BP0902-26 Generator Fire Pump Maint.pdf

PDF 2 MB Posted

Attached to
Generator and Fire Pump Maintenance and Repair
Solicitation number
BP#0902-26
Issued by
Monroe County, Rochester City, New York

About this file

This is a Bid Proposal document issued by Monroe County, New York, Division of Purchasing for generator and fire pump maintenance and repair services (BP0902-26). The contract covers comprehensive preventative maintenance (PM) inspections, services, and supplemental load bank testing for the County's emergency standby generator and fire pump infrastructure systems across multiple departments, including Monroe Community Hospital, Frederick Douglass Greater Rochester International Airport, Monroe County Sheriff Department, Department of Environmental Services, Monroe County Public Safety, Monroe County Parks Department, and Seneca Park Zoo. The bid was scheduled for October 15, 2026, at 11:00 am, with all requests for clarification to be submitted in writing by noon on Wednesday, October 7, 2026. The contract period runs from the date of award through October 31, 2027, with options to renew for up to four additional twelve-month periods with mutual consent of both parties. All work must comply with current NFPA 110 and NFPA 25 standards and OEM specifications, with the Authority Having Jurisdiction (AHJ) to be notified prior to and immediately following any servicing or testing.

The County intends to award the bid to the lowest responsive and responsible bidder based on the total bid amount, and bidders must submit pricing for all line items to be considered. Bid security is not required. All bid submissions must include a signed original and one copy of the bid proposal, debarment certification, equal pay certification, unit price sheets, insurance requirements including NYS Workers' Compensation and Disability forms, and an MBE/WBE/SDVOB Utilization Plan with documentation or a waiver application. The County maintains M/WBE/SDVOB requirements with specific participation goals and payment deduction provisions for non-compliance. The unit price sheet lists over 60 generator units and fire pump systems of varying kilowatt capacities across multiple County facilities, with service codes including GSVC1-4 (generator inspections, oil changes, and battery replacements), LBT1-2 (annual and triennial load bank testing), TA-LT (thermal analysis and load transfer testing), and FPSVC1-2 (fire pump annual maintenance and battery replacement). Contractors must also submit fixed hourly billing rates for out-of-scope follow-up repairs and maintenance, with emergency service travel mileage applicable only to emergency calls calculated from the contractor's primary office address to the service location. All laboratory diagnostic reports and test data must be submitted to the respective AHJ within 30 days of work completion.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MONROE COUNTY

BID PROPOSAL

Division of Purchasing County Office Building, Room 200

39 West Main Street Rochester, NY 14614

(585) 753-1100

BID PROJECT NUMBER: 0902-26 BID TITLE: GENERATOR AND FIRE PUMP

MAINTENANCE AND REPAIR

BUYER: Sean Wilcox BID TIME: 11:00 am PHONE: 585-753-1136 BID DATE: October 15, 2026

THIS BID HAS MONROE COUNTY M/WBE/SDVOB REQUIREMENTS

BID SECURITY REQUIRED: No: __X___ Yes, in the amount of ___ as specified herein

ITEM

AND/OR

GROUP NO.

ESTIMATED

QUANTITY

ARTICLES OR SERVICES

UNIT

PRICE

EXTENSION

(TOTALS)

ROOF

GENERATOR AND FIRE PUMP

MAINTENANCE AND REPAIR

Per attached specifications and Unit Price Sheet

TOTAL BID

ALL BID SUBMISSIONS MUST INCLUDE (at time of bid opening):

One (1) SIGNED original and one (1) copy of:

Bid Proposal Debarment Certification Equal Pay Certification

Unit Price Sheets Insurance Requirements, Including additional endorsements and NYS Workers’ Comp. & Disability forms

Appendix MBE/WBE/SDVOB Utilization Plan AND MBE/WBE/SDVOB Reporting Documents, OR Waiver Application Any Addendums posted in addition to the Bid Document

I have received, read and agree to the terms and conditions as set forth in General Terms and Conditions, Monroe County, attached, and any special terms and conditions set forth in the General and Technical Specifications herein. I have read, understand and agree to all Instructions to Bidders (including the Non-Collusion Bidding Certification) on the reverse hereof. I hereby recognize and agree that upon execution of this document by an authorized officer of Monroe County, that this document, together with the Contractor’s bid as accepted by Monroe County and all other documents prepared by or on behalf of Monroe County for this bid solicitation, shall become the binding contract between the parties for the services to be provided in accordance with the terms and conditions set forth herein.

FIRM NAME SIGNED BY

ADDRESS PRINTED NAME

TITLE

FEDERAL ID NO. PHONE NO.

E-MAIL ADDRESS FAX NO.

BID ACCEPTANCE AND CONTRACT AWARD

The above bid is accepted, except as noted, and the contract is awarded to you for the following item(s):

Authorization to furnish supplies/services will be made via Purchase Order, as appropriate, signed by the Monroe County Purchasing Manager, or designated agent. Contract period from to .

Date: BY:

Colleen D. Anderson, Purchasing Manager, Monroe County

INSTRUCTIONS TO BIDDERS

• All public bids must be submitted to Purchasing in sealed envelopes which clearly identify the bid project number and the title of the service/product being bid. Any other writing on the envelope, with the exception of company logos, etc. may result in bids being misplaced and otherwise rejected.

• Unsigned bids may be rejected as informal.

• Questions regarding ambiguities or the propriety of these specifications should be addressed, in writing, to the Buyer, prior to the formal bid opening. Such questions will not be entertained after said bid opening.

