivery to BNL.

All test data shall be documented in the Factory Acceptance Test report and sent to BSA prior to the

Instrument delivery. Acceptance of the test data is contingent upon data review and written approval by BSA technical representative prior to shipment of the Instrument.

3.1.4 Installation

3.1.4.1. The Contractor shall provide a footprint of the Instrument and utilities requirements.

3.1.4.2. The Contractor shall be responsible for all Instrument installation. BSA will not supply personnel for installation tasks other than identified herein. Unloading of containers and trucks, and staging of the Equipment at the installation site, shall be performed by BSA riggers. The Contractor shall not be permitted to drive BSA-owned forklifts for any reason. The Contractor shall submit an installation work plan that includes all onsite installation activities in a step-by-step format at least two months before the scheduled start of installation activities. This plan is a necessary prerequisite for obtaining a work permit and must be approved by BSA prior to the start of installation activities. The person

(or persons) responsible for all onsite installation activities shall participate in the work planning process for the purpose of obtaining a work permit. This shall be completed during the Technical Review as well as after the Technical Review in video conferencing and/or teleconferences.

3.1.4.3. All training and safety requirements identified during the work planning process (or by

BSA ES&H/Training staff members) shall be successfully completed by Contractor personnel who are participating in onsite installation work prior to issuance of a work permit and prior to installation.

3.1.4.4. BSA shall be responsible for offloading and rigging of heavy equipment. Contractors may operate their own rigging/cranes that are installed as part of their equipment, original equipment manufacturer (OEM) components. These must first be inspected by BSA.

3.1.4.5. Electrical tools/equipment needed for installation shall be inspected by BSA prior to use at BNL, to ensure compliance with electrical safety standards referenced herein.

3.1.4.6. The Installation Work Plan shall include at a minimum:

a. Work instructions/ installation plan: job steps or detailed step-by-step instructions

b. Prerequisites: preparatory actions to be performed before work can be started and any administrative and physical requirements (for example, review/ inspection/ approval of equipment, training, etc.)

c. Precautions: Identify hazards and precautions that must be observed during performance of work in the Job Hazard Analysis (JHA)

d. Identification for hold points and other monitoring

e. Operational limits imposed

f. Coordination of tasks

g. Special conditions for working alone

h. Scheduling, coordination, and notification

i. Changes impacting configuration management

j. ES&H work controls for mitigating identified hazards based on the following hierarchy, as practical:

i) Elimination/substitution of hazards

ii) Engineering controls

iii) Administrative controls and work practices

iv) Personal protective equipment

3.1.4.7. Note that disposal of waste packing material shall be the responsibility of BSA.

3.1.4.8. The Contractor shall supply all bolt-on wheels, transportation carts and custom tooling required for the installation of the Instrument which will remain the property of the

Contractor at Contract Completion.

3.1.4.9. During assembly of all components, proper alignment and tightening shall be assured by the use of appropriate tools (e.g., torque wrenches) and by following the procedures recommended by the manufacturer, including the use of alignment tools and bolt-tightening sequences, etc.

3.1.4.10. Installation includes hardware and software setups for computer-based control of the

Instrument.

3.1.5 Acceptance Testing at BNL

The Instrument shall be tested at BNL by the Contractor to demonstrate full compliance with this

SOW and theTechnical Specification documents. The tests listed in the SOW and the Technical

Specification documents shall be conducted on the Instrument at BNL according to the ATP, prior to final acceptance.

3.1.6 Commissioning

The Contractor shall be responsible for the commissioning of the Instrument. Commissioning shall be defined as all test and demonstration work performed on site at BNL. Commissioning of the

Instrument on site in its final configuration shall be performed with samples supplied by BSA and agreed to by Contractor. The Instrument shall be able to demonstrate the performance specifications as outlined in the separate Technical Specification document.

3.1.7 Training

During the commissioning phase of the contract, the Contractor shall provide hands-on training at

BNL for two (2) BSA scientific and/or technical staffs for the safe operation and maintenance of the

Instrument. This training shall be conducted at BNL for a period of three (3) working days during commissioning for the Instrument.

3.2 Design and Design Review Requirements

3.2.1 Preliminary Design Report

A preliminary design to meet all the technical requirements shall be presented to BNL staff. A three-dimensional depiction in .easm file, CAD file, or similar format, shall be provided to BNL. A video conference meeting shall be held to discuss the design and facilitate questions. Changes to be incorporated shall be agreed upon by both BNL and the Contractor.

