Brand Name Justification Electrical Meters 24B0013.pdf

PDF 243 KB Posted

Attached to
VGLZ242004 Replace MV Transformers TP170A and T170B.
Solicitation number
W50S8524B0013
Issued by

About this file

This document is a Simplified Acquisition Procedures (SAP) Determination Memorandum for a sole source acquisition. It justifies the acquisition of a specific brand name electric meter, the Itron Centron Polyphase electric meter (with RF) - ITRON CP3 9S CL20 3 ERT DEMAND + CLOCK, which is the new Selfridge Design Standards approved meter and a direct replacement to a previous Itron meter. The memorandum explains that this Itron meter is the only source reasonably available due to radio frequency compatibility requirements and security/operational constraints. The estimated amount for this acquisition is $500. The contracting officer has determined the price to be fair and reasonable. This sole source acquisition is in the best interest of the government.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SIMPLIFIED ACQUISITION PROCEDURES (SAP)

DETERMINATION MEMORANDUM FOR SOLE SOURCE ACQUISITIONS OVER THE MICRO-PURCHASE THRESHOLD BUT NOT

EXCEEDING THE SIMPLIFIED ACQUISITION THRESHOLD FAR 13.106-3(b)(3)(i)

SOLICITATIONS MAY BE LIMITED TO ONE SOURCE ONLY IF THE CONTRACTING OFFICER DETERMINES THAT ONLY ONE SOURCE IS REASONABLY AVAILABLE. WHEN THE CUSTOMER DESCRIBES AN ITEM OR SERVICE, WHICH LIMITS THE AVAILABILITY TO ONE SOURCE, THE DETERMINATION MUST EXPLAIN WHY THE ITEM OR SERVICE PROVIDER IS THE ONLY ONE THAT WILL MEET THE GOVERNMENT'S REQUIREMENT. STATEMENTS SUCH AS "ONLY KNOWN SOURCE" OR "ONLY SOURCE WHICH CAN MEET THE REQUIRED DELIVERY DATE" ARE INADEQUATE TO SUPPORT A SOLE SOURCE PURCHASE. THIS FORM MAY BE USED IN LIEU OF THE DETERMINATION DESCRIBED IN FAR 13.106. THE CUSTOMER SHALL PROVIDE THE FOLLOWING INFORMATION:

QUOTE/SOLICITATION NUMBER: W50S85-24-B-0013

ESTIMATED AMOUNT (Not exceeding $250,000): $500.00 for a 480-volt Electric Meter

BRAND NAME BUY YES NAME OF PROPOSED CONTRACTOR

DESCRIPTION OF SUPPLIES OR SERVICES REQUIRED AND THE INTENDED USE:

Model G981682 Itron Centron Polyphase electric meter (with RF) - ITRON CP3 9S CL20 3 ERT DEMAND + CLOCK

UNIQUE CHARACTERISTICS THAT LIMIT AVAILABILITY TO ONLY ONE SOURCE, WITH THE REASON NO OTHER SUPPLIES OR

SERVICES CAN BE USED:

The Itron Centron Polyphase electric meter (with RF) - ITRON CP3 9S CL20 3 ERT DEMAND + CLOCK is the new Selfridge Design Standards approved electric meter. This Itron model electric meter is a direct replacement to the previous Itron electric meter and is approved by Selfridge Communications for radio frequency range. The Itron Centron Polyphase electric meter (with RF) - ITRON CP3 9S CL20 3 ERT DEMAND + CLOCK will be part of the future energy data collection system.

REASON THAT SUGGESTED SOURCE IS THE ONLY SOURCE WHICH CAN PROVIDE THE SUPPLIES OR SERVICES AND DETAILED

DESCRIPTION OF MARKET RESEARCH PERFORMED:

The Itron Centron Polyphase electric meter (with RF) - ITRON CP3 9S CL20 3 ERT DEMAND + CLOCK is the new Selfridge Design Standards approved electric meter. This Itron model electric meter is a direct replacement to the previous Itron electric The unit has undergone technical scrutiny by the 127 Communications Squadron and its radio frequency is compatible with current base missions. The 127 Communication Squadron can realistically provide only 1 radio frequency for this application due to security and operational constraints.

EXPLAIN WHY AN ADEQUATE PURCHASE DESCRIPTION OR OTHER INFORMATION SUITABLE TO SOLICIT BY FULL AND

OPEN COMPETITION HAS NOT BEEN DEVELOPED OR IS NOT AVAILABLE:

N/A

PROVIDE A STATEMENT OF ACTIONS, IF ANY, THE GOVERNMENT MAY TAKE TO REMOVE OR OVERCOME ANY BARRIERS TO

COMPETITION BEFORE FUTURE ACQUISITIONS ARE REQUIRED:

The Government will continue to seek out vendors proposing cost-effective solutions that meet the Government's needs. Additionally, we will continue to conduct market research to find equipment/systems that are not proprietary in nature.

I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.

Signature

Darren Burton Contracting Officer Representative

FAIR AND REASONABLE COST DETERMINATION

I hereby determine that the anticipated cost to the Government for this contract action will be fair and reasonable based on the Independent Government Estimate (IGE) and price analysis of the general contractor’s proposal. Therefore, certified cost or pricing data is not required per 15.403-1(b)(3).

CONTRACTING OFFICER CERTIFICATION

I CERTIFY THAT THIS JUSTIFICATION IS ACCURATE AND COMPLETE TO THE BEST OF MY KNOWLEDGE AND BELIEF, AND THAT COMPLETING THIS PURCHASE AS A SOLE SOURCE/BRAND NAME IS IN THE BEST INTEREST OF THE GOVERNMENT. ADDITIONALLY, I APPROVE THIS JUSTIFICATION TO LIMIT COMPETITION SUBJECT TO THE AVAILABILITY OF FUNDS AND PROVIDED THAT THE SERVICES OR SUPPLIES HEREIN DESCRIBED HAVE OTHERWISE

BEEN AUTHORIZED FOR ACQUISITION.

Signature

Steven A. Stocking Contracting Officer

1055159340C Pencil

2024-07-16T10:22:10-0400
STOCKING.STEVEN.ANSELM.1055159340
2024-05-17T13:02:18-0400
BURTON.DARREN.MICHAEL.1098710775

File details come from the government source that posted it. Updated .