• Where a Bid Security is indicated on the face of the proposal, the security must be attached to the Proposal as an earnest of good faith. In this case, any bid without a bid security may be rejected as informal.

The Purchasing Manager reserves the right to reject any and all bids, to waive any informality in the bids and to make awards in the best interest of Monroe County.

NON-COLLUSION BIDDING CERTIFICATION

By submission of this bid, each bidder and each person signing on behalf of any bidder, certifies and in the case of a joint bid, each party thereto certifies as to its own organization, under penalty of perjury, that to the best of knowledge and belief:

1. The prices in this bid have been arrived at independently without collusion, consultation, communication or agreement, for the purpose of restricting competition, as to any matter relating to such prices with any other bidder or with any competitor.

2. Unless otherwise required by law, the prices, which have been quoted in its bid, have not been knowingly disclosed by the bidder and will not knowingly be disclosed by the bidder prior to opening, directly or indirectly, to any other bidder or to any competitor.

3. No attempt has been made or will be made by the bidder to induce any other person, partnership or corporation to submit a bid for the purpose of restricting competition.

CERTIFICATION REGARDING

DEBARMENT, SUSPENSION AND RESPONSIBILITY

The undersigned certifies, to the best of his/her knowledge and belief, that the Bidder and its principals:

1. Are not presently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded by any Federal department or agency;

2. Have not within a three (3) year period preceding this transaction/application/ proposal/contract/agreement been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain or performing a public (Federal, State or local) transaction or contract under a public transaction;

violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction or records, making false statements or receiving stolen property;

3. Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity

(Federal, State or local) with commission of any of the offenses enumerated in paragraph 2 of this certification; and

4. Have not within a three (3) year period preceding this transaction/application/ proposal/contract/agreement had one or more public transactions (Federal, State or local) terminated for cause or default.

CERTIFICATION REGARDING MONROE COUNTY PROCUREMENT POLICY

AND CONSEQUENCES FOR VIOLATION

The undersigned certifies, to the best of his/her knowledge and belief, that the Bidder and its principals:

5. Have read and understand the Monroe County Procurement Policy and agree to abide by its terms (http://www2.monroecounty.gov/purch-overview.php);

6. Understand that any violation of the Monroe County Procurement Policy may result in the exclusion of any response to a public bid, Request for Proposals (RFP) or Request for Qualifications (RFQ) submitted on our behalf; and

7. Understand that any contract or agreement entered into subsequent to a violation of this policy during the procurement process is null and void.

Date: ____________________ _______________________________ [Print Name of Bidder]

By: ___________________________ [Signature]

[Print Name]

[Print Title/Office]

BIDDER MUST COMPLETE THIS FORM AND SUBMIT WITH BID.

Revised 10/3/2013

MONROE COUNTY EQUAL PAY CERTIFICATION

The undersigned certifies, to the best of his/her knowledge, that the Contractor:

1. Compensates its employees in compliance with the Federal Equal Pay Act, 29 USC § 206, and the New York State Labor Law § 194, as amended from time to time (“Equal Pay Laws”).

2. Has not been subject to an adverse finding by the United States Department of Labor, New York State Department of Labor or a court of law with regard to the Equal Pay Laws within the previous five years (“Adverse Finding”). If the Contractor has been subject to an Adverse Finding, the Contractor shall immediately disclose in writing the outcome and circumstances of such Adverse Finding to the County Purchasing Manager at the following address: Room 200, County Office Building, 39 West Main Street, Rochester, New York 14614.

3. Is not the subject of any currently pending claims involving the Equal Pay Laws. If the Contractor is the subject of any currently pending claims involving the Equal Pay Laws, the Contractor shall immediately disclose in writing to the County’s Purchasing Manager the nature and status of such claims.

4. Acknowledges that the violation of one or more of the Equal Pay Laws or its filing of a false or misleading Monroe County Equal Pay Certification during the term of the Contractor’s agreement with Monroe County may constitute grounds for the County in its sole discretion to immediately terminate such agreement with the Contractor and for determining the Contractor to be not qualified to participate in future Monroe County contracts.

5. Acknowledges that the Contractor will cooperate with the County’s compliance monitoring and periodic auditing of Certifications provided by the Contractor to the County.

Date: ____________________ _______________________________ [Print Name of Contractor]

By: ___________________________ [Signature]

[Print Name]

[Print Title/Office]

9/4/2020

BIDDER MUST COMPLETE THIS FORM AND SUBMIT WITH BID

TERMS AND CONDITIONS

BID ITEM: GENERATOR AND FIRE PUMP MAINTENANCE AND REPAIR

FOR: Department of Environmental Services

PURCHASING

CONTACT:

The Buyer, identified below, is the sole point of contact regarding this Bid from the date of issuance until the bids are opened and the results made public.

Sean Wilcox

Monroe County Division of Purchasing

39 West Main Street, Room 200

Rochester, NY 14614

Email: swilcox@monroecounty.gov

All requests for bid clarification must be submitted in writing to the Buyer referenced above and received no later than noon (Eastern Standard Time) on Wednesday, October 7, 2026.

All questions will be answered and documented in writing as an Addendum to the Bid. These will be sent out to all Bidders who received the original Bid no later than Friday, October 9, 2026.

DUPLICATE COPIES: PLEASE SUBMIT YOUR BID IN DUPLICATE; THE ORIGINAL AND ONE

(1) COPY.

BID INFORMATION: At the time of bid, the bidder shall supply detailed specifications covering the item(s) contained herein and shall clearly indicate any areas in which item or items offered do not fully comply with the specifications contained herein.