3.2.2 Final Design Report

A final design that incorporates and documents changes from the preliminary design shall be submitted to BNL. The final design shall be a three-dimensional depiction in .easm file, CAD file, or similar format. The instrument design in an .easm file or similar format shall be submitted. A video conference may be convened if deemed necessary.

3.2.3 Approval to Proceed

BSA must approve in writing the final design, including any modifications introduced at the Final

Design Review Meeting before the Contractor proceeds with ordering material and components.

3.3 Manufacturing Requirements

3.3.1 Acceptance Test Procedure

The contractor shall provide an ATP that is in accordance with this SOW/Technical Specification and all reference documents noted herein. The ATP must be approved by BSA prior to use. The

ATP shall ensure that all test requirements as defined in the safety codes referenced herein are achieved.

3.3.2 Commissioning Reports

A Commissioning report shall be provided by the Contractor. The report shall include, but not limited to, the results of all tests performed including graphs, printouts, drawing updates, calibration data, and control system tuning parameters. The Contractor shall be responsible for remedying any noncompliance regarding the requirements in this SOW/Technical Specification, subject to BSA approval. A summary sheet including demonstrated remedy of any non-compliances shall be included. Final acceptance is contingent on BSA data review and written approval by BSA.

3.4 Management

3.4.1 Program Plan

Within the timeframe listed in Section 5, the Contractor must deliver a detailed program plan which includes a milestone schedule defining the design validation, manufacturing, inspection, testing, installation and commissioning phases in sufficient detail to allow regularly scheduled progress monitoring. It shall be submitted for review and approval by BSA within the timeframe indicated in the Contract.

3.4.2 Progress Teleconference

Beginning within the timeframe listed in Section 5, monthly program technical and progress teleconferences and/or meetings between the Contractor and BSA shall be held at a mutually scheduled time. The discussions shall include the Contractor’s progress, technical and contractual questions, presentations of analysis or testing results, design reviews, value engineering, trouble shooting, material status, tooling status, resources, and manufacturing issues.

3.4.3 Manufacturing/Inspection/Test Plan

A manufacturing plan shall be developed, which identifies the manufacturing processes of work required to complete all efforts as identified in this SOW. It shall be submitted for review and approval by BSA within six (6) weeks after award of contract. The plan my be a single document, or may make use of existing travelers or other suitable planning and control documents. It shall address the Material Requirements Planning (MRP), and at a minimum include manufacturing, inspection, and test steps including identification of critical manufacturing operations and parts/subassemblies showing integrated flow into the end item(s). If the Contractor does not have an MRP system in place, then details for purchasing all raw materials, shop loading (by work center), and a schedule for manufacturing all components and assemblies through packaging and shipping shall be provided by the Contractor.

3.4.4 Performance Reporting

Throughout the life of the contract, the Contractor shall supply a written report by the fifth of every month to the BSA technical representative and contractual representative clearly detailing progress through the prior month with respect to the program. This shall include milestone charts, detailed progress, open items, problems, recommended solutions, and risk mitigation.

3.5 Documentation and Data Management

3.5.1 All the documentation provided by the Contractor shall be in English.

3.5.2 All engineering drawings shall:

a. Be formatted in accordance with ASME Y14.5M-2008

b. Have views shown in third angle projection

c. Preferably use metric dimensions and tolerances

d. Have a separate parts list

e. Have part number designations in accordance with LT-ENG-RSI-STD-002

3.5.3 The Contractor shall provide an electronic copy (email, plus either CD ROM or USB data storage device) of all required documentation as noted in this SOW. Manufacturing drawing CAD files of all components and assemblies shall be in any of these formats: STP, SAT, IGS, IAM, or IPT.

3.5.4 End Item Documentation Package

The Contractor shall provide an electronic copy of the End Item documentation package in accordance with the schedule set forth in this SOW. The End Item documentation package shall consist of the following documentation:

a. Acceptance Test Reports and copies of test certificates

b. All manuals

c. Completed travelers (documents following instrument throughout manufacturing process)

d. Manufacturing/ Inspection/Test data for inspections performed at incoming inspection or during manufacturing

e. Certificate of Conformance as specified in Section 4

f. Copies of specification/ data sheets for viewports.

g. Copies of the Contractor’s (or Subcontractors’) weld certification/test reports

h. Documentation of required proof test procedures and results for vacuum vessels

i. Certification that all required pressure relieving devices used are approved by either the

ASME or National Board of Boiler Inspectors (NBBI)Acceptance Test Reports and copies of test certificates

3.5.4.1 Documents

The Contractor shall provide an electronic copy (on a USB stick or BSA identified

FTP site, in Microsoft Office format, or drawing format described in section 3.4 with formal “controlled copies” in PDF format) of the following documentation:

a. All documentation identified in this SOW

b. All parts and assembly solid models

c. User/operational manual

3.5.4.2 Operation and Maintenance Manuals

The Contractor shall provide the operation and maintenance manual in electronic format with formal PDF format on a USB stick and provide two (2) hardcopies.

