BoQ - 191T7023Q0025.pdf
PDF 279 KB Posted
- Attached to
- AC Replacement at Telephone Unit, Rome, Italy
- Solicitation number
- 191T7023Q0025
- Issued by
-
Department of State
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cover Letter - 191T7023Q0025.pdf | ||
| Tech.Specifications - 191T7023Q0025.pdf | ||
| SF-1442 - 191T7023Q0025.doc | DOC document | |
| RFQ 191T7023Q0025 - AC Replacement at Telephone Unit.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No. DESCRIPTION QUANTITY
UNITY COST
TOTAL COST
1 Protection of floor and surfaces with cardboard sheeting and poly sheets lump sum
Removal of all furniture that may impact on the correct execution of the work and transportation to a storage location as directed by the COR, within the Tri‐Missions Campus.
lump sum
3 Removal of the existing A/C outdoor and indoor units and transportation to authorized landfill lump sum
4 Removal of the existing piping and electrical and communication cables lump sum
5 Wall finishing and painting of the walls to restore them to their original conditions lump sum
Demolition by cut of the masonry walls to run pipes and cables. All pass through‐holes in structural masonry and floors, will be reinforced with metal frames in order to maintain structural integrity. if the walls are to be fireproof, additional fireproof plating is to be foreseen with products that guarantee same fireproof characteristics of the walls.
lump sum
Supply and installation of a new A/C system as described in the drawings. Air conditioning system includes indoor packaged unit, insulated copper pipes (5/8 + 1/2), drainpipes, remote condensers, bus cables, wall mounted control units, fixtures, brackets, additionale refrigerant charge (100g each meter) and additionale oil charge (50g each siphon), etc. The new A/C units shall be equipped with the “long distance kit”, the check valve on the supply and the solenoid valve on the liquid line.
lump sum
8 Connect and configure the new A/C system to the existing Building Automation System. lump sum
Supply and installation of new electrical and communication cables to feed all the internal units and the remote condensers.
lump sum
Supply and installation of new drain lines for the units. The new drain line shall connect to the existing ones and shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.
lump sum
Supply and installation of new drain lines for the units. The new drain line shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.
lump sum
Connect the new drain line to the existing one. All the masonry and plumbing work needed to connect the drain pipe to the bathroom drainage is included in this SOW.
lump sum
Install a new electrical panel to be connected to an existing 40 A circuit breaker on the PM/D1 through a
Cu/EPR‐XLPE 5G4. The new electrical panel shall be wall mounted, 36 modules, with terminals and lump sum
14 Start up of the system by Manufacturer authorized technicians. lump sum
15 Costs for safety lump sum
MSB TELEPHONE FRAME UNIT
Euro 2000
TOTAL COST
1 Protection of floor and surfaces with cardboard sheeting and poly sheets lump sum
Removal of all furniture that may impact on the correct execution of the work and transportation to a storage location as directed by the COR, within the Tri‐Missions Campus.
lump sum
3 Removal of the existing A/C outdoor and indoor units and transportation to authorized landfill lump sum
4 Removal of the existing piping and electrical and communication cables lump sum
5 Wall finishing and painting of the walls to restore them to their original conditions lump sum
6 Close the holes in the window panes to restore them to their original conditions
Demolition by cut of the masonry walls to run pipes and cables. All pass through‐holes in structural masonry and floors, will be reinforced with metal frames in order to maintain structural integrity. if the walls are to be fireproof, additional fireproof plating is to be foreseen with products that guarantee same fireproof characteristics of the walls.
lump sum
Supply and installation of a A/C system. The dual split unit system shall be composed of two internal units
(12000BTU each) and an external unit 24000BTU, drainpipes, bus cables, wall mounted control units, fixtures, brackets, etc.
lump sum
Connect and configure the new A/C system to the existing Building Automation System (BACnet or
Modbus) lump sum
Supply and installation of new electrical and communication cables to feed all the outdoor and indoor units lump sum
Supply and installation of new drain lines for the units. The new drain line shall connect to the existing ones and shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.
lump sum
Supply and installation of new drain lines for the units. The new drain line shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.
lump sum
Connect the new drain line to the existing one. All the masonry and plumbing work needed to connect the drain pipe to the bathroom drainage is included in this SOW.
lump sum
Install a new electrical panel to be connected to an existing 20 A circuit breaker on the PB/AU through a
Cu/EPR‐XLPE 5G4. The new electrical panel shall be wall mounted, IP65, with terminals and transparent door. Supply and install the new electrical cables as described below. The new panel shall be composed of:
o Magneto thermic and GFCI serving the A/C unit 1: 2 poles 20A, Ith:20A, Idn: 0.3 (B type), Im:200A, Icu/Icn: 6kA – electrical cable: Cu/EPR‐XLPE 3G4 (FG16OM16) lump sum
15 Costs for safety lump sum
USUN DATA RACKS
TOTAL COST
1 Protection of floor and surfaces with cardboard sheeting and poly sheets lump sum
Removal of all furniture that may impact on the correct execution of the work and transportation to a storage location as directed by the COR, within the Tri‐Missions Campus.
lump sum
3 Removal of the existing A/C outdoor and indoor units and transportation to authorized landfill lump sum
4 Removal of the existing piping and electrical and communication cables lump sum
5 Wall finishing and painting of the walls to restore them to their original conditions lump sum
6 Close the holes in the window panes to restore them to their original conditions
Demolition by cut of the masonry walls to run pipes and cables. All pass through‐holes in structural masonry and floors, will be reinforced with metal frames in order to maintain structural integrity. if the walls are to be fireproof, additional fireproof plating is to be foreseen with products that guarantee same fireproof characteristics of the walls.
lump sum
Supply and installation of a A/C system. The dual split unit system shall be composed of two internal units
(12000BTU each) and an external unit 24000BTU, drainpipes, bus cables, wall mounted control units, fixtures, brackets, etc.
lump sum
Connect and configure the new A/C system to the existing Building Automation System (BACnet or
Modbus) lump sum
Supply and installation of new electrical and communication cables to feed all the outdoor and indoor units lump sum
Supply and installation of new drain lines for the units. The new drain line shall connect to the existing ones and shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.
lump sum
Supply and installation of new drain lines for the units. The new drain line shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.
lump sum
Connect the new drain line to the existing one. All the masonry and plumbing work needed to connect the drain pipe to the bathroom drainage is included in this SOW.
lump sum
Install a new electrical panel to be connected to an existing 20 A circuit breaker on the PB/AU through a
Cu/EPR‐XLPE 5G4. The new electrical panel shall be wall mounted, IP65, with terminals and transparent door. Supply and install the new electrical cables as described below. The new panel shall be composed of:
o Magneto thermic and GFCI serving the A/C unit 1: 2 poles 20A, Ith:20A, Idn: 0.3 (B type), Im:200A, Icu/Icn: 6kA – electrical cable: Cu/EPR‐XLPE 3G4 (FG16OM16) lump sum
15 Costs for safety lump sum
GRAND TOTAL
CONSULATE DATA RACKS