SUBMITTAL OF

FORMAL

PROPOSAL:

Bid proposal must be legible and submitted in the original form, bearing an original signature. EMAILS AND FACSIMILES ARE NOT ACCEPTABLE.

All bidders must submit proof that they have obtained the required Workers’

Compensation and Disability Benefits Insurance coverage or PROOF that they are exempt if awarded the contract. (Visit www.wcb.ny.gov for forms.)

SPECIFICATION

ALTERATIONS:

Specifications will be construed to be complete and be considered the entire description of the goods or services upon which Monroe County is now seeking bids. Only formal written addenda can materially alter this set of specifications. No verbal statement made by a Monroe County employee or anyone else is binding nor shall such statement be considered an official part of this public bid proposal.

QUALIFIED BIDDER: Each bidder must be prepared to present satisfactory proof of his capacity and ability to perform this contract. Such proof may include, but is not limited to, an inspection of the bidder’s facilities and equipment, financial statements, references and performance of similar contracts. The Purchasing Manager reserves the right to reject any bid where the bidder cannot satisfy the

County as to their ability to perform. Monroe County reserves the right to mailto:swilcox@monroecounty.gov http://www.wcb.ny.gov/ reject any and all bids if the Monroe County Purchasing Manager deems said action to be in the best interests of Monroe County.

CONTRACT TERM: Contract will start with the date of the contract award and run through

October 31, 2027, with the option to renew the contract up to four (4) additional twelve (12) month periods with the mutual consent of both parties.

METHOD OF

AWARD:

Monroe County intends to award the bid to the lowest responsive and responsible bidder, based on the TOTAL. Bidder must bid on all items in order to be considered. The County reserves the right to reject any and all bids if the Purchasing Manager deems said action to be in the best interest of the County.

PRICE CHANGES: Price changes may be proposed by either party on a quarter annual basis no less than (30) days prior to the end of such quarter year, or no less than (30) days prior to the end of contract term, based upon manufacturer or supplier price changes that must be supported with specific documentation justifying the change. Should proposed price changes not be acceptable to both parties, the contract may be terminated by either party at the end of the quarter year or contract term.

NYS DOL

CONTRACTOR

REGISTRATION:

No contractor shall bid on a public work project covered under these contract documents unless such contractor is registered pursuant to Chapter 31, Article 8, Section 220-I of New York State Labor Law. Sub-contractors must be registered prior to commencing any work on the project covered under these contract documents. The contractor shall submit its certificate of registration at the time the bid is made. Bids submitted without the required certification of registration shall be considered as nonresponsive.

Applications for registration shall not be accepted as a substitute for a certification of registration for the purposes of this section. The contractor shall submit the sub-contractor’s certificate of registration in accordance with

General Condition 42, Shop Drawings, but not less than 15 calendar days prior to the sub-contractor’s start of work.

NYS WAGE RATES: Pursuant to the provision of Section 220-A of the New York State Labor Law, as amended, the Contractor (and related Subcontractors) will be obligated to pay all workers in the covered classes only the applicable prevailing wage rates and supplements. The minimum hourly wage rate to be paid the various classes of labor performing work under this contract shall be in accordance with schedules which have been established or may hereafter be established or increased, by the New York State Department of Labor during the contract term. Refer to NYS Wage Schedule PRC#2026026392 developed for this project.

COMPLIANCE WITH

THE LAW:

The Contractor agrees to procure all necessary licenses and permits. The

Contractor shall comply with all laws, rules and regulations pertaining to the payment of wages and all other matters applicable to the work performed under this contract.

MINIMUM ORDER: No minimum order is specified for this contract. Agencies must be able to order as needed. Political subdivisions and others authorized by law may participate in this contract.

PURCHASE ORDER

ISSUANCE:

Delivery of services may be directed by the receipt of a Purchase Order only.

Items that are not part of this bid will not be paid for by Monroe County.

As to all purchase orders issued by Monroe County, exceptions may only be authorized, in writing, by the Purchasing Manager or her authorized agent prior to delivery.

WARRANTY

GUARANTEE:

All warranties by manufacturer shall apply. Bidder shall, as part of its proposal, furnish its warranty/guarantee for all goods/services to be furnished hereunder. As a minimum, Bidder shall warrant all goods for a period of one

(1) year from date of acceptance. Bidder shall be obligated to repair or replace all defects in material or workmanship which are discovered or exist during said period. All labor, parts and transportation shall be at Bidder's expense.

BILLING

PROCEDURE:

All invoices for items sold any authorized agency as a result of this contract must be billed in the following manner: Purchase Order #, Quantity, Description of Item Purchased, BP#, Item #, Extension and Total. ALL

INVOICES MUST BE MARKED WITH THE PURCHASE ORDER NUMBER.

INVOICES WITHOUT THIS INFORMATION WILL NOT BE PROCESSED

FOR PAYMENT.

SECURITIES AND

INSURANCE:

Any Certificate of Insurance, Bonds, or other forms of security required by this bid are to be submitted to the Purchasing Manager no later than ten (10) normal business days following the date of notification of award. Documents must be received by the close of business, 5:00 PM, on that day.

UNCONTEMPLATED

PURCHASES:

Monroe County reserves the right to request separate bids for such quantities of items on this contract that may be best procured via separate public bid offering and to otherwise act in furthering its own best interests.

SUBCONTRACT: The successful Bidder shall not subcontract any work without first obtaining the written consent of the Monroe County Purchasing Manager.

