BRIC_Grant_and_Schedule.pdf

PDF 73 KB Posted

Attached to
Pump Station 1 and Soquel Pump Station Design
Solicitation number
RFP No. PW-0268
Issued by
Santa Cruz County, San Francisco City, California

About this file

This is a BRIC Grant and Schedule document prepared by the City of Santa Cruz Department of Public Works for the Pump Station 1 and Soquel Pump Station Design project. The project involves the rehabilitation of Pump Station No. 1 located south of the Laurel Street Bridge and the construction of a new Soquel Pump Station south of Soquel Avenue Bridge on the west side of the San Lorenzo River. The approved schedule contains six main tasks with a notice to proceed on May 1, 2026, followed by additional hydraulic modeling, basis of design, 50% design, 90% design, 100% design, and project management phases. Due dates for these tasks span from July 1, 2026, through March 26, 2027, with the 90% and 100% design phases scheduled for January 15, 2026, and March 1, 2026, respectively.

The total project budget is approximately $1,800,000, with allocated BRIC funding distributed across the scheduled tasks: Additional Hydraulic Modeling ($44,659.00), Basis of Design ($250,000.00), 50% Design ($467,000.00), 90% Design ($450,000.00), 100% Design ($400,000.00), and Project Management ($136,911.60). The project is funded by a Federal Emergency Management Agency (FEMA) BRIC grant. The City anticipates that a contract extension will be necessary to allow adequate time for completion of the required consulting and engineering support services.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment G - BRIC Grant and Schedule

Task Name Allocated BRIC Funding Due Date 0 Notice to Proceed - 5/1/2026 1 Additional Hydraulic Modeling $44,659.00 7/1/2026 2 Basis of Design $250,000.00 9/1/2026 3 50% Design $467,000.00 11/1/2026 4 90% Deisgn $450,000.00 1/15/2026 5 100% Deisgn $400,000.00 3/1/2026 6 Project Management $136,911.60 3/26/2027

This project is funded by a FEMA BRIC grant. The schedule below is the approved schedule. The City assumes an extension will be necessary to allow adequate time for completion of the required services.

Sheet1

File details come from the government source that posted it. Updated .