Operation and maintenance manuals shall include:

3.5.5 A title to the front cover, identifying the title of the project and the date of issue

3.5.6 A table of contents

3.5.7 A general description of the Instrument installation

3.5.8 Copies of any permits to use copyrighted material

3.5.9 A technical description of each system and subsystem to allow the correct and safe operation, maintenance and repair of all systems and subsystems installed, including:

i. Operating manuals at all modes of operation described in

Technical Specification document

ii. Standard maintenance operations not limited to beam alignment and adjustment of lens operations

iii. Trouble shooting techniques

iv. Recommendations for preventive maintenance

v. Disassembly, repair, cleaning and adjustment procedures

vi. List of recommended spare parts to keep on hand

vii. Software documentation and source code for open-source processing routines

3.6 Configuration Management

The Contractor shall establish and maintain a configuration control system to assure that all end items

(including spares) are of the proper configuration, and that all approved configuration changes are incorporated at the specified effectivity points. Records shall be maintained verifying the configuration of each item.

3.7 Software Requirements

The Contractor shall provide and maintain the capability to receive and send CAD files of all components or assemblies in STP, SAT, IGES, IAM, or IPT file format at the request of BSA.

3.8 Environment, Safety and Health (ESH)

The Contractor shall design and build all equipment in accordance with ESH requirements in the appropriate specifications, codes, standards, and other documents listed in Section 2 of this SOW.

3.8.1 Contractor Work on Site at BNL

BSA will identify and designate space necessary to safely perform staging and installation activities.

Any cordons, stanchions, or barriers required to designate and isolate the Contractor’s work area will be supplied by BSA.

Contractor shall submit a Job Hazard Analysis (JHA) identifying work hazards associated with the installation of the instrument including a list of hazardous materials and Safety Data Sheets (SDS) to BSA for approval with the Installation Work Plan.

3.8.2 Electrical Safety

3.8.2.1 All electrical equipment and components must be manufactured in accordance to

U.S. standards and comply with NFPA70. The instrument shall be listed by a

Nationally Recognized Testing Laboratory (NRTL). If the instrument is not

NRTL-listed, the Contractor shall arrange for a third-party NRTL Field

Evaluation to be done onsite at the completion of installation. The cost of the field evaluation shall be included in the quote. Any additional charges require BNL’s prior written approval. Note that CE is not on the list of OSHA approved NRTLs.

A report on the results of the field evaluation must be provided to BNL’s Electrical

Authority Having Jurisdiction (AHJ), and approved before the equipment is to be energized.

3.8.2.2 The contractor shall supply the following to BSA:

3.8.2.2.1 Documentation for the equipment installation, operation, service and maintenance that describes operation, shutdown, safety concerns, and nonstandard installations

3.8.2.2.2 Schematics, drawings, and bill of materials describing power feeds, voltages, currents and parts used for construction, maintenance, and operation of the equipment.

3.8.2.2.3 Safety Requirements and emergency shutdown procedures of equipment including lockout/tagout (LOTO) requirements.

3.8.2.2.4 Documentation of specific hazards associated with the equipment.

3.8.2.2.5 Documentation shall be provided if special tools, PPE, or other equipment is necessary for proper maintenance and operation of equipment.

3.8.2.3 The contractor shall include safety-related design concepts for electrical equipment and installations. Following methods can be considered:

3.8.2.3.1 Installing finger-safe components, covers, and insulating barriers to reduce access to exposed energized electrical conductors and circuit part due to inadvertent movement

3.8.2.3.2 Substituting ≥50 volts control circuit with non-hazardous <50 volt circuits.

3.8.2.3.3 Separate enclosures for hazardous and non-hazardous electrical conductors and circuit parts.

3.8.2.4 The Contractor shall ensure that the equipment is marked with the NRTL certification or Field Evaluation label to include the manufacturer, model #, manufacturing date, drawing number, current draw, power, frequency voltages entering and leaving the control cabinets, and equipment. Caution, Warning, or

Danger labels shall be affixed to the exterior describing specific hazards and safety concerns. Refer to ANSI Z535, Series of Standards for Safety Signs and

Tags, for more information on precautionary labeling of electrical system or equipment

3.8.2.5 All exposed electrical connections/terminations ≥50 volts shall be covered so that workers are protected from the hazards of electrical shock during operation and when performing service & maintenance. Plexiglas® is not allowed; Lexan® may be used for inadvertent contact. Electrical insulation must be Low Smoke, Zero

Halogen (LSZH), Fire Retardant, and rated for its application. Non-LSZH cables shall be permitted in length <50 feet.