Notwithstanding the foregoing, subcontractor(s) set forth in a Bidder's

MBE/WBE/SDVOB Utilization Plan submitted pursuant to the Minority and

Women Owned Business Enterprise Requirements and approved by the

County’s Director of Diversity, Equity, and Inclusion shall be deemed to be approved subcontractor(s).

RELATED ITEMS: The County reserves the right to add miscellaneous related items to this contract during the contract term upon agreement by both parties as to the price. Approval must be given in writing by the Purchasing Manager or her

Designee.

REPORT OF

PURCHASE:

The Contractor must, upon request, provide the County Purchasing Manager with detailed information showing how much of each item was delivered under this contract.

INDEMNIFICATION: The Contractor agrees to defend, indemnify and save harmless the County, its officers, agents, servants and employees from and against any and all liability, damages, costs or expenses, causes of action, suits, judgments, losses and claims of every name not described, including attorneys’ fees and disbursements, brought against the County which may arise, be sustained or occasioned directly or indirectly by any person, firm or corporation arising out of or resulting from the performance of the services by the Contractor, arising from any act, omission or negligence of the Contractor, its agents and employees or arising from any breach or default by the Contractor under this

Agreement. Nothing herein is intended to relieve the County from its own negligence or misfeasance or to assume any such liability for the County by the Contractor.

OTHER AGENCIES: The Contractor(s) must honor the prices, terms and conditions of this contract with political subdivisions or districts located in whole or in part within Monroe

County. In addition, the contractor may, but is not required to, extend the prices, terms and conditions of this contract to any other political subdivision or district. Usage of this contract by any of these other political subdivisions or districts will have to be coordinated between that subdivision or district and the contractor. Orders placed against this contract between any subdivision or district will be contracts solely between the Contractor(s) and those entities.

Monroe County will not be responsible for, nor will it have any liability or other obligation for, such contract between the Contractor(s) and any third party.

EQUAL PAY

CERTIFICATION:

Prior to the execution of this Agreement, the Contractor shall submit to the

County an Equal Pay Certification (“Certification”) affirming the Contractor’s compliance with the Federal Equal Pay Act, 29 USC § 206 and New York

State Labor Law §194, as amended from time to time (“Equal Pay Laws”). As set forth in the Certification, the Contractor’s violation of one or more of the

Equal Pay Laws or its filing of a false or misleading Certification during the term of this Agreement may constitute grounds for the County in its sole discretion to immediately terminate the Agreement and for determining the

Contractor to be not qualified to participate in future Monroe County contracts.

Terms & Conditions-Term Contract-Commodity-Single Award.doc (8/03)

MINORITY AND WOMEN’S BUSINESS ENTERPRISE REQUIREMENTS

a. Requirements

The Bidder shall take affirmative steps to afford opportunities for MBE and WBE firms on the project and the Bidder shall make its best efforts to meet the MBE/WBE participation goals established for this project. The specific affirmative steps to be taken by Bidder are described in subparagraph c below.

The Bidder shall designate, in writing, an executive of its company who will have overall responsibility for implementing the Bidder's MBE/WBE Utilization Plan. The successful Bidder shall be responsible for maintaining records showing subcontractor awards to MBE and WBE firms and all specific efforts to award subcontracts to such firms even if not successful. A copy of the monthly report form is included in these Requirements. This report form is to be completed by the successful Bidder and submitted to the County with each monthly progress payment application.

Bidders that are either MBEs or WBEs will be allowed to include their own participation towards meeting MBE/WBE participation goals established for this project. In the event a Bidder is a MBE, such Bidder shall remain subject to the goal of subcontracting at least three percent (3%) of the total cost of services to a WBE. In the event a Bidder is a WBE, such Bidder shall remain subject to the goal of subcontracting at least twelve percent (12%) of the total cost of services to a MBE. In the event a Bidder is both a MBE and WBE, the Bidder shall choose one of the two designations and shall remain subject to the subcontracting best efforts requirement for the designation not chosen.

M/WBE firms must be certified by the New York State office of Minority and Women’s Business Development or the Monroe County M/WBE Certification Program (locally funded contracts only). The County reserves the right to require specific certification program(s) for its projects.

The successful Bidder shall also be required to submit payment records, which demonstrate payment by the Bidder to all subcontractors, including the MBE and WBE firms utilized on the project. Such submissions shall include affidavits certifying payments to subcontractors for work previously paid for by the County. A copy of the Affidavit of Payment form to be utilized by the Bidder is included in these Requirements

b. Bidder's Detailed M/WBE Utilization Plan

A M/WBE utilization plan shall be submitted with each Bid. The utilization plan must include a detailed MBE/WBE Utilization Plan form and a signed Letter of Intent from each of the MBE/WBE firms identified in the Plan. The Plan must identify the MBE and WBE firms to be utilized by the Bidder. If specific spend information is not available, complete details must be provided on the actual work M/WBEs will complete on the project, together with an explanation as to why spending data is not available. If a firm is unable to show obtainment of program goals when submitting the utilization plan, Bidder must submit a Request for M/WBE Utilization Waiver with the initial bid. An approved Utilization Plan or granted utilization waiver will be required prior to contract issue. If the Utilization Plan is reviewed and determined to be insufficient and/or a utilization waiver is not granted, the bid may be disqualified as non-responsive.

The County’s Director of Diversity, Equity, and Inclusion (DEI) shall be responsible for approving Bidder’s MBE/WBE Utilization Plan; any utilization waiver applications; and/or reviewing each subcontractor's MBE or WBE certifications.

The successful Bidder will be obligated, throughout the term of the Contract, to furnish to the

County’s M/WBE/SDVOB Program Manager copies of all subcontracts with M/WBE firms for Project work.

