boynton 27-014B Boynton Harbor Marina Fuel System Electrical Conduit and Piping Sump Repairs - Final .pdf

PDF 2 MB Posted

Attached to
Boynton Harbor Marina Fuel System Electrical Conduit & Piping Sump Repairs
Solicitation number
ITB No. 27-014B
Issued by
Palm Beach County, Florida

About this file

This document is a final project specification for Boynton Harbor Marina Fuel System Electrical Conduit and Piping Sump Repairs, issued by the City of Boynton Beach, Florida, under Bid No. 26-112B. The project scope includes replacement of all corroded rigid metal conduit (RMC) with marine-grade rigid aluminum conduit, replacement of deteriorated electrical fittings, removal and replacement of electrical conduit and fuel/vent piping entry boots, and repair of product piping entry boots at gasoline and diesel storage tank platform (STP) sumps using ICON material. The work additionally requires raising all electrical fittings and seal-offs to a minimum of 6 inches above finished dock or concrete surfaces and coordination of all required inspection hold points with the engineer, owner, and Florida Department of Environmental Protection representative. The contractor must furnish all labor, tools, equipment, materials, transportation, and services necessary to complete the project in accordance with the bid documents, design plans (MDM Drawings G-1.0, G-2.0, and G-3.0 dated April 29, 2026), and technical specifications provided.

All proposed improvements must be completed in compliance with applicable federal, state, county, and local regulatory requirements, including Florida Administrative Code 62-761 (Florida Underground Storage Tank Regulations), 40 CFR Part 280, 2023 Florida Building Code Eighth Edition, 2023 Florida Fire Prevention Code Eighth Edition, and applicable National Fire Protection Association standards (NFPA 30, 30A, and 303) and the National Electrical Code (NFPA 70). The contractor is responsible for furnishing all required engineering, shop drawings, permits, bonds, securities, licenses, and insurance necessary to complete the project as specified.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID (ITB)

Boynton Harbor Marina Fuel System Electrical Conduit & Piping Sump Repairs

ITB No. 27-014B

PUBLISH DATE:

October 29, 2026

NON-MANDATORY PRE-BID

CONFERENCE:

November 10, 2026 at 10:00 AM

Join Here:

Meeting ID: 212 486 179 255 074 8

Passcode: JG94ts2b +1 872-215-6235,,57476112# United States

BOYNTON HARBOR MARINA

735 CASA LOMA BLVD

BOYNTON BEACH, FL 33435

ALL QUESTIONS DUE:

November 17, 2026 by 3:00 PM

BID DUE AND OPENING DATE:

November 23, 2026 at 3:00 PM

Join Here Meeting ID: 261 861 492 687 956 4

Passcode: n6rW6ec2

+1 872-215-6235,,209813489# United States, CITY OF BOYNTON BEACH

ROOM 115

100 E. OCEAN AVENUE

BOYNTON BEACH, FL 33435

Where to Deliver Bid Submittal

Bids&tenders Online Submission Only

Boynton-beach.bidsandtenders.net

Bonds Required for This Project: Bid Bond, Payment and Performance Bond

City of Boynton Beach Purchasing Division

ITB NO. 27-014B Boynton Harbor Marina – Fuel Dock and Slips

INVITATION TO BID

BOYNTON HARBOR MARINA — FUEL SYSTEM ELECTRICAL CONDUIT & PIPING

SUMP REPAIRS

ITB NO. 27-014B

TABLE OF CONTENTS

ADVERTISEMENT

PURCHASING DIVISION

SECTION I – INSTRUCTION TO BIDDERS – SUBMISSION REQUIREMENTS

1.0 DEFINITIONS

“Addenda”

“Agreement”

“City” or “Owner”

“Contract Administrator”

“Contract Documents”

Defective

Effective Date of the Agreement

“Interested parties”

“Notice to Proceed”

“Online e-procurement system” or “e-procurement system”

“Procurement Services”

“Bidder/Offeror/Responder”

“Invitation to Bid (ITB) Solicitation”

“Sub-Contractor”

“Responsible Bidder”

“Responsive Bidder”

“Successful Bidder" or “Contractor”

“Written Amendment”

“Unit Price or Hourly Wage Work”