3.8.2.6 The contractor shall include safety-related design concepts for electrical equipment and installations. Following methods can be considered:

3.8.2.6.1 Installing finger-safe components, covers, and insulating barriers to reduce access to exposed energized electrical conductors and circuit part due to inadvertent movement.

3.8.2.6.2 Substituting ≥50 volts control circuit with non-hazardous <50 volt circuits.

3.8.2.6.3 Separate enclosures for hazardous and non-hazardous electrical conductors and circuit parts.

3.8.2.7 Electrical wiring must be installed in a neat and workmanlike manner.

3.8.2.8 Teflon® shall not be used as an insulation material, except in small quantities

3.8.3 Pressure Safety

For process piping requirements, the contractor shall use ASME B31.3 or equivalent approved by BSA in writing. The liquid nitrogen, gaseous nitrogen, and cooling water lines shall be designed to ASME B31.3 requirements. In all cases, 100% proof testing shall be completed on each component to 150% of the maximum working pressure for hydrostatic tests, or 110% of the maximum working pressure for pneumatic tests.

To prevent inadvertant overpressurization of vacuum vessel(s), the system must be supplied with burst disk per ASME BPVCode.

3.8.4 Fire Safety

3.8.4.1 The Contractor shall ensure that any electrical equipment or wiring minimizes combustibility by the use of flame-resistant materials.

3.8.4.2 The Contractor shall ensure that any cable tray minimizes the possibllity to damage cables. All cables to be installed in a cable tray shall be rated for Cable

Tray use. The cable shall have the TC (Tray Cable) and NRTL markings. If a

Contractor elects to use a cable not marked for Tray Cable use, then the

Contractor shall use a cable that will meet IEEE 1202 or equivalent approved by BSA in writing. BSA shall approve the use of all non-NRTL marked tray cables in advance of the Contractor ordering the cable.

3.8.4.3 All other cables shall be Low Smoke Zero Halogen (LSZH). Non-LSZH cables shall be permitted in length <50 feet.

3.8.5 Attachment Points and Lifting Fixture

3.8.5.1 The Contactor shall provide lifting eyes, either permanent or removable, on each piece of equipment or stand of sufficient capacity and number to allow the equipment to be safely lifted.

3.8.5.2 All lifting fixtures must meet the requirements specified in ASME B30.26 (Rigging

Hardware) and ASME BTH-1 (Design of Below-the-Hook Lifting Devices, Design

Category “A”).

3.8.6 Radio Frequency Safety

Any component using radio frequencies (i.e. plasma sources), should be labeled with the appropriate warnings following 29 CFR 1910.97 - ANSI C95.2-1982. Once installed radiofrequency radiation exposures limits shall not exceed Threshold Limit Values

(ACGIH TLV – 2016) and Safety Levels (ANSI/ IEEE C95.1).

3.9 Packaging

In preparation for shipping, the Instrument shall be covered or wrapped for protection against weather elements, dust, and damage to projections, shock loads, impacts, and rubbing. The Instrument shall be properly braced and cushioned within the packing so that it will not shift during handling and shipment. The method of shipping will be specified by BSA one month prior to delivery.

3.9.1 After the component or piece of the Instrument has been cleaned and tested, it shall be packed to ensure that it remains clean and free from damage during both storage and shipping. All seal faces and/or knife edges should be protected. Vacuum components shall be backfilled with dry nitrogen gas.

3.9.2 Added protection against contamination and humidity shall be given to the sensors and electrical connections. Durable materials, such as clean wood, bubble wrap, or similar non-contaminating materials, are to be used to support and protect the components from one another during transit and storage. Peanut-type material shall not be used for packaging.

3.9.3 All assemblies or sub-assemblies with moving parts shall be secured to prevent damage due to unwanted motion or vibration. The packaging must be designed to withstand acceleration loads in excess of twice the acceleration due to gravity (>2g0).