Failure to provide the County with a copy of such subcontracts prior to commencement of the subcontracted work shall constitute a breach of Bidder’s obligations and the County shall have the right, at its discretion, to order the work suspended until Bidder has complied with this provision. Any costs associated with or resulting from a suspension of work due to Bidder’s failure to comply with this provision shall be Bidder’s sole responsibility.

Any amendments to the Utilization Plan submitted by Bidder must be approved by the County’s M/WBE/SDVOB Program Manager, including, without limitation, changes in the work to be subcontracted to MBE/WBE firms; changes in the use of MBE/WBE firms; and/or substitutions of MBE/WBE firms.

Updated utilization plans shall be submitted for change orders over $20,000.

c. Disqualification of Proposals

Without limiting other grounds for the disqualification of bids on the basis of nonresponsiveness and/or nonresponsibility, the County may disqualify a bid as being nonresponsive and/or nonresponsible for failure to provide a timely MBE/WBE Utilization Plan, obtain a waiver, and/or remedy noted deficiencies in the Bidder's MBE/WBE Utilization Plan.

d. Best Effort

Where it appears that a Bidder, after making its best efforts, cannot comply with M/WBE participation requirements, a Bidder may submit a written application with its bid requesting a partial or total waiver of such requirements, setting forth the reasons for the Bidder’s inability to meet any or all of the participation requirements and an explanation of the efforts undertaken by the Bidder to obtain the required participation of certified businesses. The County’s Director of DEI will evaluate utilization waiver applications to determine if the Bidder’s efforts are sufficient to grant the waiver. Efforts to obtain M/WBE participation that are merely pro forma are not best efforts, nor are efforts that, even if they are sincerely motivated, given all relevant circumstances, could not reasonably be expected to produce a level of M/WBE participation sufficient to meet the goal. In order to evaluate a Bidder’s best efforts, the County’s Director of DEI will consider the quality, quantity, and intensity of the different kinds of efforts that the Bidder has made. Below is a list of the types of actions which the County’s Director of DEI will consider as part of the Bidder’s best efforts to obtain M/WBE participation. It is not intended to be a mandatory checklist, nor is it intended to be exhaustive or exclusive. Other factors or types of efforts may be relevant in appropriate cases:

1. The Bidder shall conduct market research to identify small business contractors and suppliers and solicit, through all reasonable and available means, the interest of all certified M/WBEs that have the capability to perform the work of the contract. This may include attendance at pre-bid and business matchmaking meetings and events; advertising and/or written notices; posting of notices of sources sought and/or requests for proposals, written notices or emails to all certified M/WBEs listed in the appropriate directory of certified firms that specialize in the areas of work desired and which are located in the area or surrounding area.

2. The Bidder shall solicit this interest as early in the bidding process as practicable, to allow the M/WBEs to respond to the solicitation and submit a timely offer. The Bidder shall determine with certainty if the M/WBEs are interested by taking appropriate steps, including following up the initial solicitation with at least one additional solicitation via a different media. The Bidder shall solicit quotes from qualified firms listed in the NYS M/WBE or Monroe County directory, regardless if they have their own database of M/WBE firms. The Bidder shall keep records of efforts to solicit and negotiate with M/WBEs as evidence of best efforts. These records must include the firms contacted, method of contact, evidence of actions, and contact information of individuals that were sent outreach efforts. M/WBE firms should be given a minimum of 10 business days to submit quotes.

3. Selecting portions of the work to be performed by M/WBEs in order to increase the likelihood that the M/WBE goal will be achieved. This includes, where appropriate, either breaking down operations or combining like or related operations into logistically and economically feasible units to facilitate M/WBE participation, even when the Bidder might prefer to perform these work items with its own forces. This may include, where possible, establishing flexible time frames for performance and delivery schedules in a manner that encourages and facilitates M/WBE participation.

4. Providing interested M/WBEs with adequate information on where and how to obtain the plans, specifications, and requirements of the contract in a timely manner to assist them in responding to a solicitation with their timely offer.

5. Negotiating in good faith with interested M/WBEs. It is the Bidder’s responsibility to make a portion of the work available to M/WBE subcontractors and material suppliers and to select those portions of the work or material needs consistent with the available M/WBE subcontractors and material suppliers in order to facilitate M/WBE participation. Evidence of such negotiation includes the names, addresses, and telephone numbers of M/WBEs that were considered; a description of the information provided regarding the plans and specifications for the work selected for subcontracting; and evidence as to why additional agreements could not be reached for M/WBEs to perform the work.

6. Additional Costs. The fact that there may be some additional costs involved in finding and using M/WBEs is not in itself sufficient reason for a Bidder's failure to meet the contract M/WBE goal, as long as such costs are reasonable. The ability or desire of a Bidder to perform the work of a contract with its own organization does not relieve the Bidder of the responsibility to make best efforts.

7. Replacement Firms. A Bidder’s inability to find a replacement M/WBE at the original price is not sufficient to support a finding that best efforts have been made to replace the original M/WBE The fact that the Bidder has the ability and/or desire to perform the contract work with its own forces does not relieve the Bidder of the obligation to make best efforts to find a replacement M/WBE, and it is not a sound basis for rejecting a prospective replacement M/WBE’s reasonable quote.

8. Making efforts to assist interested M/WBEs in obtaining bonding, lines of credit or insurance as required by the Department or the Bidder.

9. Making efforts to assist interested M/WBEs in obtaining necessary equipment, supplies, materials, or related assistance.