1.2 PRE-BID MEETING

1.3 ONLINE E-PROCUREMENT SYSTEM SUBMISSION OF THE BID – (bids&tenders)

1.4 EXAMINATION OF CONTRACT DOCUMENTS AND PROJECT SITE

1.5 ELIGIBILITY OF BIDDER

1.6 MINIMUM QUALIFICATIONS OF BIDDERS

1.7 REFERENCES AND REFERENCE CHECK / DISQUALIFICATION PROCEDURE

1.8 CONTACT INFORMATION AND QUESTIONS

1.9 CLARIFICATIONS, QUESTIONS AND ADDENDA FOR THIS SOLICITATION

1.10 MISTAKES WITHIN SOLICITATION

1.11 SUBMISSION OF THE BID

1.12 SOLICITATION FORMS

1.13 BID BOND GUARANTY SUBMITTAL

1.14 BIDDER'S COMPLIANCE WITH FLORIDA STATUTES AND CITY CODES

1.13.1 ANTI-KICKBACK AFFIDAVIT

1.13.2 NON-COLLUSION AFFIDAVIT

1.13.3 FOREIGN ENTITY AFFIDAVIT

1.13.4 ANTI-HUMAN TRAFFICKING AFFIDAVIT

1.13.5 CONFLICT OF INTEREST

1.13.6 E-VERIFY FORM UNDER SECTION 448.095

1.13.7 CERTIFICATION PURSUANT TO FLORIDA STATUTE § 287.135

1.13.8 ANTITRUST CAUSE OF ACTION (Bid Rigging)

1.15 SUB-CONTRACTORS

1.16 ESCALATOR CLAUSE

1.17 EXCEPTIONS BY BIDDER

1.18 QUANTITIES

1.19 BID TABULATION

1.20 UNBALANCED BIDS

1.21 UNIT PRICES AND ADDITIONAL QUANTITY

1.22 TIE BIDS

1.23 EXECUTION OF SOLICITATION DOCUMENTS

1.24 SOLICITATION DEADLINE

1.25 CITYS RIGHT TO REJECT BID SUBMITTALS

1.26 DISQUALIFICATION OF BIDDER

1.27 NO SUBMITTAL

1.28 INTERPRETATIONS/CONE OF SILENCE/LOBBYING

1.29 TRADE SECRET

1.30 WITHDRAWAL OF BID

1.31 PROTEST PROCEDURE

1.32 CONFLICT OF INTEREST / GIFT POLICY

1.33 GIFT POLICY

1.34 CONFIRMATION OF MINORITY-OWNED BUSINESS

1.35 AWARD OF CONTRACT

1.36 SAMPLE DRAFT AGREEMENT

1.37 SIGNING OF CONTRACT

1.38 PAYMENT AND PERFORMANCE BOND

1.39 ON PUBLIC ENTITY CRIMES CONVICTED VENDOR LIST

1.40 BUSINESS INFORMATION – JOINT VENTURE

1.41 PROHIBITION AGAINST CONSIDERING SOCIAL, POLITICAL, OR IDEOLOGICAL

INTERESTS IN GOVERNMENT CONTRACTING

SECTION II – SPECIAL CONDITIONS

2.1 HISTORY AND BACKGROUND OF THE CITY OF BOYNTON BEACH

2.2 PURPOSE OF PROJECT

2.3 SCOPE AND DESCRIPTION OF WORK

2.4 DETAILED REQUIREMENTS

2.5 INSPECTION HOLD POINTS

2.6 Applicable Codes, Standards, and References (Technical Compliance)

2.7 SAFETY REQUIREMENTS

2.8 LICENSES

2.9 PROJECT TIMELINE

2.10 ENGINEERS ESTIMATE

2.11 LIQUIDATED DAMAGES

2.12 ENUMERATION OF PRECEDENCE OF BID DOCUMENTS

2.13 INTENT

2.14 PERFORMANCE, PAYMENT AND WARRANTY BONDS

2.15 SUBMITTALS

2.16 ASSIGNMENT OF CONTRACT

2.17 INSURANCE REQUIREMENTS

2.18 TERMINATION

2.18.1 DEFAULT AND TERMINATION FOR CAUSE:

2.18.2 TERMINATION FOR CONVENIENCE OF CITY

2.18.3 REMEDIES:

2.18.4 FUNDING OUT

2.19 DIRECT OWNER PURCHASES

2.20 CONTRACTOR’S RESPONSIBILITY

2.21 DAMAGE TO PUBLIC AND/OR PRIVATE PROPERTY

2.22 PERMITS AND LICENSES

2.23 SITE INSPECTION – CITY

2.24 WAIVER OF LIENS

2.25 PAYMENT

2.26 CONTRACT DOCUMENTS

2.27 CHANGE ORDERS

2.28 CHANGES TO SCOPE AND ADDITIONAL SERVICES

2.29 CHANGES IN THE WORK/CONTRACT PRICE

2.30 CHANGES IN CONTRACT TIME

2.31 CITY’S OPTION

2.32 LOCATION OF EXISTING UTILITIES

2.33 CONFLICT WITH EXISTING UTILITIES

2.31 CONTINGENCY FUNDING

SECTION III – GENERAL TERMS AND CONDITIONS

3.1 FAMILIARITY AND COMPLIANCE WITH LAWS, LEGAL CONDITIONS CODES AND

REGULATIONS:

3.2 CONFLICT OF INTEREST

3.3 DISPUTES

3.4 FEDERAL AND STATE TAX:

3.5 PURCHASE ORDER REQUIRED:

3.6 COMPLIANCE WITH OCCUPATIONAL SAFETY AND HEALTH:

3.7 PALM BEACH COUNTY INSPECTOR GENERAL:

3.8 OTHER AGENCIES

3.9 VENUE AND GOVERNING LAW:

3.10 NON-DISCRIMINATION & EQUAL OPPORTUNITY EMPLOYMENT

3.11 INDEPENDENT CONTRACTOR RELATIONSHIP:

3.12 OMISSION OF DETAILS

3.13 LEGAL EXPENSES:

3.14 NO THIRD-PARTY BENEFICIARIES:

3.15 SCRUTINIZED COMPANIES:

3.16 NON-EXCLUSIVE

3.17 ENDORSEMENTS

3.18 DRUG-FREE WORKPLACE

3.19 PROHIBITED TELECOMMUNICATIONS EQUIPMENT

3.20 RIGHTS IN DATA

3.21 DOCUMENTATION OF COSTS

3.22 PUBLIC RECORDS

3.23 SOVEREIGN IMMUNITY

GENERAL CONDITIONS FOR CONSTRUCTION

ARTICLE 1 – DEFINITIONS

CONSULTANT

ARTICLE 2 – PRELIMINARY MATTERS

2.1 DELIVERY OF BONDS AND INSURANCE CERTIFICATES:

2.2 COPIES OF DOCUMENTS:

2.3 NOTICE TO PROCEED:

2.4 COMMENCEMENT THE WORK:

2.5 PRE-CONSTRUCTION MEETING:

2.6 SITE MOBILIZATION MEETING:

2.7 PROGRESS MEETINGS

2.8 PRE-INSTALLATION MEETING:

2.9 FINALIZING SCHEDULES:

2.10 SUBMITTAL PROCEDURES:

2.10.2 RELATED SECTIONS:

2.10.4 PRODUCT DATA

2.10.5 CONSTRUCTION SUBMITTALS

ARTICLE 3 – USE OF CONTRACT DOCUMENTS

3.1 INTENT:

3.2 REFERENCE TO STANDARDS:

3.3 REVIEW OF CONTRACT DOCUMENTS:

3.4 ORDER OF PRECEDENCE OF CONTRACT DOCUMENTS:

3.5 AMENDING CONTRACT DOCUMENTS:

3.6 REUSE OF DOCUMENTS:

ARTICLE 4 – SITE OF WORK

4.1 AVAILABILITY OF LANDS:

4.2 REPORTS OF PHYSICAL CONDITIONS:

4.3 PHYSICAL CONDITIONS – UNDERGROUND FACILITIES:

4.4 DIFFERING SITE CONDITIONS

4.5 REFERENCE POINTS:

ARTICLE 5 – BONDS AND INSURANCE

5.2 INSURANCE:

ARTICLE 6 – CONTRACTOR’S RESPONSIBILITIES

6.1 CONTRACTOR STATUS:

6.2 CONTRACTOR RISK:

6.3 SUPERVISION AND SUPERINTENDENCE:

6.4 LABOR, MATERIALS AND EQUIPMENT:

6.5 CONCERNING SUBCONTRACTORS:

6.6 PATENTS, FEES AND ROYALTIES:

6.7 PERMITS, LAWS AND REGULATIONS:

6.8 TAXES:

6.9 RECORD DOCUMENTS/RIGHT TO AUDIT:

6.10 SAFETY, PROTECTION AND EMERGENCIES:

6.11 SHOP DRAWINGS AND SAMPLES:

6.12 SITE CLEAN UP:

6.13 PUBLIC CONVENIENCE AND SAFETY:

6.14 SANITARY PROVISIONS:

6.15 INDEMNIFICATION:

6.16 CLAIMS:

6.17 RESPONSIBILITY FOR CONNECTING TO EXISTING WORK:

6.18 WORK IN STREET, HIGHWAY AND OTHER RIGHTS-OF-WAY:

6.19 COOPERATION WITH GOVERNMENTAL DEPARTMENTS, PUBLIC UTILITIES, ETC.:

6.20 USE OF PREMISES:

6.21 PROTECTION OF EXISTING PROPERTY IMPROVEMENTS:

6.22 TEMPORARY HEAT:

6.23 SCHEDULE:

6.24 CONTINUING THE WORK:

6.25 CONTRACTOR’S GENERAL WARRANTY AND GUARANTEE:

6.26 DELETION/OVERSIGHT/MISSTATEMENT:

6.27 EXCEPTIONS TO SPECIFICATIONS:

6.28 SILENCE OF SPECIFICATIONS:

6.29 QUALITY:

6.30 CONDITIONS OF MATERIALS:

6.31 DISPOSAL:

6.32 OCCUPATIONAL HEALTH AND SAFETY:

6.33 OCCUPATIONAL, SAFETY AND HEALTH ASSOCIATION (OSHA)

6.34 CONDITIONS AND PACKAGING:

6.35 UNDERWRITERS’ LABORATORIES (UL):

6.36 ASBESTOS:

6.37 CLOSE-OUT SUBMITTALS

6.37.2 CLOSE-OUT PROCEDURES

6.37.3 FINAL CLEANING

6.37.4 ADJUSTING

6.37.5 PROJECT RECORD DOCUMENTS

6.37.6 OPERATION AND MAINTENANCE DATA:

6.37.7 SPARE PARTS AND MAINTENANCE PRODUCTS:

6.37.8 WARRANTIES:

6.37.9 MAINTENANCE SERVICE:

6.37.10 ASBESTOS CERTIFICATION:

6.37.11 PRODUCTS:

6.38 TEMPORARY BARRIERS AND ENCLOSURES:

6.38.2 ENTRY CONTROL:

6.38.3 DEMISING WALLS:

6.38.4 TEMPORARY FENCING:

6.39 ENVIRONMENTAL CONTROLS:

6.39.8 SUBMITTALS:

6.39.9 TEMPORARY FENCING:

6.39.10 TEMPORARY WALLS:

6.39.11 EXECUTION/INSTALLATION AND REMOVAL:

6.40 SECURITY PROCEDURES:

6.40.4 PERSONNEL IDENTIFICATION:

6.40.5 SUBMITTALS:

6.41 PRODUCT SUBSTITUTION PROCEDURES

6.41.2 CONTRACTOR’S SUBMITTAL PROCEDURES:

6.41.3 SUBSTITUTION REQUESTS

6.41.4 SCOPE OF WORK:

6.41.5 COORDINATION AND PROJECT CONDITIONS

6.42 FIELD ENGINEERING

ARTICLE 7 – OTHER WORK

7.1 RELATED WORK AT SITE:

7.2 COORDINATION:

ARTICLE 8 – THE CITY’S RESPONSIBILITIES

8.1 COMMUNICATIONS TO CONTRACTOR:

8.2 FURNISH DATA:

8.3 PAYMENTS:

8.4 LANDS, EASEMENTS: REPORTS AND TESTS:

8.5 CHANGE ORDERS:

8.6 SUSPENSION OF WORK:

8.7 ESTIMATED DOLLAR VALUE:

8.8 QUANTITIES:

8.9 ADDITIONAL TERMS AND CONDITIONS:

ARTICLE 9 – CONSULTANT’S STATUS DURING CONSTRUCTION:

9.1 CITY’S REPRESENTATIVE:

9.2 VISITS TO SITE:

9.3 PROJECT REPRESENTATION:

9.4 CLARIFICATIONS AND INTERPRETATIONS:

9.5 MEASUREMENTS:

9.6 REJECTING DEFECTIVE WORK:

9.7 SHOP DRAWINGS, CHANGE ORDERS AND PAYMENTS:

9.8 DETERMINATIONS FOR UNIT PRICES:

9.9 DECISIONS ON DISPUTES:

9.10 INSPECTION AND TESTING:

9.11 LIMITATIONS ON CONSULTANT:

ARTICLE 10 – CHANGES IN THE WORK

10.1 AUTHORIZED CHANGES IN THE WORK

10.2 UNAUTHORIZED CHANGES IN THE WORK

10.3 EXECUTION OF CHANGE ORDERS:

ARTICLE 11 – CHANGE OF CONTRACT PRICE

11.1 GENERAL

11.2 COST OF THE WORK:

11.3 CONTRACTOR’S FEE:

11.4 ALLOWANCES:

11.5 UNIT PRICE WORK:

11.6.1 OMITTED WORK:

ARTICLE 12 – CHANGE OF CONTRACT TIME

12.1 GENERAL

12.2 LIQUIDATED DAMAGES

ARTICLE 13 – TESTS AND INSPECTIONS, CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK

13.1 NOTICE OF DEFECTS:

13.2 ACCESS TO WORK:

13.3 TESTS AND INSPECTIONS:

13.4 UNCOVERING WORK:

13.5 CITY MAY STOP THE WORK:

13.6 CORRECTION OR REMOVAL OF DEFECTIVE WORK:

13.7 ONE-YEAR CORRECTION PERIOD:

13.8 ACCEPTANCE OF DEFECTIVE WORK:

13.9 CITY MAY CORRECT DEFECTIVE WORK:

ARTICLE 14 – PAYMENTS TO CONTRACTOR AND COMPLETION:

14.1 SCHEDULE OF VALUES

14.2 UNIT PRICE BID SCHEDULE

14.3 APPLICATION FOR PAYMENTS:

14.4 CONTRACTOR’S WARRANTY OF TITLE:

14.5 REVIEW OF APPLICATIONS FOR PAYMENT:

14.6 SUBSTANTIAL COMPLETION:

14.7 PARTIAL UTILIZATION:

14.8 FINAL INSPECTION:

14.9 FINAL APPLICATION FOR PAYMENT:

14.10 FINAL PAYMENT AND ACCEPTANCE:

14.11 WAIVER OF CLAIMS:

14.12 PUNCHLIST PROCEDURES:

14.13 RETAINAGE PROCEDURES:

ARTICLE 15 – SUSPENSION OF WORK AND TERMINATION:

15.1 CITY MAY SUSPEND/STOP WORK:

15.2 CITY MAY TERMINATE FOR CAUSE:

15.3 CITY MAY TERMINATE WITHOUT CAUSE:

15.4 REMOVAL OF EQUIPMENT DUE TO TERMINATION:

15.5 CONTRACTOR MAY STOP WORK OR TERMINATE:

ARTICLE 16 -DISPUTE RESOLUTION

16.1 GOOD FAITH EFFORT:

16.2 MEDIATION:

ARTICLE 17 – MISCELLANEOUS:

17.1 GIVING NOTICE:

17.2 COMPUTATION OF TIME:

17.3 NOTICE OF CLAIM:

17.4 CULMULATIVE REMEDIES:

17.5 ACCIDENT AND PREVENTION:

17.6 FLORIDA PRODUCTS AND LABOR:

17.7 EMPLOYEES:

17.8 NON-DISCRIMINATION:

17.9 DRUG-FEE WORKPLACE:

17.10 PUBLIC ENTITY CRIMES:

17.11 ASSIGNMENT:

17.12 VENUE:

17.13 FUNDING OUT:

17.15 DEBARMENT:

17.16 REQUIREMENTS FOR PERSONNEL ENTERING CITY PROPERTY:

17.17 PRODUCT RECALL:

17.18 RIGHTS TO BID DOCUMENTS:

17.19 SEVERABILITY:

17.20 VERIFICATION OF EMPLOYMENT STATUS:

17.21 ABBREVIATIONS AND SYMBOLS:

SECTION IV – BID SCHEDULE FORM

DRAFT - AGREEMENT CONSTRUCTION (CONTRACTOR)