3.9.4 Each packing crate shall be fitted with Shockwatch and Tipwatch sensors or an equivalent approved in writing by BSA.

3.9.5 The container shall be appropriately labeled with the listing of contents, destination, gross weight, location of center of gravity, purchase order number, and contact information.

3.10 Warranty

The Contractor shall provide a one-year warranty on all parts and labor commencing with BSA’s acceptance of the installed and tested Instrument. A recommended spare parts list shall be available from the Contractor.

Remote diagnosis and troubleshooting from Contractor shall be available upon request within 24 hours during regular workdays.

4 QUALITY ASSURANCE

The Contractor shall maintain and apply an effective QA program for the design, manufacture, and testing of all systems and equipment provided.

4.1

4.2

Quality Assurance Requirements

BSA Form BNL-QA-101, "Brookhaven National Laboratory Supplier Quality Assurance Requirements," forms a part of this statement of work. Specifically, this includes the following sections:

1, 2, 3, 3.1, 3.1.3, 3.1.4, 3.2 to 3.22, 4.0, 4.1, 4.2, 4.7, 4.7.1, 4.7.3, 4.10, 4.10.1, 4.16, 4.19, 4.21, 4.31, 4.34, 4.37, and 4.39.

Notification of Change to Design, Methods, or Processes

The Supplier shall immediately notify the Buyer of any significant changes (those that may affect form, fit, function, reliability, safety, or interchangeability) in product design, fabrication methods, materials, or processing from those used by the Supplier at time of Supplier’s quotation or offer to the Buyer, which resulted in the PO.

4.3 Records

The Supplier shall retain objective evidence, including records, of the inspections and tests performed in the course of manufacturing, testing, inspecting, preserving, packaging, and preparation for shipment of procured items. These records shall be made available to the Buyer’s representative for review upon request. These records shall be maintained for a minimum of three (3) years, unless otherwise specified in the procurement documentation, after the completion of the PO/contract.

4.4 Franchised / Licensed “Distributor” Traceability

Products that are not purchased directly from the Original Equipment Manufacturer (OEM)/Original

Component Manufacturer (OCM) must be purchased only from a franchised/licensed distributor of the product being offered. The distributor shall ensure traceability of all products to the original equipment manufacturer by identifying the original manufacturer for each lot/date code on the Certificate of

Conformance. The distributor shall provide a copy of the Manufacturer’s certificate for the lot number being supplied, along with their franchised distributor certification. The distributor shall not use unapproved brokers (any company, person, or entity who is not an OEM/OCM) for the purchase of components and parts, unless pre-approval has been granted by Brookhaven Science Associates (BSA).

4.5 Material Review Board (MRB) Authority: Reserved

4.6 QA Flow-Down

The Contractor shall ensure a proper and complete flow-down of all applicable QA requirements to its suppliers and sub-tier suppliers.

4.7 Certificate of Conformance

With each shipment, the Contractor shall submit a Certificate of Conformance (C of C). In case of drop shipment, a copy of the certificate shall be submitted to BSA at the time of shipment. The certificate shall include the title of and be signed by an authorized representative of the company, and shall constitute a representation by the Contractor that:

A. Materials used are those which have been specified by BSA, and that the items delivered were produced from materials for which the Contractor has on file, reports of chemical or physical analysis, or any other equivalent evidence of conformance of such items to applicable specifications;

B. Processes used in the fabrication of items delivered were in compliance with applicable specifications included as part of the PO/contract, or BSA-approved procedures or specifications;

C. The items as delivered comply with all applicable drawings, specifications, deviations/waivers, and other requirements of the procurement documentation; and-

D. When specified, cleaning and cleanliness requirements have been completely satisfied. The C of C shall reference the Contractor’s applicable cleaning procedures.

5 DELIVERABLES

The Contractor shall supply the following:

Item Deliverable Due

BSA

Approval

1 Program Plan 2nd week after award of contract Yes

2 Technical and Progress Teleconference 2nd week after award of contract/monthly No

3 Performance reports

5th of each month after receipt of Program

Plan and within 2 weeks of key project milestones

No

4 Preliminary Technical Design 4th week after contract award Yes

5 Final Technical Design 5th week after contract award Yes

6 Equipment footprint and laboratory requirements 6th week after contract award Yes

7 Manufacturing/Inspection/Test plan 6th week after contract award Yes

8 Factory acceptance testing 50th week after award of contract Yes

9 Installation Work Plan, JHA 52nd week after award of contract Yes

10 Delivery of the Instrument 52nd week after award of contract Yes

11 Site Acceptance Test and Commissioning Report 56th week after award of contract Yes

6 SCHEDULE/ MILESTONES

The following schedules are for planning purposes only. Schedule requirements set forth in the contract will take precedence.