10. The County’s M/WBE Program Manager will provide assistance to potential bidders in connecting with M/WBEs.

1. Payment Deductions

The Bidder's failure to perform in accordance with an approved M/WBE Utilization Plan shall constitute a default by the Bidder of the obligations under the Contract. In the event of such a default by Bidder, the County shall be entitled to deduct payment to Bidder in the percentage amount of the Contract which equals Bidder’s shortfall from the M/WBE participation goals for this project. Such deductions by the County may begin with the Bidder’s initial payment application, and will carry-over to subsequent payment applications until the total amount of the deductions equals the amount of the MBE/WBE participation goal shortfall. In the event the Bidder thereafter performs in accordance with an approved M/WBE Utilization Plan, the County will reimburse any payment deductions made pursuant to this provision. In the event the Bidder continues to fail to perform in accordance with an approved M/WBE Utilization Plan, the County will retain any payment deductions made pursuant to this provision and may seek any other rights and remedies available to County under law or in equity.

f. Additional Requirements

1. M/WBE Supplier

M/WBE supplier participation shall be based on 50% of their contract amount. This participation shall be based on 100% of contract amount if said MBE/WBE installs the material they are supplying.

A supplier is a firm that owns, operates, or maintains a store, warehouse, or other establishment in which the materials or supplies required for the performance of the contract are bought, kept in stock, and regularly sold to the public in the usual course of business. It is a firm that engages in, as its principal business, and in its own name, the purchase and sale of the products in question. One who deals in bulk items such as steel, cement, gravel, stone and petroleum products need not keep such products in stock, if it owns or operates distribution equipment.

2. M/WBE Trucking

No material costs will be credited towards a project’s M/WBE goals. M/WBE trucking participation credit will be granted for the utilization of M/WBE owned or leased equipment only.

3. M/WBE Labor Only Subcontracts

The M/WBE subcontractor shall submit documentation of the relationship between its work force and the Bidder’s work force. The Bidder and the M/WBE subcontractors shall submit copies of the certified payrolls to the County (or designee).

4. M/WBE Subcontract to Non-MWBE

In order to allow management flexibility for M/WBE firms, the M/WBE firms are permitted to subcontract up to 49% of any single M/WBE subcontract to non-M/WBEs and still have the whole M/WBE subcontract count towards fulfillment of the M/WBE utilization requirement. If the M/WBE firm contracts out more than 49% of any single M/WBE subcontract to non-M/WBE firms, the Subcontract between the M/WBE and the prime Bidder shall no longer be considered a bona fide M/WBE subcontract.

g. Conditions of Participation

M/WBE participation will be counted toward meeting the M/WBE contract goals, subject to all of the following conditions:

1. Commercially Useful Function

The Bidder is responsible for ensuring that M/WBEs working on the contract perform a commercially useful function. A M/WBE is considered to perform a commercially useful function when it is responsible for the execution of a distinct element of work on a contract and carries out his/her responsibilities by actually performing, managing, and supervising the work involved in accordance with normal industry practice (except were such practices are inconsistent with the M/WBE regulations). Arrangements that erode the ownership, control, or independence of the M/WBE or in any other way does not meet the commercially useful function requirement, the Bidder shall receive no credit toward the goal.

2. Work Force

The M/WBE firm must employ a work force (including administrative and clerical) separate and apart from that employed by the Bidder, other subcontractors on the project, or their affiliates. This does not preclude the employment by the M/WBE of an individual that has been previously employed by another firm involved in the Contract, provided that the individual was independently recruited by the M/WBE in accordance with customary industry practice. The routine transfer of work crews from another employer to the M/WBE shall not be allowed.

3. Supervision

All work performed by the M/WBE must be controlled and supervised by the M/WBE without duplication of supervisory personnel from the Bidder or other subcontractors. This does not preclude routine communication between the supervisory personnel of the

M/WBE and other supervisors necessary to coordinate the work of the contract.

4. Equipment

M/WBE subcontractors may supplement their equipment by renting or leasing additional equipment in accordance with customary industry practice. However, no more that 50% of the equipment required to perform the work of the subcontractor may be obtained from the Bidder, other subcontractors on the project, or their affiliates. If the M/WBE obtains equipment from any of those sources, the County of Monroe shall receive from the M/WBE documentation demonstrating that similar equipment and terms could not be obtained at a lower cost from other customary sources of equipment. The required documentation shall include, but not be limited to, copies of the rental or leasing agreements, and the names, addresses, and terms quoted by other sources of equipment.

h. Certification Process

The State of New York and Monroe County maintains a list of firms which have previously been certified as MBE's or WBE's as those terms are defined below.

1. Definitions

The following terms are defined as follows:

(a) Minority Business Enterprise (MBE) - an independent business completely or substantially owned, controlled and operated by one or more members of specified minority groups or socially and economically disadvantaged individuals.

(b) Women's Business Enterprise (WBE) - an independent business completely or substantially owned, controlled and operated by one or more women.

(c) Independent - demonstrably free from any control, domination or undue influence by individuals or businesses who are not intended to be primary beneficiaries of the MBE/WBE program.

(d) Business - an entity capable of performing a commercially useful function, including management and supervision of the work.

(e) Owned, controlled and operated minority or women owners must: (a) have at least 51% of the beneficial ownership interest of the business; (b) share in the risks and profits commensurate with their percentage of ownership; (c) possess the power to direct or cause the direction of the management and policies of the business; (d) be actively involved in the day to day management and operation of the firm.

(f) Specified minority groups - Black Americans, Hispanic Americans, Native

Americans and Asian Pacific Americans.

