BP-3A_Addendum No.2.pdf
PDF 46 KB Posted
- Solicitation number
- RFP BCPS 210000001095 3
- Issued by
- Kent County, Brooklyn Village, Michigan
About this file
This is an addendum to the original contract documents for Byron Center Public Schools' 2020 Bond Project BP-3A regarding Intermediate School Earthwork and Pavements. Addendum No. 2, issued on March 5, 2021, serves as a modification to the previously distributed contract documents and is incorporated as part of the overall Contract Documents. The addendum addresses changes, clarifications, and corrections to the original bid specifications and may or may not result in cost adjustments to contractor proposals.
The addendum provides a reference drawing in the form of a comprehensive grading site plan prepared by TowerPinkster to assist bidding trades in developing accurate proposals. Contractors are required to incorporate any changes in cost resulting from this addendum into their formal proposals. No specific response dates, site visit requirements, or bidders' meetings are detailed in this addendum document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BP-3A_Addendum No.1.pdf | ||
| 02.BP-3A_Advertisement to Bid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Byron Center Public Schools ADDENDUM NO. 2
BP-3A: Intermediate School -Earthwork and Pavements
Bids & Construction | Addendum No.2 | 03.05.2021 Page 1 of 1
March 5, 2021
Byron Center Public Schools
PROJECT: 2020 Bond, BP-3A: Intermediate School -Earthwork and Pavements
ADDENDUM NO. 2
The following items are changes, clarifications, corrections of errors, etc., with respect to the Contract
Documents previously issued. This addendum shall be a part of the Contract Documents.
Items listed below may or may not affect the cost of the Contractor's Proposal. Changes in cost shall be incorporated in the Contractor's Proposal.
ITEM No. 1: DRAWING FOR REFERENCE ONLY –ATTACHED
• See TowerPinkster’s Addendum No. 2 summary write-up information for the provided comprehensive grading site plan to assist trades in bidding efforts.
File details come from the government source that posted it. Updated .