Article 1. SCOPE OF WORK

Article 2. CONSULTANT

Article 3. CONTRACT TIME, TERMINATION, LIQUIDATED DAMAGES

Article 4. CONTRACT PRICE

Article 5. PAYMENT PROCEDURES

Article 6. BONDS

Article 7. CONTRACTOR GUARANTEE

Article 8. CHANGE ORDER

Article 9. CONTRACTOR’S UNDERSTANDING

Article 10. CONTRACT DOCUMENTS

Article 11. NOTICE

Article 12. INDEMNIFICATION

Article 13. REIMBURSEMENT OF CONSULTANT EXPENSES

Article 14. FLORIDA’S PUBLIC RECORDS LAW

Article 15. E-VERIFY

Article 16. REPRESENTATIONS OF CONTRACTOR

Article 17. LIENS

Article 18. IRON AND STEEL PRODUCTS

Article 19. INSURANCE

Article 20. DEFAULT OF CONTRACT & REMEDIES

Article 21. SOVEREIGN IMMUNITY

Article 22. FORCE MAJEURE

Article 23. MATERIALITY AND WAIVER OF BREACH

Article 24. INDEPENDENT CONTRACTOR

Article 25. OWNERSHIP AND USE OF DOCUMENTS

Article 26. ATTORNEY’S FEES

Article 27. WAIVER OF CHAPTER 558, FLORIDA STATUTES

Article 28. SURVIVAL

Article 29. TERMINATION FOR NON-APPROPRIATION

Article 30. THIRD-PARTY BENEFICIARIES

CORPORATE ACKNOWLEDGEMENT

APPENDIX I - VENDOR INSURANCE REQUIREMENTS – PROCUREMENT

APPENDIX 2 – BIDDER REFERENCE LIST FORM

APPENDIX 3 – REFERENCE CHECK SCORE SHEET (FOR CITY USE ONLY)

Attachments:

Exhibit 1 – PBCERM - Approved Plans

Exhibit 2 – Boynton Harbor Marina Engineering Inspection Report

Attachment C – Geotechnical Report

ITB NO 27-014B BOYNTON HARBOR MARINA — FUEL SYSTEM ELECTRICAL CONDUIT & PIPING SUMP REPAIRS

THE CITY OF BOYNTON BEACH

ADVERTISEMENT

NOTICE TO BIDDERS

FOR

BOYNTON HARBOR MARINA — FUEL SYSTEM ELECTRICAL CONDUIT &

PIPING SUMP REPAIRS

ITB NO. 27-014B

Electronic Invitation To Bid (ITB’s) shall be received by the e-procurement system up until November 23, 2026; No Later Than 3:00 P.M. (Local Time); unless specified otherwise and may not be withdrawn within ONE HUNDRED TWENTY (120) days after such date and time.

All ITB’s received will be publicly opened and acknowledged of receipt by the City’s Procurement Department via the e-procurement system electronically. The e-procurement system does not permit ITB’s received after the assigned date and time. For the above reasons, it is recommended that the proposer(s) allow sufficient time to complete your online Submission and to resolve any issues that may arise.

ATTENTION, ALL INTERESTED BIDDERS:

To obtain documents online, please visit Boynton-beach.bidsandtenders.net. and https://boynton-beach.bidsandtenders.net/Module/Tenders/en. Documents are not provided in any other manner.

SCOPE OF SERVICES:

The City of Boynton Beach “City” Public Works Engineering Department is requesting sealed bids from qualified and experienced firms to provide construction services for the complete repair of existing deficiency’s at the Boynton Harbor Marina — Fuel System Electrical Conduit & Piping Sump Repairs located at 735 Casa Loma Blvd., Boynton Beach, FL 33435. The work includes the replacement of all corroded rigid metal conduit (RMC) with marine-grade Rigid Aluminum Conduit, replacement of deteriorated electrical fittings, removal and replacement of electrical conduit and fuel/vent piping entry boots, repair of product piping entry boots at the gasoline and diesel STP sumps using ICON, raising of all electrical fittings and seal-offs to a minimum of 6 inches above the finished dock/concrete surface, coordinate and pass all required inspection hold points with the Engineer, Owner, and Florida DEP representative. The project includes repairing all other items as necessary to correct existing deficiencies as well as repairing the design as shown on MDM Drawings G-1.0, G-2.0, and G-3.0 (dated 04-29-2026), in support of compliance with FAC 62-761 and 40 CFR Part 280.

The Contractor shall furnish all labor, tools, equipment, materials, supplies, manufactured articles, furnishing all transportation and services, and essential communications, etc., as necessary to complete the project, as indicated in the Special Conditions, Special Provisions, Project Design Plans, Technical Specifications and Bid No. 26-112B Documents herein, along with all engineering, shop drawings, and other documentation necessary to obtain all applicable permits and all bonds, securities, licenses and insurance to complete the project as specified herein and within the Project Design Plans. All proposed improvements shall be completed in accordance with the project bid documents, design plans, details, technical specifications/scope of work and all applicable federal, state, county and local regulatory requirements including but not limited to FAC 62-761 (Florida UST Regulations); 40 CFR Part 280; 2023 Florida Building Code, 8th Ed.;

2023 Florida Fire Prevention Code, 8th Ed.; NFPA 30, 30A, 303; NEC (NFPA 70).

The City reserves the right to award more than one Bidder. The Bidder(s) shall act as an independent contractor and not as an employee of the City.

Questions related to this ITB are to be submitted to the Purchasing representative through the e-procurement system only by clicking on the “Submit a Question” button for this specific solicitation.

PRE-BID CONFERENCE:

A NON-MANDATORY Pre-bid Conference & possible Site Visit is scheduled for November 10, 2026, at 10:00 A.M. to be held at Boynton Harbor Marina, 735 Casa Loma Blvd, Boynton Beach, Florida 33435. Please note that this meeting will be recorded and uploaded to Bids&Tenders but it is highly encouraged that all parties interested in bidding on this project should try to attend this meeting.

The purpose of this meeting is to provide a forum for all concerned parties to discuss the proposed term contract, answer questions on the solicitation document, review the qualifications requested, provide instructions for submitting proposals, and discuss other relevant issues.

In the event that any discussions or questions at the pre-bid meeting require, in the City’s opinion, official additions, deletions, or clarifications of the solicitation or any other document, the City will issue an addendum to this ITB, as the City determines is appropriate.

No oral representation or discussion taking place at the pre-bid meeting will be binding or may be relied upon by any person or entity. All questions prior to and after the pre-bid meeting shall be submitted in writing through the City’s e-procurement platform by the deadline for questions outlined on page # 1.