(g) Socially and economically disadvantaged - member of a group or an individual found to be socially and economically disadvantaged by the U.S.

Small Business Administration under Section 8(a) of the Small Business Act, as amended (15 USC Section 637 (a)).

SERVICE-DISABLED VETERAN OWNED BUSINESSES REQUIREMENTS

a. Requirements

The Bidder shall take affirmative steps to afford opportunities for Certified SDVOB Firms on the project and shall make its best efforts to meet the participation goals established for this project. The specific affirmative steps to be taken by the Bidder are described in subparagraph d below.

The Bidder shall designate, in writing, an executive of its company who will have overall responsibility for implementing the Bidder's SDVOB Utilization Plan. The Bidder shall be responsible for maintaining records showing subcontractor awards and all specific efforts to award subcontracts to such firms even if not successful. A copy of the monthly report form is included in these Requirements. This report form is to be completed by the Bidder and submitted to the County with each monthly progress payment application.

Bidders that are a Certified SDVOB Firm will be allowed include their own participation towards meeting SDVOB participation goals established for this project.

The Bidder shall be required to submit payment records, which demonstrate payment by the Bidder to all subcontractors, including Certified SDVOB Firms utilized on the project. Such submissions shall include affidavits certifying payments to subcontractors for work previously paid for by the County. A copy of the Affidavit of Payment form to be utilized by the Bidder is included in these Requirements.

b. Bidder's Detailed SDVOB Utilization Plan

SDVOB utilization plans shall be submitted with each bid. The utilization plan must include a detailed SDVOB Utilization Plan form and a signed Letter of Intent from each of the Certified SDVOB Firms identified in the Plan. The Plan must identify the Certified SDVOB Firms to be utilized by the Bidder. If specific spend information is not available, complete details must be provided on the actual work Certified SDVOB Firms will complete on the project, together with an explanation as to why spending data is not available. If a firm is unable to show obtainment of program goals when submitting the utilization plan, the Bidder must submit a Request for SDVOB Utilization Waiver with the initial bid. An approved Utilization Plan or granted utilization waiver will be required prior to contract issuance. If the Utilization Plan is reviewed and determined to be insufficient and/or a utilization waiver is not granted, the bid may be disqualified as non-responsive.

The County’s Director of Diversity, Equity, and Inclusion (DEI) shall be responsible for approving the Bidder's SDVOB Utilization Plan; any utilization waiver applications; and/or reviewing each subcontractor's Certified SDVOB Firms certifications.

The Bidder will be obligated, throughout the term of the Contract, to furnish to the County’s M/WBE/SDVOB Program Manager copies of all subcontracts with Certified SDVOB Firms for Project work.

Failure to provide the County with a copy of such subcontracts prior to commencement of the subcontracted work shall constitute a breach of the Bidder's obligations and the County shall have the right, at its discretion, to order the work suspended until the Bidder has complied with this provision. Any costs associated with or resulting from a suspension of work due to the Bidder’s failure to comply with this provision shall be the Bidder's sole responsibility.

Any amendments to the SDVOB Utilization Plan submitted by the Bidder must be approved by the County’s M/WBE/SDVOB Program Manager, including, without limitation, changes in the work to be subcontracted to Certified SDVOB Firms; changes in the use of Certified SDVOB Firms; and/or substitutions of Certified SDVOB Firms. Updated utilization plans shall be submitted for change orders over $20,000.

c. Disqualification of Proposals

Without limiting other grounds for the disqualification of bids on the basis of nonresponsiveness and/or nonresponsibility, the County may disqualify a bid as being nonresponsive and/or nonresponsible for failure to provide a SDVOB Utilization Plan, obtain a waiver, and/or remedy noted deficiencies in the contractor's SDVOB Utilization Plan.

d. Best Effort

Where it appears that a Bidder, after making its best efforts, cannot comply with SDVOB participation requirements, a Bidder may submit a written application with its bid requesting a partial or total waiver of such requirements, setting forth the reasons for the Bidder’s inability to meet any or all of the participation requirements and an explanation of the efforts undertaken by the Bidder to obtain the required participation of certified businesses. The County’s Director of DEI will evaluate utilization waiver applications to determine if the Bidder’s efforts are sufficient to grant the waiver. Efforts to obtain SDVOB participation that are merely pro forma are not best efforts, nor are efforts that, even if they are sincerely motivated, given all relevant circumstances, could not reasonably be expected to produce a level of SDVOB participation sufficient to meet the goal. In order to evaluate a Bidder’s best efforts, the County’s Director of DEI will consider the quality, quantity, and intensity of the different kinds of efforts that the Bidder has made. Below is a list of the types of actions which the County’s Director of DEI will consider as part of the Bidder’s best efforts to obtain SDVOB participation. It is not intended to be a mandatory checklist, nor is it intended to be exhaustive or exclusive. Other factors or types of efforts may be relevant in appropriate cases:

1. The Bidder shall conduct market research to identify small business contractors and suppliers and solicit, through all reasonable and available means, the interest of all Certified SDVOB Firms that have the capability to perform the work of the contract. This may include attendance at pre-bid and business matchmaking meetings and events; advertising and/or written notices; posting of notices of sources sought and/or requests for proposals, written notices or emails to all Certified SDVOB Firms listed in the appropriate directory of certified firms that specialize in the areas of work desired and which are located in the area or surrounding area.

2. The Bidder shall solicit this interest as early in the bidding process as practicable, to allow the Certified SDVOB Firms to respond to the solicitation and submit a timely offer. The Bidder shall determine with certainty if the Certified SDVOB Firms are interested by taking appropriate steps, including following up the initial solicitation with at least one additional solicitation via a different media. The Bidder shall solicit quotes from Certified SDVOB Firms listed in the NYS or US SBA SDVOB Directories regardless if they have their own database of SDVOB firms. The Bidder shall keep records of efforts to solicit and negotiate with Certified SDVOB Firms as evidence of best efforts. These records must include the firms contacted, method of contact, evidence of actions, and contact information of individuals that were sent outreach efforts Certified SDVOB Firms shall be given a minimum of 10 business days to submit quotes.

3. Selecting portions of the work to be performed by Certified SDVOB Firms in order to increase the likelihood that the SDVOB goal will be achieved. This includes, where appropriate, either breaking down operations or combining like or related operations into logistically and economically feasible units to facilitate SDVOB participation, even when the Bidder might prefer to perform these work items with its own forces. This may include, where possible, establishing flexible time frames for performance and delivery schedules in a manner that encourages and facilitates SDVOB participation.

4. Providing interested Certified SDVOB Firms with adequate information on where and how to obtain the plans, specifications, and requirements of the contract in a timely manner to assist them in responding to a solicitation with their timely offer.

5. Negotiating in good faith with interested Certified SDVOB Firms. It is the Bidder’s responsibility to make a portion of the work available to Certified SDVOB Firms subcontractors and material suppliers and to select those portions of the work or material needs consistent with the available SDVOB subcontractors and material suppliers in order to facilitate SDVOB participation. Evidence of such negotiation includes the names, addresses, and telephone numbers of Certified SDVOB Firms that were considered; a description of the information provided regarding the plans and specifications for the work selected for subcontracting; and evidence as to why additional agreements could not be reached for Certified SDVOB Firms to perform the work.

6. Additional Costs. The fact that there may be some additional costs involved in finding and using Certified SDVOB Firms is not in itself sufficient reason for a bidder's failure to meet the contract SDVOB goal, as long as such costs are reasonable. The ability or desire of a Bidder to perform the work of a contract with its own organization does not relieve the Bidder of the responsibility to make best efforts.

7. Replacement Firms. A prime contractor’s inability to find a replacement Certified

SDVOB Firms at the original price is not sufficient to support a finding that best efforts have been made to replace the original Certified SDVOB Firm. The fact that the contractor has the ability and/or desire to perform the contract work with its own forces does not relieve the contractor of the obligation to make best efforts to find a replacement Certified SDVOB Firms, and it is not a sound basis for rejecting a prospective replacement Certified SDVOB Firms reasonable quote.

8. Making efforts to assist interested Certified SDVOB Firms in obtaining bonding, lines of credit or insurance as required by the Department or the Bidder.

9. Making efforts to assist interested Certified SDVOB Firms in obtaining necessary equipment, supplies, materials, or related assistance.

10. The County’s M/WBE/SDVOB Program Manager will provide assistance to potential bidders in connecting with Certified SDVOB Firms.

2. Payment Deductions

The Bidder’s failure to perform in accordance with an approved SDVOB Utilization Plan shall constitute a default by the Bidder of the obligations under the Contract. In the event of such a default by the Bidder, the County shall be entitled to deduct payment to the Bidder in the percentage amount of the Contract which equals the Bidder’s shortfall from the SDVOB participation goals for this project. Such deductions by the County may begin with the Bidder’s initial payment application, and will carry-over to subsequent payment applications until the total amount of the deductions equals the amount of the SDVOB participation goal shortfall. In the event the Bidder thereafter performs in accordance with an approved SDVOB Utilization Plan, the County will reimburse any payment deductions made pursuant to this provision.

In the event the Bidder continues to fail to perform in accordance with an approved SDVOB Utilization Plan, the County will retain any payment deductions made pursuant to this provision and may seek any other rights and remedies available to the County under law or in equity.

3. Definitions. The following terms are defined as follows:

A. Certified SDVOB Firms—Federal SDVOSB Certified Contractors and/or

State SDVOB Certified Contractors.

B. Federal SDVOSB Certified Firms—Service–Disabled Veteran–Owned

Small Business Concerns that have been certified by the U.S. Small Business Administration in accordance with 13 C.F.R. Part 128.

C. SDVOB Utilization Plan—A plan prepared by a contractor and submitted in connection with a proposed county contract. The utilization plan shall identify Certified SDVOB Firms, if known, that have committed to perform work in connection with the proposed county contract as well as any such Certified SDVOB Firms, if known, which the contractor intends to use in connection with the contractor’s performance of the proposed county contract. The plan shall specifically contain a list, including the name, address and telephone number, of each Certified SDVOB Firms with which the contractor intends to subcontract.

D. State SDVOB Certified Firms—Service-Disabled Veteran-Owned Business

Enterprises that have been certified by the New York State Division of Service- Disabled Veterans’ Business Development in accordance with Veterans' Services Law § 41.

BP#0902-26

GENERATOR AND FIRE PUMP

MAINTENANCE AND REPAIR

SPECIFICATIONS

SECTION 1: GENERAL REQUIREMENTS

1.1 PURPOSE AND REQUIREMENTS

The Contractor shall provide all labor, transportation, materials, tools, equipment, and certified technicians required to perform comprehensive Preventative Maintenance (PM) inspections, services, and supplemental load bank testing for the County’s emergency standby generator and fire pump infrastructure systems.

All work must comply with current NFPA 110 (Standard for Emergency and Standby Power Systems), NFPA 25 (Standard for the Inspection, Testing,…