BoQ - 191T7023Q0025.pdf

PDF 279 KB Posted

Attached to
AC Replacement at Telephone Unit, Rome, Italy
Solicitation number
191T7023Q0025
Issued by

View the file

Other files

File Type Posted
Cover Letter - 191T7023Q0025.pdf PDF
Tech.Specifications - 191T7023Q0025.pdf PDF
SF-1442 - 191T7023Q0025.doc DOC document
RFQ 191T7023Q0025 - AC Replacement at Telephone Unit.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. DESCRIPTION QUANTITY

UNITY COST

TOTAL COST

1 Protection of floor and surfaces with cardboard sheeting and poly sheets lump sum

Removal of all furniture that may impact on the correct execution of the work and transportation to a storage location as directed by the COR, within the Tri‐Missions Campus.

lump sum

3 Removal of the existing A/C outdoor and indoor units and transportation to authorized landfill lump sum

4 Removal of the existing piping and electrical and communication cables lump sum

5 Wall finishing and painting of the walls to restore them to their original conditions lump sum

Demolition by cut of the masonry walls to run pipes and cables. All pass through‐holes in structural masonry and floors, will be reinforced with metal frames in order to maintain structural integrity. if the walls are to be fireproof, additional fireproof plating is to be foreseen with products that guarantee same fireproof characteristics of the walls.

lump sum

Supply and installation of a new A/C system as described in the drawings. Air conditioning system includes indoor packaged unit, insulated copper pipes (5/8 + 1/2), drainpipes, remote condensers, bus cables, wall mounted control units, fixtures, brackets, additionale refrigerant charge (100g each meter) and additionale oil charge (50g each siphon), etc. The new A/C units shall be equipped with the “long distance kit”, the check valve on the supply and the solenoid valve on the liquid line.

lump sum

8 Connect and configure the new A/C system to the existing Building Automation System. lump sum

Supply and installation of new electrical and communication cables to feed all the internal units and the remote condensers.

lump sum

Supply and installation of new drain lines for the units. The new drain line shall connect to the existing ones and shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.

lump sum

Supply and installation of new drain lines for the units. The new drain line shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.

lump sum

Connect the new drain line to the existing one. All the masonry and plumbing work needed to connect the drain pipe to the bathroom drainage is included in this SOW.

lump sum

Install a new electrical panel to be connected to an existing 40 A circuit breaker on the PM/D1 through a

Cu/EPR‐XLPE 5G4. The new electrical panel shall be wall mounted, 36 modules, with terminals and lump sum

14 Start up of the system by Manufacturer authorized technicians. lump sum

15 Costs for safety lump sum

MSB TELEPHONE FRAME UNIT

Euro 2000

TOTAL COST

1 Protection of floor and surfaces with cardboard sheeting and poly sheets lump sum

Removal of all furniture that may impact on the correct execution of the work and transportation to a storage location as directed by the COR, within the Tri‐Missions Campus.

lump sum

3 Removal of the existing A/C outdoor and indoor units and transportation to authorized landfill lump sum

4 Removal of the existing piping and electrical and communication cables lump sum

5 Wall finishing and painting of the walls to restore them to their original conditions lump sum

6 Close the holes in the window panes to restore them to their original conditions

Demolition by cut of the masonry walls to run pipes and cables. All pass through‐holes in structural masonry and floors, will be reinforced with metal frames in order to maintain structural integrity. if the walls are to be fireproof, additional fireproof plating is to be foreseen with products that guarantee same fireproof characteristics of the walls.

lump sum

Supply and installation of a A/C system. The dual split unit system shall be composed of two internal units

(12000BTU each) and an external unit 24000BTU, drainpipes, bus cables, wall mounted control units, fixtures, brackets, etc.

lump sum

Connect and configure the new A/C system to the existing Building Automation System (BACnet or

Modbus) lump sum

Supply and installation of new electrical and communication cables to feed all the outdoor and indoor units lump sum

Supply and installation of new drain lines for the units. The new drain line shall connect to the existing ones and shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.

lump sum

Supply and installation of new drain lines for the units. The new drain line shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.

lump sum

Connect the new drain line to the existing one. All the masonry and plumbing work needed to connect the drain pipe to the bathroom drainage is included in this SOW.

lump sum

Install a new electrical panel to be connected to an existing 20 A circuit breaker on the PB/AU through a

Cu/EPR‐XLPE 5G4. The new electrical panel shall be wall mounted, IP65, with terminals and transparent door. Supply and install the new electrical cables as described below. The new panel shall be composed of:

o Magneto thermic and GFCI serving the A/C unit 1: 2 poles 20A, Ith:20A, Idn: 0.3 (B type), Im:200A, Icu/Icn: 6kA – electrical cable: Cu/EPR‐XLPE 3G4 (FG16OM16) lump sum

15 Costs for safety lump sum

USUN DATA RACKS

TOTAL COST

1 Protection of floor and surfaces with cardboard sheeting and poly sheets lump sum

Removal of all furniture that may impact on the correct execution of the work and transportation to a storage location as directed by the COR, within the Tri‐Missions Campus.

lump sum

3 Removal of the existing A/C outdoor and indoor units and transportation to authorized landfill lump sum

4 Removal of the existing piping and electrical and communication cables lump sum

5 Wall finishing and painting of the walls to restore them to their original conditions lump sum

6 Close the holes in the window panes to restore them to their original conditions

Demolition by cut of the masonry walls to run pipes and cables. All pass through‐holes in structural masonry and floors, will be reinforced with metal frames in order to maintain structural integrity. if the walls are to be fireproof, additional fireproof plating is to be foreseen with products that guarantee same fireproof characteristics of the walls.

lump sum

Supply and installation of a A/C system. The dual split unit system shall be composed of two internal units

(12000BTU each) and an external unit 24000BTU, drainpipes, bus cables, wall mounted control units, fixtures, brackets, etc.

lump sum

Connect and configure the new A/C system to the existing Building Automation System (BACnet or

Modbus) lump sum

Supply and installation of new electrical and communication cables to feed all the outdoor and indoor units lump sum

Supply and installation of new drain lines for the units. The new drain line shall connect to the existing ones and shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.

lump sum

Supply and installation of new drain lines for the units. The new drain line shall be realized with sufficient slope (at least 1,5%) to allow condensate drain by gravity.

lump sum

Connect the new drain line to the existing one. All the masonry and plumbing work needed to connect the drain pipe to the bathroom drainage is included in this SOW.

lump sum

Install a new electrical panel to be connected to an existing 20 A circuit breaker on the PB/AU through a

Cu/EPR‐XLPE 5G4. The new electrical panel shall be wall mounted, IP65, with terminals and transparent door. Supply and install the new electrical cables as described below. The new panel shall be composed of:

o Magneto thermic and GFCI serving the A/C unit 1: 2 poles 20A, Ith:20A, Idn: 0.3 (B type), Im:200A, Icu/Icn: 6kA – electrical cable: Cu/EPR‐XLPE 3G4 (FG16OM16) lump sum

15 Costs for safety lump sum

GRAND TOTAL

CONSULATE DATA RACKS