LOBBYING / CONE OF SILENCE:

Consistent with the requirements of Chapter 2, Article VIII, Lobbyist Registration, of the Palm Beach County Code of Ordinances, Boynton Beach imposes a Cone of Silence. A cone of silence shall be imposed upon each competitive solicitation as of the deadline to submit the proposal, bid, or other response and shall remain in effect until the City Commission awards or approves a contract, rejects all bids or responses, or otherwise takes action that ends the solicitation process.

While the cone of silence is in effect, no Offeror or its agent shall directly or indirectly communicate with any member of the City Commission or their staff, the Manager, any employee of Boynton Beach authorized to act on behalf of Boynton Beach in relation to the award of a particular contract or member of the Selection Committee in reference to the solicitation, with the exception of the Purchasing Manager or designee. (Section 2-355 of the Palm Beach County Code of Ordinances.) Failure to abide by this provision may serve as grounds for disqualification for award of contract to the Offeror. Further, any contract that violates the cone of silence shall render the transaction voidable.

The cone of silence shall not apply to oral communications at any public proceeding, including pre-bid conferences, oral presentations before Selection Committees, contract negotiations during any public meeting, presentations made to the City Commission, and protest hearings.

Further, the cone of silence shall not apply to contract negotiations between any employee and the intended awardee, any dispute resolution process following the filing of a protest between the person filing the protest and any employee, or any written correspondence with Boynton Beach as may be permitted by the competitive solicitation. Additionally, the cone of silence shall not apply to any purchases made in an amount less than the competitive solicitation threshold set forth in the Purchasing Manual.

PUBLIC RECORDS DISCLOSURE:

Pursuant to Florida Statutes §119.071, sealed Proposal responses received by the City in response to an Invitation to bid are exempt from public records disclosure requirements until thirty

(30) days after the opening of the Proposals unless the City announces intent to award sooner. If the City rejects all Responses submitted in accordance with an Invitation To Bid, and the City concurrently provides notice of its intent to reissue the competitive solicitation, the rejected Responses remain exempt from public disclosure until such time as the City provides notice of a decision or intended decision concerning the competitive solicitation or until the City withdraws the reissued competitive solicitation. A Bid response, or reply is not exempt for longer than twelve

(12) months after the initial City notice rejecting all Bids.

PURCHASING DIVISION

Our Mission Statement: We are unwavering in our commitment to promoting integrity, transparency, and fairness in every step of the procurement process. This dedication is the cornerstone of our mission.

We strive to maximize value for our community by fostering competitive opportunities for local businesses, ensuring compliance with regulations, and delivering exceptional service to our stakeholders. Through collaboration, planning, and innovation, we aim to support the city’s goals while enhancing the economic vitality of our region.

Our Purpose: The City of Boynton Beach's Purchasing Division is dedicated to fostering equitable and fair competition in our solicitations through a transparent procurement process. We actively collaborate with local vendors to ensure that every participant has an equal opportunity to secure government contracts. Our commitment to fairness and transparency is unwavering.

Our Key Goals: As guardians of the public trust, our Purchasing Division is deeply committed to its purpose and mission. Upholding the values of vision, integrity, efficiency, and quality service, we strive to fulfill our commitments with unwavering dedication.

Our Community Impact: Our local, state, and nationwide vendors are essential partners in our purpose and mission. We are dedicated to collaborating with qualified, competitive vendors who share our commitment to quality, efficiency, teamwork, and exceptional customer service.

A Message to our Vendors and the Community:

Your work as a vendor is not just about delivering products and services. It's about enhancing the overall value of our services to our residents. We expect high-quality products and efficient services, delivered on time and as specified, to make a real difference in our community.

Additionally, we anticipate that our vendors will collaborate with us as a team and maintain the highest standards of integrity in all interactions with the city’s offices and departments. These are expectations and standards we hold all our vendors to.

Diligence in fulfilling the requirements of this solicitation will significantly enhance the overall quality of services delivered to our community. The City seeks a firm that embodies these principles in its work, and the successful candidates will be evaluated against the performance standards detailed in this solicitation.

ITB NO. 27-014B Boynton Harbor Marina Fuel System Electrical Conduit & Piping Sump Repairs

BOYNTON HARBOR MARINA — FUEL SYSTEM ELECTRICAL CONDUIT

& PIPING SUMP REPAIRS

ITB No. 27-014B

SECTION I – INSTRUCTION TO BIDDERS – SUBMISSION

REQUIREMENTS

Procurement Definition: It is the intent of the City to award this bid to the lowest responsible and responsive bidder.

The City reserves the right to accept or reject any or all bids and to waive any informality concerning the bids when such a rejection or waiver is deemed to be in the best interest of the City.

1.0 DEFINITIONS

Whenever the following terms appear in the Invitation to Bid, the intent and meaning shall be interpreted as follows:

“Addenda” Written or graphic instruments issued before opening ITBs that clarify, correct, or change the solicitation requirements or the contract document.

“Agreement” The written agreement between the City and the Contractor covering the scope of work to be performed, including other Contract Documents attached to the Agreement and made a part thereof. The words “Agreement” and “Contract” are used interchangeably.

“City” or “Owner” The City of Boynton Beach, Florida, a municipal corporation of the State of Florida “Contract Administrator” The Department’s Director or some other employee expressly designated as Contract Administrator in writing by the Director, who is the representative of the City concerning the Contract Documents.

“Contract Documents” The contract documents consist of this Agreement, conditions of the contract (General, Supplementary, and other Conditions), of this Solicitation, all addenda issued prior to, all modifications issued after execution of this Agreement, Notice of Award, Notice to Proceed, Certificate(s) of Insurance, Bonds and any additional modifications and supplements, Change Orders and Work directive changes issued on or after the effective date of the Contract. These contract documents form the Agreement, and all are as fully a part of the Agreement if attached to this Agreement or repeated therein.

Defective An adjective which when modifying the Work refers to Work that is unsatisfactory, faulty or deficient, or does not conform to the Contract Documents, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents.

Effective Date of the Agreement The date indicated in the Agreement on which it becomes effective, but if no such date is indicated it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver.

“End User (EU)” Internal Member of the City Staff who has requested a procurement service. Also known as a Stakeholder (SH) “Interested parties” Firms or bidders interested in the ITB and plan to eventually become bidders.

“Notice to Proceed” A written notice given by the City to the Contractor fixing the date on which the Contract Time will commence to run and on which the Contractor shall start to perform the Consultant’s obligations under the Contract Documents. Such Notice is to be issued by the City and project Contract Administrator.

“Online e-procurement system” or “e-procurement system” The City of Boynton Beach’s solicitation management system is “bids&tenders.”

“Procurement Services” The Procurement Division - Department of Finance of the City of Boynton Beach.

“Bidder/Offeror/Responder” Any individual, firm, or corporation submitting a bid for this project, acting directly or through a duly authorized representative. For the purpose of this solicitation, the terms “Offeror” and “Bidder” are used interchangeably and have the same meaning.