Milestone Calendar weeks after award

Preliminary Technical Design Submitted 4th week

Final Technical Design Approved 5th week

Factory Acceptance Test Report 50th week

Installation Work Plan, JHA 52nd week

Delivery to BNL 52nd week

Commissioning of instrument 55th week

Training on instrument 55th week

Delivery of End Item Documentation Package 55th week

7 VALUE ENGINEERING

The Contractor is encouraged to make recommendations for changes that might lead to an improvement in performance, reliability, quality, safety, or reduction in cost. Simplicity in operation, ease of maintenance, and an improvement in the performance and reliability of the specific functions beyond the requirements of this specification are objectives which shall be considered in the production. Where it appears a substantial improvement in simplicity of design, performance, ease of maintenance or reliability will result from the use of materials, parts and processes other than those specified, it is desirable that their use be investigated.

Ultralow Temperature Quantum Materials/Devices measurement system Technical Specification

QA Category: A-2

CENTER FOR FUNCTIONAL

NANOMATERIALS

BROOKHAVEN NATIONAL

LABORATORY

BROOKHAVEN SCIENCE ASSOCIATES

UPTON, LONG ISLAND, N.Y. 11973

PROJECT:

Ultralow Temperature Quantum Materials/Devices measurement system

Technical Specification

Version 1

SPC-UTQMD-CFN-001 Feb. 05, 2026

Document Number Date

Jiho Sung

CFN Staff Scientist

Signed by: Sung, Jiho

Aaron Stein

CFN

Chief of Staff

Signed by: Stein, Aaron

Wai-Lin Ng

CFN ES&H

James Buddenhagen

CFN Operations

Nicole Magliulo 2/23/2026

Nicole Magliulo

Quality Assurance

Kevin Yager

CFN Director

VERSION CONTROL SHEET

VERSION DESCRIPTION DATE AUTHOR APPROVED BY

1 First Release Feb. 05, 2026 J. Sung See cover sheet.

“This document contains BNL procurement requirements and specifications for solicitation and technical evaluation. The information is high-levl and does not include the details necessary for "development" or "production" as defined under 15 CFR § 772.1, 22 CFR § 120.33, or 10 CFR Part 810; therefore, it does not constitute export-controlled technology of technical data.”

Contents

1. INTRODUCTION

1.1 Overview

1.2 Definitions

2. SCOPE OF SUPPLY

2.1 General Information

3. CONFIGURATION & PERFORMANCE REQUIREMENTS

3.1 Pulse tube cryocooler and compressor

3.2 Cryostat and radiation shields

3.3 Gas handling system

3.4 Control and diagnostics

3.5 Bottom loading fast sample exchange

3.6 Experimental wiring

3.7 Cryogen-Free magnet

3.8 Optical access ports

3.9 Microwave readout module

3.10 Service feature, system installation and commissioning

4. OPTIONAL ITEMS

4.1 System care service

5. OTHER REQUIREMENTS

5.1 Magnetic fringe field

5.2 Delivery and Installation

CENTER FOR FUNCTIONAL

NANOMATERIALS

BROOKHAVEN NATIONAL LABORATORY

BROOKHAVEN SCIENCE ASSOCIATES

UPTON, LONG ISLAND, N.Y. 11973

PROJECT:

Ultralow Temperature Quantum Materials/Device measurement system Technical Specification

Version 1

SPC-UTQMD-CFN-001 Feb. 05, 2026

Document Number Date

Intentionally left blank

1. INTRODUCTION

1.1 Overview

The ultralow temperature quantum materials/devices measurement system (“UTQMD”) is a cryogen-free dilution-refrigerator platform with an integrated high-field magnet, designed for electronic transport measurements and optical spectroscopy of two-dimensional heterostructure devices, as well as RF dielectric-loss characterization using high-Q microwave resonators for superconducting qubit materials. The system offers an automated bottom loading fast sample exchange, enabling cooldown from room temperature to 20 mK temperatures within nine (9) hours. It is equipped with multiple DC and RF wiring lines and provides optical access via ports and fiber feedthroughs.

The UTQMD at the Center for Functional Nanomaterials shall be aimed at a milli-Kevin characterization platform for a broad range of quantum materials and devices, including graphene,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .