Blair Square Improvements Questions 1.pdf
PDF 90 KB Posted
- Attached to
- Blair Square Improvement Construction
- Solicitation number
- BD-22-1627-BOS17-BOS17-76487
- Issued by
- Middlesex County, Massachusetts
About this file
This document is a set of prospective bidder questions and answers related to the Blair Square Improvements construction project issued by the Town of Holliston Facilities Department in Massachusetts. The first question pertains to the treatment of the triangular kiosk, which is to be textured powder coated in black, and the material for the bulletin cases, which will be cork. The second question concerns the water connection work, for which the Town will provide the main connection with a shut-off valve and meter, and the contractor is responsible for running the piping to the various water access points.
The related state and local contract opportunity is for the Blair Square Improvement Construction project located in the state of Massachusetts. No additional details about the project scope, timeline, or procurement process are provided in the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Blair Square Technical Specs.pdf | ||
| Blair Square Bid Plans.pdf | ||
| IFB Blair Square Improvements Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF HOLLISTON
FACILITIES DEPARTMENT
703 Washington Street 508-958-4416 Holliston, MA 01746 June 28, 2022
PROSPECTIVE BIDDERS QUESTIONS #1
BLAIR SQUARE IMPROVEMENTS
Question 1: Will the Triangular Kiosk be painted or powder coated? Also, would you like the material in the bulletin cases to be metal for magnets or a cork-like material for push pins ?
Answer 1: The kiosk is to be textured powder coated in black color. The inner material in the bulletin case is to be cork.
Question 2: There is a pay item for “Water Connection w/Piping” but there is no information on this work. Can you provide plans for this?
Answer 2: The Town will provide the connection to the water main with a shut off valve and meter. The contractor is responsible for running the piping from the shut off valve to the hose bibs, dog-pots and water bubbler.