“Invitation to Bid (ITB) Solicitation” It is the intent of the City to award this bid to the lowest responsible and responsive bidder. The City reserves the right to accept or reject any or all bids and to waive any informality concerning the bids when such a rejection or waiver is deemed to be in the best interest of the City.

“Sub-Contractor” Any person, firm, entity, or organization, other than the employees of the bidder, who contracts with the Contractor to furnish labor, or labor and materials, in connection with the work or services to the City, whether directly or indirectly, on behalf of the Contractor.

“Responsible Bidder” This means a person or firm capable of fully performing the requirements in the ITB and agreement and having the tenacity, perseverance, experience, integrity, reliability, capacity, facilities, equipment, and credit to ensure good faith performance.

“Responsive Bidder” This means a Person or firm who has submitted a bid that conforms in all material respects to the requirements outlined in this ITB.

“Successful Bidder" or “Contractor” The individual or firm who successfully receives the award for work to be completed as defined by this solicitation. Also referred to as Contractor or Vendor.

“Written Amendment” A written amendment of the Contract Documents, signed by the City and the Consultant on or after the Effective Date of the Agreement and typically dealing with non-technical aspects rather than strictly work-related aspects of the Contract Documents.

“Unit Price or Hourly Wage Work” Work to be paid for based on unit prices outlined within the ITB.

1.2 PRE-BID MEETING

The City may hold a pre-bid conference for this project which may include a site visit. The information regarding such meeting will be noted on the cover page or advertisement page of this document.

1.3 ONLINE E-PROCUREMENT SYSTEM SUBMISSION OF THE BID – (bids&tenders)

1.3.1 The City of Boynton Beach utilizes an electronic online e-procurement system service to notify and distribute its solicitation documents; please visit Boynton-beach.bidsandtenders.net.

1.3.2 To obtain documents online, please visit Boynton-beach.bidsandtenders.net.

1.3.3 Before registering for the opportunity, you may preview the solicitation documents with a Preview Watermark. Documents are not provided in any other manner.

1.3.4 Bidders are cautioned that the timing of their Submittal submission is based on when the Submittal is RECEIVED by the e-procurement System, not when a Submittal is submitted, as the Submittal transmission can be delayed due to file transfer size, transmission speed, etc.

1.3.5 For the above reasons, sufficient time is recommended to complete your ITB Submission and resolve any issues that may arise. The online e-procurement system’s web clock shall determine the closing time and date.

1.3.6 Bidders should contact bids&tenders support listed below at least twenty-four (24) hours prior to the closing time and date if they encounter any problems.

1.3.7 The e-procurement system will send a confirmation email to the Bidder advising that their submittal was submitted successfully. If you do not receive a confirmation email, contact bids&tenders support at support@bidsandtenders.net.

1.3.8 Bidders shall be solely responsible for maintaining accurate contact data through the Bids and Tenders system. The City shall under no circumstances be responsible for any errors or omissions in vendor’s contact information on file with

Bids and Tenders. Updates to contact information may be requested by contacting

Bids and Tenders at support@bidsandtenders.org .

1.3.9 It is the Responding firm's responsibility to read and understand the requirements of this bid request. Unless otherwise specified, the Responding firm must use the bid form located online for Invitation for Bid document.

1.3.10 All bids shall be submitted in the English language. All prices, terms and conditions bid in the submitted response shall be expressed in U.S. Dollars and will be firm for acceptance for ONE HUNDRED TWENTY (120) calendar days from the date of the bid opening unless otherwise stated by the City.

1.3.11 The Responding firm preparing a bid in response to this solicitation shall bear all expenses associated with its preparation. The Responding firm shall prepare a bid with the understanding that no claim for reimbursement shall be submitted to the City for expenses related to its preparation.

1.4 EXAMINATION OF CONTRACT DOCUMENTS AND PROJECT SITE

1.4.1 Before submitting a bid, each Offeror must visit the site (if applicable to the project) to become familiar with the facilities and equipment that may in any manner affect cost or performance of the work; must consider federal, state, grant requirements (if Applicable) and local laws, ordinances, rules, and regulations that may in any manner affect cost or performance of the work, must carefully compare the Offeror's observations made during site visits or in a review of applicable laws with the Bid Documents; and must promptly notify the Procurement Officer of all conflicts, errors and discrepancies, if any, in the solicitation documents.

1.4.2 Bidders shall satisfy themselves by personal investigation and by such other means as they may deem necessary or desirable as to the conditions affecting the proposed work and the cost.

1.4.3 No information derived from maps, plans, specifications, or from the Engineer, City Manager, or their assistants or any other department of the City shall relieve the contractor from any risk or from fulfilling all terms of the contract.

1.4.4 The bidder is required to conduct a full and thorough investigation of the premises prior to submitting a bid.

1.4.5 It is the bidder’s sole responsibility to determine the amount of labor and materials needed to complete all aspects of the project.

1.4.6 If the pre-bid meeting is deemed mandatory and a bidder does not attend and sign in to the sign in sheet for the mandatory pre-bid meeting, the bid submission will not be considered.

1.4.7 The Offeror, by and through the submission of a Bid, agrees that it shall be held responsible for having examined the facilities and equipment (if applicable), is familiar with the nature and extent of the work and any local conditions that may affect it, and is familiar with the equipment, materials, parts, and labor required to perform the work successfully.

1.5 ELIGIBILITY OF BIDDER

1.5.1 To be eligible to respond to participate in this ITB, the proposing firm or principals must demonstrate that they, or the principals assigned to the contract, have successfully provided services of similar magnitude as those specified in SCOPE OF WORK (PROJECT) of this solicitation and can demonstrate they have the experience with large-scale private sector clients and the managerial and financial ability to perform the services successfully.

1.6 MINIMUM QUALIFICATIONS OF BIDDERS

1.6.1 No e-submission will be accepted from, nor will any contract be awarded to, any person who is in arrears to the City of Boynton Beach upon any debt or contract or who has defaulted, as surety or otherwise, upon any obligations to the City, or who has been deemed irresponsible or unreliable to the City.

1.6.2 Awards will be based on past performance and quality of work in addition to the Contractor’s ITB response as outlined within this solicitation document.

1.6.3 If selected for a contract, all Contractors must perform to the satisfaction of the City before being considered for award of additional contracts.

1.6.4 A satisfactory record of integrity with previous work performed.

1.6.5 Qualified legally to enter into a Contract within the State of Florida and the City of

Boynton Beach.

1.6.6 Supplied all necessary licensing information in connection with the inquiry concerning responsibility.

1.6.7 Contractors whose performance is unsatisfactory shall be subject to debarment or suspension.

1.7 REFERENCES AND REFERENCE CHECK / DISQUALIFICATION PROCEDURE

1.7.1 Reference Submission Requirement. Each Bidder shall submit, on the City’s Reference List Form (Exhibit 1), a minimum of three (3) and a maximum of five (5) completed projects of similar size, scope, and complexity to the Project, performed within the preceding five (5) years. Each reference shall include the owner/agency name, a current contact name, telephone number, and email address, the original and final contract value, the original and final contract time, and a brief description of the work. Failure to submit the required references with the bid, or upon request by Procurement Services, shall be grounds for a determination of non-responsiveness.

1.7.2 Reference Check Process. The City will contact each listed reference using the City’s standard Reference Check Score Sheet (Exhibit 2) and will complete this process for the apparent low responsive Bidder before recommending award. The City is not obligated to contact references for any Bidder other than the apparent low Bidder unless and until a determination of non-responsibility is made as to that Bidder.

1.7.3 Definition of an Unsatisfactory Reference. A reference is considered unsatisfactory if it discloses any one or more of the following: (i) termination of a contract for default or cause within the preceding five (5) years; (ii) assessment of liquidated damages, or a claim for delay damages, exceeding five percent (5%) of the contract value on a similarly-sized project; (iii) a documented finding of defective work, poor workmanship, or failure to timely correct non-conforming work; (iv) suspension or debarment by any public entity; or (v) the reference states, when asked directly, that it would not recommend or would not re-hire the Bidder for a project of similar size and scope.

1.7.4 Disqualification Threshold. The apparent low Bidder shall be deemed non-responsible, and its bid rejected on that basis, if the reference check returns (i) two

(2) or more Unsatisfactory References, or (ii) one (1) Unsatisfactory Reference involving termination for default/cause or debarment/suspension. This determination is a finding of non-responsibility under Section 1.6 and 1.25 above, not a finding of non-responsiveness, and does not require a determination of collusion, fraud, or misrepresentation.

1.7.5 Notice to Bidder. Procurement Services shall issue a written Notice of Non- Responsibility Determination to the affected Bidder identifying the basis for the determination. The Bidder may submit a written response within three (3) business days of the notice. After considering any timely response, the Purchasing Director (or designee) shall issue a final determination. A Bidder may challenge a final determination only through the Protest Procedure at Section 1.30 above.

1.7.6 Moving to the Next Lowest Bidder. If the apparent low Bidder is determined non-responsible under this Section, the City shall reject that bid and repeat the reference check procedure on the next lowest responsive Bidder, continuing in ascending price order, without the need to cancel or reissue the solicitation. Each successive Bidder subjected to this process shall be given the same notice and response rights described above.

1.7.7 Documentation. Procurement Services shall retain the completed Reference Check Form(s), the Notice of Non-Responsibility Determination (if any), and any Bidder response in the procurement file as the basis for the responsibility determination.

1.8 CONTACT INFORMATION AND QUESTIONS

For inquiries regarding this solicitation Bidders must submit questions online at https://boynton-beach.bidsandtenders.org/Module/Tenders/en Once on the webpage bidder should click the solicitation they are interested in and click the “Submit a Question Button”. All questions will be reviewed by the City and answered in the form of an addendum which will be uploaded to the City’s website and available for all firms registered as plan holders.

1.9 CLARIFICATIONS, QUESTIONS AND ADDENDA FOR THIS SOLICITATION

1.9.1 The City may issue an addendum to change the intent or to clarify the meaning of the solicitation and Contract documents.

1.9.2 Since all addenda are available to Bidders through the City’s e-Procurement system Boynton-beach.bidsandtenders.net, it is the responsibility of each Bidder to have received ALL addenda issued.

1.9.3 Bidders should check online at Boynton-beach.bidsandtenders.net before submitting their bid and until the bid closing time and date in the event, to ensure no additional addenda are issued.

1.9.4 If a Bidder submits their bid before the BID closing time and date and an addendum has been issued, the e-procurement system shall WITHDRAW the bid.

1.9.5 The submittal status will change to an INCOMPLETE STATUS, and the Bid will be withdrawn. The Bidder can view this status change in the “MY BIDS” section of the e-procurement system.

A. The Bidder is solely responsible for creating any required adjustments to their Bid, acknowledging the addenda, and ensuring the re-submitted Bid is RECEIVED by the e-procurement System no later than the stated Bid closing time and date.

B. The Bidder is responsible for submitting written questions or requesting clarification for items included in this solicitation through bids&tenders.

C. Any and all responses to questions or inquiries, interpretations, and supplemental instructions will be in the form of a written addenda, which, if issued, will be posted through bids and tenders.

D. No verbal interpretations may be relied upon.

E. Failure of any Bidder to receive any such addenda or interpretation shall not relieve any Bidder from any obligation under a response as submitted.

All addenda so issued shall become a part of the solicitation document.

F. The Bidder shall acknowledge receipt of any addenda through the e-procurement system by checking a box for each addenda and any applicable attachment.

G. It is the Bidder's responsibility to have received all issued addenda. Bidders should check online at Boynton-beach.bidsandtenders.net prior to submitting their Submittal and up until the BID closing time and date in the event additional addenda are issued.

H. Interested parties may preview the solicitation documents with a Preview Watermark before registering for the opportunity. Documents are not provided in any other manner.

I. If any interested parties have received this ITB packet from a source other than bids&tenders directly and the Interested Party is not registered with bids&tenders, they must register with bids&tenders.

J. No negotiations, decisions, or actions shall be initiated by the Bidder as a result of any discussions with a City employee.

K. Only those communications in writing from the Purchasing Division may be considered a duly authorized expression. Also, only communications from Bidders submitted through bids&tenders in writing will be recognized by the City as duly authorized expressions on behalf of the Bidder.

L. Late Submittal Responses are not permitted by the e-procurement system.

M. To ensure receipt of the latest information and updates via email regarding this solicitation, or if a Bidder has obtained this Solicitation from a third party, the responsibility is on the Bidder to create an e-procurement system vendor account and register as a plan taker for the solicitation with bids&tenders.

N. All expenses for making SUBMITTAL responses to the City are to be borne by the Bidder.

1.10 MISTAKES WITHIN SOLICITATION

Bidders are cautioned to examine all terms, conditions, specifications, Scope of Work, exhibits, addenda, delivery instructions, and special conditions pertaining to the solicitation. Failure to examine all pertinent documents shall not entitle the Bidder to any relief from the conditions imposed in the contract and may lead to the rejection of a bid.

1.11 SUBMISSION OF THE BID

1.11.1 The City’s e-procurement solicitation system shall receive ELECTRONIC BID

SUBMISSIONS ONLY.

1.11.2 HARDCOPY SUBMISSIONS ARE NOT PERMITTED.

1.11.3 Electronic Invitation to Bid for this solicitation shall be received by the City’s e-procurement system no later than the time outlined on page #1 of this solicitation.

1.11.4 Late responses are not permitted by the e-procurement system. It shall be the sole responsibility of the Bidder to have their Invitation to Bid submittal submitted online.

1.11.5 All bids shall be submitted in English.

1.11.6 All prices, terms, and conditions proposed in the submitted response shall be expressed in U.S. Dollars and will be firm for acceptance for ONE HUNDRED TWENTY (120) calendar days after the closing of the ITB.

1.12 SOLICITATION FORMS

1.12.1 The Bidder will submit a response to the solicitation on the bid submission forms provided. All bid submission prices, amounts, and descriptive information must be entered into the e-procurement system bids&tenders.

1.12.2 The Bidder must state the price and the time of delivery for which they propose to deliver the equipment or service requested.

1.12.3 The Bidder must be licensed to do business as an individual, partnership, or corporation in the State of Florida.

1.12.4 All bid submission forms should be executed and submitted for easy identification.

Responses not submitted on bid submission forms may be rejected.

All bid submissions are subject to the conditions specified in this solicitation document. Submittals that do not comply with these conditions may be rejected.

THE FOLLOWING FILLABLE DIGITAL FORMS HAVE BEEN CREATED AND

MUST BE SUBMITTED / ACKNOWLEDGED WITH EACH BID:

A. Certification B. Vendor Drug-Free Workplace C. Bidder’s Qualification Statement D. Confirmation of Minority Business E. Scrutinized Companies List F. E-Verify Compliance G. Sub-Contractor Form H. Firm’s Primary Ownership I. Local Boynton Beach Preference J. Palm Beach County Inspector General Acknowledgement

1.12.5 FORMS THAT MUST BE UPLOADED TO THE DOCUMENT UPLOAD SECTION

A. Document Upload 1: Non-Collusive Affidavit & Acknowledgement B. Document Upload 2: Scrutinized Companies Affidavit and E- Verify C. Document Upload 3: Bid Bond and Bid Bond Acknowledgement (SEE BID

BOND SUBMITTAL BELOW)

D. Document Upload 4: Foreign Entity Ownership Affidavit E. Document Upload 5: Anti-Human Trafficking Affidavit F. Document Upload 6: Anti Kickback Affidavit G. Document Upload 7: Proof of State Certified Licenses H. Document Upload 8: Certificate of Insurance – Proof of Requirements I. Document Upload 9: Internal Revenue Service Form W-9 J. Document Upload 10: Optional

1.13 BID BOND GUARANTY SUBMITTAL

To participate in this Invitation to Bid (ITB), an acceptable Bid Bond, Cashier’s Check, Money Order, Irrevocable Letter of Credit, or Certified Check payable to the City of Boynton Beach in an amount not less than five percent (5%) of the bid price is required for this project. Additional bonding requirements may be specified in the Special Provisions of this solicitation. The Bid Bond must be executed by a surety company authorized to do business in the State of Florida or secured in a manner deemed satisfactory by the City of Boynton Beach.

If a bid guarantee is required, the bidder should upload a true copy of the Bid Bond to the City’s website at the time of online submission via Bids and Tenders.

Specific Instructions:

A bid security bond is required for this project.

An acceptable Bid Bond, Cashier’s Check, Money Order, Irrevocable Letter of Credit, or Certified Check for five percent (5%) of the bid price must accompany your bid.

A scan or copy of the original Bid Bond should be submitted with your electronic bid response.

The original Bid Bond (raised seal or thicker stock paper) must be received via U.S. Mail, air or ground courier, messenger service, or in person to the following address before the bid due date:

100 East Ocean Ave, 4th Floor – Purchasing, Boynton Beach, FL 33435

The City may allow the original Bid Bond to be submitted within three (3) business days after the bid opening, provided the bidder uploaded a scanned copy of the Bid Bond with their initial submission.

Failure to submit the original Bid Bond as outlined will result in the bid being deemed non-responsive.

1.14 BIDDER'S COMPLIANCE WITH FLORIDA STATUTES AND CITY CODES

1.14.1 ANTI-KICKBACK AFFIDAVIT

Each Bidder shall complete the Anti-Kickback Affidavit Form and shall submit this form with their Bid. The City considers the failure of the Bidder to submit this document to be a major irregularity and may be cause for rejection of the Bid.

1.14.2 NON-COLLUSION AFFIDAVIT

Each Bidder shall complete the Non-Collusive Affidavit Form and shall submit this form with the bid. The City considers the failure of the Contractor to submit this document to be a major irregularity and may be cause for rejection of the bid. A Bidder shall not collude, conspire, connive or agree, directly or indirectly, with any other Bidder, firm or person to submit a collusive or sham response in connection with the work for which the response has been submitted; or to refrain from responding in connection with such work or have in any manner, directly or indirectly, sought by person to fix the price or prices in the bid or of any other Bidder, or to fix any overhead profit, or cost elements of the bid price or the bid price of any other responder, or to secure through any collusion, conspiracy, connivance, or unlawful agreement any advantage against any other Bidder, or any person interested in the proposed work. The Bidder certifies there has been no collusion with any other firm or employees from any other firm who will be submitting a bid on the same project. Each Bidder shall complete the Non- Collusive Affidavit Form and shall submit this form with the bid. The City considers the failure of the Bidder to submit this document to be a major irregularity and may be cause for rejection of the bid.

1.14.3 FOREIGN ENTITY AFFIDAVIT

Through the submission of a bid for this ITB, Bidder ensures that it is not owned by the government of a foreign country of concern as defined in Section 287.138, Florida Statutes. (Source: § 287.138(2)(a), Florida Statutes); The government of a foreign country of concern does not have a controlling interest in Entity. (Source:

§ 287.138(2)(b), Florida Statutes); The Entity is not organized under the laws of and does not have a principal place of business in, a foreign country of concern.

(Source: § 287.138(2)(c), Florida Statutes); The Entity is not owned or controlled by the government of a foreign country of concern, as defined in Section 692.201, Florida Statutes. (Source: § 288.007(2), Florida Statutes); The Entity is not a partnership, association, corporation, organization, or other combination of persons organized under the laws of or having its principal place of business in a foreign country of concern, as defined in Section 692.201, Florida Statutes, or a subsidiary of such entity. (Source: § 288.007(2), Florida Statutes); The Entity is not a foreign principal, as defined in Section 692.201, Florida Statutes. (Source: § 692.202(5)(a)(1), Florida Statutes); and The Entity is in compliance with all applicable requirements of Sections 692.202, 692.203, and 692.204, Florida Statutes.

1.14.4 ANTI-HUMAN TRAFFICKING AFFIDAVIT

Each offeror shall complete and upload the Anti-Human Trafficking Affidavit to attest to the following: Through the submission of a bid for this project: Pursuant to section 787.06(13), Florida Statutes, the Entity does not use coercion for labor or services as defined in Section 787.06, Florida Statutes, entitled “Human Trafficking”.

1.14.5 CONFLICT OF INTEREST

The award hereunder is subject to the provisions of Chapter 112 of the State of Florida Statutes. Responding bidders shall disclose the name of any officer, director, partner, proprietor, associate or agent who is also a public officer or employee of the City or any of its agencies.

1.14.6 E-VERIFY FORM UNDER SECTION 448.095

By submission of this bid, Bidder and if awarded, CONTRACTOR certifies that it is aware of and complies with the requirements of Section 448.095, Florida Statues, as may be amended from time to time and briefly described herein below.

Definitions for this Section:

"Contractor" means a person or entity that has entered or is attempting to enter into a contract with…